Modularization
Managing construction risk through
reduction of site manhours
Global leader in
modular solutions
Pioneering in plant modularization
Technip Energies’s expertise and needs, offering extensive methods for plantwide
know-how cover all aspects of experience in working with modularization planning.
modularization from design to yards, particularly in Asia and We have now referenced more
onsite integration. We assist our optimized designs to reduce than 2,000 fabrication partners
clients in defining the strategy or mitigate construction risks. who are classified and regularly
that best fits their project We have developed numerical assessed.

Modular projects for the last 10 years ONSHORE


OFFSHORE

FORT MCMURRAY CNRL YAMAL LNG

+40
YEARS OF EXPERIENCE IN
MARTIN LINGE

MODULARIZATION ARCTIC LNG 2

ZADCO SRP
DAS ISLAND OAG
PACIFIC NORTH WEST
UPPER ZAKUM 750
KARISH FPSO

+20
MAJOR PROJECTS
BLADE
DELIVERED OR UNDER
CONSTRUCTION PETRONAS FLNG
TORTUE FPSO

LAKE CHARLES
EAST AREA ICHTHYS FPSO
PRELUDE FLNG

+1.2 MT
CORAL FLNG
FPSO P58, P62 KONIAMBO

OF LNG MODULES
DELIVERED IN ROVUMA
LAST 10 YEARS
LIBRA FPSO
MOHO NORD WHEATSTONE
FPSO P76, P56
OFON 2

2 Modularization Modularization 3
Leading design and
fabrication of all
types of modules
As an EPC contractor and modularization specialist, Technip
Energies takes turnkey responsibility for delivery of process
plants using a wide range of modules from small to mega. Each
project is unique and no matter its size, a tailor-made cost
effective modular solution is available to our clients.

The types of modules range from skids to


packages, buildings, process and utilities.

Onshore Offshore
small

MODULARIZATION
projects projects MITIGATES RISK
IN HARSH
OAG Das Island Energean Karish FPSO ENVIRONMENTS
710 t max/module 1,260 t max/unit
Recent project achievements
9,800 t total 13,200 t topsides + 1 LQ
have shown that modularized
construction provides
Large

Koniambo-Nickel Shell Prelude FLNG schedule certainty in


3,640 t max/module 5,800 t max/unit seemingly impossible places.
37,000 t total 76,000 t topsides
• Inside the arctic circle
Yamal LNG Martin Linge Extreme cold and polar nights
like on the Yamal LNG project
8,200 t max/module 10,500 t max/unit
in Siberia
480,000 t total 25,000 t 3UPF + 1 LQ
• Remote South
Arctic LNG 2 Wheatstone CPP Pacific islands
MEGA

13,900 t max/module 35,000 t topsides Sparse population such as for


518,000 t total the Koniambo Nickel Smelter
project in New Caledonia

• Artificial islands
in the Arabian gulf
Heat stress as for the Upper
Zakum 750 project in the
Arabian gulf

4 Modularization Modularization 5
Why
modularize?
Modularization is a strategy for industrial plant construction that
relies on the portioning of a facility into prefabricated sub-units
assembled in well-equipped and well-located fabrication yards
to be then transported to often remote construction sites where
modules are interconnected.t

Technip Energies has successfully executed projects using many types of modules from small
truckable skids to complete process units in mega modules.

When to consider What can be modularized?


modularization ?
Modularization can avoid cost
and schedule overruns on the
most challenging sites.
INADEQUATE OR HIGH COST
WORKFORCE

• High direct manpower cost Process units Buildings


• Unavailable local workforce
• Shortage of skilled The many advantages of modularization
manpower

