You are on page 1of 22

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/267610747

Risk-Based Inspection Applied to Main Steam and Hot Reheat Piping Systems

Conference Paper · January 2007


DOI: 10.1115/PVP2007-26375

CITATION READS
1 111

1 author:

Marvin Cohn, P.E., P.Eng., FASME


Intertek
48 PUBLICATIONS   106 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Ranking of Creep Damage in Main Steam Piping System Girth Welds Considering Multiaxial Stress Ranges View project

NDE for Detection of Flow Accelerated Corrosion View project

All content following this page was uploaded by Marvin Cohn, P.E., P.Eng., FASME on 22 July 2018.

The user has requested enhancement of the downloaded file.


Risk-Based Inspection
Applied to Main Steam
and Hot Reheat Piping
Systems
TP174
July 2007

By
Marvin J. Cohn
Aptech Engineering Services, Inc.

Proceedings of PVP2007 2007 ASME Pressure Vessels and Piping Division


Conference July 22-26, 2007 San Antonio, Texas, PVP2007-26375
Risk-Based Inspection Applied to
Main Steam and Hot Reheat Piping Systems
By Marvin J. Cohn
Aptech Engineering Services, Inc.

ABSTRACT field conditions and inspection results, are


Many utilities select critical welds in their main enhanced to reduce the uncertainty in the
steam (MS) and hot reheat (HRH) piping quantitative probability of failure value for
systems by considering some combination of each particular location and to determine a
design-based stresses, terminal point more accurate estimate for future inspection
locations, and fitting weldments. The intervals. Based on the results of many
conventional methodology results in frequent HEPLC projects, the author has determined
inspections of many low risk areas and the that most of the risk (regarding failure of the
neglect of some high risk areas. This paper pressure boundary) in MS and HRH piping
discusses the use of a risk-based inspection systems is associated with a few high priority
(RBI) strategy to select the most critical areas that should be examined at appropriate
inspection locations, determine appropriate intervals.
reexamination intervals, and recommend the
most important corrective actions for the The author has performed many studies using
piping systems. RBI principles for MS and HRH piping
systems over the past 15 years. This life
The high energy piping life consumption management strategy for MS and HRH critical
(HEPLC) strategy applies cost effective RBI welds is a rational approach to determine
principles to enhance inspection programs for critical weldment locations for examinations
MS and HRH piping systems. Using a top- and to determine appropriate reexamination
down methodology, this strategy is intervals as a risk-based evaluation technique.
customized to each piping system, considering Both consequence of failure (COF) and
applicable effects, such as expected damage likelihood of failure (LOF) are considered in
mechanisms, previous inspection history, this methodology. This paper also provides a
operating history, measured weldment wall few examples of the application of this
thicknesses, observed support anomalies, and methodology to MS and HRH piping systems.
actual piping thermal displacements.
NOMENCLATURE
This information can be used to provide more The following nomenclature and acronyms
realistic estimates of actual time–dependent are used in this paper:
multiaxial stresses. Finally, the life
consumption estimates are based on realistic C = Material constant for LMP
weldment performance factors. D =Specified outside diameter of
pipe
Risk is defined as the product of probability P = Pressure
and consequence. The HEPLC strategy T = Time (hours)
considers a more quantitative probability tm = Specified minimum wall
assessment methodology as compared to thickness of pipe
most RBI approaches. Piping stress and life T = Test temperature (Rankine)
consumption evaluations, considering existing σH = Hoop stress

APTECH TP174
1
COF = Consequence of failure inspection projects have focused on detection
CRA = Comparative risk assessment and repairs. The HEPLC strategy shifts the
HEP = High energy piping methodology from detection and repairs to
HEPLC = high energy piping life prediction and prevention.
consumption
HRH = Hot reheat The conventional approach to choose critical
LMP = Larson-Miller parameter girth welds in MS and HRH piping systems
LOF = Likelihood of failure includes some combination of design-based
MS = Main steam stresses, terminal points, and fitting weldments
NWT = Nominal wall thickness subject to stress intensification [1-5]. This
OD = Outside diameter of pipe conventional methodology has not
PDP = Piping displacement profile substantially changed over the past 20 years.
RBI = Risk-based inspection
RHOH = Reheat outlet header Within the past decade, Tennessee Valley
SHOH = Superheat outlet header Authority (TVA) developed a different
TVA = Tennessee Valley Authority approach to prioritize their 24 seam welded
piping systems for examinations [6]. They
INTRODUCTION revised their as-designed piping stress
Power plant piping operated at high pressures analyses to consider the existing hanger
and high temperatures is typically described conditions, such as topped-out and bottomed-
as HEP. The MS and HRH piping systems out hangers. Based on the results of their
are included in this category. These piping revised ASME B31.1 Code piping stress
systems have a finite practical operating life analyses, system modifications were made
because of the continual accumulation of where necessary to restore each piping system
creep and fatigue damage. These two to Code requirements.
damage mechanisms may also combine
synergistically (creep/fatigue interaction) to The seam welds were separately prioritized
reduce the operating life well below life using the following strategy. A regression
predictions using creep or fatigue life analysis of base metal stress rupture data
calculations alone. While the probabilities of (multiple heats) was performed to determine
these failures are low, the major concerns in the mean curve and the standard error of the
older power stations are consequence based estimate for the applicable materials. For
and include the potential for catastrophic each data point, the time to rupture and test
failure, power plant personnel safety, and the temperature was used to determine the
potential for long-term outages. applicable Larson-Miller parameter value:

