Professional Documents
Culture Documents
Va2-Yu03-P0lf-150001 - Overall - Plant Operation Philosophy - Rev 0
Va2-Yu03-P0lf-150001 - Overall - Plant Operation Philosophy - Rev 0
Owner’s Engineer
Contractor
Sub-Supplier
Project
Title
RECORD OF REVISION
Rev. Date Page Affected Description of Revision
Rev.0 1 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
CONTENTS
1. GENERAL ............................................................................................................................ 3
1.1. PROJECT GENERAL ........................................................................................................ 3
1.2. PLANT CONFIGURATION .............................................................................................. 4
1.3. ABBREVIATION ................................................................................................................ 6
2. UNIT OPERATION ............................................................................................................ 7
2.1. NORMAL OPERATION OF THE UNIT ......................................................................... 7
2.1.1. CONSTANT PRESSURE OPERATION .......................................................................... 7
2.1.2. SLIDING PRESSURE OPERATION ................................................................................ 8
2.1.3. FREQUENCY CONTROL ................................................................................................. 8
2.1.4. FUEL CHANGE OVER ...................................................................................................... 8
2.2. ABNORMAL OPERATION OF THE UNIT .................................................................... 9
2.2.1. ISLAND OPERATION (HOUSE LOAD OPERATION) ................................................ 9
2.2.2. LOSS OF UNIT AUXILIARY POWER .......................................................................... 10
2.2.3. TOTAL GRID BLACK OUT ........................................................................................... 10
2.2.4. RUNBACK OPERATION ................................................................................................ 10
2.2.5. BOILER OPERATIONS WHEN STG TRIPS ............................................................... 10
3. UNIT CONTROL .............................................................................................................. 11
3.1. FUNCTION OF UNIT MASTER CONTROL................................................................ 11
3.2. CONTROL MODE OF UNIT MASTER CONTROL ................................................... 12
4. BFP AND TRANSFER ECO. INLET FCV TO MOV ................................................... 12
5. STEAM TURBINE BYPASS SYSTEM .......................................................................... 13
5.1. FUNCTION FOR UNIT START-UP ............................................................................... 13
5.2. MONITORING OF STEAM PRESSURE ...................................................................... 13
5.2.1. SLIDING OPERATION OF THE UNIT......................................................................... 13
5.2.2. CONSTANT OPERATION OF THE UNIT ................................................................... 13
5.3. QUICK DUMP OF THE STEAM DURING ABNORMAL OPERATION ................. 14
6. SUPPLY OF AUXILIARY STEAM FOR UNIT START-UP ....................................... 14
7. UNIT MASTER TRIP AND PROTECTION.................................................................. 15
7.1. IN CASE OF STG TRIP ................................................................................................... 15
7.2. IN CASE OF BOILER TRIP ............................................................................................ 16
7.3. IN CASE OF ALL CWP TRIP ......................................................................................... 16
Rev.0 2 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
1. General
This document provides the general description about overall plant operation philosophy for
Vung Ang 2 THERMAL POWER PROJECT.
This document is supplemented by other engineering documents such as P&ID, System
description, Design criteria, Logic and loop diagram, Key single lie diagram, Overall plant
startup & shutdown procedure and etc.
The Facility is consistd of two 600 MW nominal, net capacity Units, firing imported coals. The
design steam conditions of the Units are at enhanced super-critical levels.
The Facility is designed to fire a mixture of bituminous and sub-bituminous coals, to be delivered
to the Site by sea going vessels.
The generated output of the plant will be transmitted to the national electricity network by 500
kV connections.
Plant is designed to operate safely and reliably, and be able to deliver the full electrical output for
each Unit at TMCR condition.
Valve-wide-open (VWO) of the turbine is defined as 103% of throttle steam flow at TMCR
conditions. VWO gross output will be approx.102.8% of TMCR gross output.
The steam evaporation rate of the boiler at BMCR is at least equal to the sum of the steam flow
required by the turbine at its valve wide open (VWO) rating plus the auxiliary steam
consumption requirements.
The Facility is capable to operate on sliding pressure, between 40% and 100% TMCR while the
steam pressure will remain constant below 40% TMCR.
The specific conditions associated with guaranteed performance levels are as stated in the table
below.
Air temperature (dry bulb) 32 °C
Relative humidity 84 %
Atmospheric pressure 1013 mbara
Sea water temperature at condenser inlet 29.3°C
Make-up water flow 0% with cycle isolation condition
Auxiliary steam flow 0%
Feedwater Heaters All in service
Rev.0 3 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
The coals fired during Commissioning and Testing shall have constituents and fuel
characteristics as shown in Chapter 2, paragraph 2.2.2 of the Owner’s Technical Requirements.
