Professional Documents
Culture Documents
Construction processes
Forming methods
Formwork technology
References
Edition 03/2011
PERI GmbH
Formwork Scaffolding Engineering
P.O. Box 1264
89259 Weissenhorn
Tel.: +49 (0)7309.950-0
Fax: +49 (0)7309.951-0
info@peri.com
www.peri.com
1
Contents
Introduction References 32
History 4
Technology Substructures
2
Superstructures Superstructure/Special Construction Technologies
T-Beam
Bridge over the Tommarpsan, Bonded Steel Construction
Simrishaun, Sweden 104
Pedestrian Bridge, Kirchenlaibach, Germany 106 Weichsel Bridge, Warsaw, Poland 148
Connecting Bridge, Zurich Railway Station Annex,
Cross-Section of Box Girder Switzerland 150
Eisenbachtal Bridge, High Speed Railway Line Intercity Express Route – New Danube Bridge,
Rhein-Main, Germany 108 Ingolstadt, Germany 152
Bridge over the Isar, Highway A92, Neufarn, Germany 110 Tisza Bridge, Hungary 154
Ebro Viaduct, Spain 112
Loewenberg Viaduct, Switzerland 114 Addresses
PERI International 156
PERI Germany 158
Cantilevered Parapets
3
Introduction
This brochure is intended to give an History With the industrial revolution, construction
overview of different construction methods technologies for bridges have changed.
and technologies as well as of different During ancient times, early wooden beam After cast-iron constructions in the 19th
formwork systems, which are related to bridges helped in developing human civili- century, technical inventions like reinforced
the construction of bridge structures. zation. concrete have continuously improved the
Due to increased trading with neighbours, bearing capacity and life-span of bridges.
Construction technologies, in which in business and traffic developed alongside Scientific engineering technology replaced
situ concrete as well as PERI products and infrastructure networks, which also included the well-tested manual construction of earlier
engineering services are used, are mainly river and valley crossings. Technical advance- times. New construction technologies paved
taken into consideration. ment enabled increasingly challenging bridge the way for impressive bridge constructions,
constructions. which are remarkable from a technical and
This brochure is divided into two main Long suspension bridges were built in China aesthetic point of view.
sections: In the first section, bridge and India four thousand years ago for cross- An example of this engineering achievement
constructions, the different designs and ing ravines. In the 6th Century BC, King is the Oeresund bridge connecting Denmark
construction methods as well as the form- Nebukadnezar of Babylon built a bridge over and Sweden, which was one of the largest
work systems used for construction are the Euphrates. In order to erect rock piers in bridge projects in Europe.
described in general. the river bed in a better manner, the course
In addition to this, special construction of the Euphrates was changed. Initial arched
technologies that are currently used are bridges made of rock were built by the
illustrated in detail. Etruscans and later by Romans, whose
Reference projects are given in the second artistic aqueducts rose to architectural fame.
section. The monumental Pont du Gard, for example
guided water for over fifty kilometres across
the valley of the Gardon river from Uzes to
Nîmes in Southern France.
4
Pont du Gard near Nîmes,
France, 50 m high and
269 m wide-spanned aque-
duct with three bridges on
top of each other, which
are made of rocks joined
without using mortar
(Started in 19 BC).
Bridge of Oeresund
Project, which connects
Sweden and Denmark
with a four-lane highway.
5
Basics
Bridge structures can be differentiated Structural Components Quantity, design and dimensions of individual
based on various criteria. structural components are variable and
Important components of depend on factors like span, shape of the
Type and usage of the bridge (road, railway bridge structures are: superstructure, live loads, intended use or
or pedestrian bridge) dimensions.
Suspension
Cornice
Superstructure
Pylon
Pier
Foundation
Abutment
6
Technology
All superstructure variants, for which a load Arched bridges can be identified at first A load-bearing point above the superstruc-
transfer takes place due to a construction glance due to their design. ture in the form of a pylon is a peculiarity
component being stressed on the curve, are Forces in an arched framework are exclusive- of all suspension bridges. Tensile forces
considered as girder bridges. From simple ly induced in the foundation or the arch are induced through suspensions like steel
massive slabs up to multi-stem box girder springer. ropes or chains. The largest span widths
bridges, the superstructure has always the can be achieved with suspension bridges.
same function. Therefore, the area of appli- The so-called tie rod bridges present a
cation of girder bridges is extensive. further variant, but are very rarely built.
Girder bridge, Viaduc de Marnaval, RN 67, Arched bridge, Santa Lucia, Castellaneta, Suspension bridge, Second Severn Crossing Bridge,
St. Dizier, France Italy England/ Wales
Load Load
Load
Load
7
Technology
Foundation Formwork
Level foundation is the most-common type Special foundations like well foundations,
for bridge foundations. rammed piles, bored piles and louvered
The flat foundation bottom is guided onto the slides, are used when the site does not have
load bearing site. Load bearing takes place bearing capacity or if there are other conflict-
through surface pressure at the site. Dimen- ing factors like ground water, river courses or
sions of the foundation are determined from restricted spaces of a pad foundation.
the height of the load to be transferred and At the same time, loads are transferred to
characteristic values of the soil. deeper layers. They still require a load distri-
bution baulk or a slab as a connecting link
Formwork Technology between the pier foot and special foundation.
As a rule, this load distributing component
The formwork for the foundation must be acts as a level foundation. Therefore, consid-
designed in such a manner that horizontal erable time and cost implications are associ-
green concrete pressure due to large founda- ated with special foundations.
tion heights can be absorbed by the form-
work. Normally the opposite side of the Formwork Technology
formwork is anchored for absorbing these
forces. As a result of large foundation dimen- The same systems that are used for level
sions, the formwork may get deformed due foundations are used for the formwork of
to strain in tie rods. These deformations can load distribution components in special
be avoided by using a boom support system foundations.
for single-sided load transfer.
Due to limited requirements for the concrete
surface of foundations, panelized wall form-
work systems are normally used for this pur-
pose. Girder wall formwork systems are used
only for a greater number of applications and
longer application periods or for irregular
shapes.
8
Substructure
Abutment Formwork
Technical Description
Formwork Technology
9
Technology
Formwork Technology
Technical Description
Formwork Technology
11
Technology
Construction in Phases,
Self-Climbing Formwork for High Piers and Pylons
Technical Description
Formwork Technology
23.50
19.50
15.50
11.50
+94.50
Technical Description
Formwork Technology
Architecturally designed
piers with visible concrete
surfaces (top) and form-set
with PERI VARIO girder
wall formwork, MULTI-
PROP system and HD 200
heavy load supports (left).
Project: Channel bridge,
water crossroads in
Magdeburg, Germany.
14
Pier and Pylon
Pier Head
Formwork Technology
Overview of platform
on the pylon shaft.
