TIME SCHEDULE / S CURVE

PEKERJAAN : GEDUNG AULA JASA RAHARJA


LOKASI : Jl. HR.Rasuna Said Kav.C-2 Kuningan 12920 Jakarta Selatan DKI Jakarta

May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23


BOBOT 1 2 3 4 5 6 7 MASA PEMELIHARAAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 90 Hari Kalender
NO URAIAN PEKERJAAN 24 31 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13
30 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19
(%) 22-May 29-May 5-Jun 12-Jun 19-Jun 26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct 30-Oct 6-Nov 13-Nov BLN KE
28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 1 2 3

100,0% 100,0% 100,0% 100,0%


1 PREPARATION
KICK OFF MEETING
WORKSHOP & CLARIFICATION DESIGN 95,4%

SHOP DRAWING & APPROVAL TIDAK USAH ADA


MATERIAL SAMPLE & APPROVAL 90,2%

2 PRE CONSTRUCTION 0,80%


SITE HANDOVER
83,8%
SITE PROTECTION
SITE MARKING & APPROVAL
LIGHTING & POWER FOR CONSTRUCTION
TIDAK USAH ADA
77,4%
GENERAL CLEANING & RUBBISH REMOVAL
PPE & SAFETY EQUIPMENT
MATERIAL MOBILIZATION & DEMOBILIZATION 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07%
71,0%
INSURANCE - CONTRACTOR'S ALL RISK, THIRD PARTY LIABILITY

3 LONG LEAD MATERIAL


TIDAK USAH ADA 64,6%

4 PRODUCTION & DELIVERY

5 STRUCTURE 57,7%
STRUCTURE AULA
REINFORCEMENT PARTITION 0,28% 0,09% 0,09% 0,09%
REINFORCEMENT CEILING 2,07% 0,41% 0,41% 0,41% 0,41% 0,41%
50,7%
REINFORCEMENT COLUMN & SLAB 0,59% 0,10% 0,10% 0,10% 0,10% 0,10% 0,10%
REINFORCEMENT COLUMN FIRST FLOOR 0,65% 0,13% 0,13% 0,13% 0,13% 0,13%
REINFORCEMENT GRIDER 1,37% 0,34% 0,34% 0,34% 0,34%
STRUCTURE LOBBY 43,3%
STEEL STRUCTURE & COLUMN FOR HOME LIFT 1,29% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14%
REINFORCEMENT STAIR & STEEL STRUCTURE 0,76% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08%
STRAUSS PILE 0,11% 0,04% 0,04% 0,04%
LOBBY STRUCTURE STAIRS 36,0%
1,13% 0,13% 0,13% 0,13% 0,13% 0,13% 0,13% 0,13% 0,13% 0,13%

6 FIT OUT
ARCHITECTURE INTERIOR
DIRINCI (DINDING, LANTAI,
24,71%
PLAFOND, KUSEN) 2,06%
29,1% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06%
LOBBY 17,54% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25% 1,25%
24,8%
7 DRAINASE & LANDSCAPE 4,25% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35% 0,35%
20,6%
8 MEP
AULA DIRINCI (LIGHTING, AUDIO VIDEO,
43,91%CCTV, DLL) 2,20% 2,20% 2,20% 2,20% 2,20%
16,0%
2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20% 2,20%
LOBBY 0,56% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06% 0,06%

9 PROJECT HANDOVER 11,2%


FINAL CLEANING BEFORE COMPLETION
TEST COMMISSIONING 6,5%
JOIN INSPECTION & DEFFECT RECTIFICATION
PROJECT COMPLETION 3,20%
PROJECT HANDOVER 0,21% 0,28% 0,48%
0,07% 0,14%

100%
RENCANA PROGRESS MINGGUAN 0,07% 0,07% 0,07% 0,07% 0,20% 2,72% 3,27% 4,76% 4,73% 4,60% 4,26% 4,26% 6,94% 7,32% 7,32% 7,02% 6,87% 6,41% 6,41% 6,41% 6,41% 5,16% 4,69% - - -
RENCANA KOMULATIF PROGRESS MINGGUAN - 0,07% 0,14% 0,21% 0,28% 0,48% 3,20% 6,5% 11,2% 16,0% 20,6% 24,8% 29,1% 36,0% 43,3% 50,7% 57,7% 64,6% 71,0% 77,4% 83,8% 90,2% 95,4% 100,0% 100,0% 100,0% 100,0% TIDAK USAH ADA
PROGRESS AKTUAL MINGGUAN 0,00% 0,11% 0,00% 0,00%
KOMULATIF PROGRESS AKTUAL MINGGUAN 0,00% 0,11% 0,11% 0,11%
DEVIASI 0,07% 0,03% 0,10% 0,17%

Jakarta,
PT. Gema Grahasarana Tbk

KOLOM TTD KOLOM TTD Juhendi KOLOM TTD


Diajukan DiPeriksa
Project Manager
DiSetujui
Kontraktor Konsultan Pemberi Tuga