GUARD HOUSE
PROPOSED TO DEMOLISH
EXISTING CONCRETE STAIRS
2
2100 EQUIPMENT ROOM PROPOSED TO RELOCATE
EXISTING GATE
FUEL
TANK
EMPTY BIN
50 KVA
GENSET
4620
EDP
MTS
ECB-1
ATS MDP
CR
5 2X25 KVA
POLE MOUNTED
TRANSFORMER
PLDT CANLUBANG
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-01
GENERAL NOTES, VICINITY MAP &
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: EXISTING SITE DEVELOPMENT PLAN
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
4250 3800 4250
A B C D E
A-1 C-1 C-2 C-3
2400 1365 10635 7700
2000
1
1500
GUARD HOUSE
3750 PROPOSED
COMFORT ROOM
2 RELOCATED EXISTING
MAIN GATE
2100 EQUIPMENT ROOM
200
3
400
E.F. E.F.
3' 1650
PROP. 500L
FUEL TANK
1000 800
1000
1200
4
900 900
132KW GENSET
132KW GENSET
650
600 600 1300 500
PROPOSED
2525
PROP. ACU
MAIN PANEL
PROPOSED
EXTENDED DCPDB EQUIPMENT
1200
PROP. DCPDB
LOT 3 20AT, 230V, 2P
1000 FUTURE FUTURE FUTURE FUTURE FUTURE FUTURE FEED A 1&2 NEMA 1 ECB 2500
EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT PROP. DCPDB 336
FEED B 3&4 2900
2500
STACU 1
PROP.
450
5TR
20AT, 230V, 2P
506
PROP. 5TR
NEMA 1 ECB
1500
ACCU 1
4'
STACU 2
PROP.
288
5TR
4620
PROPOSED 2000L
5TR (STANDBY)
288
STACU 3
PROP.
NEMA4X ECB 1
800 FUTURE FUTURE FUTURE FUTURE FUTURE FUTURE
PROPOSED 1000A
RECTIFIER 600
2525
EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT 20AT, 230V, 2P 40AT, 230V 1100 1520 800 1520 1100
SYSTEM NEMA 1 ECB
NEMA4X ECB 2 & 3
2500
ACCU 2 & 3
PROP. 5TR
PROPOSED PROPOSED
FUTURE FUTURE BATTERY 200AH BATTERY 200AH 600 750
BATTERY BATTERY EXP. TO 1000AH EXP. TO 1000AH 600 600 1300 936
AC COMPLEMENT ELP
400
300 200
600 600 1100
336 500 800 800 800 800 800 800
5 4"
PROPOSED 3x50KVA
TRANSFORMER
SCHEDULE OF FINISHES
PLDT CANLUBANG
REMARKS BRAND
GENSET PAD
PLAIN CEMENT PLASTERED PAINTED FINISH
ALL CONC, PLASTER MIXED W/ SAHARA INTEGRAL WATERPROOFING
EPOXY PAINT
OFF WHITE
PLDT BLUE
-
-
SAME
SAME
-
-
BOYSEN, DUTCH BOY OR APPROVED EQUAL
METAL LOUVER PAINTED (ENAMEL PAINT) W/ RED LEAD PRIMER PLDT BLUE - SAME - BOYSEN, DUTCH BOY OR APPROVED EQUAL
CEILING PLAIN CEMENT PLASTERED PAINTED FINISH OFF WHITE - SAME - BOYSEN, DUTCH BOY OR APPROVED EQUAL
FLOOR PLATFORM EPOXY PAINT PLDT BLUE - SAME - BOYSEN, DUTCH BOY OR APPROVED EQUAL
ROOF SLAB HYDROFLEX BITUMEN MEMBRANE BLACK SUBMIT SAMPLE FOR APPROVAL BOYSEN, DUTCH BOY OR APPROVED EQUAL
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-02
PROPOSE SITE DEVELOPMENT PLAN
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: CONTRACTOR'S SCOPE OF WORKS, SCHEDULE OF FINISHES
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
PLDT CANLUBANG
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-03
ISOMETRIC VIEW (EQUIPMENT ROOM)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: DETAIL DESIGN
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
A-1 C-1 C-2 C-3
A-1 C-1 C-2 C-3
4250 3800 4250
4250 3800 4250
900 900
DD DD
600 600
650
1300
ROOF LINE
STORAGE ROOM
2525
STORAGE ROOM
2525
PROP. ACU
MAIN PANEL
PROPOSED 1200
EXTENDED DCPDB EQUIPMENT
PROP. DCPDB
FUTURE LOT 3 20AT, 230V, 2P
1000 FUTURE FUTURE FUTURE FUTURE FUTURE FEED A 1&2 NEMA 1 ECB
EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT PROP. DCPDB
336
FEED B 3&4
STACU 1
PROP.
