Professional Documents
Culture Documents
Track System
Requirements
Synopsis
The purpose of this document is to
ensure the safe performance of the
track system by specifying minimum
requirements for the design,
construction, inspection and
maintenance of the track system and
by specifying minimum actions to
restore safety in the event of a system
failure.
Contents
Section Description Page
Part A
Issue Record 2
Responsibilities 2
Compliance 2
Health and Safety Responsibilities 2
Supply 2
Part B
1 Purpose 3
2 Scope 3
3 Definitions 3
4 Principles 4
5 Requirements for track geometry design 5
6 Requirements for the track system and components 14
7 Requirements for track construction and commissioning 19
8 Requirements for track inspection, testing and recording 21
9 Requirements for track maintenance and corrective action 29
10 Requirements for track changes and renewals 36
References 37
RAILTRACK 1
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 2 of 38
Part A
Issue Record
This document will be updated when necessary by distribution of a complete
replacement.
Responsibilities
Railway Group Standards are mandatory on all members of the Railway Group *
and apply to all relevant activities that fall into the scope of each individual’s
Railway Safety Case. If any of those activities are performed by a contractor, the
contractor’s obligation in respect of Railway Group Standards is determined by
the terms of the contract between the respective parties. Where a contractor is
a duty holder of a Railway Safety Case then Railway Group Standards apply
directly to the activities described in the Safety Case.
* The Railway Group comprises Railtrack and the duty holders of the Railway
Safety Cases accepted by Railtrack.
Compliance
The provisions in this document are to be complied with from 03 June 2000
unless otherwise noted below.
Supply
Controlled and uncontrolled copies of this document may be obtained from the
Industry Safety Liaison Dept, Safety and Standards Directorate, Railtrack PLC,
Railtrack House, DP01, Euston Square, London, NW1 2EE.
2 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 3 of 38
Part B
1 Purpose
The purpose of this document is to ensure the safe performance of the track
system by specifying minimum requirements for the design, construction,
inspection and maintenance of the track system and by specifying minimum
actions to restore safety in the event of a system failure.
2 Scope
The contents of this document apply to all running lines and sidings on Railtrack
Controlled Infrastructure, as defined in Appendix A to GA/RT6001. This includes
sections of track with permissible or enhanced permissible speeds up to and
including 140mph. The contents also apply to sections of track carrying vehicles
with axle loads up to and including 25.5 tonnes.
3 Definitions
All technical terms used in this document, other than those given below, have
the meanings defined in GC/RC5603.
For the purposes of this document, cant deficiency is always the cant deficiency
at the rail head, not that experienced within the body of a vehicle.
Curvature
The reciprocal of the radius of a curve.
CWR
Abbreviation for ‘continuous welded rail’.
1. Rails installed in the track that have been welded together to form a
single rail greater than a nominal 55m in length.
2. Track constructed with continuous welded rail.
Non-ballasted track
Track that is not supported on ballast, including concrete slab track, track
supported on longitudinal timbers and directly fastened track on bridges.
Non-strengthened S&C
S&C that is not strengthened S&C. See also ‘Strengthened S&C’.
Overspeed
The amount by which the actual speed of a train could exceed the enhanced
permissible speed for any reason.
RAILTRACK 3
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 4 of 38
Permissible speed
The maximum permitted speed over a section of line that applies to trains when
not operating at an enhanced permissible speed. Permissible speeds are
detailed in the Sectional Appendix.
Reference specification
A specification describing the performance characteristics required from the
track system. The performance characteristics may be achieved by using
components other than those detailed within the specification.
RT60 S&C
Inclined, strengthened S&C incorporating 60 E 1 rail (formerly known as UIC 60
rail) with a geometry design specified by Railtrack to give reduced track forces.
S&C
Abbreviation for ‘switches and crossings’.
Strengthened S&C
S&C designed for use in CWR without the need for adjustment switches to
protect it from thermal forces.
Track category
The classification of a section of track by usage and speed, so that requirements
relating to design, maintenance, renewal and inspection of the track may be
specified and applied. The procedure for categorising track is given
in GC/RT5023.
Track fault
A hazardous track geometry condition requiring remedial attention. In this
document, the conditions covered by this term include twist (crosslevel), track
gauge, vertical profile (including cyclic top) and lateral alignment.
