PERT CPM DIAGRAM

START

A 1

1
D B

8 8
8 8
C

7
4 5
F E G

4
H 5

7 7

J
4
2

FINISH
TASK DURATION (WEEKS)
CODE
A Finding and excavating land 1

B Setting up the materials 4

C Lay concrete foundation 7

D Erection of the structure 8

E Supports for walls/ceiling/floor/stairs 5

F Designing electrical wirings 4

G Sanitary and electrical installations 7


(Light Fixtures/Switches)
H Interior plumbing 7

I Water and electrical source Testing 4

J Clean up 2