15
Technology
16
Superstructure
Massive Slab Cross-Section for Span Widths up to 10 m Span width for individual bridge spans is the
main criterion for selecting the superstruc-
ture variant. Apart from external parametric
conditions like specifications of the builder or
site, geographical conditions affect the selec-
tion of the construction principle.
Box Girder Cross-Section for Span Widths up to 200 m Construction technologies described below
14,75 bridge deck cover a large part of the common
cross-sections.
3,20
8,59
6,55
17
Technology
Superstructure on Falsework
Falseworks help in transferring structural However, this type of falsework construction Light Falsework /
loads arising while constructing the super- does not correspond with the latest techno-
structure over its own foundation to the soil logy. We distinguish the following: Surface Scaffolding
directly or indirectly.
Light falsework / surface scaffolding Technical Description
This takes place through frame supports or
pipe scaffolding systems that can be insert- Heavy falsework
ed. Likewise, scaffolding of individual pipes Light shoring systems act as a surface
that are joined at any desired point using support for the actual superstructure
pipe couplings are also possible. formwork.
The ground surface of the superstructure
is completely arranged for load transfer.
Loads to be transferred for each scaffold-
ing strut may go up to approx. 60 kN,
depending on the scaffolding system.
The technology is similar for all applicable
systems. Due to system components with
Over 16 m high shoring, a dead weight of up to approx. 25 kg,
constructed using a load columns or load column sections are
MULTIPROP system, for developed.
concreting road slab of
120 to 160 m long steel
A flat covering is put on these braced
sections, which serve as scaffoldings, which simultaneously acts as
bridge elements for a formwork floor for the field team and for
the 1,092 m long elevated transporting.
bridge of Öresund link.
In case of surface joints, these covering
levels are doubled. If the selected support-
ing system does not have permission for
the self-supporting application, diagonal
guy ropes must be fitted for transferring
horizontal forces.
Formwork Technology
18
Superstructure
Heavy Falsework
Technical Description
Formwork Technology
Horizontal pre-assembly of
a shoring frame plate made
of standard components of
PERI HD 200 heavy load
system like frame carriers
and heavy load supports.
19
Technology
T-beam Cross-Section
Technical Description Formwork Technology
Superstructures for bridges with medium Beams as partially finished components In case of T-beam cross-sections in in-situ
span widths (up to approx. 30 m) are replaced by a slab in in-situ concrete: concrete, stems and slabs are built in a con-
designed as a T-beam cross-section. It con- In this case, only one shoring is required for creting process. Stem formwork must be
sists of a road slab, stem, cantilever slabs supporting the finished components. For the designed in such a way that it can absorb
and if necessary cross beams. The large section between the girders, mostly one joist loads due to the dead weight and the pres-
structural height at comparatively lower formwork is used. sure of green concrete.
weights allows larger span widths. Complete superstructure in in-situ concrete:
In this case, the entire structure is form set. To be able to build the shape and to absorb
Two variants can be differentiated for In order to carry off pressure of green con- loads bridge rafters 1) from lattice beams,
construction: crete, tie rods are normally guided through steel beams and heavy load shafts are
stems. assembled.
Such a modular and flexible system almost
allows formworking all structural cross-sec-
tions and also simultaneous scaffolding.
Thus, concrete loads like green concrete
pressures can also be transferred.
Cross-section of the box girder is the ideal The floor formwork is built on falsework with For transferring green concrete pressure,
cross-section for straight and curved large a joist framework. Intermediate beams must internal and external stem formworks are
bridges. Span widths over 100 m are possi- be brought in the section of stems to be able anchored against each other. External stem
ble with pre-stressed concrete. to transfer increased concrete loads. and cantilever formwork consist of variable
Box girder is designed with one or more cells Internal stem formwork consists of mating frameworks (Bridge rafters1)). At the same
depending on the superstructure width. Con- elements, which are exactly adjusted as per time, they carry dead weight of the green
struction of the superstructure takes place in the shape of the structure. Internal stem concrete and transfer loads due to concreting
two concreting sections. In the first phase, formwork with concrete spacers are support- operations in the falsework or sub-structures
the floor slab is form-worked and concreted ed on the formwork floor. in a secured manner. As a rule, rafters are
with open stems . In the second phase, road constructed from system components; spe-
slabs and cantilevers are constructed. cial components are not required. Formwork
beams are laid over steel beams for con-
struction. Steel beams are connected with
joining components. Heavy load supports are
used as diagonals. The horizontal loads are
transferred with scaffolding pipe bonds and
couplings.
Cantilevered Parapets
Formwork insertion on
the cantilevered parapet
carriage PERI GKW takes
place by a shaft device
with a wedge connection.
It is designed in such a
manner that the form-
work need not be joined
with the cantilever slab
of the bridge.
max. 5.00
22
Superstructure
A well-protected technician
travels with the pre-assem-
bled platform in a working
cage for assembling and
dismantling.
23
Technology
Special construction technologies for building In order to plan a suitable formwork solution, A particular advantage of the cantilever
the superstructure are used when construc- close co-operation of all parties involved in launching method is that a uniform frame-
tion on a falsework is very expensive, very the construction is essential. It guarantees work can be developed. At the same time,
time-consuming or not technically feasible. the best possible application of the material heavy lifts are not required. Continuous repe-
Such special solutions are developed with to be used and best possible work flows tition of the same activities in phase-wise
the help of standard formwork components with determined time and work cycles. In construction results in time advantages. This
and specifically adjusted as per the need of addition to this, relevant work documents rational working method is reflected in its
the construction site. Thus, bridge construc- and manuals are provided to people on the efficiency.
tions can be done economically even in construction site in which the intended
these cases. formwork application is explained in detail. In the case of the cantilever launching
method, there is a relatively high planning
certainty in regards to construction time
since work can be done in a field workshop
without being affected by the weather. More-
over, required materials can be stocked only
at one place.This enables short transport
routes and optimum utilisation of roads.
Cantilever launching
bridge Woronora,
Australia
(Also see page 134).
24
Workflow
Cantilever Launching Method
Technical Description
Formwork Technology
For example:
26
Special Construction
27
Technology
Mobile Falsework
With the help of mobile scaffolding, individual Technical Description Formwork Technology
bridge spans can be constructed irrespective
of the height over the ground level. At the In this process, the falsework is moved to a As a rule, bridge structures that are con-
same time, span widths of up to 50 m can new concreting position along with the form- structed with the help of mobile falsework-
be realised. Formwork and scaffolding units work. Contrary to the cantilever launching sare are designed as box girder cross-sec-
are always connected with each other and method (compare page 24 ff), the concreted tions. In exceptional cases, even T-beam
are moved together. component remains in its position. cross-sections are used.