Since the catastrophic HEP seam weld failures LMP = T ( C + log t ) (1)
of Mohave (1985) and Monroe (1986),
electric power utilities have become more A lower bound base metal curve was selected
interested in developing and implementing as the 95 percent confidence band (i.e., 95
examination and fitness-for service percent of the failure observations lie above
evaluations of their HEP systems. As the minimum curve). The lower bound
summarized in Table 1, at least 31 failures or weldment curve was estimated by reducing
substantial cracks in Grade 11 (1-1/4Cr the lower bound base metal curve 10% on
1/2Mo) and Grade 22 (2-1/4 Cr 1Mo) seam- strength, accounting for reduced weldment
welds or clamshell welds have occurred from properties.
1979 through 2000. Conventional utility

APTECH TP174
2
The hoop stress for each seam weld geometry consumption methodologies discussed in this
was calculated as: paper are not ASME Code approved
techniques to predict remaining lives for MS
σ H = P ( D − 0.8 t m ) / 2 t m (2) and HRH piping system girth and seam welds.

where P was the “consistent design pressure.” HEPLC METHODOLOGY


a value higher than the expected operating The HEPLC methodology has three basic
pressure, but no greater than the specified phases: data collection, evaluation, and
design pressure. recommendations. The data collection phase
includes obtaining information on design and
Subsequently, TVA plotted each of the σH post construction piping and supports. Effects
values with their respective design of current anomalies are considered in the
temperature and operating hours on the log prioritization of critical examination locations.
stress vs. LMP figure. The seam welds were Furthermore, results of the examinations at
ranked in comparison to the distance from the the most critical locations are used to
threshold lower bound weldment curve. determine the degree of material damage
specific to each location.
As an alternative to the conventional industry
approaches, a HEPLC methodology has been A typical list of design data to be collected is
used by the author to prioritize material provided in Table 2. These eight items are
damage locations based on applicable typically used as a basis for the as-designed
damage mechanisms, realistic multiaxial piping stress analyses, for compliance to the
stresses, and weldment life consumption applicable code, and for prediction of pipe
evaluations. This methodology is customized thermal expansion displacements.
to each piping system, considering applicable
affects, such as operating history, measured A typical list of post construction piping
weldment wall thicknesses, observed support system data collected for an HEPLC program
anomalies, and actual piping thermal is provided in Table 3. Some of these data
displacements. are readily available, such as cumulative
operating hours, number of startups, normal
The HEPLC methodology has been pressures and temperatures, recent walkdown
incorporated into an RBI process, evaluating records, recent nondestructive examination
COFs and LOFs. A semi-quantitative records, recent transient events, and recent
illustration of the risk matrix for MS and HRH weld repairs. Other items may not exist, such
piping systems is presented in Figure 1. As as piping and weldment measured wall
discussed below, there are three distinct COF thicknesses, thermocouple data, older hanger
categories and as many as five LOF adjustments, and older weld repairs. The
categories. The various combinations of the weld reinforcement and counterbore profiles
COF and LOF categories can be used to are particularly important for the evaluation of
reveal the highest risk in the upper left corner highest ranked HEPLC locations. This post
and the lowest risk in the bottom right corner. construction information is implemented in
the as-found piping stress analyses, life
The ASME Code has provided no mandatory consumption evaluations, and the overall life
or nonmandatory rules for the calculation of management evaluations.
life consumption in MS and HRH piping
systems, subject to creep and fatigue damage
in weldments. Therefore, the innovative life