Track gauge
The distance between the running edges of the rails in a track, measured without
load at right angles to the rails in a plane 14mm below their top surface. See
also ‘Loaded track gauge’.
Track system
The assemblage of rails, rail supports, rail fastenings, sleepers, timbers or
bearers and ballast or other forms of support, acting together to provide
guidance and support for rail vehicles
4 Principles
4.1 General Requirement
The track is to provide for the safe guidance and support of vehicles. This
principle supports HMRI Safety Principle 5.
4 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 5 of 38
Trends in track faults and track quality are to be monitored and action plans to
deal with problems identified are to be prepared and executed.
The lateral stability of the track system is to be maintained to ensure the safe
guidance and support of vehicles taking account of maintenance activities and
temperature variations.
On overhead electrified lines, the relative positions of the track and the contact
wire are to be maintained to minimise the likelihood of an overhead line
equipment dewirement.
Inspection, maintenance and renewal plans are required for particular elements
of the track associated with a higher likelihood of derailment.
Broken and defective components that may adversely affect the safe guidance
and support of vehicles are to be replaced.
5 Requirements for
track geometry design
5.1 Normal limiting design values and exceptional limiting design values
This section specifies normal limiting design values and exceptional limiting
design values for track geometry parameters. When a design value is quoted
without being described as either normal or exceptional, it is the only limiting
value and no exceptional limiting value is permitted.
Wherever reasonably practicable, the normal limiting design values shall not be
exceeded.
RAILTRACK 5
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 6 of 38
Where design values exceeding the normal limiting design values are used, the
increase in risk arising from their use shall be assessed and managed. Records
of the assessments made shall be kept with the design records required by
section 5.8.
The design of horizontal alignments shall allow for the effective maintenance of
track geometry, taking into account the proposed methods of maintenance
(mechanical or manual).
The requirements for the alignment of track at buffer stops and arresting devices
are given in GC/RT5033.
The requirements for structure and passing clearances are set out in
GE/RT8029.
The requirements to be met before permissible speeds are altered are set out in
GK/RT0007.
The enhanced permissible speed shall be calculated for each type of train on
each curve. The speed on each track of a double or multiple line shall be
considered separately. On bi-directional tracks, the speed in each direction shall
be considered separately.
The calculation of enhanced permissible speed shall take account of the factors
listed in section 5.2.2 together with the following additional factors:
The enhanced permissible speed shall ensure that the likelihood of overturning
is within tolerable limits.
• effective controls are in place to ensure that the speed of trains is reduced
to a value not greater than the permissible speed whenever the wind speed
exceeds, or is predicted to exceed, the chosen maximum wind speed on the
curve;
• the procedures for implementing the controls to reduce the speed of trains
are fully documented and made available to all those responsible for the
safe operation of trains.
It shall be permissible to choose fixed maximum values for loss of cant and
reduction in curve radius when calculating enhanced permissible speeds
provided:
• effective systems are in place for monitoring track geometry and maintaining
it to a standard that ensures the chosen maximum values for loss of cant
and reduction in curve radius are never exceeded;
• the chosen maximum values for loss of cant and reduction in curve radius
are fully documented and made available to those responsible for the
maintenance of the track.
The value of the factors used in the calculation of enhanced permissible speeds
shall be reviewed at five yearly intervals to determine their continuing validity.
RAILTRACK 7
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 8 of 38
• the ability of vehicles likely to use the line to traverse the curves;
• the likelihood of buffer locking;
• vehicle coupling and interconnection designs.
A length of straight track not less than 3m long shall be provided between the
reverse curves if one of the curves has a radius of less than 160m.
• the proportions of the various types of traffic using the line, considering
relative speeds and axle loads, and the resultant variation in lateral force
and loading on both rails;
• structure, passing and electrical clearances;
• relative levels of adjacent tracks;
• the permissible speed and any enhanced permissible speeds;
• the permitted values of cant deficiency;
• the permitted values of cant gradient and rates of change of cant and cant
deficiency on the transitions either side of the circular curve;
• the presence of S&C and the permitted value of negative cant.
A small radius curve is one for which the equation above gives a cant less than
the limiting values given in section 5.3.4.
Where existing small radius curves are discovered to have an installed cant
exceeding the limits specified in this section, action shall be taken to reduce the
cant. Where reasonably practicable, the cant shall be reduced within six months
of discovery.