Depending on the shape of the structure, an
A decisive advantage of mobile falsework is upper or a lower mobile support is used. In the case of mobile falseworks, the form-
that construction can be done span-wise in work is constructed from standard compo-
short phase times with less labour costs. The advantages of the upper system are high nents of the girder wall formwork. Steel
capacity on curves and free selection of the beams with special connections and joints
Construction of bridges with mobile false- bridge cross-section. Moreover, the railway are mainly used for mobile support.
work is economical from structural lengths of loading gauge under the new structure is not
300 m onwards. This is equivalent to a num- affected normally. While planning, it must be ensured that the
ber of at least eight sections to be concret- formwork and scaffolding systems are well
ed. The variant with the lower mobile support is coordinated since there is a close interaction
advantageous due to lower cost implications. between both systems.
Furthermore, pre-assembled reinforcing ele-
ments can be brought in with the crane (time
advantage) and suspensions through the
structure are not required.
28
Special Construction
29
Technology
In this case, the bridge deck is made of two Technical Description Formwork Technology
different materials. The lower component,
the trough or in the case of an open cross- In the case of bonded steel constructions, Support formwork elements are used as
section, individual longitudinal beams are construction materials are used according to formwork elements on the bonded steel
made of a steel construction, whereas the their specific material characteristics. Thus, formwork carriage. Mostly the lower edge of
upper component, that is the road slab with components that are stressed with tensile the cantilever is a suitable plane surface so
cantilevers, is constructed in concrete. forces are made of steel and those stressed that the element can be supported in a rela-
with compressive forces are made of rein- tively simple manner. Higher requirements
A particular advantage of bonded steel forced concrete. In the first work process, a are posed on the carrier equipment, form-
construction is that it only needs a short steel beam in the form of an I-beam or a box work carriage or the trough bracket. The carri-
construction time due to a predominant pre- girder cross-section is brought into position. er equipment must have adjustment options
assembly, which also reduces construction Subsequently, a formwork carriage is placed for setting the inclination of the cantilever
costs. Bonded steel constructions have less- on the top flange of the steel trough for and the traverse and longitudinal bridge
er dead weights than pre-stressed concrete inserting cantilever formworks. inclination.
superstructures. Therefore, larger span This carriage covers the sections in a reci-
widths are possible for the same load. procating rolling process depending on the
bridge length or if two carriages, covers
castor and interstice are used.
However, in case of small bridge structures,
a more favourable formwork solution is
desired since usage of the formwork carriage
would not be economical due to short-term
PERI bonding formwork usage of material. For these cases, special
carriage used for construction scaffolding solutions with brackets are used.
of Werratal bridge BAB A7
Hanover-Munich.
30
Special Construction
1st phase
Set up the carriage
2nd phase
Reinforcing and concreting
3rd phase
Procedure
31
35 Years of International Project Experience are a Strong
Basis for Efficient Formwork and Scaffolding Solutions
Cantilevered launched
formwork for the main
section of the Lek Bridge,
Netherlands. Starting from
the piers near the river
banks, the pre-tensioned
hollow box is formed and
launched approx. 80 m
until the roadway meets
over the middle of the
river.
32
The following pages show successful solutions of international
bridge projects which illustrate the high standard of PERI formwork
technology.
Substructures
34 Abutments
38 Columns / pylons:
Construction methods: monolithical, in cycles,
with climbing formwork, with self climbing formwork,
construction of special structures
80 Pier head
Superstructures
86 Superstructure on falsework:
light falsework / surface falsework,
heavy falsework / system HD 200
100 Formwork for superstructures:
solid slab, slab girders, cross section of hollow box
116 Cantilevered parapets:
cantilevered parapet carriage, cantilevered parapet platform,
special structures and bridge sanitation
33
Bridge Abutments
Thick walls in varying heights and oblique Very often, horizontal of vertical board struc- Motorway crossing
angled return walls constitute the main tures are requested. abutment of the S-Bahn
to Munich Airport II.
problems of abutments. Joint Venture Spange
Formwork systems that can be erected and Neufahrn.
Rebounds and wall reinforcement in the removed without any problems – adjusted to Girder wall formwork
upper wall section add to this. the special requirements of the respective VARIO with board
structure formlining.
project – are imperative. Contractor: Heilit &
Woerner, Auer
34
Substructures/Abutments
35
Bridge abutments near Braunschweig, Germany
As part of the extension of the A2 national In order to realise the required surface struc- Alfred Brandt, Supervisor:
motorway from Hanover to Berlin, several ture as well as the smooth change from “Only few connecting parts
were necessary for the
bridge constructions crossing the new route straight to curved wall sections without triple TRIO Structure exten-
were necessary. having to renounce from system elements, sion. Support was carried
the contractor decided in favour of TRIO out with RS 1000 push-pull
Part of the bridge construction between Structure and RUNDFLEX formwork ele- props, connection of the
elements by the BFD align-
Boimstorf and Lehre near Braunschweig ments. These two systems can be combined ment coupler.”
feature the 128a and 128b abutments which without any adaptation by means of the BFD
had to be formed with board structured sur- alignment coupler and permit the adequate
faces and regular horizontal construction form lining in order to achieve the requested
joints. structure of the surface.
36
Substructures/Abutments
1.40
Formwork plan: despite The required construction
the demanding layout, the joint layout was achieved
whole construction could by applying wooden strips
be formed with 100% to the plywood.
system formwork
components.
1.40
Smooth connection of
TRIO and RUNDFLEX is
due to the compatibility
of the two systems.
8.95
4.35
38
Substructures/Piers/Pylons
39
Bridge over the Danube, Leipheim /Town Bridge Frankfurt / Oder, Germany
PERI supports bridge constructors all over Abutment with TRIO panel
the word with cost-effective formwork sys- formwork.
tems and solutions, comprehensive service
and know-how. These factors make a deci-
sive contribution to ensure a safe and eco-
nomical completion of every project.
40
Substructures/Piers/Pylons
Ground plan and section For the construction of the four river piers in
illustrate the difficult layout architectural concrete of this border-crossing
of the river piers. Surfaces
had to be formed in archi- bridge structure, PERI planned and assem-
tectural concrete quality. bled two complete formwork sets. PERI’s
pre-assembly service in Berlin punctually
delivered large-size units of VARIO GT 24
girder formwork in transportable dimensions
of up to 6.80 x 2.50 m to the site. Optimal
execution of this special form, and surface
layout of these constructions (alternating
10.73
41
Dartford Bridge over the Thames, England
42
Substructures/Piers/Pylons
43
Hadath-Syrian Border Highway, Lebanon
Section
6.00
Ground plan
The complete
formwork is
moved in only
four crane lifts.
Reinforcement can
be safely fixed
inside the protec-
tion of the retract-
ed formwork.
