A. SUB STRUCTURE
1 Excavation and Masonry Works…… ETB 876,414.43
2 Concrete Works………………....... ETB 1,244,916.22
3 Masonry Works………………....... ETB 212,417.40
B. SUPER STRUCTURE
1 Concrete Works ............................. ETB 15,089,471.30
2 Block Works .................................. ETB 466,942.80
3 Almunium Works ........................... ETB 3,498,804.00
4 Finishing Works .............................. ETB 22,149,964.87
5 Painting Work ......................................... ETB 17,571,707.00
6 Electrical installation........................ ETB 961,175.00
7 Sanitary installation.......................... ETB 1,226,958.40
Sub-Total B ............ ETB 60,965,023.37
organic soil. Price also includes grabbing roots and tree stamps
where
such are encountered. m² 26 400 10,400.00
1.02 Bulk excavation to reduce level from the natural ground level to a 0.00
depth not exceeding 150cm. m³ 195 620.73 121,042.35
1.03 Excavate pit for isolated footing in ordinary soil to a depth not 0.00
exceeding 300cm starting from reduced level. m³ 260 196.8 51,168.00
1.04 Trench excavation for masonry wall in ordinary soil to a depth not 0.00
exceeding 80cm. m³ 230 125.7 28,911.00
1.05 Back fill around isolated footings, footing columns and around 0.00
masnory with selected material from off site and well ram in layers 0.00
every 20cm interval. m³ 520 582.32 302,806.40
1.06 Fill under ground floor slab with selected material. The filling shall 0.00
be performed in layers of 10cm with watering and consolidating each 0.00
layer properly. m³ 520 347.49 180,694.80
1.07 Cart away and spread surplus excavated material to municipality 0.00
approved fill site. m³ 85 1,023.23 86,974.55
1.08 25cm thick basaltic stone hardcore well rolled consolidated and 0.00
blinded with crushed stone. m² 203 465.11 94,417.33
This Chapter Total Carried to Summary………………………… 876,414.43
2. CONCRETE WORKS
Supply and cast 5cm thick lean concrete in C-7 concrete quality with
2.01
minimum cement content of 190Kg/ m3 :-
5. ALMUNIUM WORKS
Pricing Notes
Prices for windows and doors are to include for all sub-frames, cover
plates, glazing shims, tape, compound, draught strips and weather
gaskets and seals fitted into jambs, heads and thresholds etc.…
Prices for windows and doors are to include for any necessary
isolation strips, gaskets, sleeves etc… and coating of bitumen
solution necessary to prevent corrosion between dissimilar materials
Prices for windows and doors pointed with sealant are to include for
primer and backing materials as necessary.
Prices includes for openable windows and doors latches and locks
Prices to include for 30x3mm L-section aluminium for rain water
drip at soffit of all of exposed windows and doors.
Price shall include good quality iron mongery, door stopper,
cylindrical lock and handle (EU product)
m2
7. FINISHING WORKS
WALLS
PLASTER FOR WALL FINISHES
Pricing Note:-
Prices for plaster generally are to include all angles and stop beads,
mesh between two different structural elements.
Prices for plaster includes corner protection in 30x30x3mm steel
angle section with mesh to be embedded in plastering.
Price shall include 30x3mm L-Angle water drip on all exposed
window cill and window soffit.
Cement sand plaster ratio 1:3
Apply two coats plaster to prepare for tiling and other finishes
including cleaning the surface and making good of corners according
to specifications.
Plaster on external walls to be finished off with quartz plasters
m2
One mist coat and two full coats of emulsion paint on concrete
9.02
ceiling, underside of stair, exposed columns and beams m2 178 2,339.58 416,445.24
Location: - Adama , East Shewa Zone For Abay Bank S.C
Client: - Yonatan Amezene Page 6 of 35
Hotel BILL OF QUANTITIES AND SPECIFICATION
TOTAL TOTAL
BUDGET BUDGET
ITEM DISCRIPTION UNIT UNIT PRICE QUANTITY AMOUNT(BIRR)
Apply one coat of Quartz plaster on cleaned surface with
intermittent
drying. Material, texture and color to be approved by engineer
prior to application of plaster. Trowel apply material to plastered
external concrete and masonry walls as per specification. Price
9.03 includes all the necessary related civil works.
