The report compares the planned and actual steel dispatches for January 6, 2023. It shows that the actual dispatch was 35,382 pieces totaling 389,159 tonnage, which was lower than the planned 38,274 pieces and 436,708 tonnage. The differences were 2,892 pieces and 47,550 tonnage. The actual dispatch met 92% of the planned amount. There was 47,549.52 tonnage pending delivery to customers Yegna, Aregawi, and Hona.
The report compares the planned and actual steel dispatches for January 6, 2023. It shows that the actual dispatch was 35,382 pieces totaling 389,159 tonnage, which was lower than the planned 38,274 pieces and 436,708 tonnage. The differences were 2,892 pieces and 47,550 tonnage. The actual dispatch met 92% of the planned amount. There was 47,549.52 tonnage pending delivery to customers Yegna, Aregawi, and Hona.
The report compares the planned and actual steel dispatches for January 6, 2023. It shows that the actual dispatch was 35,382 pieces totaling 389,159 tonnage, which was lower than the planned 38,274 pieces and 436,708 tonnage. The differences were 2,892 pieces and 47,550 tonnage. The actual dispatch met 92% of the planned amount. There was 47,549.52 tonnage pending delivery to customers Yegna, Aregawi, and Hona.