44
Substructures/Piers/Pylons
This 430 m long viaduct is part of an Arabian CB 240 climbing brackets used in the shafts Massimo Appiani,
trunk road connecting Lebanon and Syria. enabled 6.00 m high lifts to be concreted Project Manager:
“We could maintain the
20 piers up to heights of 73 m had to be daily. Horizontally-arranged SB-2 brace 24 hour cycle with the
constructed for two parallel bridge lanes. frames carried the loads from the can- CB climbing techniques.
tilevered pier heads. Considerable time and The system proved to be
PERI supplied the complete formwork plan- crane capacity was saved through moving flexible and easy to use in
the daily work.”
ning as well as the formwork and the climb- complete formwork units in one lift.
ing systems for this, and for the 14 piers for
the 310 m long Viaduct Grand Hotel further
along the road.
Economical: complete
transport units with climb-
ing brackets and VARIO
panels were moved to the
next pier in one lift.
4.71
45
Motorway viaduct near Souillac, France
Philippe Boisrobert,
Supervisor:
“The fast moving times
surprised us. Our expecta-
tions were fully met with
this formwork solution. It
only took 110 working days
to accomplish each 50 set-
tings of the two formwork
units. All requirements
Ground plan of pier with were fulfilled and the con-
changing geometry. crete design was success-
fully achieved.”
47
A 71 Motorway Bridge near Besedau, Germany
This newly constructed bridge on the A71 Contractor: J.G. Müller, Wetzlar 6.20
Erfurt – Schweinfurt motorway has a length Field service: PERI Germany, Weissenhorn
and Ebersgöns
of 690 m and spans the Saale river valley.
A total of eight pairs of reinforced concrete
piers, with a special pier head design, sup-
port the two separately constructed carriage-
way superstructures.
6.02
assembled pier head formwork to the con-
struction site. Planned by PERI engineers in
the technical department and expertly imple-
mented by assembly specialists at the PERI
plant in Weissenhorn, a cost saving solution
was created which allowed the exact realisa-
tion of the pier heads on-site.
48
Substructures/Piers/Pylons
When the first piers were erected, the use of the pier shaft formwork units was
casting pit for the construction of the super- planned by the production planning depart-
structure was installed at the same time. ment of the contractor.
Conforming with PERI standard elements
dimensions, the pre-tensioned hollow box
was concreted cycle by cycle in a longitudinal
direction and then moved over the piers
using the incremental launching method.
Realisation of the casting pit as well as the
Marian Koscielniak,
Contracts Manager:
“There are a lot of positive
things to say about PERI.
Besides the excellent tech-
nology, their engineers are
prepared to solve any prob-
lem directly on-site. This is
also applies to the PERI
delivery service which
delivers on time which
includes those orders
placed at short notice.”
49
Uddevalla bron, Sweden
50
Substructures/Piers/Pylons
3.31
1.25
3.93
3.93
Inclined-positioned ACS
system with working plat-
forms always in a horizon-
tal position in spite of
varying inclinations.
Contractor:
SKANSKA; Sweden
Field service:
PERI Sweden, Huddinge
PERI Germany, Weissenhorn
51
Kao-Ping-His Bridge, Taiwan
At a height of 42 m, the
pylon legs are joined by a
cross beam. It carries the
roadway slab and transfers
the loads to the pylons.
8.57
7.52
Parallel-connected ACS units
climbed at a 72° inclination. 1.46 4.84 1.22
Working platforms were
always kept a horizontal a
position.
a concreting platform, b
b intermediate platform
4.20
73,50
183,50
110,00
Ryoji Kikawa,
Project Manager:
“Thanks to the excellent
advice by the PERI super-
visor, performance was
perfect. The initial concret-
ing cycle of 12 days could
rapidly be reduced to 10
days.”
53
Viaduct de Millau Motorway Bridge, France
This very spectacular bridge project in south- To ensure that the construction work was
west France was designed by the English carried out on schedule, PERI delivered vari-
architect, Sir Norman Foster. Eight sections, ous formwork and scaffolding systems to the
with lengths of 2 x 204 m and 6 x 342 m, site. Their use was strictly in accordance
span the River Tarn valley. A total of 7 rein- with the construction schedule on the various
forced concrete pylons of heights between piers which meant use on either different
78 and 245 metres will support the 32 metre piers or combined together on one.
wide steel superstructure with its trapezoidal-
shaped hollow box girders and the securing Altogether, this correspons to around
of the steel pylons carrying the stay cables. 6,500 m2 of formwork for the single and
double piers, 196 PERI ACS-R (self-climbing)
The Viaduct de Millau is part of the fast brackets, 96 PERI SKSF 240 (crane-lifted)
motorway connection between Paris and the brackets and 12 scaffolding modules (special
Mediterranean area of southern France. The design) which are used as internal scaffolding
French government granted usage rights for on the double piers.
the structure over the next 75 years to the
Eiffage construction group and, in return, an
inventory warranty for 120 years was agreed.
Marc André,
Site Manager:
Phillippe Blondeau,
Quality Assurance:
54
Substructures/Piers/Pylons
55
Viaduct de Millau Motorway Bridge, France
56
Substructures/Piers/Pylons
59
Viaduct de Millau Motorway Bridge, France
14 (2 x 7) complete climb-
ing scaffold units made
up of PERI ACS-R self-
climbers with telescopic Standard section of double
working platforms were pier with customised inter-
used on the double box nal scaffolding and ACS-R
piers. on the outside.
4.00
60
Substructures/Piers/Pylons
14.70
14.20
16.20
15.00
17.00
25.00
63
Arthur Ravenel Jr. Bridge, Charleston, USA
64
Substructures/Piers/Pylons
65
Arthur Ravenel Jr. Bridge, Charleston, USA
Two 175 m high piers, at a distance of 472 m With PERI ACS, four work-
ing levels together with the
from each other, take the loads of this cable formwork are lifted from
stay construction which connects both sides cycle to cycle without the
of the Cooper River. use of a crane: concreting
The short construction time together with platforms, shuttering and
striking levels, climbing and
tough logistical requirements (all materials finishing platforms used to
had to be transported to both piers using disassemble the climbing
barges) and the necessity to save on crane shoes and anchors.
capacity meant that the use of a self-climb-
ing formwork system was essential.
PERI engineers designed an extremely effi-
Peo Halvarsson,
cient formwork concept containing detailed Contract Manager:
pre-determined working speeds. These were “Previous experience, the
maintained by the construction crews with a inexpensive price and an
high degree of productivity. The high require- excellent working relation-
ship with the PERI engi-
ments placed on the concrete surfaces neers made our decision
together with the dimensional accuracy were regarding the choice of
fully met using PERI ACS combined with formwork supplier an easy
VARIO GT 24 girder wall formwork. The scaf- one. The PERI solution pro-
vided us with a formwork
folding units remained permanently connect- system with which we
ed to the structure even during climbing could work quickly and pro-
which ensured high levels of safety through- duce quality results at the
out. All wind loads were taken into consider- same time.”
ation during the planning phase.
