You are on page 1of 2

risk management: demolition

Demolition – taking into account any other buildings


that may have stood there before. If, for
example, a gasworks installation stood in
the same spot previously, flammable

assessing the risks and toxins that could easily ignite, such as
toluene, may still be present in the
ground.
Following on from the structural

planning for safety analysis and of equal importance, is to


ensure that any parties requiring notifi-
cation, such as local authorities and in
particular the environmental health
officer, are properly informed before the
demolition process is commenced, as the
demolition techniques that will be
John Thoday, Managing Director of The Health & Safety allowed will vary from area to area. In
People, outlines the safety issues that structural engineers many densely populated city or urban
areas, for example, restrictions may be
should be aware of during a demolition project imposed to control noise or air pollution,
which will influence the type of demoli-
tion technique selected. A more

D
emolition work can be a very safety issues at each stage of the demoli- commonly used demolition method
dangerous activity if it is not tion process and are in a unique position chosen for these heavily built-up loca-
handled in the correct manner. to reduce the risks that arise. They have tions is deconstruction. This process will
Only by conducting a thorough risk a key role to play in providing involve the careful bit-by-bit dismantling
assessment of all the work-related information for the initial health and of a structure with a wide range of
dangers, identifying the possible hazards safety plan. Structural engineers are machines from hand-held breakers to
at the worksite and of the activities to be ideally placed to fulfil this role due to the cranes.
carried out, is the process made safer. skills and knowledge they possess. Not The possible collapse mechanism of the
All demolition works fall within the only do they have a thorough under- structure is a further determinant in
scope of the Construction (Design and standing of the design and materials deciding which demolition technique to
Management) Regulations 1994 (CDM). used in a wide range of structures, they use. The structural engineer will be
Therefore before a demolition project also have an appreciation of the weight perfectly placed to assess the behaviour
begins a competent planning supervisor load that each building can withstand, of a structure during its collapse and will
must be appointed, in order to ensure putting them in a perfect position to make suggestions regarding the safest
that all those involved in the design influence the reduction of risks. and most efficient method to protect
phase of the project pay adequate atten- surrounding properties. The structural
tion to reducing risks, both to the workers Structural analysis engineer’s knowledge is also crucial
involved in the project and to the general The first stage in the demolition process during the pre-weakening stage, where
public. The planning supervisor is respon- involves an initial structural analysis of inspections can highlight whether any
sible for ensuring that an initial health the building to be demolished and an structural members can be removed to
and safety plan is drawn up before any identification of any potential hazards maximise the overall effectiveness of the
contractors are appointed to carry out the such as the presence of hazardous mate- actual demolition action, without affect-
work. This plan is designed to draw rials or contaminants. For example, it is ing the short-term stability of the struc-
together all the information gathered not uncommon for older buildings to ture.
from the client and the designers during contain asbestos in insulating board, The choice of demolition technique is
the early planning stages of the project, cladding, flooring or roofing materials. not a precise science, however, and those
in order that health and safety issues are The whole investigation process will be parties responsible for the final decision
made clear to potential contractors. extremely detailed, even analysing the may choose a method simply because it
Designers are expected to address land on which a structure stands and was used successfully on a similar struc-
ture in the past.
Before the demolition process begins
an assigned party (the Principal
Contractor) needs to be appointed to take
responsibility for health and safety
during the complete duration of the
demolition work. The Principal
Contractor assumes responsibility for the
health and safety of those parties
involved, such as demolition or sub-
contractors and also those indirectly
involved, such as members of the public.
In addition to the CDM Regulations
which place a number of requirements on
those nominated as responsible for health
and safety on a project, there is also an
obligation to comply with a number of
other regulations. These include the
Management of Health and Safety at
Work Regulations 1999, Manual
Car park being Handling Operations Regulations 1992,
demolished Personal Protective Equipment at Work
(Photo courtesy Regulations 1992, Construction (Health,
Babtie) Safety and Welfare) Regulations 1996,