The coal shall be as close as possible to the performance coal in composition and characteristics
such that a reasonable comparison to guaranteed performance can be made. During the boiler
efficiency test, the heating value and constituents of the test coal (including volatile matter and
fixed carbon) shall be within a +/- 5% (relative) band of the performance coal analysis for ASME
Code test corrections to apply.
Correction shall follow ASME PTC 4.
The Net Electrical Output Guarantee (NEOG) and Net Heat Rate Guarantee (NHRG) shall be
based on Performance Coal” as specified in Chapter 2, paragraph 2.2.2 of the Owner’s Technical
Requirements.
Rev.0 4 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
Rev.0 5 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
1.3. Abbreviation
APC Automatic Plant Control
APS Automatic Plant startup & shutdown Sys.
BFP Boiler Feedwater Pump
BLR Boiler
BMCR Boiler Maximum Continuous Rating
BOP Balance of Plant
CEP Condensate Extraction Pump
CID fan Combined Induced Draft fan
CRH Cold Reheat
CRV Combined Reheat Valve
CW Circulating Water
CWP Circulating Water Pump
DFO Distillate Fuel Oil
ESP Electro Static Precipitator
FCV Flow Control Valve
FD fan Forced Draft fan
FGD Flue Gas Desulfurization System
FW Feed Water
GAH Gas Air Heater
GR fan Gas Recirculation fan
H/W Hot Well
HDR Header
HP High Pressure
HRH Hot Reheat
HTR Heater
ID fan Induced Draft fan
IP Intermediate Pressure
LDC Load Dispatch Center
LDO Light Diesel Oil
LP Low Pressure
M-BFP Motor driven-Boiler Feedwater Pump
MCV Main Control Valve
MFT Master Fuel Trip
Misc. Miscellaneous
MOV Motor Operated Valve
O&M manuals Operating & Maintenance manuals
OFA Over Fire Air
P&I diagrams Piping & Instruments diagrams
PRDS Pressure Reducing and Desuperheating station
RFV Reverse Flow Valve
RPM Revolution Per Minute
RO Rated Output
SAH Steam Air Heater
SCR Selective Catalytic Reduction
SSDV Steam Seal Dump Valve
STG Steam Turbine Generator
SW Sea Water
TBN Turbine
TMCR Turbine Maximum Continuous Rating
UMC Unit Master Control
VWO Valve Wide Open
Rev.0 6 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
2. Unit Operation
Unit operation of the plant is classified into normal operation and abnormal operation.
Main Steam pressure is divided into 2 sections in operating load range of the unit.
Main Steam pressure at inlet of Steam Turbine maintains;
- From 275 bar(a) to 110 bar(a), sliding when load of unit is between 665 MW (100%
load of TMCR) and 266 MW (40% load of TMCR)
- 110 bar(a), constant when load of the unit is equal or lower than 266 MW (40 % load
of TMCR)
Rev.0 7 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
Rev.0 8 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
During AVT(O) mode, ammonia dosing will be done to maintain pH levels in the range of 9.2 –
9.6.
OT is normally applied during on-load steady state operation
If cation conductivity is stable at less than 0.15 μS/cm at CPP outlet and boiler economizer inlet,
OT is applicable by operator.
During treating boiler water by OT, vent valve into atmosphere installed on de-aerator has to be
maintained close and pH should be maintained 8.0 to 8.5 by adjusting ammonia dosing
After transition to OT operation, If cation conductivity(at Eco. Inlet) exceed 0.15 μS/cm (up to
0.3 μS/cm), the pH should be increased to more than 9.2 while continuing to dose oxygen.
If cation conductivity(at Eco. Inlet) exceed 0.3 μS/cm, oxygen dosing should be suspended, and
chemistry regime should revert to AVT(O).
If cation conductivity(at Eco. Inlet) exceed 1.0 μS/cm, the plant shall be immediately shutdown.
In case of the house load operation, the unit control system reduces its loads rapidly to prevent
turbine overspeed and each steam turbine generator supply power to its auxiliaries to maintain
the minimum loads and allowable maximum period of the house load operation is one (1) hours.
As per the house load operation command signal boiler enters run back operation mode and
maintains 40% of TMCR. During this operation surplus steam due to load difference between
boiler and steam turbine generator is delivered into ST condenser through HP and LP bypass
station, and power operated relief valve at boiler final superheater outlet can be used if necessary.
HP turbine exhaust steam is sent to condenser by opening ventilator valve automatically to
prevent from HP tubine exhaust overheating and the steam temperature will be controlled by
desuperheater during this operation.
If the grid recovers from the normal condition within one(1) hour, the unit may prepare re-
synchronization to the grid and increase power generation after successive grid re-connection.