9. ELECTRICAL INSTALLATION
Supply and install :-
1 Power & Tele Intakes (Provisional Quantity) Manhole
Manhole in bricks and with concrete base internally of
1000x1000x1000mm including concrete cover with lifting hole.
a) Diameter 25 mm No
a) diameter 25mm No
Supply, install, test & commission uPVC (PN6) waste water drainage
and vent pipes according to where shown on the drawings, complete
with all the necessary connecting pieces, accessories & civil works
thereto.
a) Diameter 50 mm Ml 275.00 60.00 16,500.00
b) Diameter 75 mm Ml
b) Diameter 110 mm Ml 715.00 42.00 30,030.00
2 Supply and install Vent Caps made of rigid uPVC to be connected
to the roof terminal of vent pipe as shown on the riser diagram,
complete with all the necessary sealing, gaskets to roof water proofing
membrane including stainless steel screws/as required and all other
accessories.
a) Diameter 50mm No 250.00 1.00 250.00
b) Diameter 110mm No 500.00 1.00 500.00
3 Supply, install, test & commission uPVC (PN6) waste water drainage
from the manhole to the septic tank and storm water drainage from
ditch to municipal drain line and the the minimum slope as shown
on the drawing or natural ground slope whichever is greater on firm
bed of sand 150mm thick below and 200mm thick above te crown of
pipe in open ground.
Manhole
8 Construct circular sewer Man Hole made of RC concrete with
internal diameter of 600mm , 10mm thickness and 900mm(avg.
depth), Botom slab by mass concrete benching size diameter 700mm
and thikness 100mm concrete. 80mmTop RC slab with diameter
8mm reinforcement bar c/c 200mm both ways. The bottom slab
shall rest on 150mm thick well compacted selected material. Unit
price shall include excavation, cart-away, compaction and back-fill all
the nessecery works as required and all assistance civil works there to.
4 Kitchin Sink
Supply and fix Approved standard TEKA or Equivalent
stainless steel kitchen sink Grade SS-304 of complete
with chrome plated GROHE or Equivalent cold and hot
water mixing battery (chrome plated faucet), Chrome
plated brass Bell type smell trap, plug, chain holder,
drain pipe, mixing faucet, etc; and all other
accessories. Flexible hose to be GROHE or Equivalent
and should be capable of resisting pressure of 4 bar. No. 5700.00 12.00 68,400.00
Size: 1500 x 600 mm (Double Bowel)
5 Floor Drian
Supply, fix, test & commission approved quality Floor Drain made
of polished stainless steel complete with P-Smell trap (minimum
depth of 75mm) and all other necessary connecting fittings and
accessories for the proper installation and operation of the drain.
Ml
3 Supply and fix 6kg Dry CO2 Fire Extinguisher for ABCE class of
fire as where shown on the drawing in basement parking. The
material shall comply with TUV, BSI, NFPA or equivalent institution
certification and approval. Complete with approved standard hanging
and fixing material
Ml
4 PUMPS
Price shall also include fuel tank for stand-by pumps adequate atleast
for two hours, exhaust duct system for diesel stand-by pump and all
civil assistant works. The work shall be carried out in accordance
with the manufacturer's instruction and as shown on the drawings.
The price shall include all the necessary accessories required for the
proper operation of the system but not specified or shown on the
drawing. Manufacturing and test certificate shall be submitted and
approved by the consultant prior to installation or purchase. The Fire
pump set should have FM Approval, and UL Listed.
Main Electric pump'
Type: NAFFCO or Equivalent
Number of pumps = 1 Pc
Capacity: 22 liter/second, at head of 70 meter
Main Diesel Fire Pump ( including Exhaust duct)'
Type: NAFFCO or Equivalent
Number of pumps = 1
Capacity:22 liter/second, at head of 70 meter
Jocky Pump'
Type: NAFFCO or Equivalent
Number of pump = 1 Pc pcs
Capacity: 2 liter/second, at head of 72 meter
1 400.00
1.55 d=1.55m F-1 (20pcs)
620.73 m3 including working space 20 2.00 L=1.50+0.25+0.25=2.00m
2.00 w=1.50+0.25+0.25=2.00m
- m3
F-2 (20pcs)
20 1.60 L=1.10+0.25+0.25=1.60m
620.73 m3 (item 1-1.02) 1.60 w=1.10+0.25+0.25=1.60m
1.03…… Bulk excavation in weathered rock to a
depth not exceeding 1500mm to reduce level - m3
- m3 (item 1-1.06)
1 400.00 A=1852.00m2
0.00 d=0.00m
- m3 (item 1-1.03)
- m3 (item 1-1.04)
1.07…… Pit excavation in hard rock to a depth not 1.10……. Pit excavation in hard rock to a depth
exceeding 1500mm from reduced ground level. exceeding 1500mm but not exceeding 3000mm.