3 August 2004 – The Structural Engineer|19


risk management: demolition

Provision and Use of Work Equipment vibration caused by these power tools can
Regulations 1998, Lifting Operations and lead to permanently disabling injuries in
Lifting Equipment Regulations 1998 and the hands and arms of users, including
the Reporting of Injuries, Diseases and conditions such as vibration white finger
Dangerous Occurrences Regulations and carpal tunnel syndrome.
1995. Advice on how to reduce the threat is
These requirements were put into now available. For example, the HSE is
place to improve the overall management encouraging employers to manage the
and co-ordination of health, safety and health risks posed to their employees
welfare throughout all stages of a from hand-arm vibration at work. It
construction or demolition project. recommends a number of steps. Firstly,
Equally important is adherence to the many manufacturers are now recognising
British Standards codes of practice, the risk that high power tools present
particularly BS 6187:2000, the code of and many now offer products that emit
practice for demolition work. lower levels of vibration, but it would
After the designers’ assessment of the require a bit of research to identify these.
risks, the contractors involved in the A small opening • the designed drop spot where the bulk Alternatively, best practice procedures
project also need to conduct their own approx. 20ft of the structure is designed to drop; should be put into place limiting the
assessments of the risks involved in their wide, was left for • a predicted debris location, as the zone amount of exposure time each individual
work; ideally they will seek the advice of the rubble to where the remainder of the debris from has with these types of power tools.
the structural engineer. Once these risk leave the site the structure is likely to come to rest; Rotation schemes can be implemented to
assessments have been completed, docu- (Photo courtesy • a buffer area between the predicted ensure that users are regularly swapped
mentation needs to be drawn up in the Babtie) debris area and the exclusion zone over whilst using the same piece of equip-
form of a method statement to provide all perimeter. ment.
those parties involved in the demolition In general, however, the demolition
process with a clear outline of all the This advice certainly helps but there are industry should be praised for the health
procedures they will have to undertake no guidelines regarding the size of the and safety standards that it maintains on
and any potential hazards or problems four areas that make up this total exclu- site. Generally, it is safer to venture on to
they may encounter. It will summarise sion area. It is entirely up to the individ- a demolition site than a construction site.
what they are going to do, how they are ual to make his/her assessment on the It appears that the more obvious the
going to do it and the safety implications day. dangers the greater the likelihood that
of each individual activity. It may sound an inherent safety culture will develop.
simple, but it is the key to their devising Other considerations Credit also needs to be given to the
a safe method of work. Other areas to consider in regard to work developments in technology that have
Once the technique for demolition has on the demolition site are the wearing of also made demolition work safer. More
been chosen an initial preparation of the personal protective equipment (PPE) and demolition work is now done by machines
building should be conducted before the the safe operation of equipment. In the than ever before, including high-reach
actual demolition is commenced. This will area of PPE, there is advice available machines, tower and high cranes,
involve the decommissioning and soft regarding the types of clothing that can hydraulic attachments and even remotely
stripping of any materials, fixtures and be worn for added protection, but this controlled machines and robotic devices
fittings from the building, which could tends to be limited. The Health & Safety which take people away from the front
involve anything from elevator lifts to Executive issues guidance notes for the line of the demolition work site.
communications equipment. It is essen- wearing of safety helmets in the construc- The creation of a health and safety
tial to ensure that any services such as tion industry, which is of equal impor- plan and an accurate assessment of the
gas and electricity are disconnected tance on the demolition site, but less risks before commencing a demolition
before the demolition process is information is available regarding protec- project is absolutely crucial if the process
commenced. tion for other areas of the body. is to be a smooth one. However, it is a
Yet it soon becomes obvious after the common misconception that the extra
risk assessment process that workers will time taken at the beginning of a project
‘It appears that the more obvious require further protection at the demoli- to implement a health and safety plan
tion work site. One such area concerns will actually lengthen the whole
the dangers the greater the the wearing of respiratory protection. It is timescale of that project; the opposite is
essential that the correct types of mask actually true. Time-savings can be
likelihood that an inherent safety are worn during and in the aftermath of achieved as it is less likely that problems
the demolition process and that they are will be encountered if they are already
culture will develop’ robust enough to protect against the highlighted.
presence of contaminants. For some types In the long run the implementation of
Demolition zones of work, particularly asbestos removal an effective health and safety plan not
If the explosive charge demolition tech- operations, specialised respirators will be only protects all those professionals
nique is selected it is essential that required. Additionally, although it may involved in a project but also improves
adequate exclusion zones are put into seem obvious, the wearing of high visibil- their reputation, as there will be fewer
place. However, the size of these exclusion ity clothing is also critical to ensure that accidents on site. As a consequence they
zones is often subject to personal inter- all workers on site can be clearly seen at will be more likely to pick up repeat
pretation. There are sources of guidance all times. The correct specification of PPE business. se
on how to minimise the risks from such a is vital and it is crucial that those individ-
demolition technique. For example, The uals assigned responsibility for PPE • Further information on health and
Health and Safety Executive (HSE) before a demolition project begins, ensure safety within the demolition process
provides best practice guidelines on the that everyone on site has the right from: The Health & Safety Executive
use of safe exclusion zones when employ- protection. (www.hse.gov.uk/pubns/conindex.htm);
ing explosive charges for demolition, Careful thought should also be given to The Health & Safety People (16A Market
which recommend exclusion zones to the types of equipment used during Square, Sandy, Beds, SG19 1HU; tel:
consist of four component parts: demolition work. For example, the risk to 01767 682 800; email:
• the plan area, covering that area of the workers regularly using hand held break- enquiries@healthandsafetypeople.com;
structure to be demolished; ers is very real. Constant exposure to the web: www.healthandsafetypeople.com).

20|The Structural Engineer – 3 August 2004

You might also like