Professional Documents
Culture Documents
Incorrect
Errors can be introduced when performing infrared thermography condition monitoring
due to which of the following
(Correct)
Color of material
Shiny surfaces
(Incorrect)
Material geometry
Explanation
All options provided can result in errors while measuring with infrared thermography
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition 256
Question 2: Incorrect
A condition-based maintenance program can be characterized by a combination of the
following phases except
Diagnosis/Prognosis
Process
(Correct)
Remedy
(Incorrect)
Surveillance
Explanation
Any condition-based maintenance program can be characterized by a combination of
three phases -
Diagnosis / Prognosis — isolating the cause of the problem and developing a corrective
action plan based on its condition and remaining life.
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition Pg 245
Question 3: Incorrect
Displacement, Velocity, and Acceleration describe are used in condition monitoring to
measure
Vibrations
(Correct)
Pressure
Flow rates
(Incorrect)
Leaks
Explanation
The three key measures used to evaluate the magnitude of vibrations are:
• Displacement
• Velocity
• Acceleration
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 248
Question 4: Correct
In a system involving a pump, coupling, and a motor, the reliability of each component is
90%. In such a case, the reliability of the overall system (pump-coupling-motor together)
(Correct)
Explanation
This system is connected in series so reliability = 0.9 X 0.9 X 0.9 = 72.9%
Note.
System Reliability for series connection is always lower than the reliability of the
individual components
System reliability for a parallel connection is always higher than the reliability of the
individual components
Further reading
https://www.intechopen.com/chapters/50094
Question 5: Incorrect
Which of the following maintenance metrics are dependent on the mean time between
failures (MTBF)
(Incorrect)
(Correct)
Further reading
https://www.fiixsoftware.com/mean-time-between-fail-maintenance/
Question 6: Incorrect
A condition monitoring technique that is especially attractive for identifying hot and cold
spots in energized electrical equipment, large surface areas such as boilers and building
roofs, and other areas where “stand-off” temperature measurement is necessary is
known as
Ultrasonic testing
(Incorrect)
Infrared thermography
(Correct)
Infrared Spectroscopy
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 254
Question 7: Correct
Testing a limit switch during normal operation to see if it will work when called upon is
an example of
PM activity
(Correct)
Default activity
Further reading
https://reliabilityweb.com/tips/article/definition_failure_finding_task#:~:text=A
%20routine%20maintenance%20task%2C%20normally,item%20is%20about%20to
%20fail.
Question 8: Correct
Run to failure will be applicable to all the following except
Ceiling tiles
Interior paintwork
Lead-acid batteries
(Correct)
Metal roofs
Explanation
Run to failure is a maintenance strategy where maintenance is only performed when
equipment has failed
In a lead-acid battery, electrolyte levels should be just below the bottom of the vent well,
about ½ - ¾ inch above the tops of the separators, and the electrolyte level should not
drop below the top of the plates this means that inspection and maintenance are
required for Lead-acid batteries and therefore are not candidates for a run to failure
maintenance strategy.
Further reading
https://www.fiixsoftware.com/blog/run-failure-make-part-maintenance-planning/
#:~:text=Run%20to%20failure%20is%20a,to%20minimize%20total%20maintenance
%20costs.
Question 9: Correct
A process that is used to determine “What maintenance must be done” to ensure that a
physical asset continues to fulfill its intended functions in its present operating context,
is called
Maintainability process
Condition monitoring
Fault tree
(Correct)
Explanation
Reliability-centered maintenance (RCM) is a corporate-level maintenance strategy that
is implemented to optimize the maintenance program of a company or facility. The final
result of an RCM program is the implementation of a specific maintenance strategy on
each of the assets of the facility.
Question 10: Correct
The bathtub curve is widely used in reliability engineering and deterioration modeling.
The area of a bathtub curve characterized by an increasing failure rate
Detectable failures
(Correct)
Random failures
Explanation
The area characterized by an increased failure rate is known as the wear out failures
Question 11: Incorrect
In a system,
R2>R1>R3
R1>R2>R3
R1>R3<R2
(Incorrect)
R3>R2>R1
(Correct)
Explanation
active redundancy and standby redundancy are forms of parallel connection
The reliability of the whole system in parallel configuration is much higher than in series
configuration. The components in parallel improve system reliability whereas
components in series lower system reliability.
Further Reading
Maintenance & Reliability best practices 2nd edition by Ramesh Gulati Chapter 6
Question 12: Correct
Which option is false about Maintenance?
(Correct)
Further reading
https://hpreliability.com/operating-at-peak-inherent-capability/
Question 13: Incorrect
An asset is composed of four parts. In order for the asset to function properly, each of
the parts must function. Two of the parts each have a reliability of 96% and the other
two each have a reliability of 99.%
What is the overall probability that the product will function properly?
90.3%
(Correct)
100%
95.4%
98.3%
(Incorrect)
Explanation
This system is connected in series because all parts are required to function for the
asset to fuction properly. For systems connected in series
Rsystem = R1 X R2 X R3 X R4
Question 14: Incorrect
Which of the following is an example of a scheduled discard activity?