Appendix C of GM/RT2141 quotes values for cant on small radius curves for the
purpose of computer simulations designed to examine whether a vehicle has an
acceptable resistance to flange climbing derailments at low speed.
8 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 9 of 38
• 110mm on plain line CWR and the through route of strengthened S&C in
CWR;
• 110mm on the turnout route of RT60 S&C;
• 75mm on fixed obtuse crossings;
• 90mm elsewhere.
An exceptional limiting design value for cant deficiency on plain line jointed track
of 110mm shall be permissible for diesel multiple units with axle weights less
than 11 tonnes fully seated and fitted with bogies and air suspension, provided:
• the intrinsic track quality has been assessed and is considered suitable;
• the condition of joints has been assessed and is considered suitable.
An exceptional limiting design value for cant deficiency on plain line CWR of
150mm shall be permissible for vehicles, other than freight vehicles, accepted
for running at this cant deficiency, provided no features likely to contribute to
lateral misalignment are situated on the transition or circular curve. Features
considered likely to contribute to lateral misalignment shall include catch points,
adjustment switches, level crossings, longitudinal timbers and directly fastened
track on bridges.
The term ‘plain line’ excludes the through route of S&C (see section 5.3.10).
The normal limiting design values for cant deficiency shall be:
• 185mm for curve radii less than 700m but greater than or equal to 400m;
• 265mm for curve radii greater than or equal to 700m.
The exceptional limiting design values for cant deficiency shall be:
• 225mm for curve radii less than 700m but greater than or equal to 400m;
• 300mm for curve radii greater than or equal to 700m.
RAILTRACK 9
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 10 of 38
The maximum cant deficiencies for curve radii less than 400m shall be the same
as those for permissible speeds specified in section 5.3.7.
The limiting design values quoted in this section shall be reduced where
necessary to meet the requirements of section 5.2.3.
Exceptionally, a cant deficiency higher than the normal limiting value shall be
permissible on strengthened S&C, up to a limit of 200mm, provided the radius is
greater than or equal to 400m. Where a cant deficiency higher than the normal
limiting value is proposed, its value shall be assessed, taking into account the
following factors:
• any special features incorporated into the S&C that increase the fixity of the
track alignment and crosslevel and eliminate potential sources of
misalignment;
• the track geometry on the approach to the S&C, including the proximity of
any designed change in cant deficiency;
• the proposed maintenance regime for the section of track concerned;
• any relevant local features or sources of risk to trains.
Detailed records of the assessment shall be retained with the design records
required by section 5.8.
Where cant deficiencies above 110mm are proposed, the S&C shall be of a
strengthened design with flat bottom rails, concrete bearers and high speed
check rails with extended entry flares.
Where cant deficiencies above 150mm are proposed, additional special features
shall be incorporated that:
5.4 Transitions
5.4.1 Transition curves
Where reasonably practicable, a transition curve shall be provided between two
circular curves or between a circular curve and straight track. Curvature shall
increase (or decrease) regularly over the whole length of the transition curve.
Designs of transition curves shall take the permissible speed and any enhanced
permissible speeds into account, together with the cant and radius on adjoining
curves.
On transitions between reverse curves, the point of zero cant shall coincide with
the reverse point (point of zero curvature). Where reasonably practicable, the
rates of change of cant, cant deficiency and curvature shall be approximately the
same on either side of the reverse.
The clothoid spiral (or its close approximation, the cubic parabola) is the usual
form of transition used on Railtrack controlled infrastructure. The limiting values
for rates of change of cant and rates of change of cant deficiency defined in
sections 5.4.3 to 5.4.6 assume this transition form.
10 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 11 of 38
RAILTRACK 11
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 12 of 38
Where other forms of transition are used, the peak rate of change of cant and
the peak rate of cant deficiency shall be specified to suit the degree of
smoothing offered by the transition’s form. The peak rate of change of cant
deficiency shall not exceed the values noted in sections 5.4.5 and 5.4.6 by more
than 33%.
The deflection of the track at skew underbridges during the passage of trains
shall be taken into account when proposing to install cant gradients approaching
this value.
The exceptional limiting design value for rate of change of cant shall be 85mm/s.
