You are on page 1of 72

THE PAPUA NEW GUINEA

UNIVERSITY OF TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
UNIT 3: PROJECT
CE 202 – CIVIL PLANNING USING
ENGINEERING SYSTEMS II
MS PROJECT
Creating a Project Plan

Prepared by:
Ms. Grace Wantepe
CE 202 Lecturer

Week 6 L6, Sem 2, 2019


2

Lecture Outline Preview


 This lecture will provide:
 Introduction to laying out most commonly
used project fields, for easiest data entry
 Introduction to configuring MS Project in a
typical layout tools, displaying typically
needed data
 Step-by-step creation of a simple sample
project
 Thislecture is prepared as the third of
three blocks in a building block
approach
CE 202: Civil Engineering Systems II
3

MS Project Rules of the Road


 Be prepared before using MS Project
 Have the required building blocks
defined
 Identify a clear project goal
 Identify tasks, resources, requirements,
limitations
 Identify relationships between tasks
 Constraints and Dependencies
 Identify a defined sequence for tasks
 Likeany tool, MS Project cannot define
the goal of a project, the user must do
that
CE 202: Civil Engineering Systems II
4

Building a Sample Project


Customizing the Layout

 Start by adding the Project Guide and desired


toolbars (refer to the previous unit for info)
 Next, configure the WBS (Tasks Lists) fields to
reflect the information desired
 The default configuration contains 7 columns
(fields) that show typical information
 Indicators, task name, duration
 Start, finish, predecessors, resource names
 Columnpositions can be changed by dragging
a column left or right (just like in MS Excel)
CE 202: Civil Engineering Systems II
5

Building a Sample Project


Customizing the Layout

 Right
mouse click when in the task area to bring up
a submenu

Select Insert Column

CE 202: Civil Engineering Systems II


6

Building a Sample Project


Customizing the Layout

A dialogue box will appear providing a


wide range of choices to add
information…
 Scroll to “Cost” and select it

A cost column has been added

CE 202: Civil Engineering Systems II


Building a Sample Project
Customizing the Layout

 Repeat this process adding these columns


 Critical, % Complete, Total Slack

Each column has hints, tips and detailed instructions that are
accessible by rolling the mouse over the column header

CE 202: Civil Engineering Systems II 7


Building a Sample Project
Customizing the Layout

 Drag
and drop columns for layout
according to personal preference…

CE 202: Civil Engineering Systems II


8
9

Building a Sample Project


Customizing the Display Settings

 Next, set customized display settings

Tools Menu, Options… Use the tabs….

CE 202: Civil Engineering Systems II


10

Building a Sample Project


Customizing the Display Settings

 For this project use the default settings on


 The schedule and calendar tabs
 The edit, view, and calculation tabs
 Itis best to use the default settings until a
higher degree of comfort is achieved
 Once customized, these settings can be
set as default to reduce setup time

CE 202: Civil Engineering Systems II


11

Customizing the PERT Entry Sheet


Building a
 Open the PERT Entry
Sample Project
 Use the same “Insert
Sheet column” techniques to
add the same
columns…

CE 202: Civil Engineering Systems II


12

Customizing the PERT Entry Sheet

 The
Building a Sample Project
result will be the PERT Entry Sheet plus the
other columns from the task list
 This is not required but saves work later…

Mouse-over help/hints and tips are available in all views

CE 202: Civil Engineering Systems II


13

Building a Sample Project


Customizing Gantt Chart Display

• Customize the display for best results


• Use the default setting or add personal touches
• Switch from PERT Entry Sheet view to Gantt
View

