1 Initial design HW/SW specification for Core, RNC and TRS, including 1.1. ODF/DDF planning Traffic modeling and basic capacity dimensioning for RNC and 1.3 Core as well as IP Backbone network plus IP RAN 2 CS Core design 2xMSSs, 4xMGWs 2.1 VoIP Server HLD 2.2 Specification 2.3 Logical interface planning 2.4 CS Core nodes interconnection planning 2.5 Databuilding 3 PS Core design 2xGGSN, 3xSGSN 3.1 HLD 3.2 Specification 3.3 Logical interface planning 3.4 PS Core nodes interconnection planning 3.5 Databuilding 4 RNC design 4xRNCs 4.1 HLD 4.2 Specification 4.3 Logical interface planning 4.4 RNC/MGW/MSS/SGSN/GGSN nodes interconnection planning 4.5 Databuilding 5 IP backbone/backhaul design 51 HLD 5.2 Specification 5.3 Links capacity verification (within Core, between Core and RAN) 5.5 RAN/Core nodes interconnection planning
5.6 IP network drawings
6 Microwave planning 6.1 HLD 6.2 Specification 6.3 Links capacity verification (within Core, between Core and RAN) 7 Radio planning 7.1 Radio parameters 7.2 XML preparation Integration planning and implementation between PS, CS and IP 8 Integration planning networks 8.1 Drafting PATs for acceptance 8.2 Benchmarking QoS parameters 9 First Call Making of first call on the network 9.1 Verifying network quality on the services offered SHARE OF RESPONSIBILITIES
Share of responsibilities between Pulsmade (P) and Tagtel Communication (T)
# Work description Responsible
1.1 Project Project plan development P 1.2 management Project plan approval T 1.3 Acceptance procedure for design team work’s outcome P 1.4 Design team deliverables P 1.5 Acceptance procedure approval T 2.1 Input data for List of sites and number of nodes for CS Core, PS Core, T network design RNCs, NodeBs, IP backbone and backhaul 2.2 CS/PS traffic model and user profile’s traffic P T 2.3 Access to NetACT: CM Operation Manager, WBTS Site P T Manager, Reporting Suite/Report Builder, Application Launcher. 2.4 HW/SW specification for CS/PS Core, RNC, NodeBs, IP P T backbone and backhaul, DDF/ODF 2.5 3G Site list with azimuths, coordinates, Site ID RNC ID T WBTS ID WCEL ID Latitude, Longitude, Azim height tilt
2.6 Core and RNC rooms dimensions T
2.7 Digital maps for planning tool T 2.8 Power consumption of the RNCs and Core equipment T 2.9 Naming, numbering and general info for RAN and CS/PS P T Core (nodes IDs, nodes names, ip supernets, LACs, RACs, SPCs etc.) 2.10 Numbering plan, roaming info for CS/PS Core P T 2.11 Interconnection plans with PSTN, PLMN and Internet P T 2.12 Interconnection with OSS NetAct T 2.13 CS/PS/RNC/IP BB dimensioning P 2.14 RNCs and CS/PS Core layouts P T 3.1 Synchronization Network diagram in terms of synch-signal delivery to RAN, P T CS Core, PS Core, ToP 3.2 RNC/access Microwave radio (MWR) planning P 3.3 transmission Iub over IP planning P design 3.4 IuCS, IuPS and Iur over IP planning P 3.5 ODF/DDF planning for RNC sites P 3.6 ODF/DDF planning for NodeBs sites P 3.7 Network diagram in terms of RNC P 3.8 Network diagram in terms of NodeBs and MWR P 3.9 RNCs databuilds P 3.10 NodeBs databuilds P 3.11 MWR databuilds P 3.12 Acceptance of the RNCs and NodeBs design results T 4.1 CS Core design B,C, D, F, Mc, Nb, Nc, IuCS over IP planning P 4.2 ODF/DDF planning for MSS/MGW/HLR sites P 4.3 Network diagram in terms of MSS/MGW/HLR P 4.4 MSS databuild P 4.5 MGWs databuilds P 4.6 HLR databuild P 4.7 Billing design P 4.8 Acceptance of the MSSs and MGWs design results T 5.1 PS Core design Gi, Gn, Gr, Gs, IuPS over IP planning P 5.2 ODF/DDF planning for SGSN/GGSN sites P T 5.3 Network diagram in terms of SGSN/GGSN P 5.4 SGSNs databuilds P 5.5 GGSNs databuilds P 5.6 Billing design P 5.7 Acceptance of the SGSNs and GGSNs design results T 6.1 IP backbone and ODF/DDF planning for IP backbone and backhaul sites P 6.2 backhaul design Network diagram in terms of IP backbone and backhaul for P RAN, CS/PS Core 6.3 Cisco routers and switches databuilds P 6.4 Acceptance of the IP Backbone and Backhaul design results T 7.1 RF planning RNC XML database P
7.2 Node B xmls P
7.3 Input data for RF planning (maps, tilts, tss data, ) T
8.1 MW planning MW integration data P
8.2 Maps for planning, TSS data, LOS T
8.3 MW network architecture P
9.1 First Call Making a first call on the network P