Around 1,000 m2 of VARIO GT 24 girder wall
formwork was used as well as eight ACS-V
platforms for the inclined pier sections and
eight ACS-R platforms for the sloped areas.
On the lower half of the piers, up to the
change in slope, one concreting section of
4.15 m was finished per week. Due to the Climbing cycle sequence
for change in inclination
simplified reinforcement arrangement and on bridge pier.
smaller construction geometry, concreting
took place every four to five days and the
contractors were able to reduce the sched-
uled pour sequence from seven to five days.
67
Waterways crossing Magdeburg, Germany
Rothensee Sluice
This construction was built to connect the 6,600 m2 VARIO formwork had to be sup- deflection of the formwork was less than
Mitteland canal to the Magdeburg harbour plied for these project. 4 mm for a 4.60 m concreting cycle height.
and River Elbe.
By rear tensioning the formwork units, the
All requirements were completely fulfilled by number of time-consuming ties was signifi-
TRIO panel formwork and VARIO elements. cantly reduced and large units could remain
6,800 m2 of TRIO formwork and more than connected for moving. The maximum
Reinhard Meyer,
Senior Foreman:
“We had absolutely no
problems with the VARIO
climbing formwork. This is
a solid formwork system
which only needs two ties
per cycle height.”
70
Substructures/ Piers/Pylons
R=4
4.33
9.70
A
0.40 2.70 0.40 2.70 0.40 2.70 0.40
R
=
9.
00
Section A - A
Marinko Marohnić,
Project Manager
Contractor:
Viadukt Bau AG, Zagreb,
Hidrogradnja, Sarajevo
Field Service:
PERI Croatia
71
BCarinski Bridge,Mostar,Bosnia-Herzegovina
72
Substructures/ Piers/Pylons
73
Bridge over the River Raab, Hungary
The town of Sarvar had to suffer years of The contractor decided in favour of a PERI Jenő Bodor,
traffic congestion before a ring road was solution based on the VARIO GT 24 system. Site Manager:
“Apart from a few special
constructed to alleviate the situation. Near With the addition of arched-shaped timber components for the closing
the well-known west Hungarian health resort, formers between plywood and girders, an of very complicated sur-
the federal highway No. 84 crosses the River ideal formwork geometry was achieved. The faces, we could work
Raba. The designated bridge was built as a individual VARIO elements moved by a crane exclusively with rented
PERI system components.
steel composite construction. could be quickly combined by means of In this way we were able
extension splices on the girder joints and uni- to achieve the minimum
In order to take the steel arches of the main versal couplings on the steel waler joints. tolerance of only 1 cm
bridge section – with a 78 m span – specially Through the high stability of these system even at the reinforced con-
crete and steel construc-
designed reinforced concrete abutments connections, and the reliable load transfer via tion connecting points.”
were erected on the banks of the river. The SLS heavy duty spindles and MULTIPROP
bearing walls, with an inclination of 45°, and spindles, realisation of the complicated con-
the lower elements of the frame optically struction along with high quality concrete
follow the arch of the steel main beam and surfaces could be carried out simultaneously.
transfer the loads to the foundations. The
riverside wall surface is softened by partially
curved cavities.
74
Substructures/Piers/Pylons
75
Bridge over the Leie, Waregen, Belgium
Right on Time
With PERI Formwork Technology
Travelling outside and inside formwork
on PD 8 tables adjustable for heights.
76
Substructures/Piers/Pylons
77
Fuldatal Bridge, Kassel, Germany
As part of the Hannover-Würzburg high-speed On the other, the inclination and curvature, The heart of the system was a lattice girder,
rail link development, the vertical and arched which varied with each lift, had to be taken with articulated formwork panels and climb-
piers of the Fuldatal Bridge near Kassel were into consideration. ing hydraulics, placed in the pier´s box sec-
constructed using PERI self-climbing form- tion.
work. The individual concreting sections of the arch
bow were 3.20 m. Shuttering, reinforcement work, concreting,
Passengers on the Inter-City express trains striking and moving were carried out in a
have exactly 11 seconds to admire the beau- In addition, it was necessary for all eight three-day cycle.
ty of the Fulda Valley as this is the time that forming surfaces, reinforcement areas, mov-
the train takes to cross the 1,100 m long and ing and adjustment equipment to be acces- The total of 22 vertical piers were formed
up to 65 m high bridge before entering in the sible. The deflection of the steel structure with first generation PERI self-climbing form-
next tunnel. caused by dead loads and concreting forces work (KG 240 with hydraulically driven multi-
also had to be considered. purpose tracks).
The arched (A-frame) piers were designed to
transfer the horizontal loads created when a PERI’s solution was to create an arched pier
train crosses the bridge. formwork system that climbed automatically.
Constructed in 3-day
cycles: PERI self-climbing
arched pier formwork for
the Fuldatal Bridge
Morschen, near Kassel.
78
Substructures/Piers/Pylons
79
Bridge over the Triebisch Valley, Nossen, Germany
248.20
202.40
81
Highway extension, Hrdlořezy, North Czechia
3.20
1.30
A
4.50
1.90
A
4.80
1.30
Section A – A through the pier head Ground plan of the pier with formwork
82
Substructures/Pier cap
83
Creve Cœur Lake Memorial Park Bridge, St. Louis, USA
84
Substructures/Pier Heads
26.05
VARIO girder wall formwork was used for MULTIPROP supporting system transfers
the web and cantilever formwork. the fresh concrete loads from the can-
tilever without any problems.
11.55
MULTIPROP
MP 350
Haunched table
87
Ladce motorway bridge – Sverepec, Beluša crossing, Slovakia
On the D1 motorway, between Ladce and Both the shape of the ground and the longi-
Sverepec, there is a 380 m long, curved tudinal and transversal slopes of the structur-
bridge. The 12.94 m wide roadway super- al geometry were compensated by the
structure was designed as a pre-tensioned, ST 100 falsework. Steel supports already on
double hollow box that was constructed in site could also be well integrated into the
ten concreting sections. superstructure. The cantilevered and external
PERI system components were exclusively web formwork of completely pre-assembled
used for the formwork and falsework: quickly VARIO units was placed on the falsework so
erected ST 100 stacking towers for the 13 m that only the coupling of the units had to be
high and 55 m long falsework in the first sec- carried out at a height of 11-13 m.
tion, flexible VARIO units as soffit, web and
cantilevered formwork. Only 3.55 m long The site executed the pro-
ject cost-effectively with
steel beams were needed as special parts 880 m2 of VARIO and
for rational construction. 8,000 m3 of ST 100 stack-
ing towers.
88
Superstructures/Falsework
12.94
Timesaving: the VARIO units of the can- The cantilevered and external web form-
tilevered and external web formwork can work can be perfectly adjusted to the
be moved with the PERI C-hook in one lift. slope by articulated couplings and heavy-
duty props.