DERISKED CONSTRUCTION KINDER ON THE ENVIRONMENT AND LOCAL


PRODUCTIVITY BARRIERS COMMUNITIES
• Overcome low availability of skilled
• Harsh climate manpower on site • Little or no dependence on local resources
• Political and social instability • Mitigate harsh climatic conditions • Decrease impact to local infrastructure
• Lack of construction • Simplified coactivities (SIMOPS) • Reduce temporary construction and storage areas
equipment Piperacks • Controlled fabrication environment • Overcome site constraints
• Limit interfaces (schedule derisking)
DIFFICULT SITE ACCESS • Reduce site congestion IMPROVED QUALITY
• Manage political and economical instabilities
• Complex or elongated • Simplify customs procedures • Reliable QHSE management
logistics • Lower costs
REDUCED SITE COSTS • Higher and better controlled productivity
• Availability of skilled manpower
Skids Utilities • Construction manhours • Easier monitoring of progress and work fronts
• Flatten peak manpower • Integrated fabrication facilities
To ensure the full benefit from modularization, planning in the • Work on construction equipment • Quick access to sea
project must be done at the earliest. • Site supervision • Module precommissioning
Refer to “Prefabrication, Preassembly, Modularization, and • Decreased camp size • Real estate availability
Offsite Fabrication in Industrial Construction: A Framework for • Simplified logistics (material and personnel)
Decision-Making”.

6 Modularization Modularization 7
From concept Organization of a
to delivery modularized project
Technip Energies modularization expertise is A modularized project organization differs from a pure
available from the earliest project phases. stick-built approach. Technip Energies’s experience
shows that these differences fall into four main areas.
Project knowledge:
site survey, infrastructure PROCESS, SAFETY • MOF / site Infrastructure
u Identify constraints and logistics, labor... AND ENGINEERING • SPMT simulation for offloading
/ transportation / installation
• Process development • Preservation and
to consider module
v Assess optimized extent maintenance up to handover
arrangement and
of modularization subsequent layout

w Develop preliminary
• Safety studies to be FABRICATION YARD
Modular design conducted at the earliest
definition and modularization plan stage • Early identification and
selection based on yard
optimization • Instrumentation and capabilities
x Screen and preselect electrical design focusing
and experience
suitable yards on minimizing
inter-modules cabling • Access and offloading
strategy
Decision on extent and local cabinet outside
of the modules • Precommissioning and
of Modularization commissioning capabilities
y Refine modularization /
• Steel structures defined (utilities)
fabrication plan for marine and land
transportation • Validate QHSE plan
U Select yards and freeze • Adapted civil designs
(underground and CONSTRUCTION SITE
execution strategy foundations)
• Civil (roads, platforms,
sewage, networks)
Finalize execution strategy
and pricing
SCHEDULE AND LOGISTICS • Hookup
V Start fabrication • Earlier procurement to suit • Pressure testing including
closure welds
module fabrication sequence
and duration • Cable pulling
• Optimized overall • Heavy lifts for equipment
Derisked outside modules
W Module transportation construction schedule
execution Pre-FEED considering site • Final precommissioning
and commissioning
X Installation and hook up activities, module fabrication
FEED duration at multiple yards
and erection sequence
EPC preparation
• Optimization of the module
at Overall plant mechanical shipping plan including
EPC
eventual transshipment
completion
• Heavy transportation vessel
screening and selection

8 Modularization Modularization 9
Floatover /
Unideck
Over four decades, Technip Energies has built up a worldwide
track record, designing and installing very large offshore platform
Stick-built vs. modular topsides by floatover and offering industry leading expertise
Technip Energies has developed NIMO, a ASSESSMENT OF MODULARIZATION in Transport & Installation (T&I) engineering design and
proprietary numerical simulation tool based on
Monte Carlo algorithms, to assess the best
T&I operation management.
Manhours Cost
construction strategy for a given project.
Our optimized solutions for modularization are based
MAIN OBJECTIVES: on demonstrated successful applications in EPCI projects:
Pre-assembly,
Pre-assembly,
Identify the optimum extent of modularization packing,
shipping and
packing, • Module weighing with load
(corresponding to minimum CAPEX) in terms of: delivery
shipping and
cells or hydraulic jacks

Site Construction
delivery

• module size/weight
Mechanical
Electrical
• Module load out by skidding
or with SPMT
• offsite manhours transferred from site to yard Instrumentation

Site Construction
Mechanical

• Outline the associated execution strategy


Electrical
Instrumentation
• Transportation by barges or
heavy transportation vessels
• This assessment needs only a few inputs, Civil

mainly an equipment list, and can therefore


Civil
• Module load in and setting on
be deployed very early in the project. Stick-Built Modular foundation supports.