The exceptional limiting design value for rate of change of cant shall be 95mm/s.
• 55mm/sec on plain line and on bull head and inclined flat bottom S&C other
than RT60 S&C;
• 80mm/s on vertical S&C and RT60 S&C.
Exceptional limiting design values for rate of change of cant deficiency shall be:
• 55mm/s on bull head and inclined flat bottom S&C other than RT60 S&C
(unchanged from the normal limiting design value);
• 70mm/s on plain line;
• 80mm/s on vertical S&C (unchanged from the normal limiting design value);
• 95mm/s on the turnout route of RT60 S&C.
The rate of change of cant deficiency at the switch toes can be disregarded.
The exceptional limiting design value rate of change of cant deficiency shall be
150mm/s on plain line.
The limiting design values for rate of change of cant deficiency on S&C shall be
the same as those at permissible speed specified in section 5.4.5.
The design of vertical alignments shall allow for the effective maintenance of
track geometry, taking into account the proposed methods of maintenance
(mechanical or manual).
12 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 13 of 38
Where reasonably practicable, vertical curves shall not coincide with horizontal
transition curves.
Designs using small radius vertical curves shall take account of the following
factors:
• the ability of vehicles likely to use the line to traverse the curves
(considering, for example, vertical buffer locking and vehicle coupling and
interconnection designs);
• clearances to features on the track under the vehicle;
• clearances to structures over the track.
The normal limiting design value for vertical curve radii shall be 1000m, subject
to the factors listed above.
The exceptional limiting design value for vertical curve radii shall be 500m,
subject to the factors listed above. Where radii less than 1000m are used, there
shall be at least 30m constant gradient between reverse vertical curves.
Consideration shall be given to the need for ballast retaining walls to permit the
provision of adequate ballast shoulders where there is a significant difference in
level between adjacent tracks.
Where existing track has been designed to give a nominal track gauge of
1432mm, the need to maintain this gauge shall be considered when short
lengths of track are renewed or components are replaced.
Section 6.5.1 gives associated requirements for the provision of check rails.
Track gauge shall be widened by moving the inner rail away from the designed
track centre line to ensure alignment continuity along the outer (steering) rail.
Appendix C of GM/RT2141 quotes values for gauge widening for the purpose of
computer simulations designed to examine whether a vehicle has an acceptable
resistance to flange climbing derailments at low speed.
In S&C, rails shall have a nominal inclination of 1 in 20 towards the track centre
line or be vertical, depending on the design of S&C considered. Where rails in
S&C are vertical, it shall be permissible for the rails in short lengths of adjacent
plain line also to be vertical.
Records of vertical curves with radii less than 1000m shall be maintained.
Details to be recorded shall include:
The design cant shall be indicated on site at regular intervals throughout the
length of all curves on lines in track categories 1A, 1 and 2.
The requirements for marking track geometry on site apply to both existing and
new and altered track. The required marking shall be provided where it does not
currently exist.
14 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 15 of 38
The infrastructure controller shall agree with vehicle designers the records of
track geometry parameters required for vehicle design purposes.
The need for a length of straight track or transition between small radius reverse
curves shall be considered, taking account of the following factors:
• the ability of vehicles likely to use the line to traverse the curves;
• the likelihood of buffer locking;
• vehicle coupling designs.
A length of straight track not less than 3m long shall be provided between the
reverse curves if one of the curves has a radius of less than 160m.
The requirements for the alignment of track at buffer stops and arresting devices
are given in GC/RT5033.
All new sidings, whether straight or curved shall, where reasonably practicable,
be designed without cant.
The reference specification for CWR on straight track in track category 1A shall
be:
RAILTRACK 15
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 16 of 38
The reference specification for CWR on straight track in track categories 1 and 2
shall be:
The reference specification for CWR on straight track in track category 3 and
below shall be:
The requirements for ballast and ballast profiles are set out in GC/RT5014.
Curves with radii of 600m or less shall have a minimum of 28 sleepers per 18m
length of track.
Curves with radii of 400m or less shall have a means of providing additional
lateral restraint (for example, lateral resistance end plates fitted to sleeper ends).
The additional lateral restraint shall provide a factor of safety against lateral
movement equivalent to or better than that of a curve of 401m radius with 28
monobloc concrete sleepers per 18m length of track.