APTECH TP174
3
RANKING COFS estimated average operating pressure, pipe
For HEP systems, the COFs are separated diameter, and pipe thickness were used to
into three distinct categories: seam-weld determine a normalized hoop stress (a near
failures, clamshell weld failures, and girth weld mid-wall location using the Lamé equation
failures. Subcategories could also be [7], optimized for minimum data scatter).
evaluated, such as the pipe location (a high or Then, the normalized hoop stress was plotted
low personnel traffic area) and pipe size (main against the LMP value for each of the
run, vent line, or drain line). Seam-weld historical incidents, as illustrated in Figure 2.
failures (straight or bent spools) can be For Grade 11 material, a value of 20 was
catastrophic in nature, as has been observed selected for the LMP material constant, C. A
in Table 1 Incidents 1, 13, 14, 22, and 29. lower bound threshold of seamed pipe/elbow
These failures typically have high economic failures (or near failures) was drawn through
costs. the lowest data points. The mean and
minimum stress rupture curves of base metal
Clamshell elbow failures can be serious, but creep rupture failures [8 and 9] are also
have not been as catastrophic in nature as illustrated in Figure 2. Finally, the data points
seam-weld failures. In Table 1, the for the applicable seam or clamshell welds are
Incidents 2, 3, 5, 8, and 18 resulted in also plotted in Figure 2.
relatively less damage and shorter shutdowns
as compared to the classic seam-weld failures. In this case, the pipe material is Grade 11
Because the length of propagation is limited, (A387 Gr C), and the unit had already
clamshell elbow failures have had lower operated for 200,000 hours. Figure 2
consequences than seam-weld failures. These illustrates that the 19-1/4 inch pipe can
failures typically have high economic costs. If operate at least another 200,000 hours before
seamed pipe and clamshell elbows exist in the intersecting the threshold line of historical
same piping system, it is common for the seamed pipe/elbow failures. The 27-inch pipe
clamshell elbows to fail prior to the seam can operate substantially more than 200,000
welds because the intrados hoop stress on a hours before intersecting the threshold of
clamshell elbow is greater than the hoop stress historical seamed pipe/elbow failures. Both of
in the seamed pipe. these seam-welded piping system examples
have relatively low LOF values.
As demonstrated by many MS and HRH girth
weld failures, they tend to be leak-before- The CRA evaluation indicates that if this unit
break. Although serious, they have not been is operated in the future as in the past, this
catastrophic in nature and typically have unit can operate for several more decades
relatively medium economic costs. before the seam-welds will have indications of
creep damage. Nevertheless, it is
RANKING LOFS FOR SEAM AND CLAM recommended that the seam-welds be
SHELL WELDS examined one time to reveal any substantial
Since 1999, the basic methodology for fabrication defects. The one-time
prioritization of seam and clamshell welds examination will also provide the actual seam-
used by the author is CRA. The author has weld wall thickness, which can be used to
collected seam and clamshell weld failure (or fine-tune the applied hoop stress. In addition,
near failure) data for Grades 11 and 22 the high traffic areas should have seam-weld
materials. For each incident, the time and evaluations periodically to confirm that there
estimated operating temperature is used to are no substantial indications.
determine the applicable LMP value. The

APTECH TP174
4
In several of the author’s projects it has been approaches for selecting critical locations lack
found that the normal operating conditions the following considerations:
(temperature and/or pressure) are
substantially below the design conditions. In „ Actual pipe and weldment
such cases, the CRA evaluations have thicknesses significantly different than
frequently indicated decades of operation (if specified
operated in the future the same as in the past) „ Constant support hangers with
prior to further concern of pressure boundary nonlinear loading
failure. „ Variable spring hangers loaded
significantly different than specified in
METHODOLOGY – RANKING LOFS FOR the design
GIRTH WELDS „ Improperly functioning hangers (e.g.,
The author has found that piping system topped-out or bottomed-out) [12]
displacements in MS and HRH piping systems „ Code stresses (sustained load and
can be significantly different than the original thermal expansion stress range) that
design predictions. Actual displacements can do not include the hoop stress
be influenced by additional supports, missing „ Multiaxial operating stresses
supports, malfunctioning supports, and pipe „ Time-dependent creep stress
interferences. All of these post construction relaxation (shakedown)
anomalies should be identified by the piping „ Weldment material properties and
system hot and cold walkdowns and creep damage rates
considered in an as-found piping system stress „ Cumulative time-dependent
analyses. Simulation of observed piping creep/fatigue life consumption
displacements and conditions results in more evaluations
realistic estimates of current stresses. These
post construction phenomena are evaluated As compared to the conventional approaches
in a HEPLC program. of selecting critical examination locations, the
HEPLC methodology considers the above
A comparison of the conventional important issues and has successfully
methodology results to the highest ranked predicted material creep/fatigue damage in
HEPLC locations was discussed in 1997 [10]. girth welds of MS piping systems [12-15].
In a review of 18 MS and HRH piping These papers demonstrate that the predictive
systems, the conventional industry approach approach of this methodology is very cost
resulted in the selection of 6 to 20 critical effective.
welds for each of the 18 piping systems.
However, in almost every case, at least one of DOCUMENTATION OF PIPING SYSTEM
the top three ranked HEPLC locations was ANOMALIES
not captured by the conventional approach. The piping system hot and cold walkdowns
The one exception was a piping system with are more than hanger walkdowns. In addition
18 conventionally selected locations. to assessing the conditions of hangers and
supports, all piping deformation, piping
A comparison of the Code [11] results to interferences, and observed system anomalies
observed creep damage concluded that there are documented. It is also prudent to include
is poor correlation between Code high stress the first few supports of drain lines, auxiliary
locations and observed creep damage [12, steam lines, and extraction lines in the
13]. This poor correlation is at least partly walkdowns.
due to the fact that the conventional

