MISAMIS ORIENTAL- 1 RURAL ELECTRIC SERVICE COOPERATIVE, INC.

POBLACION LAGUINDINGAN, MISAMIS ORIENTAL 9019

Service Area Offices: Central - LAGUINDINGAN | West – MANTICAO | EAST – Opol | South – Talakag, Bukidnon
Hotline # SUN.09228558560 | SMART.09209558560 | GLOBE.09173258560
officeofthegm@moresco1.com

SWITCHING PROTOCOL
DATE June 27, 2023 (TUESDAY)

TIME 06:00 AM - 06:00 PM

PURPOSE Scheduled Power Interruption


1. Replacement of M2 Line Protection Relays associated 5LI1OPO-LUG at Opol SS
2. PM of line associated high voltage equipment and secondary devices
3. To conduct various line maintenance activities in accordance with our Annual Maintenance Plan (AMP) for CY 2023

AFFETED AREAS NGCP OPOL-LUGAIT 69KV LINE (NO LOAD)

ACTIVITY PERSON RESPONSIBLE


TIME: 06:00 AM - 07:00 AM
1.) COORDINATE WITH NGCP LUGAIT/IACC FOR DE-ENERGIZATION OF OPOL-LUGAIT 69KV LINE MCC

2.) DE-ENERGIZATION OF NGCP OPOL-LUGAIT 69KV LINE (NO LOAD)


i) DE-ENERGIZE OPOL-LUGAIT 69KV LINE (NO LOAD). NGCP OPOL/IACC
ii) RELAY MESSAGE TO MCC (OPOL-LUGAIT 69KV LINE IS DE-ENERGIZED). NGCP OPOL/IACC
iii) RELAY MESSAGE TO LSA & MSA LEADMAN (OPOL-LUGAIT 69KV LINE IS DE-ENERGIZED). MCC

TIME: 05:00 PM - 06:00 PM


2. ENERGIZATION OF NGCP OPOL-LUGAIT 69KV LINE (NO LOAD)
i) ENERGIZE OPOL-LUGAIT 69KV LINE (NO LOAD). NGCP OPOL/IACC
ii) RELAY MESSAGE TO MCC (OPOL-LUGAIT 69KV LINE W/O LOAD IS ENERGIZED). NGCP OPOL/IACC
iii) RELAY MESSAGE TO LSA & MSA LEADMAN (OPOL-LUGAIT 69KV LINE W/O LOAD IS ENERGIZED). MCC

Prepared by: Checked by: Approved by:

06/26/2023 06/26/2023
10:30 AM 01:39 PM

VON RENIER B. DAPANAS ENGR. RONIE M. SALDIA ENGR. COLLEN B. TARCELO


SYSTEM OPERATIONS & CONTROL ENGINEER SYSTEM OPERATIONS DIVISION CHIEF ESD MANAGER