(Correct)
(Incorrect)
Explanation
A scheduled discard task involves replacing a specific part or component of a piece of
equipment at regular time intervals, regardless of its performance quality.
Of the options provided, Replacing a light bulb before it fails best fits the definition of a
scheduled discard task.
Further reading
https://www.onupkeep.com/learning/maintenance-terms/scheduled-discard-task
Question 15: Correct
The following are examples of failure modes except
(Correct)
Question 16: Incorrect
A P-F curve predicts the condition of an asset on what usually causes it to fail and
when.
P-F interval is used to determine the late finish date for a task
(Incorrect)
Equipment condition is plotted on the vertical axis while time is plotted on the
horizontal axis
The P-F interval is the time between an asset’s potential failure and its
functional predicted failure
Inspection interval must be equal or greater than the P-F interval so you can
catch a failure after it’s detectable, but before it actually occurs
(Correct)
Explanation
The equipment condition is plotted on the vertical axis while time is plotted on the
horizontal axis
The P-F interval is the time between an asset’s potential failure and its functional
predicted failure so its important that inspection intervals are smaller than the P-F
interval to catch a failure after it is detectable
The P-F interval is used to determine late finish dates of tasks eg inspections because
any deviation from the late finish date may result in a failure.
Further reading
https://www.fiixsoftware.com/blog/what-is-the-p-f-curve-p-f-interval/
Question 17: Incorrect
The Availability of an equipment is 95%. The reliability Engineer found during her
measurements that the MTBF was 100 hours. What is the repair rate?
2.5
0.25
0.19
(Correct)
1.9
(Incorrect)
Explanation
Availability = MTBF/(MTBF+MTTR)
0.95 = 100/(100+MTTR)
95+0.95MTTR=100
0.95MTTR= 100-95
0.95MTTR=5
MTTR= 5/0.95
= 1/5.26 = 0.19
Question 18: Correct
The interval between the point at which a potential failure becomes detectable and the
point at which it degrades into a functional failure is known as
P-F curve
S interval
P- F interval
(Correct)
Failure mode
Explanation
The PF interval is the period between a potential failure detected and the point of actual
failure
Question 19: Correct
Which of the following is an example of a predictive maintenance task?
(Correct)
Explanation
Predictive Maintenance (PdM) is a process for monitoring equipment during operation
in order to identify any deterioration, enabling maintenance to be planned and
operational costs reduced
Question 20: Incorrect
If an asset has a failure rate of 0.001 failure/hour, Which of the following is true
(Correct)
(Incorrect)
Reliability will increase with an increase in failure rate
Explanation
Reliability increases as MTBF increases
Question 21: Incorrect
Due to the extreme cost of interrupting production, a manufacturer has two standby
machines available in case a particular machine breaks down. The machine in use has a
reliability of 94%, and the backups have reliabilities of 90% and 80% In the event of a
failure, a backup machine is brought into service. If this machine also fails, the other
backup is used. Calculate the system reliability
85.4%
95.2%
(Incorrect)
99.9%
(Correct)
67.7%
Explanation
This scenario means that redundancy was designed into the system. This involves
providing backup components hence the system is said to be in parallel.
Question 22: Correct
A measure of oil’s resistance to flow at a specified temperature is known as
Viscosity
(Correct)
Adhesiveness
Solvency
Polarity
Explanation
The correct option is viscosity.
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 262
Question 23: Correct
Vibration analysis can be used to determine the following issues except
(Correct)
Bent shafts
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 250
Question 24: Incorrect
System reliability for components in series ---------------- as the number of components
increases
Increases
(Incorrect)
Remains unchanged
Decreases
(Correct)
Cannot be determined
Explanation
System reliability for components kept in series decreases as the number of
components increases. In this case, the system reliability is always less than the lowest
value of the reliability of any component.
Further reading
https://www.intechopen.com/chapters/50094
Question 25: Incorrect
A reliability team is performing RCM on a piece of equipment. Which of the following is
true
(Incorrect)
(Correct)
Question 26: Incorrect
A reliability engineer has been asked to classify functions for an asset.
Critical functions
Secondary Functions
(Incorrect)
Primary Functions
(Correct)
Tertiary functions
Explanation
Primary functions are the main reasons why an asset exists at all. The function that the
asset is expected to perform
Further reading
Question 27: Correct
A condition monitoring technique which of which uses high-frequency sound waves to
detect part defects such as leaks, parts seating, and cavitations is
Vibration analysis
Infrared thermography
Sound amplitude
Ultrasonic testing
(Correct)
Explanation
The correct option is ultrasonic testing.
Further reading
https://www.mromagazine.com/features/complete-list-of-condition-monitoring-
techniques/
Question 28: Incorrect
A reliability engineer is calculating the MTTR and MTBF for particular equipment. An
increasing MTTR while MTBF remains constant leads to
Reduced reliability
Increased reliability
(Incorrect)
Reduced availability
(Correct)
Increased availability
Explanation
To answer this question correctly, it is important to know the formula for availability and
reliability and their dependencies.