APTECH TP174
5
Cold walkdowns should be performed every 2 analysis predicted displacements, is illustrated
to 3 years (during a scheduled outage). Hot in Figure 4. In this case, several hangers are
walkdowns should be performed within a displacing less than 50% of their expected
month prior to the same scheduled outage. If vertical travel. The as-found PDP, indicating
hanger adjustments are implemented, a cold the observed and simulated as-found piping
walkdown should be performed after the stress displacements, is illustrated in Figure 5.
offline adjustments, and a hot walkdown In this case, the analysis vs. observation
should be performed within 6 months after support displacements are in better
startup to document any possible hanger agreement.
migration.
POSTPROCESSING OF PIPING
PIPING STRESS ANALYSES ANALYSIS RESULTS
An as-designed piping stress analysis should The HEPLC considers the elastic stress,
be performed to evaluate compliance to the defined as the multiaxial stress at time equals
applicable ASME B31.1 Code. This analysis zero. The long range elastic stress is estimated
is based on the specified design data (Table 2) using the as-found piping stress analysis
and may not accurately represent the field results for the operating stress (dead weight,
conditions. pressure, external and thermal loads) in the
direction axial to the pipe and the Lamé
Evaluation of hot and cold walkdown results equations [7] for the other two orthogonal
frequently reveals that the pipe displacements directions. The total elastic stress in a
at hanger locations can be significantly weldment is estimated as the combination of
different than predicted by the design stress the applicable initial base metal stress,
analysis. This may be due to hanger residual stress, and weld performance factor.
malfunctions (non-ideal loading), inaccurate
modeling of elbow stiffness, piping The HEPLC also considers the inelastic stress,
interferences, and incorrect thermal defined as the fully relaxed stress (due to
displacement assumptions at the terminal creep relaxation). The long range inelastic
locations. Field measurements of pipe stress is estimated using the results of the as-
thicknesses may significantly improve the found piping analysis sustained load stress
dead weight displacements and stresses. analysis in the direction axial to the pipe and
Consequently, an as-found piping stress the Bailey equations [16] for the other two
analysis should be performed to simulate field orthogonal directions. The total inelastic
conditions and obtain more accurate pipe stress in a weldment is estimated as the
stresses due to identified anomalies. combination of the applicable fully relaxed
base metal stress, residual stress, and weld
For example, a comparison of the predicted performance factor after creep relaxation.
pipe displacements at support locations to
observed field displacements was performed For low alloy ferritic steels, the stress
for a MS piping system. The MS piping redistribution from the elastic to inelastic
system isometric, from the SHOH to the two stresses is estimated using the Norton
turbine connections, is illustrated in Figure 3. equation [17] and the maximum principal
There are 15 support locations for this piping stress failure criterion. Applicable values for
system. At each support location, the vertical the empirically derived coefficients are based
displacements are illustrated in a PDP on experimental results for the appropriate
diagram. The as-designed PDP, indicating material and temperature range. This
the observed and as-designed piping stress approach to relax the applied stresses is based

APTECH TP174
6
on uniaxial testing results. Uniaxial stresses in Figure 6. The hot and cold walkdowns
are adjusted to multiaxial stress conditions by revealed that Hanger MSH-2 was topped-out
using the ASME Code Case N47-32 [18]. offline and Hanger MSH-12 was bottomed-
out off-line.
Once the effective weldment stress is
determined as a function of time, cumulative Both as-designed and as-found piping stress
life consumption for each weldment is analyses were performed for the piping
calculated for the current operating hours. system. Results of both piping systems were
Empirically derived and well characterized in compliance with the ASME B31.1 Code.
stress rupture curves have been determined However, the ranking of stresses between the
for the appropriate materials. The Robinson two stress analyses was substantially different.
linear life fraction rule [19] is then used to The top nine locations for the sustained load
determine the incremental life consumed for cases of the as-designed vs. as-found piping
the applied stress at each incremental time stress analyses had no matching node
step. An integrated life consumption value is numbers.
estimated for each girth weld at its current
operating hours. Consequently, critical welds Step-by-step details of the HEPLC
are ranked according to their predicted life methodology applied to this piping system,
consumption due to creep damage. If there including all applicable Microsoft® Excel
are many cold starts for the piping system, an calculations, were presented at the ASME
additional set of welds is ranked for possible PVP conference in Vancouver, BC (August
fatigue damage, considering the as-found 2002). The HEPLC evaluation indicated that
thermal expansion multiaxial stresses. two MS welds were near end of life (Welds A
and B in Figure 6). Both welds were
MAIN STEAM PIPING SYSTEM AT examined and had significant OD cracks. The
CHOLLA 2 circumferential crack of Weld A (the SHOH
This piping system was evaluated during a nozzle connection) is shown in Figure 7. Four
Spring 1999 scheduled overhaul [13]. It additional welds (Welds C through F in Figure
began commercial operation in 1978 and had 6), with at least ten years of predicted
accumulated 158,000 operating hours by the remaining life, were also selected for
end of 1998. examination. Welds C through F and an
additional 25 girth welds were examined, with
The piping system has a design pressure of results indicating no significant service-related
2150 psig and typically operates at 1800 psig. material damage.
The design temperature is 1015ºF and the
effective operating temperature ranges from At Weld A, the as-designed Code sustained
995ºF to 1002ºF. load stress was 3.66 ksi, with an allowable
stress of 7.62 ksi. This node was ranked 29 as
The piping base metal is specified as ASTM a sustained load in the as-designed stress
SA335-P22 (seamless pipe) and the weld analysis. However, the HEPLC as-found
metal is specified as ASME SFA 5.5 E9018- effective weldment stress (considering
B3. There are three pipe sizes: 19-inch OD malfunctioning supports) at the time of the
by 2.50-inch NWT, 15-inch OD by 2.00-inch examination (160,000 hours) was 11.14 ksi at
NWT, and 8.63 inch OD by 1.55-inch NWT. Weld A, substantially greater than the as-
designed Code stress.
An isometric of the piping system from the
SHOH to the turbine connections is illustrated