Curves over which trains may travel with cant deficiencies of between 150mm
and 225mm shall have a minimum of 26 sleepers per 18m length of track.
Curves over which trains may travel with cant deficiencies of greater than
225mm shall have a minimum of 28 sleepers per 18m length of track.
The above minima assume concrete monobloc sleepers with fastenings meeting
the requirements of the reference specification in section 6.1.1. Where
necessary, the minimum number of sleepers shall be increased to take account
of the type and condition of fastenings and sleepers.
16 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 17 of 38
The adjacent sleepers each side of a fishplated or welded rail joint shall be of the
same material and type.
CWR shall be brought to a stress free temperature selected to suit the particular
track design and the expected range of rail temperatures at its location.
Records shall be kept of the stress free temperature to which the CWR has been
brought.
CWR through tunnels more than 180m in length shall be brought to a stress free
temperature at or near the maximum of the recorded range of rail temperatures
for the particular tunnel, other than for approximately 40m at each end of the
tunnel. The track at each end of the tunnel shall be brought to a stress free
temperature meeting the requirements of section 6.1.8.
To allow for thermal forces and to reduce the likelihood of buckling, the following
shall be brought to a stress free temperature meeting the requirements of
section 6.1.8:
Tight joint fishplates shall be used where it is not practicable to install a welded
joint and where a non-insulated fishplated joint is required to connect:
• jointed track;
• non-strengthened S&C;
• other track features that do not meet the requirements of section 6.1.10.
The need for adjustment switches shall be assessed where there is a significant
change in rail section in CWR.
The need for adjustment switches shall be assessed at each end of the deck of a
new steel or concrete underline bridge where the superstructure is designed to
move relative to the abutments and the moveable length exceeds 30m. If
required, the adjustment switches shall be located as close as possible to the
ends of the bridge deck, allowing for the minimum distance permitted between a
weld and the end of the a bridge deck given in GC/RT5022.
The requirements for ballast and ballast profiles are set out in GC/RT5014.
Expansion gaps shall be provided to give an adequate allowance for thermal rail
movement, taking into account of the following:
The expansion gap between two rails shall not exceed 15mm.
18 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 19 of 38
• maintain gauge;
• provide for the maintenance of cross levels;
• minimise longitudinal rail movements;
• minimise rail rotation;
• provide adequate fixity for baseplate/chair holding-down arrangements;
• retain ballast at the interface with ballasted tracks.
The design of track supported on longitudinal timbers shall take account of the
interfaces between the ends of bridge girders, the ends of longitudinal timbers
and the position of rail joints. The design shall also allow sufficient exposure of
the timber for its effective examination during track inspections.
When the speed, axle weight or tonnage of traffic using a track supported on
longitudinal timbers increases significantly, the adequacy of the existing
arrangements for the revised conditions shall be reviewed. If necessary,
measures shall be taken to strengthen or eliminate the longitudinal timbers.
RAILTRACK 19
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 20 of 38
All check rails shall have a machined flare at each end of sufficient length to give
guidance to vehicle wheel flanges entering the flangeway.
On reverse curves where both curves are fitted with continuous check rails, the
check rails shall overlap at the point of reverse by at least 6 m, exclusive of the
flares.
No fishplated rail joint shall be permitted in either running rail on checked curves
2m before entry to or 2m following exit from the flared section of the check rail.
All catch points shall be removed from a section of line before the permissible or
enhanced permissible speed is increased over that section.
7 Requirements for
track construction and
commissioning
7.1 Track undergoing renewal or remodelling
When track is undergoing renewal or remodelling procedures shall be in place
that define:
20 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 21 of 38
This section does not apply to the reopening of the line after a bridge strike, the
requirements for which are given in GC/RT5122.
Requirements for the reopening of a line after engineering work are given in
GO/RT3000 Section T.
A line shall only be reopened after engineering work following an inspection and
production of an associated record stating that the track is fit for the proposed
speed, as described in section 7.4.
The person inspecting the track shall have knowledge of the work undertaken at
the site.
RAILTRACK 21
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 22 of 38
When, following inspection, the track is considered fit for the proposed speed or
reopening of the line, but further work will be required to avoid a reduction in
speed or closure of the line in the near future (for example, continuously welded
track not stressed but satisfactory in all other aspects), a record shall be made
stating that the site is fit for the proposed speed, subject to the outstanding work
being completed within a stated timescale. Once the outstanding work is
complete, the track shall be re-inspected in accordance with the requirements of
section 7.4.1.
