2021.04.08 Test Sequence For PMM Project (Rev7)
2021.04.08 Test Sequence For PMM Project (Rev7)
This “Test Sequence” describes proper process flow of each test item.
More detailed test process are written in “PV system Test Procedure”.
Once all the above items are finished, you can move to the next steps below.
Then, another individual inverter can be tested with the same processes from 13 to 15.
Once each individual inverter is tested, multiple inverters together can be tested with the same
processes of 14.
Project : BUILDING B PHOTOVOLTAIC SYSTEM
Location : LOT 2-A PHASE 1B FIRST PHILPPINE INDUSTRIAL PARK TANAUAN CITY BATANGAS
Subject : SOLAR SYSTEM TESTING AND COMMISSIONING DATE : 2021/4/6
2021/4/7 2021/4/8 2021/4/9 2021/4/10
ITEM WORK DESCRIPTION LOCATION AM PM AM PM AM PM AM PM
REMARKS
PV SYSTEM Testing & Commissioning (25% Completion)
1 Isolation Device Function Test (Breaker test) West Side Roof Deck Done
2 Insulation Resistance Test (AC Cables & Bus Bars) West Side Roof Deck Done
5 Insulation Resistance Test (DC Cables) West Side Roof Deck Done
Rapid Shutdown Solution (RSS) Box Functionality Test & Connection of DC cable before Testing
6 West Side Roof Deck
PV String’s open circuit voltage measurement Disconnection of DC cables after Testing
7 Rapid Shutdown Solution (RSS) Signal Detection Test West Side Roof Top
Meralco Meter
10 MERALCO Emergency button’s trip function for RSS device
Vault/West Side Roof
Deck
11 AC Circuit Test (AC voltage & Frequency measurement) West Side Roof Deck ACB ON before Testing
Zero export setting (completely limit output power from inverter), Setting on EVT panel
Connectrion of DC cables
14 Inverter Operation & Zero export test (gradually release output power from ER-West
DC Switch of Inverter ON
inverter) MCCB of AC Collection Panel ON
15 PV String’s operating current measurement West Side Roof Deck By using clamp current meter