This single-span bridge, located close to the The formwork bottom, on head spindles and
town of Graben-Neudorf, crosses the B35 GT 24 lattice girders, flowed exactly the
Federal Highway from Bruchsal to Germers- geometry of the ribbed slab which was to be
heim and serves as a flyover for a country concreted. Due to the 50 cm Rosett incre-
road. ments on the verticals as well as selective
positioning of ledgers and diagonals, an opti-
After both sets of piers were completed, a mal static working load of the falsework was
supporting scaffold system was required achieved. This also ensured that the amount
which allowed the cost-effective construction of materials actually used was that which
of the T-beam shaped superstructure cross- was only absolutely necessary.
section. The contractors decided in favour of
PERI UP Rosett.
90
Superstructures/Falsework
36.50
A B C
+ 4.79 m
± 0.00 m
37.32
0.47 1.15
0.47 1.15
0.88 1.15
2.00
2.00
2.00
4.86
4.80
4.44
4.39
4.38
4.38
Through the high rigidity On the longitudinal side of GT 24 lattice girders, used the exact cross-section of
of PERI UP, the number of the carriageway, an inte- as main and cross beams, the superstructure slab.
diagonals was kept to a grated 72 cm wide working form the basis of the form-
minimum. area with guardrails. work bottom and the nail-
disk-binder which provide
91
Czerniakowska Intersection, Warsaw, Poland
Problem-Free Construction
and Uninterrupted Traffic Flow
Cross-section of pre-
stressed hollow box
superstructure.
4,75 4,75
9,50
Warsaw’s road network is gradually being The requirements placed by the design and Through the use of HD 200 heavy duty props
upgraded to meet the demands of a modern- concrete surface finish of the viaduct piers and standard main beams, the “modular con-
day European city. Part of the Czerniakowska were met with VARIO GT 24 girder wall form- struction system” allowed an uninterrupted
intersection are two viaducts: the 430 m work, TRIO panel formwork and SRS steel flow of traffic during the whole time con-
long, 11.90 m wide CE-2 construction which circular column formwork. struction work was carried out.
links the city with the Ursynow district and
the 600 m long, 14.60 m high CE-3 which The pre-stressed hollow box construction for According to the site management, this
will connect the exit on the Siekierkowski the superstructure was formed with VARIO extraordinary achievement by PERI was com-
Bridge with the Wilanow suburb. GT 24 and MULTIFLEX using the ST 100 plimented off through the reliable material
stacking towers to safely transfer loads. logistics as well as comprehensive project
support from PERI Warsaw.
92
Superstructures/Falsework
City centre Support construction using standard parts from the HD 200 heavy duty
system. This ensures a safe transfer of loads during the building of the
superstructure. Furthermore, there was no interruptions to the flow of
traffic – up to 18,000 vehicles a day use this route.
CE-3
CE-2
Siekierkowski Bridge
CE-1
Ursynow Wilanow
(District) (District)
93
New railway bridge, Chomutov, Czech Republic
7.00
1.68
Site Manager,
Miroslav Parpel:
“With increasing height,
the steel sections take
considerably higher loads.
Assembly and handling is,
however, as easy and safe
as for the aluminium sec-
tions.”
Contractor: SSZ AG
Field service:
PERI Czech Republic, Jesenice
95
Federal Highway 13, Dresden – Berlin, Germany
The task:
10 pre-cast longitudinal beams (50 tonnes
each) had to be maintained in assembly posi-
tion until the concreting of the crossbeams
to the abutments and placing of the concrete
topping had been done. Span of the beams
was 22.30 m.
The solution:
Four main beam areas, with an approximate
height of 5.46 m each, were placed on the
abutments and central piers. For each main
beam area, 15 props were mounted which
could take a load of approx. 20 tonnes each.
They comprised of combined PERI HDS
sections 270, 90 and 30 and one HDK head
spindle each and one HDA lowering device.
Each of these components weighed less
than 30 kg.
Construction of a new bridge, part of the The latticed load-bearing structure comprised
connecting road between the town of of PERI SRU universal walers, rigid UK 70
Príbram and the village of Podlesí, had to be universal couplers as well as SLS heavy duty
carried out during 2003. spindles. Pre-assembly was simple and fast,
The foundations of the old bridge were and the construction was lifted into position
washed away during the floods in 1992 and by crane.
continued use of the bridge was no longer The 13-piece, 100 cm high trussed girder
possible. was placed on a double HD 200 main beam
with interconnected HD wedge lowering
For carrying out the construction work, PERI device boxes and horizontally stiffened with
engineers provided an interesting and unusu- bracket braces and tie rods.
Přemysl Mališ, Site Manager:
al solution for the required bridge falsework. “Together with PERI, we succeeded in
The complete superstructure was concreted Formwork comprising of GT 24 lattice girders erecting a simple support scaffold form-
in an elevated position in the first stage and, PERI AW slab edge trestle and plywood work construction across the river without
after striking, hydraulically lowered to its final supplied by the contractors completed the affecting its normal flow. The technology
also simplified the subsequent lowering
position. construction. of the bridge carriageway.”
98
Superstructures/Falsework
11.56 9.40
0.70
2.80
99
Wildwechsel Bridge, Rammenau, Saxony, Germany
On Federal Motorway 4 between Dresden In each case, four main beam areas made of
and Bautzen, a 56 m wide bridge construc- HD 200 heavy duty props with primary
tion for wild animals was built as a double beams formed the vertical load carrying sys-
span frame construction. tem for the superstructure and were braced
The abutment walls were formed together in pairs.
with the superstructure slab in one casting The cost of purchase and special elements The internal side formwork
segment. In addition, there had to be no was considerably reduced as approx. 90% for the abutments was
interruptions to the flow of traffic on the of the components used were rental parts. connected to the shoring
motorway during the whole construction and, similar to tunnel form-
work, was moved together.
period.
Contractor:
ZÜBLIN Sachsen GmbH
Field Service:
PERI Germany, Dresden
100
Superstructures/Formwork
17.68 17.68
101
A8 Motorway Junction, Pforzheim West, Germany
102
Superstructures/Formwork
103
Bridge over the River Tommarpsan, Simrishaun, Sweden
A new 36.70 m long road bridge was con- The units were prefabricated on the river whilst preparing and installing the steel
structed to carry the N4 highway over the bank to avoid assembling the scaffold over girders, the scaffold was being assembled.
Tommarpsan river. The basis of the shoring the water.
for the slab-and-beam cross-section was assembly of the scaffolding on flat ground
provided by steel girders. The rigidity of the PERI UP Rosett ledger was quicker and safer
connections enabled the prefabricated sec-
The assembly of the supporting scaffold was tions to be craned into position on the steel assembly teams could work independently
an opportunity to demonstrate the flexibility beams without any distortion. Pre-assembly of each other which avoided any downtime.
of the system with erection details provided with PERI UP Rosett provided three benefits
by PERI engineers. for the contractors:
13.80
104
Superstructures/Formwork
Johnny Anderson,
Senior Foreman and
Hans Norelius,
Project Manager, NCC:
“Due to the pre-assembled
craneable units and light-
weight PERI UP compo-
nents, we could achieve
extremely safe and fast
construction progress.