CE 202: Civil Engineering Systems II


14

Building a Sample Project


Customizing Gantt Chart Display

 Invoke the Gantt Chart Wizard…


 Can only be accessed in Gantt and
Tracking Gantt views…

CE 202: Civil Engineering Systems II


15

Building a Sample Project


Customizing Gantt Chart Display

• Select Critical Path, this will automatically


calculate and display the critical path
• Critical path is displayed in RED

CE 202: Civil Engineering Systems II


16

Building a Sample Project


Customizing Gantt Chart Display

• Select the type of data to be displayed on the


Gantt
• For this project, select custom task information

CE 202: Civil Engineering Systems II


17

Building a Sample Project


Customizing Gantt Chart Display

• A Simple visual display provides easy status


reporting…

CE 202: Civil Engineering Systems II


18

Building a Sample Project


Customizing Gantt Chart Display

• Showing dependencies between tasks is a great


way to pinpoint relationships and potential conflicts

Non-critical link

Critical Link

CE 202: Civil Engineering Systems II


19

Building a Sample Project


Customizing Gantt Chart Display
 This
format will be applied to all projects until it is
changed…

CE 202: Civil Engineering Systems II


20

Building a Sample Project


About the Gantt Chart Display

 Criticaltasks and links are always displayed in RED


 Non Critical tasks and links are displayed in blue, or
another color the user prefers
 Formats can be changed at any time during
project planning or management but…
 Settle on a simple display that works best
 KISS (Keep It Simple Son)

Sample Gantt

CE 202: Civil Engineering Systems II


21

Building a Sample Project


Setting the Project Information

 One task remains before entering data


 Set the project information

OR

For the sample project, set


the start date to 6/29/04
CE 202: Civil Engineering Systems II
22

Building a Sample Project


Set Working Times

 Set
working times by using the Task Wizard or
accessing the menu
 Forthis project use the default settings in the
Wizard

CE 202: Civil Engineering Systems II


23

Building a Sample Project


Set Working Times

 Follow the steps in the wizard…

CE 202: Civil Engineering Systems II


24

Building a Sample Project


Enter Tasks

 Tasks
can be entered using the wizard, through
the Gantt view task list or the PERT Entry sheet

CE 202: Civil Engineering Systems II


25

Building a Sample Project


Enter Tasks

• Entering data through the PERT Entry Sheet


saves time…enter data only once for several uses
– Enter data before PERT analysis is conducted
– It will also populate the task dialogue boxes
– It will also populate the Gantt Task List
• To begin, enter the task names and durations
– Enter only Optimistic, pessimistic & expected durations
– PERT analysis will populate the duration field

CE 202: Civil Engineering Systems II


26

Building a Sample Project


Enter Tasks

• For this sample project enter these tasks:


TASK Optimistic Duration Expected Duration Pessimistic Duration
Foundation 1 week 2 weeks 3 weeks
Framing 2 weeks 4 weeks 7 weeks
Roof 1 week 2 weeks 3 weeks
Electrical 1 week 2 weeks 3 weeks
Sheetrock 1 week 3 weeks 5 weeks
Interior Paint 1 week 2 weeks 4 weeks
Exterior Paint 1 week 2 weeks 3 weeks
Landscaping 1 week 2 weeks 4 weeks

CE 202: Civil Engineering Systems II


27

Building a Sample Project


Enter Tasks
 The PERT Entry Sheet Should look like this
 Notice all tasks begin and end on the same day
 PERT Analysis has not been completed
 Notice all tasks appear to be critical…
 Task Dependencies have not yet been identified

CE 202: Civil Engineering Systems II


28

Building a Sample Project


Identify Task Dependencies

• Identify which tasks must finish before others


can begin – a task dependency
– Foundation must finish before framing begins
– Highlight both tasks and click the link icon

CE 202: Civil Engineering Systems II


29

Building a Sample Project


Identify Task Dependencies

• By identifying 1 dependency the plan has


changed…
– Start and end dates, critical task status
– 1 predecessor has been set – task 1 precedes tasks 2

CE 202: Civil Engineering Systems II


30

Building a Sample Project


Identify Task Dependencies

• This can also be accomplished by using the Task


Information submenu (right mouse click)