Reliability = e−T/MTTF
From the equations above, It is clear that reliability is not dependent on the MTTR so all
options containing reliability can be eliminated.
From the availability equation, increasing the MTTR while the MTBF remains constant
results in an increased denominator while the numerator remains constant. This means
reduced availability.
Question 29: Incorrect
Why would an asset have an overall reliability that is low even though its components
have fairly high reliabilities?
(Incorrect)
(Correct)
System reliability for a parallel connection is always higher than the reliability of the
individual components
Further reading
https://www.intechopen.com/chapters/50094
Question 30: Incorrect
Which of the following technique is best to identify leaking tubes in heat exchangers
and condensers?
Infrared spectroscopy
Ultrasonic testing
(Correct)
Analytical Ferrography
Infrared thermography
(Incorrect)
Explanation
The correct option is ultrasonic testing
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 257
Question 31: Correct
The following options are objectives of Lubricant (Oil) and Wear Particle Analysis except
(Correct)
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 260
Question 32: Correct
The bathtub curve is widely used in reliability engineering and deterioration modeling.
The failure rate on the horizontal axis and time on the vertical axis
The failure rate on the vertical axis and time on the horizontal axis
(Correct)
Explanation
A Bathtub
curve shows T
The failure rate is plotted on the vertical axis and time on the horizontal axis.
Note - The bathtub curve consists of three periods: an infant mortality period with a
decreasing failure rate followed by a normal life period (also known as "useful life") with
a low, relatively constant failure rate and concluding with a wear-out period that exhibits
an increasing failure rate.
Question 33: Incorrect
If the availability of a machine is influenced by its reliability, what is the other machine
characteristic that also affects its availability?
Utilization
Quality
Maintainability
(Correct)
Maintenance
(Incorrect)
Explanation
Availability = MTBF/(MTBF+MTTR)
Question 34: Incorrect
Increase MTTR
(Correct)
(Incorrect)
Explanation
Increasing MTTR is not an objective of maintenance. Maintenance aims to minimize the
frequency of interruptions
Question 35: Incorrect
The Mean time between failure (MTBF) can be used for the following except
(Incorrect)
(Correct)
Because it predicts the time between failures it is widely used to optimize scheduled
discard and scheduled restoration activities.
MTBF also provided required information such as failure rates which are input into the
RCA process.
Further reading
https://www.fiixsoftware.com/blog/mean-time-between-fail/
Question 36: Incorrect
Water is generally referred to as a chemical contaminant when suspended in oils. The
following options are methods of determining water/moisture ingress levels in a
lubricant is known as
(Incorrect)
Crackle test
(Correct)
Infrared spectroscopy
Explanation
Total moisture count is a made-up term. All other options can be used to determine
moisture content in lubricants
Further reading
Maintenance and Reliability Best Practices by Ramesh Gulati 2nd edition pg 262
https://www.machinerylubrication.com/Read/192/water-contaminant-oil
Question 37: Incorrect
A maintenance team is conducting a brainstorming session on how to optimize their
scheduled restoration and scheduled discard activities.
Scheduled restoration and scheduled discard are generally known as
Corrective maintenance
Condition-based maintenance
(Incorrect)
Preventive maintenance
(Correct)
Default actions
Explanation
Scheduled discard task involves replacing a specific part or component of a piece of
equipment at regular time intervals, regardless of its performance quality.
Question 38: Correct
A failure mode whose failure effects do not become apparent to the operators on its
own under normal circumstances is known as
Redundancy
Hidden failure
(Correct)
Unplanned failure
Back up
Explanation
Hidden failure means a failure that is not immediately evident to operations or
maintenance personnel and has the potential for failure of equipment to perform an on-
demand function, such as protective functions in power plants and switchboards,
standby equipment, backup power supplies
Further reading
https://iadclexicon.org/hidden-failure/#:~:text=Hidden%20failure%20means%20a
%20failure,or%20lack%20of%20capacity%20or
Question 39: Incorrect
The reliability of two components are 92% and 94% respectively. Which of the following
options is true
When connected in series, resulting reliability is greater than 85% but less than
100% when connected in parallel
(Correct)
When connected in series, resulting reliability is greater than 90% but lee than
98% when connected in parallel
When connected in series, resulting reliability is greater than 85% but less than
98% when connected in parallel
(Incorrect)
When connected in series, resulting reliability is greater than 88% but less than
99% when connected in parallel
Explanation
Reliability in series = Rs= R1 X R2 = 0.92 X 0.94 = 0.865 X 100 = 86.5%
=1-(0.08 X0.06)
When connected in series, resulting reliability is greater than 85% but less than 100%
when connected in parallel
Question 40: Correct
A reliability team is analyzing potential failure modes in an asset. Failure modes may
include all of the following except
(Correct)
deterioration
design failures
Continue
Retake test