When, following inspection or re-inspection, the track is considered fit for the
proposed speed or reopening of the line without further work, a record shall be
made stating that the track is fit for the proposed speed.
The records shall normally be made using mechanical equipment such as track
recording vehicles, lightweight geometry recording trolleys or equipment on on-
track machines.
8 Requirements for
track inspection, testing
and recording
8.1 Track inspections
8.1.1 Requirement for track inspections
Track inspections shall be carried out to identify faults and defects in the track
system and its immediate environment that, if not corrected, could affect the
safety of the railway.
22 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 23 of 38
Track alignment
• misalignments, twists and dips in the track;
• gauge widening, other than designed gauge widening on tight curves;
• tight gauge opposite the noses of common crossings;
• condition and effectiveness of emergency tie bars;
Track support
• subsidence, bank slips, cutting slope slips and other earth movements;
• collapsed catch-pits;
• the presence of burrowing animals, particularly rabbits and badgers
• signs of ballast slurrying or effects of inadequate drainage on ballast
conditions;
• signs of voiding;
• significant deterioration in longitudinal timber condition;
Lineside security
• damage to fences and access gates;
• evidence of trespass and vandalism;
• encroachment;
• activities of lineside neighbours that may affect track safety, for example
construction work, crane jibs or booms swinging over the track, excavation,
tree felling and drainage works;
RAILTRACK 23
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 24 of 38
Level Crossings
• indications of deterioration or defects in any part of the track which is
concealed by the level crossing surface;
• any worsening of the track condition which is affecting, or may develop so
that it affects, the safe use of the level crossing;
• obstructions in flangeways, particularly any instances of frequent or
apparently deliberate obstruction
• defects or deterioration of the level crossing surface system;
• evidence of change in the nature or extent of use;
• accidental or deliberate damage;
• correct functioning of all telephones at unmanned level crossings;
• any other circumstances which appear likely to render the level crossing
unsafe;
Other items
• bonds detached from the rail;
• condition of third rail electrification equipment, including rail and insulators;
• permanent way materials interfering with signalling or other track mounted
equipment;
• lineside vegetation likely to foul trains or cess paths;
• lineside vegetation likely to reduce sighting distances at level crossings or to
obscure signals and speed indicators;
• condition of speed indicators and equipment for signing temporary and
emergency speed restrictions;
• flooding;
• any other items of a local nature that may compromise track safety.
Any material found obstructing flangeways during the course of inspection shall
be removed immediately.
All S&C track inspections shall be undertaken on foot from a position on or near
the line.
At least 25% of the required number of plain line track inspections shall be
undertaken on foot from a position on or near the line.
The remaining plain line track inspections shall be undertaken by inspection from
a vehicle travelling at less than 10mph or by appropriate alternative means (for
example recordings from purpose designed video camera systems mounted on
rail vehicles).
24 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 25 of 38
Vehicles used to undertake track inspections shall be of a type that allows the
requirements of sections 8.1.1 and 8.1.2 to be met. Where necessary, the
vehicle shall be stopped to permit a more detailed localised inspection on foot of
particular features.
When the track is inspected at night, adequate lighting shall be provided to allow
the requirements of sections 8.1.1 and 8.1.2 to be met.
Observed defects in bridges, viaducts, tunnels and other lineside structures shall
be reported to the Structures Manager defined in GC/RT5100.