450
5TR
20AT, 230V, 2P
506
PROP. 5TR
NEMA 1 ECB
ACCU 1
4'
STACU 2
4'
PROP.
288
5TR
5TR (STANDBY)
288
STACU 3
PROP.
506 40AT, 230V
NEMA4X ECB 1
800 FUTURE FUTURE FUTURE FUTURE FUTURE FUTURE
PROPOSED 1000A
RECTIFIER 600
2525
EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT EQUIPMENT 20AT, 230V, 2P 40AT, 230V
SYSTEM NEMA 1 ECB
NEMA4X ECB 2 & 3
2525
BATTERY ROOM EQUIPMENT ROOM
ACCU 2 & 3
PROP. 5TR
FUTURE
BATTERY
FUTURE
BATTERY
PROPOSED PROPOSED
BATTERY 200AH BATTERY 200AH
EXP. TO 1000AH EXP. TO 1000AH
600
600 600
750
1300
WALL
936
AC COMPLEMENT
LINE BELOW
300
600 600 1100
336
DD
4" 4"
PLDT CANLUBANG
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-04
GROUND FLOOR PLAN (NEW EQUIPMENT BUILDING)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: ROOF DECK PLAN (NEW EQUIPMENT BUILDING)
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
C-3 C-2 C-1 A-1 A-1 C-1 C-2 C-3
12300 12300
4250 3800 4250 4250 3800 4250
900 900
1400
3500
2100
800 800
900 900
3500
4300
800 800
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-05
ELEVATION VIEW (NEW EQUIPMENT BUILDING)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
A-1 C-1 C-2 C-3 A-1 C-1 C-2 C-3
RB-3
RB-3
RB-3
RB-3
WF-1 C-1/F-1
3' 3' RB-1 RB-1 RB-1 RB-3
RB-1
RB-1
RB-1
WF-1
WF-1
2525
2525
WF-1
mm FILL
mmØ @
RB-2
4' 4' RB-1 RB-3
WF-1
WF-1
RB-1
RB-1
RB-1
2525
2525
WF-1 WF-1 WF-1
RB-1 RB-1 RB-1 RB-3
4" C-1/F-3 C-1/F-2
4"
C-1/F-2 C-1/F-2
1 FOUNDATION PLAN( NEW EQUIPMENT BUILDING) 2 ROOF DECK FRAMING( NEW EQUIPMENT BUILDING)
CE-06 SCALE: 1:100 CE-06 SCALE: 1:100
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-06
FOUNDATION PLAN (NEW EQUUIPMENT BUILDING)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: ROOFDECK FRAMING PLAN (NEW EQUIPMENT BUILDING)
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
TAP TO NEAREST
DRAIN PIPE
900
4250 3800 4250
CB CB
125
125
DD DD DD
CB
3' 900 900 ROOF LINE
2% SLOPE
2% SLOPE
2525
2% SLOPE
BITUMEN MEMBRANE WATERPROOFING
2 SECTIONAL DETAIL PLAN
CE-13
SCALE: NTS
2525
WALL
LINE
DD
CB
4"
0.10
16MM HANDHOLE
HANDLE
0.60 M
1 DRAINAGE LINE & CATCH BASIN
0.10
CE-13 SCALE: NTS
0.40
L=0.60M
W=0.60M
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-07
DRAINAGE LINE & CATCH BASIN
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: SECTION DETAIL PLAN, CATCH BASIN DETAILS
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
100mm CHB
75
900
4.5 kg/sqm. BITUMEN WATER
PROOFING MEMBRANE FLOOR TOPPING
T.O.S +4.0m
125
SLAB REINFORCEMENT(SEE PLAN)
400
RB-1 (SEE SCHEDULE)
100 700
800
COLUMN LINE
150mm CMW
1 SECTION DETAIL
CE 8 1:125
TOP STEEL AT MID SPAN TOP STEEL CURTAILED BARS TOP STEEL AT MID SPAN
137(TYP.)
