Professional Documents
Culture Documents
Modularization
Managing construction risk through
reduction of site manhours
Global leader in
modular solutions
Pioneering in plant modularization
Technip Energies’s expertise and needs, offering extensive methods for plantwide
know-how cover all aspects of experience in working with modularization planning.
modularization from design to yards, particularly in Asia and We have now referenced more
onsite integration. We assist our optimized designs to reduce than 2,000 fabrication partners
clients in defining the strategy or mitigate construction risks. who are classified and regularly
that best fits their project We have developed numerical assessed.
+40
YEARS OF EXPERIENCE IN
MARTIN LINGE
ZADCO SRP
DAS ISLAND OAG
PACIFIC NORTH WEST
UPPER ZAKUM 750
KARISH FPSO
+20
MAJOR PROJECTS
BLADE
DELIVERED OR UNDER
CONSTRUCTION PETRONAS FLNG
TORTUE FPSO
LAKE CHARLES
EAST AREA ICHTHYS FPSO
PRELUDE FLNG
+1.2 MT
CORAL FLNG
FPSO P58, P62 KONIAMBO
OF LNG MODULES
DELIVERED IN ROVUMA
LAST 10 YEARS
LIBRA FPSO
MOHO NORD WHEATSTONE
FPSO P76, P56
OFON 2
2 Modularization Modularization 3
Leading design and
fabrication of all
types of modules
As an EPC contractor and modularization specialist, Technip
Energies takes turnkey responsibility for delivery of process
plants using a wide range of modules from small to mega. Each
project is unique and no matter its size, a tailor-made cost
effective modular solution is available to our clients.
Onshore Offshore
small
MODULARIZATION
projects projects MITIGATES RISK
IN HARSH
OAG Das Island Energean Karish FPSO ENVIRONMENTS
710 t max/module 1,260 t max/unit
Recent project achievements
9,800 t total 13,200 t topsides + 1 LQ
have shown that modularized
construction provides
Large
• Artificial islands
in the Arabian gulf
Heat stress as for the Upper
Zakum 750 project in the
Arabian gulf
4 Modularization Modularization 5
Why
modularize?
Modularization is a strategy for industrial plant construction that
relies on the portioning of a facility into prefabricated sub-units
assembled in well-equipped and well-located fabrication yards
to be then transported to often remote construction sites where
modules are interconnected.t
Technip Energies has successfully executed projects using many types of modules from small
truckable skids to complete process units in mega modules.
6 Modularization Modularization 7
From concept Organization of a
to delivery modularized project
Technip Energies modularization expertise is A modularized project organization differs from a pure
available from the earliest project phases. stick-built approach. Technip Energies’s experience
shows that these differences fall into four main areas.
Project knowledge:
site survey, infrastructure PROCESS, SAFETY • MOF / site Infrastructure
u Identify constraints and logistics, labor... AND ENGINEERING • SPMT simulation for offloading
/ transportation / installation
• Process development • Preservation and
to consider module
v Assess optimized extent maintenance up to handover
arrangement and
of modularization subsequent layout
w Develop preliminary
• Safety studies to be FABRICATION YARD
Modular design conducted at the earliest
definition and modularization plan stage • Early identification and
selection based on yard
optimization • Instrumentation and capabilities
x Screen and preselect electrical design focusing
and experience
suitable yards on minimizing
inter-modules cabling • Access and offloading
strategy
Decision on extent and local cabinet outside
of the modules • Precommissioning and
of Modularization commissioning capabilities
y Refine modularization /
• Steel structures defined (utilities)
fabrication plan for marine and land
transportation • Validate QHSE plan
U Select yards and freeze • Adapted civil designs
(underground and CONSTRUCTION SITE
execution strategy foundations)
• Civil (roads, platforms,
sewage, networks)
Finalize execution strategy
and pricing
SCHEDULE AND LOGISTICS • Hookup
V Start fabrication • Earlier procurement to suit • Pressure testing including
closure welds
module fabrication sequence
and duration • Cable pulling
• Optimized overall • Heavy lifts for equipment
Derisked outside modules
W Module transportation construction schedule
execution Pre-FEED considering site • Final precommissioning
and commissioning
X Installation and hook up activities, module fabrication
FEED duration at multiple yards
and erection sequence
EPC preparation
• Optimization of the module
at Overall plant mechanical shipping plan including
EPC
eventual transshipment
completion
• Heavy transportation vessel
screening and selection
8 Modularization Modularization 9
Floatover /
Unideck
Over four decades, Technip Energies has built up a worldwide
track record, designing and installing very large offshore platform
Stick-built vs. modular topsides by floatover and offering industry leading expertise
Technip Energies has developed NIMO, a ASSESSMENT OF MODULARIZATION in Transport & Installation (T&I) engineering design and
proprietary numerical simulation tool based on
Monte Carlo algorithms, to assess the best
T&I operation management.
Manhours Cost
construction strategy for a given project.
Our optimized solutions for modularization are based
MAIN OBJECTIVES: on demonstrated successful applications in EPCI projects:
Pre-assembly,
Pre-assembly,
Identify the optimum extent of modularization packing,
shipping and
packing, • Module weighing with load
(corresponding to minimum CAPEX) in terms of: delivery
shipping and
cells or hydraulic jacks
Site Construction
delivery
• module size/weight
Mechanical
Electrical
• Module load out by skidding
or with SPMT
• offsite manhours transferred from site to yard Instrumentation
Site Construction
Mechanical
management operations
configuration Civil works,
cable pulling,
• Method Statements for load • Coordination & supervision
out / load in during operations
underground
work, net • Module engineering for load
out /transportation / load in
working ...
