Professional Documents
Culture Documents
LSS e-Learning
Curriculum under License from
91558NSW Vocational Graduate Certificate in Lean Six Sigma
Lean Six Sigma Australasia Unit 7001A Apply Lean Six Sigma Fundamental Skills and Knowledge
Key Objectives
Learn the difference between a capacity constraint and a
time trap
Lean Definitions
The following terms are used frequently to quantitatively describe the
output of a process and the critical process steps:
Capacity: The maximum amount of product (output) a process can deliver
(produce) over a continuous period of time
Takt Rate: The amount of product (output) required by the customers over
a continuous period of time
Time Trap: The process step that inserts the most delay time into a
process
Constraint: Any process step that is unable to produce at the exit rate
required to meet customer demand (internal or external Takt rate)
Workstation Turnover Time (WTT): The time it takes for all
products/services to pass through a workstation once in a processing cycle
What Is a Constraint?
Constraints limit the output capacity of the process
(sometimes called bottlenecks)
Constraints have less capacity than the prior or
subsequent steps/operations
Constraints are time traps that cannot meet
customer demand (a constraint is ALWAYS a time This is a
trap, but a time trap may not be a constraint!)
Constraint!!
Constraints can change over time (monthly, weekly,
even daily) based upon product mixes or special causes
(new product introductions, special orders, others)
Exit
Rate
Activity 1 2 3 4 5 6 7
Max. time to
Time
meet customer
demand
Activity 1 2 3 4 5 6 7
Project Focus
Time Traps or Constraints
Time Traps
Constraints
Constraint Identification
Takt Rate Analysis
LSS e-Learning
Curriculum under License from
91558NSW Vocational Graduate Certificate in Lean Six Sigma
Lean Six Sigma Australasia Unit 7001A Apply Lean Six Sigma Fundamental Skills and Knowledge
Example of
Takt Rate Analysis
Takt Rate = “Customer Demand” Main Production Board: Operation 3
An excellent workstation visual Yesterday: 443 Units 1.61 Units/ labor hr
control tool used to help operators Today: 445 Units 1.62 Units/ labor hr
8-9 AM 60 59 -8
2-3 PM 45 44 -4
The customer daily demand is 450 3-4 PM 30 29 -5
Constraint Identification Step 3: Each hour, write in the number of units produced in the previous hour
The Constraint is the operation or process Step 4: Write in the cumulative difference between the scheduled units
produced and the actual units produced
that produces below the Takt Rate Step 5: Write in any comments (frame welder down, no glass) as a reason for
meeting or not meeting the takt rate.
Aided exercise:
Constraint vs. Time Trap
Time (secs)
per unit
35 - 35 -
30 - 30 -
30 sec 40 sec 45 sec 35 sec 30 sec 40 sec 45 sec 35 sec
25 - 25 -
Per Per Per Per Per Per Per Per
20 - unit unit unit unit 20 - unit unit unit unit
Activity 1 2 3 4 Activity 1 2 3 4
Constraint Exercise
The Process
This production process is a four
step operation
Operation 1 Operation 2
Operation 3
Operation 4 Ship
Constraint Exercise
Basic Operating Data
The company has a customer demand of 16,000 units per
week.
Constraint Exercise
Operating Capacity
Operation Capacity/Mach # Machines
Operation 1 60 units/hr 3
Operation 2 25 units/hr 5
Operation 3 35 units/hr 5
Operation 4 80 units/hr 2
__________________________________________
2. What is the factory takt rate (units/hour)?
__________________________________________
3. What is the capacity time trap in the process? What is its’ capacity (in units
per hour)?
__________________________________________
4. Is the time trap a constraint (does it take longer than the takt rate – Yes/No)?
__________________________________________
5. If an additional piece of equipment is purchased to increase capacity at the
time trap, what is the new capacity?
__________________________________________
Time Trap
Identification
Workstation Turnover Time (WTT)
LSS e-Learning
Curriculum under License from
91558NSW Vocational Graduate Certificate in Lean Six Sigma
Lean Six Sigma Australasia Unit 7001A Apply Lean Six Sigma Fundamental Skills and Knowledge
To determine the time traps in a process one must consider the different
operating parameters of both the workstations in the process and the products
flowing through the process
For example
how do setup times, processing times, and batch sizes affect individual
workstations?
We can use some fundamental analysis that relate these parameters in a term
called Workstation Turnover Time (which is comparable to inventory
turns), to calculate the time trap
Definition of
Workstation Turnover Time (WTT)
WTT is the Workstation Turnover Time
the amount of time to setup and run all parts/products/services at a given
workstation once in a processing cycle
Formula
Setup A Process A Setup B Process B Setup C Process C Setup A Process A Setup B Process B Setup C Process C
WTTZ WTTZ
Setup A Process A Setup B Process Setup A Process A Setup C Process C Setup A Process A Setup B Process B
B
WTTZ
WTT for workstation Z is the same in both scenarios
Aided exercise:
Workstation Turnover Time Example
Use the data given below to solve for WTT= [(Setup Timei )+(Process Timei
x Batch Sizei)]
WTT = [(SetupA)+(Process TimeA x Batch SizeA)+(SetupB)+(Process TimeB x Batch SizeB)]
[(4 hrs)+(.01 hrs/unit x 1000 units) + (4 hrs) + (.01 hrs/unit x 1000 units)
WTT = [(4 hrs) + (10 hrs) + (4 hrs) + (10 hrs)]
WTT = 28 hrs
Key Learning
How to identify capacity constraints in a process
LSS e-Learning
This Training Manual and all materials, procedures and systems herein contained or depicted (the
"Manual") are the sole and exclusive property of Kirtland Leadership Pty Ltd/ Lean Six Sigma
Australasia (“LSSA”).
The contents hereof contain proprietary trade secrets that remain the private and confidential property
of LSSA. Unauthorized use, disclosure, or reproduction of any kind of any material contained in this
Manual is expressly prohibited. The contents hereof are to be returned immediately upon termination
of any relationship or agreement giving user authorisation to possess or use such information or
materials. Any unauthorised or illegal use shall subject the user to all remedies, both legal and
equitable, available to LSSA. This Manual may be altered, amended or supplemented by LSSA from
time to time. In the event of any inconsistency or conflict between a provision in this Manual and any
federal, provincial, state or local statute, regulation, order or other law, such law will supersede the
conflicting or inconsistent provision(s) of this Manual in all properties subject to that law.
© 2012 by Kirtland Leadership Pty Ltd
All Rights Reserved.
“Lean Six Sigma Australasia” is a registered name of
Kirtland Leadership Pty Ltd
LSS e-Learning
Curriculum under License from
91558NSW Vocational Graduate Certificate in Lean Six Sigma
Lean Six Sigma Australasia Unit 7001A Apply Lean Six Sigma Fundamental Skills and Knowledge