CE 202: Civil Engineering Systems II


31

Building a Sample Project


Identify Task Dependencies
 Using this same technique, identify and set the other
dependencies
 The roof is dependant on completion of the framing
 Electrical is dependant on completion of the framing
 Sheetrock is dependant on completion of the electrical
 Interior paint is dependant on completion of the sheetrock
 Exterior paint is dependant on completion of the framing
 Landscaping is dependant on completion of the exterior
painting
 Take a moment to think through the logic of these
dependencies – this is a critical part of planning a project
 Hint: highlight multiple tasks by using ctrl and clicking on
link icon
 Note: Tasks may be dependant on more than 1 other task
CE 202: Civil Engineering Systems II
32

Building a Sample Project


Identify Task Dependencies

• Notice how much the plan has changed and the


PERT Analysis has not even been completed
– Critical tasks and dependencies have been identified
– Start and finish dates have been identified

CE 202: Civil Engineering Systems II


33

Building a Sample Project


Completing the PERT Analysis
• All task information has been entered, it is
time to complete the PERT Analysis
• Press the Calculate PERT icon
• Click “Yes” on option boxes
– MS Project calculates dates and durations…

CE 202: Civil Engineering Systems II


34

Building a Sample Project


Completing the PERT Analysis
• Use these durations and critical task/path
designations for the PERT Risk Analysis

CE 202: Civil Engineering Systems II


35

Building a Sample Project


Explore the other views after the PERT Analysis is complete

• By navigating through the view menu, a variety


of charts and graphs display the plan
– Note: cost and resource info has not yet been added
– The critical path has automatically been identified in
RED, as have the critical tasks
• The Gantt charts and network diagram display
the PERT Analysis data, not the user provided
estimates
• Save the project and explore the views!
CE 202: Civil Engineering Systems II
36

Building a Sample Project


Explore the other views after the PERT Analysis is complete

 Gantt Chart view


 Notice the critical path in red?

CE 202: Civil Engineering Systems II


37

Building a Sample Project


Explore the other views after the PERT Analysis is complete

• Network Diagram
• Notice the Critical Path in Red? The Critical Tasks
in Red and non-critical tasks in blue?
– MS Project calculates dates and durations…

CE 202: Civil Engineering Systems II


38

Building a Sample Project


Explore the other views after the PERT Analysis is complete

• Calendar view… an easy-to-read planning


calendar

(Extract of the
calendar view)

CE 202: Civil Engineering Systems II


39

Building a Sample Project


Explore the other views after the PERT Analysis is complete

• Other views include tracking, optimistic, and


pessimistic Gantt charts…(under more views tab)
– Note: do not reformat the pessimistic and optimistic
Gantt views, the dates will be altered

Tracking Gantt
CE 202: Civil Engineering Systems II
40

Building a Sample Project


Explore the other views after the PERT Analysis is complete

Optimistic Gantt

Pessimistic Gantt
CE 202: Civil Engineering Systems II
41

Building a Sample Project


Building a Resource List

• Next, build a resource list


– A list of people and equipment needed for the project
– Use either the wizard or the resource sheet view

CE 202: Civil Engineering Systems II


42

Building a Sample Project


Building a Resource List

• For this project use the following information:


– Painters
• Ben Johnson, $10/hr, OT $15/hr
• Amy Wilson, $17.50/hr, OT $25/hr
– Landscapers
• Adam Stevens, $20/hr, OT $30/hr
• Jill Morris, $25/hr, OT $35/hr
• Contracted Equipment/workers
– Concrete crew, $15/hr, OT $25/hr
– Framers and Roofers crews, $10/hr, OT $20/hr
– Electrician, $40/hr, OT $60/hr CE 202: Civil Engineering Systems II
43

Building a Sample Project


Building a Resource List

• The resource sheet should look like this:

CE 202: Civil Engineering Systems II


44

Building a Sample Project


Assigning Resources to the tasks

• Assign resources to tasks by any of several


methods:
– In the Task Information box
– In the task list area (WBS)
– In the PERT Entry Sheet
– Through the Wizard

CE 202: Civil Engineering Systems II


45

Building a Sample Project


Assigning Resources to the tasks

• For this project, 100% of the resource time is


available, if it needs to be changed, do so
through the resource sheet view

CE 202: Civil Engineering Systems II


46

Building a Sample Project


Assigning Resources to the tasks

• Assign tasks as follows:

CE 202: Civil Engineering Systems II


47

Building a Sample Project


Assigning Resources to the tasks

• As assignments are made, MS Project calculates


the costs…
• All required entries and calculations are
done…save the project!

CE 202: Civil Engineering Systems II


48

Building a Sample Project


Check the Project Statistics

• Checking the project statistics yields a snapshot


of costs and times

CE 202: Civil Engineering Systems II


49

Building a Sample Project


Saving a Project Baseline

• Saving a project baseline allows a user to track


progress and compare project expectations
– Compare estimates against actual durations, costs etc

CE 202: Civil Engineering Systems II


50

Building a Sample Project


Saving a Project Baseline

• A User can save up to 11 baselines in MS Project


• Very useful for situations where:
– New tasks are added
– The scope of the project changes
– Unexpected delays occur
– The project is crashed
– The project is relaxed
• Save each baseline as a new number using the
scroll down menu in the save baseline area
CE 202: Civil Engineering Systems II
51

Building a Sample Project


Adding A Few Personalized Touches

• The project is functional and complete but


adding a few extra touches gives it structure
• Add a top level task that serves as a title and
project overview

•Indent all subsequent tasks


• Do not assign resources
• Marked critical
•But is Not critical for
PERT Risk analysis
CE 202: Civil Engineering Systems II
purposes
52

Building a Sample Project


Adding A Few Personalized Touches

• Add a milestone that serves as project closure


•Link to all other physical tasks
•Mark dependencies as FF (Finish
to Finish) in Task Info Tab
• Do not assign resources
• Marked critical
•But is Not critical for PERT
Risk analysis purposes

CE 202: Civil Engineering Systems II


53

Building a Sample Project


Adding A Few Personalized Touches

• Adjust Fonts for personal preference

CE 202: Civil Engineering Systems II


54

Building a Sample Project


Adding A Few Personalized Touches

• Divide tasks into phases


– Useful for large or complex projects
– Does not change project costs/duration/integrity
– Useful where functional use can be derived from
completed tasks where project is completed in phases

CE 202: Civil Engineering Systems II


55

Building a Sample Project


Adding A Few Personalized Touches

• The result is a professional, highly visual plan

CE 202: Civil Engineering Systems II


56

Updating a Sample Project


Updating a Project

• Updating a project is simple if a few basic rules


are remembered
– Update the % complete and the date the work is done
• Otherwise MS Project assumes the date the task is competed
is the date the task was scheduled to be completed
– Enter a finish date only when the task is finished
– Enter a % complete (when work is in progress but not
complete) so MS Project can track and forecast task
and project completion

CE 202: Civil Engineering Systems II


57

Building a Sample Project


Assigning Resources to the tasks

• Updates can be made on Gantt view Task List


(WBS) view or in the Task Information Tab

Task Information Tab

Gantt view Task List CE 202: Civil Engineering Systems II


58

Managing a Sample Project


Reports and graphs

• Simple reports can help all concerned stay in


touch with a project
– Go to Reports on the View menu for a wide range of
wizard driven reports – or create a custom report!