This was something we
couldn’t do with systems
we had used in the past.”
36,70
106
Superstructures/Formwork
2.70
1.15
7.03
107
Eisenbach Valley Bridge, Germany
12.65
4.99
108
Superstructures/Formwork
Contractor:
Joint Venture Kunstbauwerke Kutscheid
MAYREDER – ILBAU
Field Service:
PERI Germany, Willich and Weissenhorn
Parallel to the A 92 Federal Highway, the The trough slab required a formwork system 60 m long casting segment
Neufahrn ring road crosses the River Isar. which was light and easy to handle as the for webs and slab. The
stopend formwork was
A three-span railway bridge was constructed cross walls and end cross girder only had done by the contractors
with a total length of 186 m. small openings measuring 1.80 x 1.10 m. on-site.
At the PERI factory in Weissenhorn, the The contractors decided on MULTIPROP 350
VARIO basic elements for the external and props and additional MULTIPROP frame was
internal webs as well as the cantilever were used as bracing during assembly.
assembled. On site under the supervision of
a PERI engineer, the VARIO elements were
put together to form braced formwork-units.
The pre-assembly phase resulted in smooth
construction progress, time-consuming on-
site adjustments were not necessary and all
components were rentable and re-usable.
110
Superstructures/Formwork
Johann Magg,
Site Supervisor:
“The decision to use this
PERI solution was the right
one and construction work
progressed quickly with
the pre-assembled units.
Both the work preparation
and implementation by the
PERI engineers was per-
fect.”
10.72 10.72
6.20 6.20
35
35
4.79
4.05
4.79
4.05
35
35
4.49 4.49
111
Viaduct over the River Ebro, Saragossa, Spain
6.80 8.05
112
Superstructures/Formwork
546.00
113
Loewenberg Viaduct, Switzerland
cross-section construction.
Phase 1
Slab formwork with addi-
tional formwork for con-
structing the upturns.
4.10
11.43
3.80
+2.68
+2.50
+2.14
Phase 2
Special formwork for
the longitudinal girders
and cantilever with
internal formwork
2.13
1.98
±0
4.30
Phase 3
Formwork for
parapets and
guardrails
114
Superstructures/Formwork
H. Casandrey, Supervisor
115
Niessenbach Bridge, A2 Motorway, Austria
116
Superstructures/Cantilevered Parapets
117
Danube Bridge, A8 Motorway, Leipheim, Germany
118
Superstructures/Cantilevered Parapets
Generously-sized platforms
on the cantilevered parapet
formwork carriage provide
safe working conditions
which results in higher
productivity.
Contractor: BILFINGER+BERGER Bau AG
Munich branch / formwork construction,
Roxheim
Field Service:
PERI Germany, Munich and Weissenhorn
119
Railway Flyover, Karlsruhe, Germany
120
Superstructures/Cantilevered Parapets
39
55
1.40
121
New development on the B 312 highway, Iller Bridge, Berkheim, Germany
122
Superstructures/Cantilevered Parapets
123
Moldau Bridge, Czech Republic / Hessigheim Weir, Neckar, Germany
One of the advantages of the PERI UP mod- Movable suspended scaffold units for
ular scaffold system can be seen with the renovation work on the steelwork of this
beam bridge over the River Moldau in the
assembly of suspended scaffold. Czech Republic.
124
Superstructures/Special components
Integrated Lock
Reduces Assembly Time
126
Superstructures/Special components
Creating a cantilever by
means of a node brace.
When bridging existing road and rail routes, The result was a three-span bridge with From a static point of view, the best solution
there is one requirement which has priority 1 x 12 m and 2 x 14 m spans. PERI UP was to create three supported spans. The
over the rest – any interruptions to the standard components were used in the pre-assembled bridge sections were quickly
normal flow of traffic must be kept to an construction. craned into position at night.
absolute minimum. With this in mind, PERI
engineers in Barcelona decided on pre-
assembled sections which could be easily
craned into position.
Longitudinal section
The temporary bridge con-
struction formed with stan-
dard components out of
the PERI UP programme.
B
12.00 14.00 14.00
2.40
B
5.60
6.90
128
Superstructures/Special components
An easily erected 40 m
long public footbridge
using standard PERI UP
Rosett materials.
Section B–B
129
BAUMA footbridge, Munich, Germany
130
Superstructures/Special components
131
Gersbachtal Bridge, Pirmasens, Germany
5.00 5.00
0.50
2.50 2.00
133
Woronora Bridge, Sutherland, Australia
The Woronora Bridge connects the suburbs Hollow-box superstructure using the Positioning the pre-cast
reinforced concrete beams
of Menai and Sutherland with the southern incremental launching sequence: and assembly of the inter-
part of Sydney. The 500 m long construction Two 30 m long casting pits were used for nal web formwork in
was carried out as a hollow-box superstruc- constructing the superstructure. After finish- casting pit 1.
ture on nine piers of up to 36 m high using ing the slab and webs in the first section,
the incremental launching method. concreting of the carriageway slab follows in
the next cycle. The sections were launched
Piers: over the piers in a weekly cycle.
The hollow piers taper towards the top which
was achieved by combining VARIO elements
and TRIO filler plates. This meant that cross-
section adjustments from cycle to cycle
could be done without altering the VARIO
units. Externally, CB 240 climbing brackets
safely carried the formwork and reinforce-
ment loads as well as the concrete pressure
into the previous sections. Distribution
beams for moving two platforms simultane-
ously, saved time and crane capacity.
VARIO GT 24 climbing
formwork with TRIO filler
plates on CB brackets with
finishing platforms.
134
Superstructures/Cantilever launching method
Robin Watt,
Senior Project Manager:
“The PERI planning and
systems helped us enor-
mously in carrying out this
project. The piers were
easy and safe to construct
and we could complete
sections for the super-
structure in less than
seven days with only slight
modifications to the stan-
dard PERI components.”
Contractor:
Barclay Mowlem Construction, Sydney
Field Service and Design:
PERI Australia, Glendenning
Casting pit 2
Striking of web formwork followed by installa-
tion of partially pre-cast slabs between the
pre-cast beams. Afterwards, the cantilever
formwork is assembled and, finally, the road-
way is concreted. 20.77
135
Swinna Poreba, Poland
136
Superstructures/Cantilever launching method
K. Rogowski, Dipl.-Ing.:
“Thanks to the technical
support provided by PERI
Warsaw, we could achieve
excellent results and main-
tain the very tight sched-
ule.”