APTECH TP174
7
Because of the malfunctioning hangers, the
HEPLC evaluation indicated substantial stress An isometric of the piping system welds, from
variations among the ranked weldments. A the RHOH to the turbine connections, is
summary of the predicted multiaxial stresses illustrated in Figure 8. The hot walkdown
at 160,000 hours for Welds A through F is revealed that two hangers were bottomed-out.
provided in Table 4. It should be noted that The cold walkdown revealed that three
Welds E and F had stresses 82% and 81% of hangers were bottomed-out and one hanger
the maximum stress (about 2 ksi below the was topped-out.
maximum stress), respectively. The lowest
stress weld was estimated to be 56% of the The as-designed piping stress analysis for this
maximum stress. piping system revealed that the sustained load
and thermal expansion stresses are in
The combination of low thermal expansion compliance with the 1967 and 2001 ASME
stresses and relatively low thermal cycles B31.1 Code stress allowables. The specified
indicated that the contribution of fatigue minimum wall thickness values are in
damage was not as important as creep compliance with the 1967 ASME Code, but
damage in this particular piping system. This do not satisfy the 2001 ASME B31.1 Code
case study illustrates that a comparison of requirements (wall thickness values are in
results from a conventional Code analysis to compliance for the maximum operating
the HEPLC approach can result in temperatures). The as-found sustained load
substantially different stresses and model node stresses satisfy the 2001 Code. At four
stress rankings. locations, the as-found thermal expansion
stresses exceed the 2001 Code requirements.
HOT REHEAT PIPING SYSTEM
This piping system was evaluated during a The specific risk matrix for this piping system
Fall 2004 scheduled overhaul. It began is illustrated in Figure 9. A previous
commercial operation in 1973 and had examination of all of the HRH piping seam
accumulated almost 200,000 operating hours welds revealed no significant indications. As
by the end of 2003. discussed above, the consequence of a seam
weld failure is “very high.” However, the
The HRH piping system has a design pressure evaluation of the 19-1/4-inch pipe seam welds
of 575 psig and typically operates at 430 psig. indicated an additional 200,000 operating
An integrated average temperature of 455 hours of remaining life, as shown in Figure 2
psig was used for the evaluation. The design (a “low” LOF rank). These seam welds are
temperature is 955ºF and the effective designated as L13 through L18 in Figures 8
operating temperature ranges from 940ºF to and 9.
950ºF. In recent years this unit has had few
thermal cycles, with less than 10 cold or warm The evaluation of the 27-inch pipe seam
starts per year. welds indicated substantially more than
200,000 operating hours of remaining life, as
The piping base metal is specified as ASTM shown in Figure 2 (a “very low” LOF rank).
A155, Class 1 (1-1/4%Cr) (seamed pipe). These seam welds are designated as L1
There are nine long radius elbows, specified through L12 in Figures 8 and 9.
as ASTM A234, Grade WP11, with intrados
and extrados seams. There are two pipe The consequence of clam shell elbow failures
sizes: 27-inch OD by 0.9375-inch NWT, and is less severe than longitudinal seam weld
19.25-inch OD by 0.625-inch NWT. failures, so they are designated as “high” COF

APTECH TP174
8
rank. Since the remaining lives of seamed or several elbows in that particular piping
elbows are slightly less than longitudinal system. Consequently, the lower bound
seams, the probabilities are slightly greater. threshold line of the seven failures or near
The clam shell elbow welds are designated as failures in Figure 2 very likely includes the
E1 through E9 in Figures 8 and 9. field testing of more than 20 pipe spools and
elbows. Therefore, this minimum threshold
The consequence of girth weld failures is line could be considered as representing the
typically less than clam shell elbow failures, so near-minimum stress rupture properties for 1-
they are designated as “medium” COF rank. 1/4Cr 1/2Mo seam-welded pipe and clamshell
The remaining lives of girth welds 23E and elbows.
23W (the two turbine connections) are only a
few years, so they have a “very high” LOF Regarding the girth weld failure prediction
rank. The remaining life of girth weld 17E evaluations, it was determined that the creep
(the east leg weld of the wye fitting) is within a strength property variations among heats
decade, so it has a “high” LOF rank. The varied less than 15% [15]. The author’s 1996
remaining lives of girth welds 1, 2, and 3 are paper regarding the ranking of critical stress
10 to 20 years, so they have a “medium” locations revealed that a comparison of the
LOF rank. The remaining 24 girth welds have fifth ranked to first ranked location had at
predicted lives greater than the top 6 ranked least a 20% variation in applied stress.
locations. Therefore, as long as the prioritized girth
welds have a stress variation greater than
As discussed above, seam welds in high 20%, the selected locations of predicted creep
personnel traffic areas should be periodically damage would govern the possibility of
examined as an extra precaution. material property variations.

