You are on page 1of 36

SAP Project System in SAP ERP 6.

0 EhP 6
Delta Presentation
September 2011
Objectives

At the end of this module, you will be able to:


• List new Project System Enhancements related to Handling Large
Projects, Extended Usability and Performance, New User Interface for
Project Planning, Simplified Reporting, Commercial Project Inception
for Professional Services, Customer Connection and Improved
Integration to Project & Portfolio Management 5.0
• Outline some of the highlights within EhP6

© 2011 SAP AG. All rights reserved. RKT 2


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 3


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 4


SAP Project System in SAP ERP 6.0 EhP 6
Handling Large Projects Delta Overview

As of SAP enhancement package 6 for SAP ERP 6.0 (EA-APPL 606 and SAP-
APPL 606), the business function Project System, Handling Large Projects 2
(OPS_PS_HLP_2) is available.
With this business function, you can use the following Enhancements in Project
System (PS):

 Functional and usability improvements in the Project Editor


 Functional and usability improvements in the Project Worklist
 Draft handling improvements
SAP ERP6.0
 Options for performance optimization
EhP6
 Date planning and scheduling features (new)
 Graphical representation of project dates using the Gantt chart
(new)

© 2011 SAP AG. All rights reserved. RKT 5


Selected Highlights
Project Worklist

In the Project Worklist, you can


Open selected projects, networks, or WBS
substructures in
 Project Editor
 Project Builder
List project, networks, and WBS based on
 Access Control Lists
 Favorites
 Objects last accessed

Go to Draft Workbench

© 2011 SAP AG. All rights reserved. RKT 6


Selected Highlights
Project Editor

The Project Editor is enhanced with Date Planning and


 Additional Data Sets for example PM/CS Order Dates Scheduling Overall Dates
Overview
 Date Planning and Scheduling (new)
 Advanced Date Overviews and Comparison
 Usability Improvements
Display PM/CS
order in hierarchy

Activity Dates Overview

© 2011 SAP AG. All rights reserved. RKT 7


Selected Highlights
Project Editor Gantt Chart (new)

In the Gantt Chart, you can:


 Display dates of project objects (Tabular area, Graphical area)
 Change dates and durations (Drag time bars for WBS elements, Specify dates in tabular
area)
 Define user-specific settings and manage variants (for example, time bar labels)
 Choose different timescales (for example, monthly)
 Print and print preview Gantt chart

© 2011 SAP AG. All rights reserved. RKT 8


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 9


SAP Project System in SAP ERP 6.0 EhP6
Extended Usability and Performance Delta Overview

As of SAP enhancement package 6 for SAP ERP 6.0 (EA-APPL 606 and
SAP_APPL 606), the business function Project System, Extended Usability and
Performance (OPS_PS_CI_2) is available.
With this business function, you can use the following enhancements in Project
System (PS):

 Performance Improvements in the Project Builder


 Performance Improvement Options in the Project Builder and
SAP ERP6.0 Network Transactions
EhP6  Display of non Archived and Archived Line Items
 Option for the Down Payment Clearing of Billing Plans and
Invoicing Plans

© 2011 SAP AG. All rights reserved. RKT 10


Selected Highlight
Performance Improvement Options in Project Builder

With SAP ERP 6.0 Enhancement Package 6 you now have the option to load
projects and networks without loading specific data and hence improve the data
loading times.
You can exclude this data on the Project Builder: User-Specific Options screen.

The performance improvement options are


• Exclude Material Master Data
• Exclude Purchase Order History

Performance
Improvement Options
in the User-specific
Option screen

© 2011 SAP AG. All rights reserved. RKT 11


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 12


SAP Project System in SAP ERP 6.0 EhP6
New User Interface for Project Planning Delta Overview

As of SAP enhancement package 6 for SAP ERP 6.0 (SAP_APPL 606), the
business function CO, Cost Center Management (FIN_CO_CCMGMT) is available.

With this business function, you can implement the New User Interface for Project
Planning.

You can use the following PS related role with this function:
 Project Planner and Cost Estimator (SAP_CO_PROJECT_PLANNER)

 Ready to use role delivered for Project Planner and Estimator


 New User Interface for Overall Planning
SAP ERP6.0
 New User Interface for Cost Estimation
EhP6  New User Interface for Cost Element Planning
 Express Planning

© 2011 SAP AG. All rights reserved. RKT 13


Selected Highlights
New User Interface for Project Planning

© 2011 SAP AG. All rights reserved. RKT 14


Selected Highlights
New User Interface for Cost Estimation

The Easy Cost Planning user interface


was reworked in Release 4.6C to use
a formula-based questionnaire to
determine the main cost blocks in a
cost estimate.

The new application builds on this work


but modernizes the user experience.

© 2011 SAP AG. All rights reserved. RKT 15


Selected Highlights
Overall Planning: Optional Excel UI

If you prefer to use the SAP Business Objects Analysis Client, you have the
option of using all Excel functions while enjoying the benefits of integration with
SAP ERP.

