You are on page 1of 12

MACOVS LIMITED

P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Date: 27/04/2023
Attention to: GM & MD
Subject: Progressive Work Report of the 3 Projects in Nipa

Contents
1. Power Project .............................................................................................................................................................. 2
1.1. Work Break-Down Structure Stages ................................................................................................................... 3
1.2. Current Work Progress........................................................................................................................................ 5
2. Aron-Sowa Road ......................................................................................................................................................... 6
2.1. Work Break-Down Structure .............................................................................................................................. 6
2.2. Factors Affecting Work Delay ............................................................................................................................ 7
2.3. Current Work Stage ............................................................................................................................................ 8
3. MPs Residency (Kiso Village) .................................................................................................................................... 9
3.1. Project Location .................................................................................................................................................. 9
3.2. Work Break Down Structure/Stages ................................................................................................................. 11
3.3. Current Work Stage .......................................................................................................................................... 12
Report Summary ............................................................................................................................................................... 12

Figure 1 Project Site Location ................................................................................................................................................ 2


Figure 2 Zone 1 (Banana Block) ............................................................................................................................................. 3
Figure 3 Preparing for foundation Figure 4 Moving pole to project site ................ 4
Figure 5 Pole foundation Figure 6 Pole Erection ............................. 4
Figure 7 Zone 2 (Guava Street)............................................................................................................................................... 5
Figure 8 Zone 3 ....................................................................................................................................................................... 5
Figure 9 Road 9m wide ........................................................................................................................................................... 6
Figure 10 Preparing for Gravelling ......................................................................................................................................... 6
Figure 11 Quarry Site-Visit Figure 12 Quarry Stockpile .................................. 7
Figure 13 Truck fuel & battery stolen ..................................................................................................................................... 8
Figure 14 Machine fuel stolen, the hose is cut ........................................................................................................................ 8
Figure 15 Project Location Kuso ............................................................................................................................................ 9
Figure 16 Perspective Image/View ....................................................................................................................................... 10
Figure 17 Clearing of vegetation & flattening of land ......................................................................................................... 11
Figure 18 ............................................................................................................................................................................... 11
Figure 19 Machine @ work .................................................................................................................................................. 12
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

1. Power Project
Project site Location.

Zone 2
Zone 1

Zone 3

Figure 1 Project Site Location


MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Figure 2 Zone 1 (Banana Block)

1.1.Work Break-Down Structure Stages


Stage 1. Preparing of Poles to be Erected.
i) Carry out all the necessary welding works at the campsite (Daniel Waswas Laydown area)

Stage 2. Pole Erection/Installation


i) Identifying and preparing the location of the pole to be erected
ii) Moving pole from cam site to the location where it will be erected
iii) Preparing for foundation and pole up the poles
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Figure 3 Preparing for foundation Figure 4 Moving pole to the project site

Figure 5 Pole foundation Figure 6 Pole Erection


MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Stage 3. Dressing poles with cross arms


Stage 4. Putting up conductors/black service line
Stage 5. Checking, tying, and pumping the conductions
Stage 6. MEN (Al-Cu); connect from the main power grid/supply to the service line

1.2.Current Work Progress


2. Erected 12 poles
3. 3 more poles are to be erected
4. Inspect existing poles whether to be used or not.
5. Working at a rate of 3/4poles per day.
6. Factors affecting work.
i) Minor quarrels with the residents living in the area the poles are to be erected.
ii) Bad weather is a challenge. when it rains we are forced to stop and it has been raining a lot in the month
of April.
iii) When manoeuvring our way around some tight locations is challenging.
At the moment we are working in Zone 1, completed Stage 1 and Stage 2 of the work. So far 12 poles have been erected
and 3 more poles to yet to be erected. The target is to get stage 2 completed by this week Friday. (30/04/2023).

Figure 7 Zone 2 (Guava Street)

Figure 8 Zone 3
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

2. Aron-Sowa Road
2.1.Work Break-Down Structure
Stage 1. Clearing & grubbing from Weap Ipa to Nipa Station (Nembi River) i.e. approximately 3.3km

Figure 9 Road 9m wide

Figure 10 Preparing for Gravelling

Stage 2. Gravelling
i) Stockpiling
ii) Moving materials with a dump truck

Stage 3. Culvert Installation


MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Figure 11 Quarry Site-Visit Figure 12 Quarry Stockpile

2.2.Factors Affecting Work Delay


i) Weather
- Since it is a fresh-cut road, during rainy days it is difficult to work.
ii) Local
- Since we resumed work on January 12 2023, the following are some of the resistance encountered:
o land issues,
o damaging machines and trucks, stealing fuel,
o threatening company employees
o Complaints from Quarry land owners
o Purchasing of fuel from Hagen to the Project Site for reasons beyond our control.
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Figure 13 Truck fuel & battery stolen

Figure 14 Machine fuel stolen, the hose is cut

2.3.Current Work Stage


i) Completed Stage 1 (clearing & grubbing) i.e. from Hindit Primary School to Nipa Station (Nembi River).
ii) About to commence on Stages 2, i.e. gravelling of subbase materials and installation of culverts. Note that
Stage 2 and Stage 3 of the work structure are intertwined.
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

3. MPs Residency (Kiso Village)


3.1.Project Location

Kaso Village

Figure 15 Project Location Kuso


MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

90m

Area 1

56m

110m

Area 2
105m

Figure 16 Perspective Image/View


MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

3.2.Work Break Down Structure/Stages


Stage 1. Stage 1. Earthworks (general clearing of waste, vegetation and topsoil to make the area flat)

Figure 17 Clearing of vegetation & flattening of land

Figure 18
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088

Figure 19 Machine @ work

Stage 2. Digging of trench/drainage around the perimeter of the designated area


Stage 3. Construction of HausMan & Grandstand
Stage 4. Obtain subbase materials (boulders) for the laydown area
Stage 5. Construction of retaining wall
i) Establishing a gabion basket to act as a retaining wall on the riverside

3.3.Current Work Stage


i) Finished clearing vegetation
ii) At the moment we’re cutting slope and planning mobilizing materials to construct HausMan & Grandstand
o We expect to have the hausMan erected within the next 14 days.

Report Summary
1. Power prophecy
o About 65% per cent of the work is completed in Zone 1. Zone 2 and Zone 3 to cover.
2. Aron-Sowa Road project
o Completed clearing grubbing or earthworks to Nipa station. (100%).
o Right doing we will be doing gravelling and culvert installation for the remaining 3km from Hindit
Primary School to Nipa Station.
3. MPs Residency
o We finished clearing vegetation and waste materials.
o At the moment, we are looking into levelling of the land and construction of HausMan & Grandstand.

Respectfully
Project Engineer.

You might also like