You are on page 1of 2

QUOTATION

DATE WIJESUNDARA CONSTRUCTION


829/3,
23/05/2023
Gemunu Mawatha,
Athurugiriya Road,
Architect.Sanjeewa Hettiarachchi Homagama.
Design Consortium Ltd, PHONE: 0729151414
No: 11 (DCL45), MAIL:wijesundarast@gmail.com

Borella Cross Road,


Off Ward Place, Colombo 08.
0112698088

MATERIAL & LABOUR CHARGES FOR SUPPLY & APPLICATION OF CEYAKRETE


SUPERPLAST WALL PLASTER

We refer your inquiry regarding the above project and append below our prices for your
kind consideration

UNIT
NO DESCRIPTION SQFT QTY RATE AMOUNT
(APPROX.)
Surface Preparation
Brick Wall to be made dry and free of dust, dirt,
1
moss, oil, grease and loose particles. 1
N/A 160.00 160.00
Application of 02 Coats of CeyaKrete
SuperPlast All in One Plaster up to the
thickness of 6mm on Walls.
Sanding & Smoothening the Wall.
Terms & Conditions

Validity : 7 Days from the above-mentioned date.

Terms of Payment: 50% advance required on confirmation, 40% on application of


CeyaKrete SuperPlast and 2 coats. Balance 10% completion of project.
(Measure & Pay Basis)

Completion : To be mutually agreed upon payment of advance.

Payment : To be made by ACCOUNT PAYEE Cheque or Bank Deposit only. Cheques


to be drawn in favors of “W.M.P.K.B.M. WIJESUNDARA”.

Bank Details : BOC – Athurugiriya,


ACC no - 88682545 (Slip has to be emailed or WhatsApp for payment
confirmation)

Other Terms : Water, Electricity should be provided by customer.


Periodical Maintenance recommended by qualified technicians.

We trust our quotation meets with your approval and look forward to receiving your valued order.
Please contact us for any further queries.

Thank you.
Yours faithfully,

…………………………………………
WC Construction

………………………………………………

Customer Acceptance