© 2011 SAP AG. All rights reserved. RKT 16


Selected Highlights
Express Planning: Overall Planning Within Express Planning

Express Planning
Framework guides
users through planning
steps.

The planning application is displayed within


Express Planning as a planning service.

© 2011 SAP AG. All rights reserved. RKT 17


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 18


SAP Project System in SAP ERP 6.0 EhP6
Simplified Reporting for Project System

As of SAP enhancement package 6 for SAP ERP 6.0 (SAP_APPL 606), the
business function CO, Cost Center Management (FIN_CO_CCMGMT) is available.
With this business function, you can use the new simplified reports (see next slide).

© 2011 SAP AG. All rights reserved. RKT 19


Simplified Reporting for Project System
Delivered Roles Include a Report Launchpad

Role: e.g. Project Planner


The WDR_CHIP_PAGE
and Cost Estimator
application calls a role-
based list of reports for
each role (report
launchpad).

© 2011 SAP AG. All rights reserved. RKT 20


Simplified Reporting for Project System
Plan/Actual/Variance Report

The new reports use


the SAP BW front
end to support drill
down (here by value
category),
aggregation, and so
on.

However, it is not
necessary to
replicate the data
to SAP BW since
it is read using
„direct access”
via data sources

© 2011 SAP AG. All rights reserved. RKT 21


Simplified Reporting for Project System
New Report: Actual/Commitments/Total/Plan

This report provides detailed cost element


information showing the actual costs, the
commitments and the planned costs for the WBS
element.

© 2011 SAP AG. All rights reserved. RKT 22


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 23


SAP Project System in SAP ERP 6.0 EhP 6
Commercial Project Inception Delta Overview

As of SAP Enhancement Package 6 for SAP ERP 6.0 (EA-APPL 606), the business
function Commercial Project Inception & Lean Staffing 2 (PRS_ERP_CPILS_2) is
available.

The Commercial Project Set-up application has been enhanced to include the
following functions:

 Ability to change and hide project definition data


 Ability to create and delete WBS elements
SAP ERP6.0  User Fields
EhP6  Ability to change the User Status
 Tree view

© 2011 SAP AG. All rights reserved. RKT 24


Selected Highlight
Commercial Project Inception

New: Toggle to Project


New: Definition maintenance
Add/Delete
WBS-elements

New: User Fields


New: Tree
View

New: Change
User Status

© 2011 SAP AG. All rights reserved. RKT 25


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 26


SAP Project System – Customer Connection Program
Development Overview

In collaboration with SAP user groups the following developments have been done
in 2011 within the SAP Customer Connection Program:

SAP R/3 4.6C and  Check Report for Project Archiving


higher
SAP ERP6.0  Enhanced Selection Options in Archiving of Project Related
EhP4 and higher Objects

SAP R/3 4.6C and  Object Currency in Project Planning Board and Structure
higher Overviews

© 2011 SAP AG. All rights reserved. RKT 27


Customer Connection
Archiving Check Report

ALV based log of warning


and error messages

Related object list and Go


to function (display the
object detail)

© 2011 SAP AG. All rights reserved. RKT 28


Customer Connection
Enhanced Selection Options in Archiving of Related Objects

Enhancement available in following reports:


Plant Maintenance Orders:
RIARCORSEL: Initial Run
RIARCORWRS: Write Program
Material Management Objects :
RM06EV70 : Pre-Processing Purchasing Document (EKKO)
RM06EV47: Pre-Processing Purchasing Document (EKKO)
RM06EW70: Write Purchasing Document (EKKO)
RM08RW47: MM Invoice (RBKP)
RM07MARCS: Material Documents (MKPF/MSEG)
RM06BV70: EBAN Pre-processing
RM06BW70: EBAN Write
For archiving of selected project related
objects it is possible to: Additional Archiving Objects Planned

1. Select objects by entering Project(s)


2. Exclude objects belonging to Project(s)

© 2011 SAP AG. All rights reserved. RKT 29


Customer Connection
Object Currency in Project Planning Board and Structure Overviews

Display of project financial


data in object currencies in
CN41 and CN41N

© 2011 SAP AG. All rights reserved. RKT 30


Agenda
SAP Project System in SAP ERP 6.0 EhP 6

Handling Large Projects


Extended Usability and Performance
New User Interface for Project Planning
Simplified Reporting for Project System
Commercial Project Inception for Professional Services
Customer Connection Related Developments
Project & Portfolio Management 5.0

© 2011 SAP AG. All rights reserved. RKT 31


Portfolio and Project Management (PPM) 5.0
Improved Integration With Project System – Delta Overview

As of SAP Portfolio and Project Management 5.0 the integration between SAP
Project System and Portfolio Management has been very much enhanced for
Capital Project Portfolio Management scenarios. The following enhanced integration
functions are available:

