Professional Documents
Culture Documents
1.0 Introduction…………………………………………………………………………… 1
2.0 Process Flow Diagram………………………………………………………………... 2
3.0 Process Description…………………………………………………………………... 4
4.0 Objectives…………………………………………………………………………….. 6
5.0 Assumptions………………………………………………………………………….. 6
6.0 Steps in designing HEN………………………………………………………………. 7
6.1 Data Collection…………………………………………………………………… 7
6.2 Identify hot and cold streams……………………………………………………… 8
6.3 Heat Capacity Determination……………………………………………………… 8
6.4 Composite curves………………………………………………………………….. 9
6.5 Pinch point………………………………………………………………………….. 11
6.6 Problem Table Analysis…………………………………………………………….. 11
6.7 Grand Composite Curve (GCC)……………………………………………………. 13
6.8 Heat Exchanger Network (HEN) design for Maximum Energy Recovery (MER)… 14
6.9 Loop Breaking - Reducing the Number of Heat Exchangers………………………. 16
7.0 Aspen Energy Analyzer………………………………………………………………… 20
8.0 Conclusion……………………………………………………………………………… 24
9.0 References……………………………………………………………………………… 25
List of Figures
Pinch Technology provides a systematic methodology for energy saving in processes. The
methodology is based on thermodynamic principles. The process design hierarchy can be
represented in onion diagram as below.
Figure 1.1: Onion Diagram of hierarchy in process design and process synthesis
Pinch Analysis always begins with material and energy balance of the process. Using Pinch
Technology, it is possible to identify appropriate changes in the core process conditions that
can have a positive impact on energy savings. After establishing heat and material balance,
targets for energy saving can be set prior to the design of the heat exchanger network. The
Pinch Design Method ensures that these targets are achieved during the network design.
Pinch Technology therefore provides a consistent methodology for energy saving, from the
basic heat and material balance to the total site utility system.
1
2.0 Process Flow Diagram
Figure 2.1: Process flow of hydrotreated vegetable oil (HVO) production from palm oil
2
H3: 173°C to 40°C
Figure 2.2: Process flow of hydrotreated vegetable oil (HVO) production from palm oil
3
3.0 Process Description
The plant operates for 330 days yearly (24 hours non-stop), taking into account the period for
scheduled annual maintenance. It produces Hydrotreated Vegetable Oil (HVO) of
approximately 206,188 tonnes/yr and by-product oxygen of approximately 62,600 tonnes/yr.
In the hydrotreatment process, liquid Crude Palm Oil (30,000 kg/hr) – stored at 30℃ and
atmospheric pressure (1.013 bar) and hydrogen gas (1,436 kg/hr) are first compressed and
heated before being fed into a dual-phase packed bed reactor. The hydrogen is generated on
site using electrolyser at 70℃ and 30 bar. Water (8,900 kg/hr) fed into the electrolyser and
is dissociated based on the principle of electrochemical reaction. The electrolysis by-product,
oxygen (7,904 kg/hr) is pressurized and stored before being processed in a bottling plant and
sold to other companies.
As the process being exothermic in nature, the reactor operates at 300℃ and 40 bar, and
contains a bed of alumina-supported Nickel Molybdenum, NiMo catalyst (NiMo/γ −Al2O3) to
promote the hydrogenation of crude palm oil components to free fatty acids, and the
simultaneous reactions of Hydrodeoxygenation (HDO), decarboxylation (DCOX) and
decarbonylation (DCO). The gaseous and liquid products formed from the reactions are
subsequently separated in three flash separators. First separator after the reactor will further
separate liquid green diesel at 180℃ and 40 bar, which are then mixed together with liquid
product from the reactor. Second separator operating at 40℃ and 15 bar aims to remove
excess water, H2O from the gas stream of the first separator, so that hydrogen can be recover
back by passing through Pressure Swing Adsorption (PSA) unit at 40℃ and 15 bar where
80wt% hydrogen gas (99.7wt% purity) is recovered from the gaseous mixture and recycled
4
back to the reactor to reduce fresh hydrogen consumption. Mixed product stream are then
further purified by passing through the third separator operating at 40℃ and 1.013 bar. The
liquid green diesel produced (C15-C18) have a purity of 94.6 wt% flowing at 26013 kg/hr.