CE 202: Civil Engineering Systems II


59

Managing a Sample Project


Budget Reports

• Budget overviews…

And budget reports that show under and over budget tasks and resources…
CE 202: Civil Engineering Systems II
60

Managing a Sample Project


Cross tabs

CE 202: Civil Engineering Systems II


61

Managing a Sample Project


Crashing a Project

• Projects can be crashed using MS Project


– Add extra resources to the resource list and assign
them to tasks to shorten project duration and/or
– Assign existing resources overtime (OT) work
– To assign overtime, insert 2 new columns in the Task
Usage View and add OT as appropriate

CE 202: Civil Engineering Systems II


62

Managing a Sample Project


Crashing a Project

• Projects can be crashed using MS Project


– Crash projects with caution – it is a disruptive action
• Do a what if crashing exercise and save the
baseline separately, keeping the original project
intact – allows exploration without risk
– Compute crash savings and costs – how much time
will be saved and how many extra $ it will cost
• Refer to early instruction units for these techniques or
• Examine variances between baseline in MS Project
CE 202: Civil Engineering Systems II
63

Managing a Sample Project


Crashing a Project

• Project will update the costs and changed


durations accordingly
• Remember – effort required to complete a
task/project remains fixed, only duration changes
• Save the baseline of a crashed project to
compare against original estimates and
expectations
• Be sure to check critical tasks status; non-critical
tasks may become critical after crashing
CE 202: Civil Engineering Systems II
64

Managing a Sample Project


What MS Project does not do

• MS Project does not


– Compute probability of on-time completion
• Do this using the Excel PERT Calculator
– Refer to previous instruction for this technique
For this project,
there is a 39.64%
probability of
completing the
project within 13
weeks (the PERT
likely duration)…
CE 202: Civil Engineering Systems II
65

Managing a Sample Project


What MS Project does not do

… a 90.54%
probability of
completing the
project within 15
weeks…

INCLUDE ONLY CRITICAL TASKS IN PERT RISK ANALYSIS


CE 202: Civil Engineering Systems II
66

Managing a Sample Project


What MS Project does not do

…but only a 3.30%


probability of
completing the
project within 11
weeks.

INCLUDE ONLY CRITICAL TASKS IN PERT RISK ANALYSIS


CE 202: Civil Engineering Systems II
67

MS Project
Review and Final Thoughts

A strong tool that saves time


 Makes tracking project status easy
 Makes communicating project status easy
 Be prepared before beginning
 Use the program resources for assistance
 Wizards, guides and help function
 Save the project data often (in 2 places)

CE 202: Civil Engineering Systems II


68

MS Project
Review and Final Thoughts

 KISS (Keep It Simple Son)


 Stay in touch with the project
 If the plan doesn’t seem right it probably isn’t
– track down suspected discrepancies
 Practice makes perfect
 MS Project get easier to use with practice
 Start with default settings and then customize

CE 202: Civil Engineering Systems II


69

MS Project
Review and Final Thoughts

 MS Project automatically
 Identifies Critical tasks & the Critical Path (in RED)
 Computes Late/Early start and finish dates
 Computes Total Slack (A.K.A Total Float)
 Critical tasks will always have ZERO Total Slack
 Effort to complete a task is fixed
 Duration changes by adding or subtracting
resources; more resources = less duration

CE 202: Civil Engineering Systems II


70

MS Project
Review and Final Thoughts

 Even the best plan is still an estimate


 A plan is only as good as the data it uses
 Bad estimates = bad plans
 Risk Analysis must be computed separately
 Construct and use an Excel-based PERT Risk
Calculator
 MS Project is just a tool, the manager owns the
project and is responsible for its health
 Communicate status frequently and clearly

CE 202: Civil Engineering Systems II


71

Resources Used in This Unit


 Dr.Anthony Filipovitch
 MS Project, by Microsoft Corporation
 MS Excel, by Microsoft Corporation
 PM Body of Knowledge (PMBOK), Philadelphia:
PMI, 2000

CE 202: Civil Engineering Systems II


72

Any Question?
You have completed
MS Project Unit 2
Please proceed to
MS Project
Assignment/Exercise

CE 202: Civil Engineering Systems II

You might also like