RAILTRACK 25
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 26 of 38
Track Frequency
Category
Jointed Track CWR Non- Strengthened
strengthened S&C
S&C
1A, 1 and Twice per Weekly, with Twice per Weekly, with
2 week, with no no more than week, with no no more than
more than 4 8 days more than 4 8 days
days between between days between between
inspections inspections inspections inspections
3 and 4 Weekly, with Once per two Weekly, with Weekly, with
no more than weeks, with no no more than no more than
8 days more than 17 8 days 8 days
between days between between between
inspections inspections inspections inspections
5 and 6 Once per two Once per four Weekly, with Weekly, with
weeks, with no weeks, with no no more than no more than
more than 17 more than 31 8 days 8 days
days between days between between between
inspections inspections inspections inspections
The risk assessment shall take into account the following factors, together with
any other relavent local factors:
Track usage
• tonnage of high axle weight trains;
• the total tonnage which has passed since last renewal;
Track components
• rail type and age and the incidence of defective and broken rails;
• type and present condition of all components including sleepers and
fastenings;
26 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 27 of 38
Track support
• ballast conditions;
• condition of drainage and culverts;
• liability to flooding;
• stability of cuttings and embankments, making allowance where necessary
for the presence of burrowing animals, particularly rabbits and badgers;
• subsidence;
• presence of longitudinal timbers;
Security
• type and condition of fences and access gates;
• likelihood of vandalism and trespass;
The risk assessment shall be recorded and records retained until superseded by
subsequent review of inspection frequencies. The risk assessment shall be
reviewed at least annually to confirm its continuing validity.
Where necessary, the frequency of track inspection shall be increased to suit the
change of track category.
On routes where short-lived flows of traffic are being carried, the frequency of
track inspection shall be increased to that of the track category for the equivalent
annual tonnage being carried during that period.
RAILTRACK 27
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 28 of 38
This track form is particularly prone to exhibit wide gauge, particularly on curved
track, due to the reduced gauge retention arrangements compared with
conventional track forms.
28 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 29 of 38
• the vertical profile (top) of the rails, filtering out wavelengths greater than
35 metres;
• the lateral alignment of the rails, filtering out wavelengths greater than
35 metres.
The standard deviation (σ) of eighth mile sections shall be calculated for each
parameter listed above.
• the vertical profile (top) of the rails, filtering out wavelengths greater than
70 metres;
• the lateral alignment of the rails, filtering out wavelengths greater than
70 metres.
The standard deviation (σ) of quarter mile sections shall be calculated for each
parameter listed above.
All reports of track quality shall be available in sufficient time for the actions
required by section 9.3 to be carried out.
All reports of track faults shall be available in sufficient time for the minimum
actions required by section 9.2 to be carried out.
Track recording shall not be relied on as the primary or only system for finding
track faults, as the frequency of running is usually insufficient for this purpose.
RAILTRACK 29
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 30 of 38
9 Requirements for
track maintenance and
corrective action
9.1 Track maintenance
Track shall be maintained in accordance with good practice. All track
components shall be in place and correctly adjusted. Track shall be managed
so that the track faults referred to in sections 9.2.2 to 9.2.6 do not normally arise.
The corrective action taken and date completed shall be recorded. Records
shall be retained for 2 years for audit purposes.
When track gauge outside these limits is identified, the track shall be inspected
and a plan of action to bring the track gauge within the limits shall be prepared
and executed within a timescale commensurate with the likelihood of derailment
involved.
The increase in gauge due to loading under traffic shall be considered during the
inspection and when formulating the plan of action.
30 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 31 of 38
If a loaded track gauge of greater than 1480mm is identified, all traffic shall be
stopped immediately and action taken to strengthen the track to bring the loaded
track gauge within the limits given in the table above.
When standard deviations greater than the maximum permitted specified in the
table below are recorded, track shall be inspected within one week. Where
reasonably practicable, action shall be taken to restore track geometry within
one month (unless the inspection shows that there are grounds to discount the
recorded standard deviation value).
If it is decided that a speed restriction is not required, the reasons for the
decision shall be recorded.
When standard deviations greater than those specified as ‘very poor’ in the table
below are recorded, the track shall be inspected within one month.
Consideration shall be given to the need for action to improve track geometry,
taking the likelihood of discrete track faults arising at the site into account.
If it is decided that action to improve track geometry is not required, the reasons
for the decision shall be recorded.
The speed used when determining the maximum permitted standard deviations
for a section of track shall be the highest permissible or enhanced permissible
speed over the section of track concerned.
32 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 33 of 38
A plan of action to improve track quality shall then be prepared and executed
within a timescale commensurate with the expected deterioration of the
conditions found and the likelihood of derailment. The plan of action shall
ensure that the need for future work to correct track faults is minimised.
RAILTRACK 33
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 34 of 38
The datum markings shall show the design level, cant and dimension to the
nearest running edge of the adjacent tracks. A record of the information given
on the datum markings shall be maintained.