SPAN L1 SPAN L2
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
SCHEDULE OF COLUMN
C1 10mm∅ LATERAL TIES
4.00 m ROOF DECK
400
400
SIZE:
400 x 400
1.0m
12- ∅16mm MAIN 100
∅10mm- @150- LATERAL TIES (3 sets)
CONFIN. REINF. ∅10@ 100 o.c , (3 sets)
0.0 m GROUND FLOOR JOINT REINF. ∅10@ 100 o.c , (3 sets)
400 400
400
SIZE: 400
400 x 400
12- ∅16mm MAIN
∅10mm- @150- LATERAL TIES (3 sets)
CONFIN. REINF. ∅10@ 100 o.c , (3 sets)
-0.9 m TOP OF FOOTING JOINT REINF. ∅10@ 100 o.c , (3 sets)
300 WALL FOOTING (SEE DETAIL)
Starter bars 8#16
NOTE:
TOP OF FOOTING 200
-0.9m
150mm THK. CHB W/Ø10mmVERT.
BARS @ 0.80m
& 10mmØ HORZ.BAR
@ EVERY 3 LAYERS OF CHB 8-16mmØ BARS B.W.O.C.
NGL. 0.0m
1300
450
450
300mm
12 - 16mm∅ BAR - B2
1300 400
3-12mmØ BARS
10mmØ TEMP. BARS
@ 300mm O.C.
500
50106
400
NGL.
400
12-16mm∅ VERTICAL BARS 0.0m
200000
NGL. 16mm∅ VERTICAL BARS 0.0m
200000
150000
150000
-0.9m
TOP OF FOOTING 100000
-0.9m
450
12 - 16mm∅ BAR - B1
12 - 16mm∅ BAR - B2
12 - 16mm∅ BAR - B2
900
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-09
WALL FOOTING DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: COLUMN DETAILS
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
TEMPERATURE BARS
BEAM BEAM
CONTINOUS BARS
CONTINOUS BARS
EXTRA BOTTOM BARS EXTRA BOTTOM BARS
BEAM
BEAM
BEAM
BEAM
BEAM BEAM
PLAN PLAN
TOP BARS EXTRA BOTTOM BARS TOP BARS EXTRA BOTTOM BARS TEMPERATURE BARS
(t)
(t)
CONTINOUS BARS CONTINOUS BARS
BEAM L/5 L/5
BEAM BEAM L/5 L/5
BEAM
L/4 L/4 L/4 L/4
L L
CROSS-SECTION CROSS-SECTION
TWO-WAY ONE-WAY
1 TYPICAL DETAIL OF RC SLAB
CE-10 SCALE NTS
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-10
SLAB DETAILS AND SCHEDULE
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
900
900
1000
ATTE
2200
ES NAT N:
2200
2200
ESC T N:SL N
E ENT T SLATE A T ANEL SL N
ST A E C NA SL N L C T AN LE TA A N L N LLE
ES NAT N:
ESC T N:S N ES NAT N: N N TS:
T S L E ATE STEEL ESC T N:S N
S ANEL NE C NS LAT N T S L E ATE STEEL
N S S N LE A ET A S ANEL NE C NS LAT N
C NA ENT ANCE E E LE E L C N S S N LE A ET A
C NA ENT ANCE E E LE E L C
N N TS:
N N TS:
PROPOSED DOORS FOR EQUIPMENT ROOM
SCALE: NTS PROPOSED DOORS FOR STORAGE ROOM PROPOSED DOORS FOR BATTERY ROOM
SCALE: NTS
SCALE: NTS
0.25 M
12 MM REBARS CROSSWISE
AND LENGTHWISE @ 0.20 M OCBW
CROSSWISE REBAR CONNECT
0.25 M
EXISTING GRADE LINE UNISTRUT CHANNEL
3000mm
45mm x 45mm x 6.00m
2mm THICKNESS
400MM
HANGER
BRANCHES
0.20M FOUNDATION 3 pcs 12mm rebars with
10mm temp bars @ 0.20 OC
25mm
EXPANDED
METAL GAUGE14
W
0
2 CABLE LADDER FOR INDOOR USE
H CE 03
STRAIGHT CABLE TRAY WITH COVER
2300
EXPANDED
METAL GAUGE14
F.F.L.