Our capabilities include in particular:

• Definition of SPMT arrangement • Interface management • Shipping plan


and optimization of module • System integration and tests • Vessel fleet monitoring
• Extensive assessment of logistics to MODULARIZATION OPTIMIZATION geometry for transportation • HAZID studies of module during navigation
determine the maximum size and weight
• Vessel screening and displacement operations • Motion & acceleration
of modules Off-site Mhrs On-site Mhrs selection thanks to fleet • Coordination with Marine monitoring of modules
• Full screening of modular configurations & market knowledge Warranty Surveyor • Weather routing services
Module Integration & Hook-up

from stick-built to maximum Ras Markaz Bio-filter


Package Module • Marine spread subcontract for approval of marine
modularization to select the best
Cost Trails

management operations
configuration Civil works,
cable pulling,
• Method Statements for load • Coordination & supervision
out / load in during operations
underground
work, net • Module engineering for load
out /transportation / load in
working ...
Optimum extent etc. • Grillage /substructure design
• Internal & external sea
fastening design
NIMO, our simulation • Specification of equipment
tool, captures all aspects 0% % Work moved off-site 100% for load out / load in
& procurement
of modularization to • Quay design verification
Maximum
support the decision- modularization & preparation
making process. • Mooring system design
• Module preservation and
energization when required

10 Modularization Modularization 11
Mega Jack and skid deck module transfer to hull

modularization
We offer this cost effective solution to handle FLNG and other deck mounted mega modules.

The mega module is moved


from the assembly area to
the quayside using SPMTs
Technip Energies has pushed the plug and play module concept
to the limit with mega modularization. Complete process units in
modules weighing up to 25 kt or more, drastically reduce
integration at the onshore or offshore construction site. It also
facilitates commissioning activities at the fabrication yards.

The Mega Modularization technology consists of merging several conventional mid-size modules The skid deck elements are
into a single mega module containing complete systems with minimum interfaces. installed on the hull deck
stools and the mega module
Main benefits is lifted to the hull deck
level using a proven elevating
DESIGN SCHEDULE AND COST FABRICATION system such as climbing
jacks or gantries equipped
• Decrease the tonnage of • Save cost and integration • Feasible for many yards with strand jacks
structural steel time • Reduce required construction
• Reduce piping quantities • Decrease the number of area at yards
• Offer dedicated local, shipments • Decrease the number of
electrical and instrumental • Maximize precommissioning / loadouts
rooms per module allowing commissioning activities at • Reduce fabrication manhours The mega module is
full cable pulling at yard yard and enable the tests of
transferred onto the hull
• Extensive dimensions provide full / integrated systems
using hydraulic skidding and
for more flexibility to develop • Minimize integration work jacked down onto the stools.
an optimal layout taking into between modules
account: Process • Shorten planning, limit Full control of the hull level
requirements, center of integration is ensured by water
gravity, safety distances, • Offer integrated construction ballasting
operation and maintenance completion and
considerations (access, precommissioning and
evacuation…) commissioning activities, to
• No need of conventional reduce the risk of carryover
central pipe rack, freeing work
After completion of skidding
unused space • Simplify precommissioning
and jacking down operations,
• Reduce overall plant and commissioning
footprint sequences for site works the skid deck elements are
retrieved onshore

A maxi modularization concept to


derisk project execution while saving
CAPEX and reducing schedule.

12 Modularization Modularization 13
Selecting and working
with fabrication yards
Assessing the yards’ technical
and commercial offering
During front-end engineering, several yards are prequalified. We use an open
bidder list to ensure the best yard is selected for a specific scope of work.

MAIN EVALUATION CRITERIA: AUDITS EARLY WORK

• HSE performance Technip Energies audits yards For selected yards, an agreement
• Quality and inspection of potential interest. Work is signed prior to final
• Fabrication capability packages can be adjusted to subcontract award to secure the
• Project management the yards’ capacity and best conditions and resources,
• Engineering capability competition may be increased. set the effective date, define
• Procurement and The preselected yards are early activities, close the audit
subcontracting plan audited a second time using actions plan and ensure the
• Resource mobilization the FMECA* methodology. immediate efficiency of the yard
• Price Main processes are audited after contract signature.
and design office disciplines Preselected yards are involved in
are reviewed. constructability reviews and
workshops to mitigate risks and
An action plan is issued to
adapt the design as necessary.
each yard. All actions are
closed out before the effective
date of the contract.