 Direct Creation of PS Project from Portfolio Item


 Synchronize Attributes and Status between Portfolio Item / PS
SAP Project and Portfolio Item Decision Point / WBS elements or
Portfolio and Network Activities
Project  Map multiple WBS elements or Network Activities to a Item
Management 5.0 Decision Point incl. Mapping Rules (e.g. map earliest start)
 Enhanced Financial and Capacity Data Integration including
Financial Download Options

© 2011 SAP AG. All rights reserved. RKT 32


Selected Highlights 1/2
Project Creation and Synchronizatzion

Navigation to PS
project from
Portfolio Item

Synchronization
of dates between
Portfolio Item and Project creation
PS project and access from
Portfolio Item

© 2011 SAP AG. All rights reserved. RKT 33


Selected Highlights 2/2
Financial Transfer

Transfer Financial Planning


data to PS projects in terms
of planned costs or budget

© 2011 SAP AG. All rights reserved. RKT 34


Summary

You should now be able to


• List new Project System Enhancements related to Handling Large
Projects, Extended Usability and Performance, New User Interface
for Project Planning, Simplified Reporting, Commercial Project
Inception for Professional Services, Customer Connection and
Improved Integration to Project & Portfolio Management 5.0
• Outline some of the highlights within EhP6

© 2011 SAP AG. All rights reserved. RKT 35


© 2011 SAP AG. All rights reserved

No part of this publication may be reproduced or transmitted in any form or for any purpose Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal
without the express permission of SAP AG. The information contained herein may be Decisions, Web Intelligence, Xcelsius, and other Business Objects products and services
changed without prior notice. mentioned herein as well as their respective logos are trademarks or registered trademarks
of Business Objects Software Ltd. Business Objects is an SAP company.
Some software products marketed by SAP AG and its distributors contain proprietary
software components of other software vendors. Sybase and Adaptive Server, iAnywhere, Sybase 365, SQL Anywhere, and other Sybase
products and services mentioned herein as well as their respective logos are trademarks or
Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft
registered trademarks of Sybase, Inc. Sybase is an SAP company.
Corporation.
IBM, DB2, DB2 Universal Database, System i, System i5, System p, System p5, System x, All other product and service names mentioned are the trademarks of their respective
System z, System z10, System z9, z10, z9, iSeries, pSeries, xSeries, zSeries, eServer, companies. Data contained in this document serves informational purposes only. National
z/VM, z/OS, i5/OS, S/390, OS/390, OS/400, AS/400, S/390 Parallel Enterprise Server, product specifications may vary.
PowerVM, Power Architecture, POWER6+, POWER6, POWER5+, POWER5, POWER, The information in this document is proprietary to SAP. No part of this document may be
OpenPower, PowerPC, BatchPipes, BladeCenter, System Storage, GPFS, HACMP, reproduced, copied, or transmitted in any form or for any purpose without the express prior
RETAIN, DB2 Connect, RACF, Redbooks, OS/2, Parallel Sysplex, MVS/ESA, AIX, written permission of SAP AG.
Intelligent Miner, WebSphere, Netfinity, Tivoli and Informix are trademarks or registered This document is a preliminary version and not subject to your license agreement or any
trademarks of IBM Corporation. other agreement with SAP. This document contains only intended strategies, developments,
Linux is the registered trademark of Linus Torvalds in the U.S. and other countries. and functionalities of the SAP® product and is not intended to be binding upon SAP to any
particular course of business, product strategy, and/or development. Please note that this
Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or
document is subject to change and may be changed by SAP at any time without notice.
registered trademarks of Adobe Systems Incorporated in the United States and/or other
countries. SAP assumes no responsibility for errors or omissions in this document. SAP does not
Oracle is a registered trademark of Oracle Corporation. warrant the accuracy or completeness of the information, text, graphics, links, or other items
contained within this material. This document is provided without a warranty of any kind,
UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group. either express or implied, including but not limited to the implied warranties of
Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are merchantability, fitness for a particular purpose, or non-infringement.
trademarks or registered trademarks of Citrix Systems, Inc. SAP shall have no liability for damages of any kind including without limitation direct,
HTML, XML, XHTML and W3C are trademarks or registered trademarks of W3C®, World special, indirect, or consequential damages that may result from the use of these materials.
Wide Web Consortium, Massachusetts Institute of Technology. This limitation shall not apply in cases of intent or gross negligence.
Java is a registered trademark of Sun Microsystems, Inc. The statutory liability for personal injury and defective products is not affected. SAP has no
control over the information that you may access through the use of hot links contained in
JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for these materials and does not endorse your use of third-party Web pages nor provide any
technology invented and implemented by Netscape. warranty whatsoever relating to third-party Web pages.
SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP BusinessObjects Explorer,
StreamWork, and other SAP products and services mentioned herein as well as their
respective logos are trademarks or registered trademarks of SAP AG in Germany and other
countries.

© 2011 SAP AG. All rights reserved. RKT 36