Nipa Projects Work Report
Nipa Projects Work Report
P O BOX 5859
BOROKO, NCD
PH: +675 72007088
Date: 27/04/2023
Attention to: GM & MD
Subject: Progressive Work Report of the 3 Projects in Nipa
Contents
1. Power Project .............................................................................................................................................................. 2
1.1. Work Break-Down Structure Stages ................................................................................................................... 3
1.2. Current Work Progress........................................................................................................................................ 5
2. Aron-Sowa Road ......................................................................................................................................................... 6
2.1. Work Break-Down Structure .............................................................................................................................. 6
2.2. Factors Affecting Work Delay ............................................................................................................................ 7
2.3. Current Work Stage ............................................................................................................................................ 8
3. MPs Residency (Kiso Village) .................................................................................................................................... 9
3.1. Project Location .................................................................................................................................................. 9
3.2. Work Break Down Structure/Stages ................................................................................................................. 11
3.3. Current Work Stage .......................................................................................................................................... 12
Report Summary ............................................................................................................................................................... 12
1. Power Project
Project site Location.
Zone 2
Zone 1
Zone 3
Figure 3 Preparing for foundation Figure 4 Moving pole to the project site
Figure 8 Zone 3
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088
2. Aron-Sowa Road
2.1.Work Break-Down Structure
Stage 1. Clearing & grubbing from Weap Ipa to Nipa Station (Nembi River) i.e. approximately 3.3km
Stage 2. Gravelling
i) Stockpiling
ii) Moving materials with a dump truck
Kaso Village
90m
Area 1
56m
110m
Area 2
105m
Figure 18
MACOVS LIMITED
P O BOX 5859
BOROKO, NCD
PH: +675 72007088
Report Summary
1. Power prophecy
o About 65% per cent of the work is completed in Zone 1. Zone 2 and Zone 3 to cover.
2. Aron-Sowa Road project
o Completed clearing grubbing or earthworks to Nipa station. (100%).
o Right doing we will be doing gravelling and culvert installation for the remaining 3km from Hindit
Primary School to Nipa Station.
3. MPs Residency
o We finished clearing vegetation and waste materials.
o At the moment, we are looking into levelling of the land and construction of HausMan & Grandstand.
Respectfully
Project Engineer.