Both waste gas streams from PSA unit as well as final separator, which has high propane
concentration is used as fuel gas to lower electricity cost while the wastewater produced from
second separator will be sent to wastewater treatment plant to comply with the industrial
effluent standard.
Hence, heat exchangers involved in the process are described. Firstly, H-201 and H-202 are
used to heat the CPO feed and water feed from 34℃ to 300℃ (1.013 bar) and 31℃ to 70℃
(1.013 bar) respectively. H-203 is then used to heat the mixed hydrogen feed from 140℃ to
300℃ (42 bar). C-201 was used to cool down the vapor stream from reactor from 300℃ to
180℃ (40 bar) before entering the first separator while C-202 and C-206 are used to cool
down the oxygen product after being compressed from 256℃ to 150 ℃ ( 100 bar) and 278℃
to 40℃ ( 200 bar) respectively. C-203 was used to cool down the vapor stream from first
separator from 173℃ to 40℃ ( 15 bar) before entering second separator while C-204 and
C-205 are both used to cool down the HVO product liquid stream from 287℃ to 180℃
( 2.5 bar) and 177℃ to 40℃ ( 2 bar) respectively.
Although operating condition is at high temperature and pressure, it can also be concluded
that the novelty of this process is having lesser harmful by-products, lesser coking and wastes
formed such as carbon dioxide thus contributing to lower global carbon footprint by being
more environment friendly.
5
4.0 Objectives
5.0 Assumptions
6
6.0 Steps in designing HEN
i. Data Collection
ii. Heat Capacity Determination
iii. Identify hot and cold streams
iv. Plot composite curves
v. Determine pinch point
vi. Problem Table Analysis
vii. Plot grand composite curve (GCC)
viii. HEN design for Maximum Energy Recovery (MER)
ix. Targets for minimum number of heat exchanger units.
From the process flow diagram in Section 2.0, streams that requires heating/cooling are
tabulated and shown in table.
7
6.2 Heat Capacity Determination
*All specific heat capacity values of each stream are obtained from Aspen Plus Simulation.
Heat Capacity (kJ/hr.°C) = Mass flow rate (kg/hr) x specific heat capacity (kJ/kg.°C)
From the stream data listed in Section 6.1, streams can be classified into hot streams and cold
streams. The data is tabulated as below.
8
6.4 Composite curves
Q=ΔT x ∑CP
The composite tables for both hot and cold streams are shown below and the composite curve
is constructed based on data in composite table as shown below too.
30.18adsa
67.12
8.40
8.11
71.16
16.674
9
Composite table for cold stream:
56.6 20.895
42.805
Composite Curve:
350
QHmin= 1390 MJ/hr
THP= 287°C
300
250 TCP=277°C
Temperature (°C)
200
150
100
50
10
6.5 Pinch point
Hot pinch temperature and cold pinch temperature are 287 °C and 277°C respectively.
There are 5 steps required to construct and analyse the problem analysis table:
Step 1: Interval temperatures (Ti) for both supply and target temperatures for all streams
∆
were calculated. Hot stream supply and target temperatures were decreased by and cold
∆
stream supply and target temperatures were increased by .
∆𝑇 10℃
𝑆𝑖𝑛𝑐𝑒 ∆𝑇 = 10℃, = = 5℃
2 2
Table 6.4: Interval temperatures of each stream
Stream CP
Type TS (°C) TT (°C) TSi (°C) TTi (°C)
No. (MJ/hr.°C)
H1 H 300 180 295 175 30.18
H2 H 256 150 251 145 8.11
H3 H 173 40 168 35 16.67
H4 H 287 180 282 175 67.12
H5 H 177 40 172 35 71.16
H6 H 278 40 273 35 8.40
C1 C 34 300 39 305 56.60
C2 C 31 70 36 75 42.81
C3 C 140 300 145 305 20.90
Step 2: Interval temperatures (Ti) were arranged from the highest to the lowest and the
temperature intervals (∆𝑇 = 𝑇 − 𝑇 ) were calculated.
