Work Item: Gravel wearing course - Road surface Graveling with specified camber, all complete Unit - 1 M3
B TOOLS/EQUIPMENT
1 Hand Tool (5% of item A) % 0.398
2 Pedestrian Roller M3 75.00 0.0133 350.00 4.667
3 Water bowser M3 50.00 0.0200 80.00 1.600
4 Dump track M3 18.00 0.055555556 62.50 3.472
Sub Total 10.136
C MATERIAL
Unit Quantity Rate
1 Gravel course materials (65 mm down,) either from M³ 1.00 2.60 2.599
quarry or river materials with fine materials.
Notes :
1. Task rate is based on the soil type.
2. Unit cost for skill labour , unskilled labour and semi skilled labour based on the government rate
3. Unit cost of equipment's are based on hiring rate per hour/per day
4. All cost belong to all of expenditures of related tax, and other cost to complete the work item