As per GI 7.024 section 9.2 critical lift plan is required for all critical lift or for a lift when
at least one vessel is afloat and the sea extends sea state 3.5(wind speed not more
than 32km/hr 20mph / 10mps or 17knots)
Officer and the crane operator must compare the date before starting the job.
Based on forecast observed weather and operations limit.
Risk to consider
Aramco Rigger duty is to provide clear signal and lift instructions by best
communication mean available. In offshore Radio is mostly used. Rigger should use
Radio communications in conjunction with the hard signals whenever possible. The
Aramco or third party designated Rigger or blanks man must wear high visibility vest
so that crane operator can immediately identify the person. The Aramco Rigger is
advised to use hand signal as well to make sure what is said in the radio.
Risk to consider
Who will consider the available power for crane? The chief, Second or third Eng. will
make sure the available power.
Picture taken at the Aramco offshore ( Marjan and Zulf ) field By Javed Kamal
Risk to consider
Pre-Use checklist.
Each Saudi Aramco certified crane operator shall perform a daily pre operation
safety inspection checklist prior to his crane and load limit using Saudi Aramco form
SA 9466. Crane need to be inspected very time before it is used
Risk to Consider
Rigger can see something which operator can't see. wire drum install above the
operator cabin
The lifting team certification as per Saudi Aramco assign capacity. Rigger 1 can lift
all type of load and also handle the critical lift. the lifting plan is requiring for all
critical lifting. Rigger one or assign Rigger 2/3 will give clear signal along with radio
communication.
Risk considers
Remembering that operator will only follow the Aramco certified signal and only
approved person is allowed to give signal.
Rigger will also pay attention to the boom and block. Always watch the blocks their
moment and distance from each other.
Risk to consider
Rigger will make sure and check the SWL of the hook and attached sling then
compare it to the applied load. Make sure All the lofting gear is in good condition
All attached device (rings, links, coupling pin etc) Shall be selected to provide
capacity equal or greater than sling used. check the safety pin on the shackles.
Risk to consider
The crane operator shall always sight on cargo or other type of heavy lift like Jacket
frame’s structure, top side, Heli pad etc. blind lift should be avoided. Radio
communication is preferred. Crane operator will not be rush especially in heavy
lifting like topside installation of jacket. He will not speed on request in such lifting.
tag line should be attached to the lifted object no matter how small or light it is.
Always keep a safe distance and use a hook to reach the tagline. when lifting from
other vessel and other boat, operator will evaluate if vessel can hold position under
the crane. specially care require for jacket lifting and topside. all the paper work like
Saudi Aramco Rigger 1 will prepared the lifting plan, other document like JSA and
Risk assessment. all critical lift required lifting plan approved by Rigger 1. Heavy Lift
lifting by the Monster like Subsea7 seven Borealis, Seven champions NPCC DLS 4000,
2000 MACDORMENT DLV 200.
Make sure the following when lifting jacket and top side in offshore
Only the authorized and essential person should be on deck in case of heavy lifting.
operator must know the load of heavy lifting. All the crane should have load charts
in the cabs stating lift capacity based on boom length, attachment, boom angel
outrigger configuration radius and lift quadrant
Risk to consider