11
Step 3: Difference in heat capacity (∑𝐶𝑃 − ∑𝐶𝑃 ) and interval enthalpies (∆𝐻 = [∑𝐶𝑃 −
∑𝐶𝑃 ] × ∆𝑇 ) were calculated using the sketch shown below.
Step 5: The minimum hot utility requirement (QHmin) is the value on the first row of the
second column of cascade whereas the minimum cold utility requirement (QCmin) is the value
on the last row of the second column of cascade. The pinch temperature is the interval
temperature at which the value zero appears in the second column of cascade. Summary of
problem table analysis method is:
12
6.7 Grand Composite Curve (GCC)
The GCC is a plot of interval temperatures against corresponding heat flow quantities. The
temperatures of the hot and cold process streams are divided into interval temperatures
according to the supply and target temperatures of the hot and cold streams, respectively. The
GCC plot depends on the process stream conditions as well as the minimum temperature
approach. The information required for the construction of the GCC comes directly from the
Problem Table Algorithm.
350
QHmin= 1390MJ/hr
300
250
Temperature (°C)
200
150
100
50
QCmin= 6949MJ/hr
0
0 1000 2000 3000 4000 5000 6000 7000 8000
Heat Load (MJ/hr)
In the figure, a red horizontal straight line shows minimum hot utility required for the process.
Hot utilities of about 1 390 MJ/hr required to do heating from 282˚C to 305˚C on cold
streams. The pinch-point temperature (282˚C) is identified where the curve touches the y-axis.
In GCC, the pinch is the point where net heat flow is 0. Cold utilities of about 6 949 MJ/hr
required to cool hot streams from 282˚C to 35˚C.
13
6.8 Heat Exchanger Network (HEN) design for Maximum Energy Recovery (MER)
Heat exchanger network (HEN) involves identifying the matches between process streams
where a match represents a counter-current heat exchanger with a specified heat load, and we
are also identifying the heaters and coolers required on process streams.
To achieve the maximum energy recovery (MER), we must make sure that the total loading
of heaters equals the minimum hot utility and the total loading of coolers equals the minimum
cold utility that was obtained from the composite curve plotted or the problem table analysis.
To achieve this in a systematic way, the streams must be represented in the form of grid. The
objectives of designing heat exchanger network are:
1. To design the network with minimum hot and cold utilities (in order to minimize
energy cost).
2. To design the network with minimum number of heat exchangers (in order to
minimize capital cost).
1. Divide the problem at the Pinch and design each half separately.
A MER design has no heat transfer across the Pinch, therefore each half is
independent.
2. Start the design at the Pinch and work away from it.
The Pinch is where the constraint is i.e. it is where the temperature approach, ∆T is
the minimum temperature approach ∆Tmin. Hence, we start the design from where
the constraint is so that the constraint can be net before moving away from the
constraint.
3. Immediately adjacent to the Pinch, there are CP constraints that must be met for
stream matches:
Above Pinch: CPhot ≤ CPcold
Below Pinch: CPhot ≥ CPcold
These constraints are necessary to ensure that the temperature profiles in the in the
exchangers do not converge when moving away from the Pinch (making ∆T <
∆Tmin).
4. Maximize exchanger loads.
In order to ensure that we obtain minimum number of heat exchangers, we should
transfer as much heat as possible in every unit. For heat exchangers, this means that
all of the smaller heat load in the two streams should be transferred in each match,
thus eliminating that stream from the design – “ticking off” the stream.
5. Use only hot utilities (heaters) above the Pinch and only cold utilities (coolers) below
the Pinch.
This is required so that we do not heat hot streams or cool cold streams.
14
The fully solved Heat Exchanger Network manually is shown in figure below.