The infrastructure controller shall specify the tolerance within which the track
position shall be maintained to minimise the likelihood of an overhead line
equipment dewirement.
A procedure shall be in place that identifies the actions required to restore the
track to the design position when it is found to be outside the specified tolerance.
The actions shall vary according to the amount by which the measured track
position varies from the design position.
34 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 35 of 38
Requirements for structure and passing clearances are set out in GE/RT8029.
The plan shall be revised when there is reason to believe that it has ceased to
be appropriate or after any significant change in circumstances at the site of the
tunnel.
The plan shall be revised when there is reason to believe that it has ceased to
be appropriate or after any significant change in circumstances at the site of the
longitudinal timbers.
RAILTRACK 35
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 36 of 38
The correction of serious track faults shall be permitted when the above
condition applies, provided controls are put in place to manage the
consequences from any resultant lateral instability in the CWR (for example, by
the imposition of a speed restriction).
Maintenance work that disturbs the ballast condition or alters the alignment shall
not be carried out whilst the rail temperature is at or below 0 °C at the following
locations:
The correction of serious track faults shall be permitted when the above
conditions apply, provided controls are put in place to manage the
consequences from any resultant track misalignments (for example, by the
imposition of a speed restriction).
During and following heavy falls of snow all flangeway gaps, switch openings,
moveable crossing openings and track mounted equipment shall be kept clear of
snow to ensure the safe passage of trains.
36 RAILTRACK
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Track System Requirements Date April 2000
Page 37 of 38
During severe frost, special inspections to identify heave or lifting of the track
due to the action of frost shall be carried out and action taken to protect traffic.
Special attention shall be given to locations that are normally wet or where
ballast is shallow (for example, over culverts or underbridges).
9.10.5 Flooding
Restrictions to be imposed on train movements due to track flooding are given in
GO/RT3000 Section W (Floods).
When the water has subsided, a special track inspection shall be undertaken to
ascertain the effect of the flooding on track integrity. Particular attention shall be
given to the following:
The requirements for assessing the risks from scour and flooding at a structure
or earthwork and for actions to be taken when flood warnings are received are
given in GC/RT5143.
10 Requirements for
track changes and
renewals
Existing track may have been designed and constructed to standards that differ
from those specified in sections 5 and 6. Where reasonably practicable, track
shall be brought up to current standards when it is renewed.
RAILTRACK 37
Withdrawn Document
Uncontrolled When Printed
Railway Group Standard
GC/RT5021
Issue One
Date April 2000 Track System Requirements
Page 38 of 38
References
Railway Group Standards
GA/RT6001 Railway Group Standards Change Procedures
GC/RC5603 Standard Definitions of Civil Engineering Terms
GC/RT5011 Track Standards Manual: Section 9 – Switch and Crossings Systems
GC/RT5014 Track Standards Manual: Section 6 – Ballast and Formation
GC/RT5022 Requirements for Rail and Rail Joints (programmed to be issued October 2000)
GC/RT5023 Catergorisation of Track
GC/RT5033 Terminal Tracks - Managing the Risk
GC/RT5100 Safe Management of Structures
GC/RT5122 Bridge Strikes – Managing the Risk
GC/RT5143 Scour and Flooding – Managing the Risk
GC/RT5161 Station Platform Design Requirements
GC/RT5180 Safe Asset Management of Infrastructure - Tunnels
GE/RT8012 Controlling the Speed of Tilting Trains Through Curves
GE/RT8029 Management of Clearences and Gauging (programmed to be issued June 2000)
GI/RT7001 Management of Safety Related Records of Elements of the Infrastructure
GK/RT0007 Alterations to Permissible Speed
GK/RT0078 Overrun Protection and Mitigation
GM/RT2141 Resistance of Railway Vehicles to Derailment and Roll-Over
GM/RT2142 Resistance of Railway Vehicles to Overturning in Gales
GO/RT3000 Master Rule Book
GO/RT3260 Competence Management for Safety Critical Work
GO/RT3411 Exceptional Weather – Managing the Risks
Other References
HS(G)153/1 HMRI Railway Safety Principles and Guidance
EN13481 Railway Applications - Track - Performance requirements for fastening systems
The Catalogue of Railway Group Standards and the Railway Group Standards
CD ROM give the current issue number and status of documents published by
the Safety & Standards Directorate.
38 RAILTRACK