ESTIMATED MATERIAL PROPERTY DISCUSSION


VARIATIONS This paper describes a viable RBI
A log stress vs. LMP evaluation of creep methodology that has been implemented for
rupture data for 2-1/4Cr-1Mo normalized and MS and HRH piping systems. The
tempered plates was performed to consider conventional methodologies result in frequent
creep rupture material property variations examinations of many low risk areas and the
[15]. Since all of the piping is operated for neglect of some high risk areas. Over the past
the same time and approximately the same 15 years, the HEPLC projects have provided
temperature, the variation in creep damage at more accurate piping stress analyses and life
the selected weldments is primarily dependent consumption evaluations than conventional
upon the applied stress. Within the stress approaches. It is common 1) to find weld
range of 3.8 ksi to 12 ksi, it was determined thickness measurements different than
that there is no more than 8% variation in specified, 2) to find malfunctioning supports in
stress (at the same LMP value) for the same the field, and 3) to determine as-found
heat of material and no more than 14% multiaxial stresses substantially different than
variation in stress from the weakest to the Code stresses. Since these common
strongest heats of material. problems are not considered in the
conventional methodologies, the HEPLC
Regarding the seamed pipe/elbow failure methodology is more applicable to select
prediction evaluations, it is noted that each critical welds subject to creep/fatigue damage.
reported failure (or near failure) incident is
likely the weakest link of 10 to 30 pipe spools

APTECH TP174
9
This suggested RBI methodology has
successfully prioritized and predicted material ACKNOWLEDGMENTS
creep/fatigue damage of girth welds in three The support of Aptech Engineering Services,
piping systems [15]. Results of the three case Inc. is greatly appreciated and acknowledged.
studies provide more credibility to this RBI
approach. REFERENCES
[1] Tynan, T.C., Dempsey, P. E., and
The suggested RBI methodology can result in Damon, J. E., 1986, “Life Extension of High
substantially different stresses and rankings of Energy Piping Systems,” 86-JPGC-Pwr-53,
critical weldments as compared to the ASME/IEEE Power Generation Conference,
conventional as-designed piping stress Portland, Oregon.
analyses, which are used to satisfy Code
requirements. The implementation of this [2] Erdos, J., Zabielski, A., and Gephart,
methodology for many MS and HRH piping J. P., 1983, “Critical Steam Piping in
systems has minimized the number of critical Operating Power Plants – Typical Failures and
examination locations while improving the Treatments,” American Power Conference
confidence level for life management 45th Annual Meeting, Chicago, Illinois.
programs. This comprehensive RBI strategy
has been used for seam-welds, clamshell [3] Wray, R. and Balaschak, J. J., 1986,
welds, and girth welds. A comparison of “Evaluation and Assessment of Steam Piping
creep rupture property variations to estimated in Older Fossil Power Plants,” Design and
weldment stresses indicates that examinations Analysis Methods for Plant Life Assessment,
of the top four or five ranked circumferential PVP-112, Pressure Vessels and Piping
welds would envelop the expected variations Conference and Exhibition, Chicago, Illinois.
in material properties.
[4] Hoffschneider, L. A., Tynan, T. C.,
and Damon, J. E., 1986, “Stress Analysis, A
CONCLUSIONS Vital Part of Critical Piping Inspections,” Fossil
There is a need to develop and apply an RBI Power Plant Workshop, Electric Power
methodology as part of a life management Research Institute, and ASME, San Antonio,
process in the selection of critical HEP welds. Texas.
The conventional Code guidelines (Code
equations and as-designed piping stress [5] Galpin, D. S., Clark, M. D., 1987,
analyses) do not adequately address the “Critical Piping Inspection,” Association of
influence of post construction anomalies and Rural Electrical Generating Cooperatives,
cumulative time-dependent creep/fatigue life Montrose, Colorado.
consumption. This paper suggests an RBI
methodology that predicts more accurate [6] Azzazy, S. E., Gateley, R. A., and
material damage rankings as compared to the Roberts, B. W., 2000, “A Review of Issues
conventional Code results and other Related to the Replacement of Seam Welded
conventional industry methods. To provide High Temperature Reheat Piping,” Aging
additional credibility for this methodology, the Management, Component and Piping
author has presented previous technical Analysis, Nondestructive Engineering,
papers that show implementation of this Monitoring and Diagnostics, PVP-409, ASME
approach has successfully predicted the most Pressure Vessels and Piping Conference,
critical locations of creep/fatigue damage of Seattle, WA, pp. 57-68.
circumferential weldments in three MS piping
systems. [7] Lamé 1852, “Lecons sur la théorie …
de l’élasticité,” Gauthier-Villars, Paris.