CABLE TRAY
CONTRACTOR: OPERATOR: PROJECT NAME: TNT ECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: T ANS E AN ENSET A E PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE
DOOR DETAILS, STAIR DETAILS
CORPORATION
SITE NAME: L T CANL AN PRC No: PTR No: REVIEWED BY: CABLE TRAY DETAILS
SITE ADDRESS: CANL AN LA NA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
3 ALTERNATIVE OFF FLOOR SUPPORT
CE-12 SCALE: NTS
4 PLATFORM PLAN
CE-12 SCALE: NTS
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-12
STEEL STAIR DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
PLDT CANLUBANG
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-13
ISOMETRIC VIEW (GENSET ROOM)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: DETAIL DESIGN
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
D-1 D-2 D-3 D-1 D-2 D-3
6740 6740
3370 3370 3370 3370
DD DD DD
3' 3' 2% 2%
E.F. E.F.
SL SL OPE
PROP. 500L
FUEL TANK
800
OPE OP SL
1000 1000 E 2%
1200
2900
2900
132KW GENSET
132KW GENSET
500
700
ROOF LINE OP
E
PROPOSED
PROPOSED
S L
2%
2500
2900
5800
DD
2900 2500
0.125M. THICK CONCRETE ROOF DECK WITH
4' 4' SAHARA WATERPROOFING IN CONCRETE MIXTURES
200
2900
E
1100 1520 800 1520 1100 OP
SL
2%
WALL
400 2% SLOPE
200 LINE BELOW DD
500 800 800 800 800 800 800
4" 4"
PLDT CANLUBANG PLDT CANLUBANG
1 GROUND FLOOR PLAN( NEW GENSET ROOM) 2 ROOF DECK PLAN( NEW GENSET ROOM)
CE-14 SCALE: 1:100 CE-14 SCALE: 1:100
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-14
GROUND FLOOR PLAN (NEW GENSET ROOM)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: ROOF DECK PLAN (NEW GENSET ROOM)
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
D-3 D-2 D-1 D-1 D-2 D-3
6740 6740
3370 3370 3370 3370
900 900
100
2500
4300
2100
300
800
5800 5800
2900 2900 2900 2900
900 900
3500 3500
800 800
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-15
ELEVATION VIEW (NEW GENSET ROOM)
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
D-1 D-2 D-3 D-1 D-2 D-3
6740 6740
3370 3370 3370 3370
RB-3
RB-3
RB-3
C-1/F-1 C-1/F-1 C-1/F-2
WF-1 WF-1
3' 3' RB-3 RB-1 RB-1
WF-1
WF-1
RB-2
RB-2
RB-2
2900
2900
GENSET FOUNDATION
GENSET FOUNDATION
ROOF LINE
C-1/F-1
5800
WF-1
RB-2
RB-2
RB-2
2900
2900
150mm THK SLAB ON FILL
12mm D.S.B. @ 300 O.C.B.W
WF-1 WF-1
1 FOUNDATION PLAN( NEW GENSET ROOM) 2 ROOF DECK PLAN( NEW GENSET ROOM)
CE-16 SCALE: 1:100 CE-16 SCALE: 1:100
CONTRACTOR: OPERATOR: PROJECT NAME: TNT O CT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: T ANSFO AND NS T AD PROFESSIONAL CIVIL ENGINEER CHECKED BY: C 1
FOUNDATION PLAN (NEW GENSET ROOM)
CORPORATION
SITE NAME: LDT CANL BAN PRC No: PTR No: REVIEWED BY: ROOF DECK PLAN (NEW GENSET ROOM)
SITE ADDRESS: CANL BAN LA NA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
C 2
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
D-1 D-2 D-3
900
6740
125
125
3'
2900
ROOF LINE
2
CE-17
SECTIONAL DETAIL PLAN
SCALE: NTS
0.125M. THICK CONCRETE ROOF DECK WITH
4' CB SAHARA WATERPROOFING IN CONCRETE MIXTURES
2900
0.10
WALL
LINE BELOW 16MM HANDHOLE
CB HANDLE
0.60 M
4"
0.10
PLDT CANLUBANG
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-17
DRAINAGE LINE AND CATCH BASIN
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: SECTION DETAIL PLAN, CATCH BASIN DETAILS
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
100mm CHB
75
900
4.5 kg/sqm. BITUMEN WATER
PROOFING MEMBRANE FLOOR TOPPING
T.O.S +4.0m
125
SLAB REINFORCEMENT(SEE PLAN)
400
RB-1 (SEE SCHEDULE)
100 700
800
COLUMN LINE
150mm CMW
1 SECTION DETAIL
CE 18 1:125
TOP STEEL AT MID SPAN TOP STEEL CURTAILED BARS TOP STEEL AT MID SPAN
137449(TYP.)