F-1 (20pcs)
20 2.00 L=1.50+0.25+0.25=2.00m F-1 (20pcs)
2.00 w=1.50+0.25+0.25=2.00m 20 2.00 L=1.50+0.25+0.25=2.00m
2.00 w=1.50+0.25+0.25=2.00m
- m3
F-2 (20pcs) - m3
20 1.60 L=1.10+0.25+0.25=1.60m F-2 (20pcs)
1.60 w=1.10+0.25+0.25=1.60m 20 1.60 L=1.10+0.25+0.25=1.60m
0.00 h=0.00m 1.60 w=1.10+0.25+0.25=1.60m
- m3 0.00 h=0.00m
- m3
- m3 (item 1-1.07)
- m3 (item 1-1.10)
1.08….. Pit excavation in ordinary soil to a depth
exceeding 1500mm but not exceeding 3000mm. 1.11…… Trench excavation in ordinary soil to a
depth not exceeding 1500mm from reduced ground
level.
F-1 (20pcs)
20 2.00 L=1.50+0.25+0.25=2.00m
2.00 w=1.50+0.25+0.25=2.00m Along Axis 1' & A-B
1 3.30 L=3.30m
- m3 1.40 w=0.90+0.25+0.25=1.40m
F-2 (20pcs) 1.45 d=1.45m
20 1.60 L=1.10+0.25+0.25=1.60m 6.70 m3
1.60 w=1.10+0.25+0.25=1.60m Along Axis 1' & B-C
0.00 h=0.00m 1 3.30 L=3.30m
- m3 1.40 w=0.90+0.25+0.25=1.40m
1.45 d=1.45m
- m3 (item 1-1.08) 6.70 m3
Along Axis 1' & C-D
1.09….. Pit excavation in weatherd rock to a depth 1 3.30 L=3.30m
exceeding 1500mm but not exceeding 3000mm. 1.40 w=0.90+0.25+0.25=1.40m
1.45 d=1.45m
6.70 m3
F-1 (20pcs) Along Axis 1' & D-E
20 2.00 L=1.50+0.25+0.25=2.00m 1 3.30 L=3.30m
2.00 w=1.50+0.25+0.25=2.00m 1.40 w=0.90+0.25+0.25=1.40m
1.45 d=1.45m
- m3 6.70 m3
F-2 (20pcs) Along Axis 1' & E-F
20 1.60 L=1.10+0.25+0.25=1.60m 1 3.30 L=3.30m
1.60 w=1.10+0.25+0.25=1.60m 1.40 w=0.90+0.25+0.25=1.40m
0.00 h=0.00m 1.45 d=1.45m
- m3 6.70 m3
- m3 (item 1-1.09)
1.12…Back fill around foundation with selected Above 0+00 and below +1.20m
material from from site and compact in layers not 1 33.41 L=13.11+20.3=33.41m
exceeding 200mm thick. 2.30 w=2.30m
1.35 d=1.35m
103.74 m3
Fill from Gread Beam Bottem to RL Under ramp
under grade through out floor area 0.5 L=5.504+5.46+5.23=16.19m
16.19
w=2.30m
1 400.00 2.30 d=1.35m
1.00 d=1.00m 1.35 m3
400.00 25.14
196.80 m3 (item 1.05)
Fill under pavement
347.49 m3 (item 1-1.14)
A=277.5m2
1 170.88
d=0.4m
0.40
m3
68.35 m3 for trench working space ( item 1.11) 1.15……. Load and cart away surplus excavated
39.34 125.7-86.36m3 =39.34m3 material to an appropriate trip.