APTECH TP174
10
[8] NRIM, 1994, “Data Sheets on the Conference, PVP-439, Pressure Vessels and
Elevated-Temperature Properties of Piping Codes and Standards, Vancouver,
Normalized and Tempered 1¼Cr-½Mo-Si B.C., Canada pp. 83-88.
Steel Plates for Boilers and Pressure Vessels
(SCMV 3-NT),” NRIM Creep Data Sheet No. [14] Cohn, M. J., 2006 “A Strategy for Life
21B, National Research Institute for Metals, Management of Main Steam and Hot Reheat
Tokyo, Japan. Piping Systems,” EPRI International
Conference on Advances in Condition and
[9] NIMS, 2001, “Data Sheets on the Remaining Life Assessment for Fossil Power
Elevated-Temperature Properties of 1¼Cr- Plants, Louisville, Kentucky.
½Mo-Si Steel Tubes for Boilers and Heat
Exchangers (STBA 23),” NRIM Creep Data [15] Cohn, M. J., 2006 “Life Management
Sheet No. 2B, National Institute for Materials Projects for Three Main Steam Piping
Science, Japan Systems,” EPRI International Conference on
Advances in Condition and Remaining Life
[10] Cohn, M. J., 1997, “High Energy Assessment for Fossil Power Plants, Louisville,
Piping Reexaminations, Fewer Locations, - Kentucky.
Higher Confidence,” ASME Pressure Vessels
and Piping Conference, PVP-359, Fitness for [16] Bailey, R. W., 1956, “Creep
Adverse Environments in Petroleum and Relationships and Their Application to Pipes,
Power Equipment, Orlando, Florida, pp. 27- Tubes, and Cylindrical Parts Under Internal
35. Pressure,” Proceeding, Institute of the
Mechanical Engineers, 164.
[11] ASME, 2004, “ASME B31.1-2004
Edition, Power Piping,” ASME Code for [17] Norton, F. H., 1929, Creep of Steel at
Pressure Piping, B31, An American National High Temperatures, McGraw-Hill, New York,
Standard, The American Society of p.67.
Mechanical Engineers, New York, NY.
[18] ASME, August 1994, “Class 1
[12] Cohn, M. J., 2001 “The TransAlta Components in Elevated Temperature
High Energy Piping Program – A Five-Year Service, Section III, Division I,” Cases of
History,” Transactions of the ASME, Journal ASME Boiler and Pressure Vessel, Code Case
of Pressure Vessel Technology, 123, pp. 65 – N47-32.
69.
[19] Robinson, E. L., July 1952, “Effect of
[13] Cohn, M. J. and Nass, D., 2002, Temperature Variation on the Long-time
“Creep Life Prediction for High Energy Piping Rupture Strength of Steels,” Transactions of
Girth Welds, Case History – Cholla Unit 2,” the American Society of Mechanical
ASME Pressure Vessels and Piping Engineers, 74, pp. 777-781.

APTECH TP174
11
Table 1
INCIDENTS OF SEAMED PIPE/ELBOW FAILURES
OR NEAR FAILURES – 1979 THROUGH 2000

Incident Date Operating Operating Operating Diameter Material


Hrs Temp (F) Press (psig) (In)
1 Jul-79 129,000 1,000 480 20.0 A387 GrC
2 Sep-82 70,700 1,005 600 30.0 A234WP11
3 Nov-82 71,800 1,005 600 30.0 A234WP11
4 1982 87,000 ~1,000 630 24.0 A234WP11
5 Jan-83 72,800 1,005 600 30.0 A234WP11
6 1983 82,000 ~1,000 630 20.0 A234WP11
7 Jul-83 82,000 ~1,000 630 25.8 A234WP22
8 Dec-83 80,000 1,005 600 30.0 A234WP11
9 Jan-84 93,000 ~1,000 630 24.0 A234WP22
10 1984 187,000 1,055 2,670 20.0 A387 GrD
11 Mar-85 87,000 1,005 600 30.0 A234WP11
12 Apr-85 87,000 1,005 600 30.0 A234WP11
13 Jun-85 88,000 1,005 600 30.0 A387 GrC
14 Jan-86 97,261 1,000 730 32.0 A387 GrD
15 May-86 186,641 1,050 400 18.0 A387 GrD
16 1986 101,000 1,000 600 30.0 A387 GrC
17 1986 172,500 1,000 470 18.0 A387 GrC
18 Jul-86 142,000 1,000 1,800 12.8 A234WP22
19 Oct-86 173,916 1,050 400 27.5 A387 GrD
20 1987 80,000 1,000 720 36.0 A387 GrD
21 Fall 1990 153,400 1,000 2,640 16.0 A387 GrD
22 May-92 212,000 1,000 480 20.0 A387 GrC
23 Sep-92 168,000 1,000 2,640 16.0 A387 GrD
Spring
24 1993 173,000 1,000 2,640 20.0 A387 GrB
A 691 1-
25 1993 100,000 990 160 36.0 1/4Cr
26 1993 149,000 1,050 515 27.6 A387 GrD
27 1993 125,000 ~1,000 3,625 18.0 A387 GrD
28 1994 278,000 1,005 2,300 14.1 A234WP11
29 Jun-96 190,000 1,000 2,640 20.0 A387 GrB
30 Aug-98 200,000 1,005 2,500 18.0 A387 GrD
31 Nov-99 198,000 1,000 2,500 20.3 A387 GrD