Otherwise, if the abnormal condition of the grid continues over one(1) hour, the unit shall
prepare to plant shutdown.
Rev.0 9 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
Reduced Reduced
List of Equipment No. of
Boiler Steam
tripped Remark
Description Specification Load Turbine Load
BOP
(equipment name) (i.e 2X50%) (Target) (Target)
CID Fan 2X50% 1 50% 50%
Note 1) In case any pulverizer trips, runback will be to 60% load if 3 pulverizers are still running, to 40% load if 2
Note 2) In case of one (1) CWP trips, the unit does not enters run back operation mode but operator shall decide whether
reducing load of the unit is required and to consider seawater temperature at the Plant common cooling water discharge
point.
Rev.0 10 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
3. Unit Control
Automatic sequencing of each power generating unit from off-line to full load with minimized
operator intervention to ensure safe, reliable and highly efficient operation will be provided.
Operator intervention will include break-points in the sequence where the operator must confirm
that all vital pre-start conditions are acceptable before proceeding. Off-line is defined as the
Feedwater tank is enough heated, the steam turbine is on turning gear, fuel oil tank and coal silo
levels are suitable for continuous firing, and all auxiliaries are in service.
After start-up is completed, the load control shall follow the electrical load set point signal
established for each unit. As per the load control, the plant will be operated automatically for the
normal condition (above plant 40% TMCR load) and the disturbance condition such as runback
or house load case.
As part of this unit level sequencing, automated functional groups and subgroups of related
equipment will be included.
All automation capabilities and supervision of normal unit or plant operation will be performed
by the operator from the DCS operator workstations in the CCR.
It is important that all start-up and shut-down sequencing and operating procedures shall be
developed in close coordination with the equipment manufacturer’s information such as start-up
curves, operation procedures, etc.
The plant normal shut-down will be initiated by a shut-down command issued by the CCR
operator. The normal shut-down sequence will allow the plant to be shutdown in efficient and
orderly manner automatically with minimized operator intervention. All precautions required for
a safe plant shut-down of each system or piece of equipment will be applied.
Rev.0 11 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
The BFP which runs variable speed modulates feedwater pressure and flow after opening pump
discharge MOV, and one BFP is able to operate 50% load of TMCR.
In principle, transfer economizer inlet FCV to MOV as following but finally decided at
commissioning stage;
During start up and low load until about 30% load of TMCR feedwater flow to boiler is regulated
by economizer inlet FCV till it becomes almost fully open.
When Unit output increases and reaches to about 30% load of TMCR, economizer inlet FCV
position will be about 80~90%. Then MOV provided in parallel to the FCV will start to open and
the FCV will keep full open position.
Simultaneously, BFP change to flow control mode with keeping 30% FCV at fixed position.
Rev.0 12 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
Rev.0 13 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
LP steam bypass valve will quickly open to pre-determined position which is calculated by
energy balance at each load of unit and desuperheating water spray valve will be activated by
enthalpy calculation and then, reheat steam pressure as well as the steam temperature at the outlet
of steam bypass valve will be managed with feedforward control.
But in case of run back operation, pressure monitoring function of HP and LP bypass system is
able to manage the over pressurization of the steam.
Auxiliary steam into auxiliary steam header which operates at 16 bar(a) will be fed in the
following order (During start-up of unit, auxiliary steam will be supplied from another operating
unit or auxiliary boiler up to following load) ;
Another unit aux. steam header ⇒ Startup unit aux. steam header : up to 20 % of TMCR load
Auxiliary boiler ⇒ Startup unit aux. steam header : up to 20 % of TMCR load
Aux. steam supply from main steam will be started when unit load is equal or higher than 10 %
of TMCR, and Aux. steam will be supplied from cold reheat steam when unit load is equal or
higher than 50 % of TMCR.
Rev.0 14 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
On an emergency turbine trip, all MSV, GV, RSV and ICV will be closed instantly.
Conditions which will cause a turbine trip are as follows:
- Generator Trip
- Stator Cooling Water Outlet Temperature high-high
- Lack of stator cooling water flow
- High vibration high-high
- Low vacuum of LP exhaust hood
- LP Turbine Exhaust Hood Temperature high-high
- LP Turbine LSB Temperature high-high
- HP Turbine Exhaust Temperature high-high
- TBN over speed
- EHC oil pressure low-low
- STG lube oil pressure low-low
- Main Oil Tank Level low
- HP turbine exhaust temperature High
- LP turbine last stage blade temp High
- Thrust Position High
Rev.0 15 of 16
OVERALL PLANT OPERATION PHILOSOPH
VA2-YU03-P0LF-150001
Rev.0 16 of 16