- m3 (item 1-1.13)
1.16…250mm thick basaltic stone hardcore well Along Axis 1' & C-D
rolled, consolidated and blinded with crushed 1 4.70 L=4.70m
stone . 0.90 w=0.90m
4.23 m2
Along Axis 1' & D-E
Along Axis b/n A-D & 1-7 and mirror 1 4.70 L=4.70m
w=0.90m
1 14.70 L=14.70m 0.90
31.64 w=31.64m m2
4.23
Along Axis 1' & E-F
465.11 m2 L=4.70m
1 4.70 w=0.90m
0.90 m2
4.23 Along Axis 1' & F-G
L=4.70m
1
4.70 w=0.90m
0.90 m2
4.23 Along Axis 11 & A-B
L=4.70m
1 w=1.00m
4.70
m2
1.00
Along Axis 11 & B-C
4.70
L=4.70m
1 w=1.00m
4.70 m2
1.00 Along Axis 11 & C-D
465.11 m2 (item 1-1.16) 4.70 L=4.70m
1 w=1.00m
2.0 CONCRETE WORK 4.70 m2
1.00 Along Axis 11 & D-E
2.01…. 50 mm lean concrete quality C-5, with 4.70 L=4.70m
minimum cement content of 150 kg /m3, of 1 w=1.00m
concrete: 4.70 m2
1.00 Along Axis 11 & E-F
a) Under Footings 4.70 L=4.70m
1 w=1.00m
m2
F-1 (43pcs) 4.70
Along Axis 11 & F-G
20 1.50 L=1.50m 1.00
L=4.70m
1.50 w=1.50m 4.70 w=1.00m
45.00 m2 1
m2
F-2 (12pcs) 4.70 Along Axis 11 & G-G'
20 1.10 L=1.10m 1.00 L=2.20m
1.10 w=1.10m 4.70 w=1.00m
m2 1
24.20 m2
69.20 m2 (item 2-2.01a) 2.20 Along Axis G & 7'-8
under massonary 1.00 L=2.85m
Along Axis 1' & A-B 2.20 w=0.90m
1 1 m2
4.70 L=4.70m
0.90 w=0.90m 2.85
4.23 m2 0.90
Along Axis 1' & B-C 2.57
1 L=4.70m
4.70
w=0.90m
0.90 m2
4.23
c) To Grade beams
1.10
Submitted by Contractor: Checked by: Approved by:
Proj/Site Engineer: Assistant Resident Engineer: Client Proj. Eng.:
Signature: Resident Engineer: Signature:
Date : Date : Date :
Page 25 of 35
3. MASONRY WORK
80.31 m3
Deduction Of Gread Beam
Along Axis G And 1
-9 4.70 L=4.70m
0.30 w=0.30m
0.50 d=0.50m
(6.35) m3
B. SUPER STRUCTURE
1. CONCRETE WORKS
6 1 15.60 On Axis C Provide, cut and fix in position sawn Zigba wood or
0.50 steel formwork which ever appropriate, in
0.30 a) Col on Gd, 1st…. & 5th floor
14.04 m3 C- 50x50 cm
6 2 16.80 On Axis D & E 6 26 1.80
0.50 2.70
0.30 758.16 m2
30.24 m3 C- 40x40 cm
6
6 1 17.45 On Axis F 4 1.60
0.50 2.70
0.30 15.71 m3 103.68 m2
6 1 17.75 On Axis F'
0.50 861.84 m2 ( Total Area of Formwork)
0.30 15.98 m3
6 -26 0.50 DDT the Volume of Concrete b) Floor Beam on Gd, 1st…. & 5th floor
6
0.50 2 29.95 On Axis 1 & 4'
0.50 (19.50) m3 6 1.00 359.40 m2
6 -4 0.40 DDT the Volume of Concrete 3 31.45 On Axis 2, 3 & 4
0.40 6 1.00 566.10 m2
0.50 (1.92) m3 2 16.50 On Axis A & B
54.55 m3 ( Total Volume of Concrete Beam work) 1.00 198.00 m2
6
c) In lift shear wall on Gd, 1st…. & 5th floor 1 15.60 On Axis C
1 8.00 Internally and Externally 1.00 93.60 m2
6 6
0.20 2 16.80 On Axis D & E
3.05 29.28 m3 6 1.00 201.60 m2
6 1 8.00 Internally and Externally 1 17.45 On Axis F
0.20 6 1.00 104.70 m2
3.05 29.28 m3 1 17.75 On Axis F'
DDT Vol of Door 6 106.50 m2
6 -1 0.70 1.00
0.20 6 -26 0.50 DDT the Volume of Concrete
2.10 (1.76) m3 1.00 (78.00) m2
56.80 m3 ( Total Volume of Concrete work) -4 0.40 DDT the Volume of Concrete
e) In Stair Case on Gd, 1st…. & 5th floor 1.00 (9.60) m2
1,542.30 m2 ( Total Area of Formwork)
6
6 1 8.00 waste c) In lift shear wall on Gd, 1st…. & 5th floor
1.00 1 16.00 Internally and Externally
DDT the External Plastering porcelain tiles floor finish and skirting