HX9
HX10
HX11
HX12
HX13
HX8
15
6.9 Loop Breaking - Reducing the Number of Heat Exchangers
NMER = 12 (Above pinch + below pinch) where [above pinch = 3 streams + 1 utility -1] and
[below pinch = 9 streams + 1 utility -1]
No of loops = 12-10 = 2
Loop 1 = RED Loop 2 = GREEN
2 loops are shown in HEN design.
HX9
HX12
16
Firstly, Loop 1 is broken where 3rd heat exchanger is removed as it has the smallest heat load.
Heat load from 3rd heat exchanger is being reduced in 2nd heat exchanger while added on to
the 1st and 5th heat exchangers.
Tx =295.78°C
Therefore, load x is reduced from the 5th heat exchanger while load x are added to 2nd and 9th
heat exchangers. New temperature is determined as below.
Ty =214.841°C
17
Then, Loop 2 is broken by removing the 6th heat exchanger as it has a smaller heat load and
does not violate ΔTmin. Hence, heat load is added to 2nd and 7th heat exchangers while heat
load is reduced for the 1st exchanger.
Tr =76.71°C
Tp =286.97°C
Tq =160.09°C
Tz =263°C
18
As there is ΔTmin violation between 1st and 4th heat exchangers, we let Tp= 277°C.
Load x is reduced for 7th heat exchangers to not violate the ΔTmin while load x is added on
to 1st and 12th heat exchangers.
Tr =84.64°C
Tp =277°C Tq =150.12°C
Tz =263°C
The heating utility after breaking the loop has increased up to 2074.92 MJ/hr. The cooling
utility after breaking the loops has increased to 7634.07 MJ/hr.
19
7.0 Aspen Energy Analyzer (AEA)
Aspen Energy Analyzer was used to compare with the manual calculation.
Firstly, data streams are firstly input.
Target View of the HEN design was obtained from Aspen Energy Analyzer, where the hot
and cold pinch, Minimum for MER and also the minimum target hot and cold utilities
required.
By comparing both manually plotted HEN and HEN plotted using Aspen Energy Analyzer,
the Pinch temperatures, heat and cooling utilities required and the number of heat
exchangers required are the same. Composite and Grand Composite curve are also listed
below, which are similar to the manual calculation as well.
20
Figure 7.4: Composite curves shown in AEA
The figure below shows the HEN design before breaking the loop, with a total of 13 units of
heat exchangers.
21
After breaking loop 1, cross pinch occurs and it’s still feasible.
By breaking loop 2, another cross pinch occurs. Pinch lines are removed. A total of 11 units
heat exchangers are present now as shown in figure below.
The heating utility after breaking the loop has increased up to 2074.92 MJ/hr. The cooling
utility after breaking the loops has increased to 7634.07 MJ/hr, which are similar to the
manual calculation.
22
Figure 7.9: Network performance shown in AEA
23
Recommended HEN Design by AEA:
The HEN Design case was converted into project to find the recommended HEN design by
the simulation. However, it is without breaking the loop. Hence, there are 13 units of heat
exchangers in one of the designs as recommended by Aspen Energy Analyzer as shown
below.
Figure 7.11: Network cost indexes and network performance of the recommended HEN
design
8.0 Conclusion
In conclusion, HEN design before and after breaking loop are feasible, as proven by the
Aspen Energy Analyzer. Both maximum energy recovery HEN design has hot utilities of
about 1 390 MJ/hr and cold utilities of about 6 949 MJ/hr. While after breaking loop was
done, number of heat exchanger units are reduced but utilities in both hot and cold increased
to about to 2074.92 MJ/hr and 7634.07 MJ/hr respectively. Number of heat exchanger units
has been reduced from 13 units to 11 units.
24
9.0 References
Gurdensen.T. Heat Integration- Targets and Heat Exchanger Network Design. Chapter 2.1 in
Handbook of Process Intergration.
Retrieved from http://www.ivt.ntnu.no/ept/fag/tep4215/innhold/Handbook%20of%20PI%20-
%20Chapter%202-1.pdf
Jiri.J, Simon & Petar 2014. Basics of Heat Integration. Retrieved from
file:///C:/Users/WINDOW~1/AppData/Local/Temp/Basics_of_Heat_Integration.pdf
25