APTECH TP174
12
Table 2

DESIGN DATA COLLECTED FOR AN HEPLC PROGRAM

Item Information
1 Piping System Layout and Spool Drawings
2 Shop and Field Weld Locations and Designations
3 Hanger Drawings, Including Loads, Total Travel, and Design Travel
4 Fitting and Valve Drawings and Weights
5 Insulation Material and Thickness
6 Piping Material Specifications
7 Piping Diameters, Nominal Wall Thicknesses, and Minimum Wall Thicknesses
8 Piping System Design Temperature and Pressure

Table 3

POST CONSTRUCTION DATA COLLECTED FOR AN HEPLC PROGRAM

Item Information
1 Total Cumulative Operating Hours
2 Piping and Weldment Measured Wall Thicknesses
3 Mode of Operation, Including the Number of Cold, Warm and Hot Start-ups
4 Piping System Maximum Temperatures and Pressures
5 Piping System Normal Temperatures and Pressures
6 Thermocouple Data (Steady State, Transients, and Ramp Rates)
7 Piping System Hot and Cold Walkdown Data
8 History of Hanger Field Adjustments (Travel and Load Adjustments)
9 Additional or Missing Supports
10 Support Repairs and Modifications
11 Movement Indicator Measurements
12 Weld Repairs and Replacements
13 Nondestructive Examination Records and a Summary of Significant Indications
14 Damage to Insulation and Lagging
15 Damage to Support Structures
16 History of Severe Transient Events and Excursions (Off-design Transients)

Table 4

CHOLLA 2 MAIN STEAM PIPING SYSTEM – RANKED WELDMENTS VS. EFFECTIVE STRESS

Rank Effective Stress % of Maximum


(ksi) Stress
1 11.14 100.0
2 11.12 99.8
3 9.75 87.5
4 9.66 86.7
5 9.18 82.4
6 9.00 80.8
Last 6.28 56.4

APTECH TP174
13
Likelihood Rank

1 2 3 4 5

1
Consequence Rank

(Seam- Highest
weld Risk
Failure)
2
(Clamshell
Weld
Failure)
3 Lowest
(Girth weld
Risk
Failure)

Figure 1 — Risk Matrix for Main Steam and Hot Reheat Piping Systems.

Figure 2 — Stress Rupture Properties for 1-1/4Cr – 1/2Mo Material.

APTECH TP174
14
Figure 3 — MS Piping System Isometric.

APTECH TP174
15
3
Observed
2
Designed
lacement (Inches)

1
Support Number
0
H1 H2 H3 H4 H5 H6N H6S H7N H7S H8E H8W H9E H9W H10E H10W H11E H11W H12 H13 H14 H15
-1

-2

Figure 4 — MS As-Designed PDP.

2
Observed
Simulated
Displacement (Inches)

1
Support Number
0
H1 H2 H3 H4 H5 H6N H6S H7N H7S H8E H8W H9E H9W H10E H10W H11E H11W H12 H13 H14 H15
-1

-2

-3

-4

-5

Figure 5 — MS As-Found PDP.

APTECH TP174
16
Figure 6 — Isometric of Cholla 2 MS Piping System.

APTECH TP174
17
Figure 7 — Cholla 2, Weldment Location A - Propagating Creep Crack.

Figure 8 — HRH Piping System – Weld Designations.

APTECH TP174
18
Likelihood Rank

Very Very
High Medium Low
High Low

L13 L1
Very through through
High
Consequence

L18 L12
Rank

E1
High through
E9

23E &
Medium 23W
17E 1, 2, & 3

Figure 9 — Specific Risk Matrix for a Hot Reheat Piping System.

APTECH TP174
19
Business Units:
Power Generation Services
Nuclear Power Services
Petrochemical Oil & Gas
Forensic Engineering
Industrial Engineering

Headquarters: Offices:
601 West California Avenue 16100 Cairnway Drive, Suite 310 139, 11215 Jasper Avenue
Sunnyvale, CA 94086-4831 Houston, TX 77084-3597 Edmonton, Alberta T5K 0L5
408.745.7000 Fax 408.734.0445 Phone: 832.593.0550 Canada
www.aptecheng.com Fax: 832.593.0551 Phone: 780.669.2869
Toll Free: 800.568.3201 Fax: 780.669.2509
Mailing: PO Box 3440 www.aptechtexas.com www.aptechtexas.com
Sunnyvale, CA 94088-3440

APTECH
View publication stats

You might also like