Optimum extent etc. • Grillage /substructure design
• Internal & external sea
fastening design
NIMO, our simulation • Specification of equipment
tool, captures all aspects 0% % Work moved off-site 100% for load out / load in
& procurement
of modularization to • Quay design verification
Maximum
support the decision- modularization & preparation
making process. • Mooring system design
• Module preservation and
energization when required
10 Modularization Modularization 11
Mega Jack and skid deck module transfer to hull
modularization
We offer this cost effective solution to handle FLNG and other deck mounted mega modules.
The Mega Modularization technology consists of merging several conventional mid-size modules The skid deck elements are
into a single mega module containing complete systems with minimum interfaces. installed on the hull deck
stools and the mega module
Main benefits is lifted to the hull deck
level using a proven elevating
DESIGN SCHEDULE AND COST FABRICATION system such as climbing
jacks or gantries equipped
• Decrease the tonnage of • Save cost and integration • Feasible for many yards with strand jacks
structural steel time • Reduce required construction
• Reduce piping quantities • Decrease the number of area at yards
• Offer dedicated local, shipments • Decrease the number of
electrical and instrumental • Maximize precommissioning / loadouts
rooms per module allowing commissioning activities at • Reduce fabrication manhours The mega module is
full cable pulling at yard yard and enable the tests of
transferred onto the hull
• Extensive dimensions provide full / integrated systems
using hydraulic skidding and
for more flexibility to develop • Minimize integration work jacked down onto the stools.
an optimal layout taking into between modules
account: Process • Shorten planning, limit Full control of the hull level
requirements, center of integration is ensured by water
gravity, safety distances, • Offer integrated construction ballasting
operation and maintenance completion and
considerations (access, precommissioning and
evacuation…) commissioning activities, to
• No need of conventional reduce the risk of carryover
central pipe rack, freeing work
After completion of skidding
unused space • Simplify precommissioning
and jacking down operations,
• Reduce overall plant and commissioning
footprint sequences for site works the skid deck elements are
retrieved onshore
12 Modularization Modularization 13
Selecting and working
with fabrication yards
Assessing the yards’ technical
and commercial offering
During front-end engineering, several yards are prequalified. We use an open
bidder list to ensure the best yard is selected for a specific scope of work.
• HSE performance Technip Energies audits yards For selected yards, an agreement
• Quality and inspection of potential interest. Work is signed prior to final
• Fabrication capability packages can be adjusted to subcontract award to secure the
• Project management the yards’ capacity and best conditions and resources,
• Engineering capability competition may be increased. set the effective date, define
• Procurement and The preselected yards are early activities, close the audit
subcontracting plan audited a second time using actions plan and ensure the
• Resource mobilization the FMECA* methodology. immediate efficiency of the yard
• Price Main processes are audited after contract signature.
and design office disciplines Preselected yards are involved in
are reviewed. constructability reviews and
workshops to mitigate risks and
An action plan is issued to
adapt the design as necessary.
each yard. All actions are
closed out before the effective
date of the contract.
14 Modularization Modularization 15
Our key references Coral South FLNG
• Client: Coral FLNG SA
KEY FIGURES
• Location: Mozambique • LNG Capacity: 3,4 MTPA
• Water depth: 2,150 m
Coral South floating liquefied natural gas (FLNG)
is the third FLNG unit in the world and the
Yamal LNG largest floating structure in Africa, making one
of Technip Energies’s most important projects.
THE LARGEST MODULARIZATION PROJECT EVER
It will be the world’s first ultra-deep-water FLNG
• Clients: Novatek, Total, CNPC and Silk Road Fund
• Location: Russia facility to operate at a water depth of 2,000m
and is expected to produce 3.4 million tonnes
Yamal LNG is a large-scale LNG project in northern (Mt) of LNG a year. The Technip Energies-led TJS
Siberia operated by the Novatek-TOTAL-CNPC-SRF Consortium involving JGC Corporation and
joint-venture. The scope of work included the design, Samsung Heavy Industries (SHI) was awarded
supply and startup of three LNG trains in an area the engineering, procurement, construction,
where major gas reserves had never been fully installation, commissioning (EPCIC) and subsea
developed due to the harsh arctic environment. scopes in a single contract, in June 2017. The
The project, completed by a joint venture led by Technip project is led by Eni alongside with the other
Energies with JGC and Chiyoda, was completed ahead Area 4 partners, namely ExxonMobil, CNPC,
of schedule and within budget despite extreme ENH, Kogas and Galp Energia.
conditions and logistics challenges through
the Bering Strait.
ACHIEVEMENTS
Safety
• TRCR 0.05 (target < 0.2); LTIR 0.011 (target < 0.07)
• >50 M MHs LTI-free achieved across all yards
Quality KEY FIGURES
• Average module carryover < 0.9% (0.16% for Tr3)
• Client satisfaction > 8/10 • 142 modules, some weighing more
than 6,500 tons
Schedule • 360 site preassembled piperacks (SPPs)
• First modules delivered 18 m after FID • 75,000 people involved
• All three train modules set on foundations within 45 m • 10 fabrication yards in China and Indonesia
• 20 heavy transportation vessels
• 1,600 supervisors in yards at peak
16 Modularization Modularization 17
Technip Energies - 02-2021 – Lonsdale Design
Contact:
modularization-technipenergies@@technipenergies.com
technipenergies.com