7.programado VS Ejecutado
7.programado VS Ejecutado
6/14/2023
12-1050 EPM 8 8 100% 4.008 0.501
6/14/2023 12-1500 EPM 4 2 50% 1.308 0.654
14-1050 E 4 3 75% 1.917 0.639
14-1050 EPM 4 3 75% 1.917 0.639
14-1500 EPM 4 3 75% 2.481 0.827
14-2000 EPM 3 3 100% 2.937 0.979
16-1350 E 6 6 100% 6.132 1.022
18-2700 CERREJON 3 2 67% 3.7 1.85
8-510 E 4 20 500% 4.12 0.206
8-750 EPM 8 0 0% 0 0.206
9-735 AFIIA 16 12 75% 2.964 0.247
12-735 AFINIA 64 49 77% 19.992 0.408
12-1030 AFINIA 32 22 69% 11.022 0.501
12-1050 EPM 8 9 113% 4.509 0.501
6/15/2023 12-1500 EPM 4 3 75% 1.962 0.654
14-1050 E 4 3 75% 1.917 0.639
14-1050 EPM 4 3 75% 1.917 0.639
14-1500 EPM 4 3 75% 2.481 0.827
14-2000 EPM 3 3 100% 2.937 0.979
16-1350 E 6 6 100% 6.132 1.022
18-2700 CERREJON 3 3 100% 5.55 1.85
6/16/2023
FECHA 6/1/2023
TOTAL UND PLANEADAS 100
TOTAL UND EJECUTADAS 137
TOTAL POSTES BAJAS 5
TOTAL POSTES DE PRIMERA 132
% REALIZADO VS EJECUTADO 37.0%
TOTAL M3 EJECUTADO 59.86
M3 PROMEDIO EJECUTADO 0.437
FECHA 6/2/2023
TOTAL UND PLANEADAS 99
TOTAL UND EJECUTADAS 126
TOTAL POSTES BAJAS 2
TOTAL POSTES DE PRIMERA 124
% PLANEADO VS EJECUTADO 27.3%
TOTAL M3 EJECUTADO 58.39
M3 PROMEDIO EJECUTADO 0.463
FECHA 6/3/2023
TOTAL UND PLANEADAS 105
TOTAL UND EJECUTADAS 112
TOTAL POSTES BAJAS 0
TOTAL POSTES DE PRIMERA 112
% PLANEADO VS EJECUTADO 6.7%
TOTAL M3 EJECUTADO 53.29
M3 PROMEDIO EJECUTADO 0.476
FECHA 6/5/2023
TOTAL UND PLANEADAS 129
TOTAL UND EJECUTADAS 110
TOTAL POSTES BAJAS 4
TOTAL POSTES DE PRIMERA 106
% PLANEADO VS EJECUTADO -14.7%
TOTAL M3 EJECUTADO 52.94
M3 PROMEDIO EJECUTADO 0.481
FECHA 6/6/2023
TOTAL UND PLANEADAS 143
TOTAL UND EJECUTADAS 136
TOTAL POSTES BAJAS 0
TOTAL POSTES DE PRIMERA 136
% PLANEADO VS EJECUTADO -4.9%
TOTAL M3 EJECUTADO 62.25
M3 PROMEDIO EJECUTADO 0.458
FECHA 6/7/2023
TOTAL UND PLANEADAS 146
TOTAL UND EJECUTADAS 134
TOTAL POSTES BAJAS 4
TOTAL POSTES DE PRIMERA 130
% PLANEADO VS EJECUTADO -8.2%
TOTAL M3 EJECUTADO 63.84
M3 PROMEDIO EJECUTADO 0.476
FECHA 6/8/2023
TOTAL UND PLANEADAS 146
TOTAL UND EJECUTADAS 129
TOTAL POSTES BAJAS 0
TOTAL POSTES DE PRIMERA 129
% PLANEADO VS EJECUTADO -11.6%
TOTAL M3 EJECUTADO 60.77
M3 PROMEDIO EJECUTADO 0.471
FECHA 6/9/2023
TOTAL UND PLANEADAS 150
TOTAL UND EJECUTADAS 139
TOTAL POSTES BAJAS 0
TOTAL POSTES DE PRIMERA 139
% PLANEADO VS EJECUTADO -7.3%
TOTAL M3 EJECUTADO 63.75
M3 PROMEDIO EJECUTADO 0.459
FECHA 6/10/2023
TOTAL UND PLANEADAS 153
TOTAL UND EJECUTADAS 137
TOTAL POSTES BAJAS 0
TOTAL POSTES DE PRIMERA 137
% PLANEADO VS EJECUTADO -10.5%
TOTAL M3 EJECUTADO 62.99
M3 PROMEDIO EJECUTADO 0.460
FECHA 6/12/2023
TOTAL UND PLANEADAS 157
TOTAL UND EJECUTADAS 141
TOTAL POSTES BAJAS 4
TOTAL POSTES DE PRIMERA 137
% PLANEADO VS EJECUTADO -10.2%
TOTAL M3 EJECUTADO 65.34
M3 PROMEDIO EJECUTADO 0.463
FECHA 6/13/2023
TOTAL UND PLANEADAS 149
TOTAL UND EJECUTADAS 142
TOTAL POSTES BAJAS 1
TOTAL POSTES DE PRIMERA 141
% PLANEADO VS EJECUTADO -4.7%
TOTAL M3 EJECUTADO 66.16
M3 PROMEDIO EJECUTADO 0.466
FECHA 6/14/2023
TOTAL UND PLANEADAS 164
TOTAL UND EJECUTADAS 153
TOTAL POSTES BAJAS 2
TOTAL POSTES DE PRIMERA 151
% PLANEADO VS EJECUTADO -6.7%
TOTAL M3 EJECUTADO 62.61
M3 PROMEDIO EJECUTADO 0.409
FECHA 6/15/2023
TOTAL UND PLANEADAS 160
TOTAL UND EJECUTADAS 136
TOTAL POSTES BAJAS 0
TOTAL POSTES DE PRIMERA 136
% PLANEADO VS EJECUTADO -15.0%
TOTAL M3 EJECUTADO 65.50
M3 PROMEDIO EJECUTADO 0.482
CORTE AL 15 DE JUNIO 6/15/2023
TOTAL UND PLANEADAS 1801
TOTAL UND EJECUTADAS 1732
TOTAL POSTES BAJAS 22
TOTAL POSTES DE PRIMERA 1710
% REALIZADO VS EJECUTADO -3.8%
TOTAL M3 EJECUTADO 797.69
M3 PROMEDIO EJECUTADO 0.461