3.40
after completing the trough, the carriageway
slab was concreted (12.60 m width / 30 cm
thick). The 16 m long cycle could then be
launched hydraulically. To achieve the
required 500 m radius, the formwork panels
were assembled as a polygon.
137
Viaduto da Ribeira de Perofilho, Portugal
138
Superstructures/Mobile falsework
139
Viaduto da Ribeira de Perofilho, Portugal
Contractor: ABRANTINA, Lisbon The TT-shaped cross-section of the bridge superstructure After a short time, 1,000 m2 of formwork is folded up
Field service: PERI Portugal, Linda-a-Velha could be constructed with only two sections. again.
140
Superstructures/Mobile falsework
Phase 1:
Striking is carried out by
folding down the VARIO
units.
74.78
6.50
40.00 40.00
80.00
Phase 2:
For moving the complete
system, the VARIO units
remain lowered. This
process is done hydrauli-
cally in 1.40 m sections.
Phase 3:
Shuttering follows in the
reverse order to striking.
7.62
141
Bauerbach Valley Bridge, Mannheim-Stuttgart, Germany
Contractor:
Joint Venture Strabag,
Dyckerhoff & Widmann
Field service: PERI
Germany, Weissenhorn
143
Bridge over the River Lek, Vianen, Netherlands
The new Lekbrug development crosses the uninterrupted passage over the area. Lower-
River Lek and consists of seven spans with a ing of the lightweight components was done
total length of 532 m. A changing hollow box manually avoiding the need for expensive
cross-section with laterally mounted diagonal hydraulic equipment.
bracing carried the 29 m wide carriageway
slab. Internal formwork
The web heights as well as the angles
In addition to a cost-effective solution for the between bottom slab and web vary from sec-
foundations and piers using VARIO girder tion to section.
wall formwork, PERI engineers also came up Using PERI SRU walers, which could be
with a logical and sound concept for the bal- dismantled step by step, and two layers of
anced cantilever procedure: walers, compensating the changes in angles
on the bottom plate proved to be no prob-
External formwork lem. Here, too, moving was carried out inex-
The external web formwork was designed to pensively using a standard chain hoist.
adapt to the varying web heights from cycle
to cycle due to the different box girder cross- Reinforcement work had to be done sepa- Bottom view of bridge featur-
ing piers and both traffic lanes.
section dimensions. It projects the lower rately i.e. whilst the internal web formwork
working platform in the small height web on one side was closed it should be possible
areas and does not have to be converted. to do the reinforcement work on the other
The pre-cast columns for the carriageway and side. This ensured free access to the web.
web connection areas created discontinuity
for the forming of the slab. Due to this, PERI The PERI formwork solution shortened the
designed the slab formwork to fold down- planned weekly cycle by half a day.
wards behind the columns thus allowing an
144
Superstructures/Balanced cantilever method
Norbert Klopf,
Site Manager:
“I’ve worked with various to the next cycle. We
PERI systems over the achieved a fantastic sur-
past 15 years and the face quality which also
cooperation with PERI met the architect’s expec-
engineers has always been tations!”
very good. The balanced
cantilever construction with
folding technology allowed Contractor: Max Boegl, Neumarkt, Germany
us to pass over the pre- Field service: PERI Germany, Weissenhorn and
cast columns when moving PERI Netherlands, Schijndel
Efficient and economical: the formwork elements are fold- Cantilever formwork in the main section of the bridge.
ed manually when moving to the next cycle. This allows Beginning with the piers positioned close to the river
an uninterrupted passage over the pre-cast columns. banks, the pre-stressed box girder is formed and concret-
ed from both sides with an approx. 80 m long cantilever
until the structure joins over the middle of the river.
Cross-section of hollow
box superstructure in
setting position showing
maximum and minimum
web heights.
2.55
6.34
145
Skye Bridge, Scotland
5.90 5.90
4.68
8.55
3.87
The roadway slab was built in the form of a The upper carriage construction was moved
steel composite construction. For this, PERI hydraulically on roller bearings, the middle
engineers developed two mobile formwork carriage by means of winches on trolleys.
carriages. They began on the west bank of
the river and worked towards the centre of The actual roadway slab formwork consisted
the bridge in 10 m casting segments. of PERI PD 8 tables with MULTIFLEX girder
Each carriage comprised of four transverse formwork on the cantilever slabs as well as
and longitudinal lattice beams, and included SKYDECK on MULTIPROP props for the mid-
a middle carriage that was connected to the dle carriage area.
lattice beams by means of vertical tension
members. Most of the components came
Efficient and safe: GKW
from the HD 200 standard programme. This cantilevered parapet car-
resulted in cost reductions on the one hand, riage from the standard
and, on the other, the individual elements PERI programme.
could be transported more easily due to the
smaller sizes.
Assembly of SKYDECK
between the superstruc-
ture beams. The easy
handling characteristics of
SKYDECK accelerates the
forming of the carriageway
slab.
149
Railway Station Bridge, Zurich, Switzerland
The new 187 m long composite bridge span- The client, Swiss National Railways (SBB), Less than five hours was needed for lower-
ning the Zurich main station area replaced a requested a formwork solution which guaran- ing, moving and positioning of the carriage.
more than 100 year old, two lane steel teed an uninterrupted flow of normal rail
arched bridge. Thanks to the fanned arrange- traffic during the concreting of the slab.
ment of the tracks below, no obstructions
were encountered during construction. Thus, Very soon after receiving the order, PERI
the number of trains arriving and leaving the delivered an efficient formwork carriage con-
station could be increased. struction which was designed for casting
lengths of 10 metres. Without the help of
The steel composite construction comprised additional lifting equipment, the carriage was
of three launched box-type steel girders (each moved from cycle to cycle using an electric
2 m high) and a concrete slab. motor and carriage.
Winfried Bergande,
Supervisor:
“PERI delivered a fantastic
formwork solution. Without
having to interrupt normal
rail traffic, we were able to
achieve a regular 4-day
cycle throughout the whole
construction period for the
10 m casting steps.”
150
Superstructures/Bonded steel construction
151
High-Speed Rail Bridge, Ingolstadt, Germany
152
Superstructures/Bonded steel construction
5.92
153
Bridge over the Theiß, Oszlár, Hungary
154
Superstructures/Bonded steel construction
155
PERI International 42
19
20
22 32 44
34
18
38
11
52
6
21
01 PERI GmbH 5 1
Rudolf-Diesel-Strasse 17 46
89264 Weissenhorn
info @ peri.com 2 30
www.peri.com 3 16
13
29
28
9
53
24 48
4
41
61
33 12
156
44
36
43
7 23
50 51 10
37
39 54
40 57
60 56
49 47 59
58 35 55
66
65
63
14
15
62 26 64
27
31
45
25
157
Formwork
Scaffolding
Engineering