(TYPICAL)
400MM
SPAN L1 SPAN L2
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-18
BEAM DETAILS AND SCHEDULE
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: PARAPET WALL DETAILS
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
SCHEDULE OF COLUMN
C1 10mm∅ LATERAL TIES
4.00 m ROOF DECK
400
400
SIZE:
350 x 350
1.0m
8- ∅16mm MAIN 100
∅10mm- @150- LATERAL TIES (3 sets)
CONFIN. REINF. ∅10@ 100 o.c , (3 sets)
0.0 m GROUND FLOOR JOINT REINF. ∅10@ 100 o.c , (3 sets)
400 400
400
SIZE: 400
350 x 350
8- ∅16mm MAIN
∅10mm- @150- LATERAL TIES (3 sets)
CONFIN. REINF. ∅10@ 100 o.c , (3 sets)
-0.9 m TOP OF FOOTING JOINT REINF. ∅10@ 100 o.c , (3 sets)
300 WALL FOOTING (SEE DETAIL)
Starter bars 8#16
NOTE:
TOP OF FOOTING 200
-0.9m
150mm THK. CHB W/Ø10mmVERT.
BARS @ 0.80m
& 10mmØ HORZ.BAR
@ EVERY 3 LAYERS OF CHB 8-16mmØ BARS B.W.O.C.
NGL. 0.0m
1300
450
300mm
8 - 16mm∅ BAR - B2
1300 400
3-12mmØ BARS
10mmØ TEMP. BARS
@ 300mm O.C.
500
50106
200000
NGL. 16mm∅ VERTICAL BARS 0.0m
200000
150000
-0.9m
TOP OF FOOTING 100000
-0.9m
450
12 - 16mm∅ BAR - B1
12 - 16mm∅ BAR - B2
12 - 16mm∅ BAR - B2
900
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-19
WALL FOOTING DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: COLUMN DETAILS AND SCHEDULE
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
TEMPERATURE BARS
BEAM BEAM
CONTINOUS BARS
CONTINOUS BARS
EXTRA BOTTOM BARS EXTRA BOTTOM BARS
BEAM
BEAM
BEAM
BEAM BEAM
PLAN PLAN
TOP BARS EXTRA BOTTOM BARS TOP BARS EXTRA BOTTOM BARS TEMPERATURE BARS
(t)
(t)
CONTINOUS BARS CONTINOUS BARS
BEAM L/5 L/5
BEAM BEAM L/5 L/5
BEAM
L/4 L/4 L/4 L/4
L L
CROSS-SECTION CROSS-SECTION
TWO-WAY ONE-WAY
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-20
SLAB DETAILS AND SCHEDULE
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
1200 1200
SEE DETAIL 1
700
1520
600
A1
GENSET FOUNDATION
1 LONGITUDINAL SECTION PLAN
NTS
400
90 150 90
CE-21
200
50x50x3mm THK.
16mmØ TOP & BOTTOM BARS ANGLE BAR
SPACED @ 150mm O.C. E.W. SCREWED AROUND 200 400
2 COATS EPOXY PAINT
500 450 1000 450 500 THE EDGES
FLOOR SLAB FLASTERED FINISH
200
100
3101 950
500
10mm Ø STIRRUPS FOOTING SCHEDULE
16mmØ TOP & BOTTOM BARS DEPTH
DIMENSIONS TOP BARS BOTTOM BARS FROM REMARKS
SPACED @ 150mm O.C. E.W. MARK NGL
LENGTH (L) WIDTH (W) THICKNESS ALONG L ALONG W ALONG L ALONG W
GENSET FOUNDATION 150 3-16mm Ø 3-16mm Ø
F-1 400 400 150 - - 500mm ISOLATED
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-21
GENSET PAD DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY: BUND WALL DETAILS
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
75mm
25mm
100mm
45
CHB WALL
°
1500mm
2700 2700
25mm
750mm 750mm
BARREL BOLT
10mm BARREL BOLT PLACED CHB WALL
AT 4 CORNERS INSIDE GA # 14 2" x 4" TUBULAR
GA # 16 PLAN FRAME ALL AROUND
HOT AIRFLOW
SHEET LOUVER
BLADES
2500mm
2800
2800
INSIDE GENSET
ROOM
GA # 14 2" x 4"
300mm TUBULAR FRAME
SCHEDULE OF DOOR
SCALE: NTS
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-22
LOUVER DOOR AND WINDOWS DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
SCOPE OF WORKS AND NOTES
16MM DIA. INTERIOR & EXTERIOR BARS @0.15M.O.C.E.W.