HSE performance improvement in execution


During execution, we continue to work with our fabrication yards to encourage quality performance
of which HSE is a central feature.

TRAINING PROGRAM comply with HSE rules and To promote environmental


maintain a proactive approach performance, we record and
• Increasing workforce HSE
awareness for a safe to safety and environmental analyze all yards’ key
project execution. protection. environmental performance
indicators on a monthly basis:
PROJECT INCENTIVE HSE CAMPAIGNS • Emissions
SCHEMES
• Increasing workforce • Energy consumption
• Enhancing HSE performance proactivity in managing risks • Water consumption
by motivating the work-force. onsite. • Waste generation
Our project incentive scheme
• Environmental awareness
and balance of conse-quences improving environmental
programs motivate personnel to performance in the yard.

14 Modularization Modularization 15
Our key references Coral South FLNG
• Client: Coral FLNG SA
KEY FIGURES
• Location: Mozambique • LNG Capacity: 3,4 MTPA
• Water depth: 2,150 m
Coral South floating liquefied natural gas (FLNG)
is the third FLNG unit in the world and the
Yamal LNG largest floating structure in Africa, making one
of Technip Energies’s most important projects.
THE LARGEST MODULARIZATION PROJECT EVER
It will be the world’s first ultra-deep-water FLNG
• Clients: Novatek, Total, CNPC and Silk Road Fund
• Location: Russia facility to operate at a water depth of 2,000m
and is expected to produce 3.4 million tonnes
Yamal LNG is a large-scale LNG project in northern (Mt) of LNG a year. The Technip Energies-led TJS
Siberia operated by the Novatek-TOTAL-CNPC-SRF Consortium involving JGC Corporation and
joint-venture. The scope of work included the design, Samsung Heavy Industries (SHI) was awarded
supply and startup of three LNG trains in an area the engineering, procurement, construction,
where major gas reserves had never been fully installation, commissioning (EPCIC) and subsea
developed due to the harsh arctic environment. scopes in a single contract, in June 2017. The
The project, completed by a joint venture led by Technip project is led by Eni alongside with the other
Energies with JGC and Chiyoda, was completed ahead Area 4 partners, namely ExxonMobil, CNPC,
of schedule and within budget despite extreme ENH, Kogas and Galp Energia.
conditions and logistics challenges through
the Bering Strait.

MODULE FABRICATION IN CHINA AND INDONESIA


Excellent yard performance based on:
Koniambo
KEY FIGURES
• Client: Xstrata
• Early interaction and extensive front-end work • Location: New Caledonia • 15 modules - 37,000 tons
• Recurrent gap analysis and audits
• Incentives for good QHSE performance • Nickel plant: 60,000 t/yr
Koniambo is a major mining and metal
• Close integration of client during selection development. It comprises an open-cut nickel
• Ferronickel production: 176,000 t/yr
mine and a pyrometallurgical plant. Koniambo • Open pit mines, wet material: 10MM t/yr
LOGISTICS • Ore to Mmtallurgical plant: 2.5M t/yr (dry)
Nickel Project is one of the world’s biggest and
• Module design: Accelerations and fatigue induced highest-grade nickel laterite deposits.
by severe navigation conditions
• Module sizing limited by Suez canal, Zeebrugge lock,
land transportation clearances
• Largest fleet of heavy transportation vessels ever
assembled 20 flat deck ships including semi-
submersibles

ACHIEVEMENTS
Safety
• TRCR 0.05 (target < 0.2); LTIR 0.011 (target < 0.07)
• >50 M MHs LTI-free achieved across all yards
Quality KEY FIGURES
• Average module carryover < 0.9% (0.16% for Tr3)
• Client satisfaction > 8/10 • 142 modules, some weighing more
than 6,500 tons
Schedule • 360 site preassembled piperacks (SPPs)
• First modules delivered 18 m after FID • 75,000 people involved
• All three train modules set on foundations within 45 m • 10 fabrication yards in China and Indonesia
• 20 heavy transportation vessels
• 1,600 supervisors in yards at peak

16 Modularization Modularization 17
Technip Energies - 02-2021 – Lonsdale Design

Contact:
modularization-technipenergies@@technipenergies.com

technipenergies.com