2.00m
Fuel Tank
0.25m 0.70m 4" THICK CHB (PLASTERED & PAINTED FIN.)
2.0m 0.40m 0.25m W/ 10MM HORIZONTAL & VERTICAL BARS
@ 0.60 M. O.C. E.W.
0.90M
0.60m
F.G.L.
0.40M
0.50M
1.50m 4.80 M.
LONGITUDINAL ELEVATION
1.25m
PLAIN CEMENT
2.50m PLASTERED PAINTED FINISH
0.90M
0.80M
0.40M
PROP. 0.90 M. HIGH BUND WALLS
0.50M
3.10M.
TRANSVERSE ELEVATION
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-23
FUEL TANK CONTAINMENT LAYOUT
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
2875
2000
1500 1250
1500 1250
STORAGE TANK
STORAGE TANK
PROPOSED
PROPOSED
2000L FUEL
2000L FUEL
4000
3500
2000
2500
2000
2500
GROUND FLOOR PLAN (FUEL STORAGE TANK) ROOF PLAN (FUEL STORAGE TANK)
SCALE 1:100MTS SCALE 1:100MTS
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-24
FUEL TANK STORAGE SHED
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .
STANDARD ROOF SHED DESIGN FOR STORAGE TANK
2'
D' E'
FLASHING
3' GA#24 RIB-TYPE ROOF ( LONG SPAN)
ATTACH TO 3" C-PURLINS
GA#24 RIB-TYPE ROOF ( LONG SPAN)
ATTACH TO 3" C-PURLINS @ 0.60M. OC.
GUTTER
4" DIAMETER G.I. PIPE 4" DIAMETER G.I. PIPE 4" DIAMETER G.I. PIPE
4" DIAMETER G.I. PIPE
SCH.40 SCH.40
SCH.40
1250mm
2000mm
1500mm 2500mm
NOTES:
Elements Materials/Specifications Schedule of Finishes
Dimensions should be based on actual site condition
Column 4” diameter G.I Pipe sch.40 Painted in Blue Elevation of roof from the ground level shall have a minimum distance of 3.00m.
Roofing should be inclined at 30 degrees
Steel Truss 2’’ x 2” x ¼” thick angle bar Painted in Gray Steel connections shall be welded type
Roofing G.A 24 Rib Type (Long Span) Any color All steel shall be provided with anti rust primer paint before applying final finish coat
All steel reinforcement shall be 12mm corrugated bar (pedestal and footing).
C-Purlins 3” x 1.5mm thick @ 800mm O.C Gray Concrete pedestal shall be 0.30m x 030m. at 0.40m height from the ground level.
Provide 8 vertical bars with 10mm dia ties.
Downspouts 3” diameter PVC Pipe (Neltex Series 1000) Orange Footing shall be 0.90m x 0.90m x 0.25m thick. Minimum depth is 0.80m. Rebar at 150mm
spacing O.C. Footing can be eccentric depending on the actual location to where the shed will
Pedestal 3000psi Concrete Plastered Smoothly
be constructed.
Flashing/Gutter Ga. 24 Same color with the roof Roof edges shall be provided with flashing
Downspouts shall be connected to the nearest drain or catch basin
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-25
FUEL TANK STORAGE SHED DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: N.T.S. .
2000
1500
PLAN VIEW
CONTRACTOR: OPERATOR: PROJECT NAME: TNT PROJECT DRAWN BY: JEHAN ENGINEERING TEAM SHEET CONTENT: SHEET NO.
PROJECT DESCRIPTION: TRANSFORMER AND GENSET UPGRADE PROFESSIONAL CIVIL ENGINEER CHECKED BY: CE-26
COMFORT ROOM DETAILS
CORPORATION
SITE NAME: PLDT CANLUBANG PRC No: PTR No: REVIEWED BY:
SITE ADDRESS: CANLUBANG LAGUNA DATE ISSUE: TIN: DATE SUBMITTED: APPROVED BY:
CE-26
SCALE: REVISION NUMBER.:
LONGITUDE: 14°13'3.54" LATITUDE: 121°8'7.908" PLACE ISSUE: DATE APPROVED: 1:100 .