the 500/220kV Grid Stations NTDC under CE AM Safety Meeting (S) NTDC Hyderabad &Quetta region during he 1 evaluation year 2021-2022 and organized Safety Meetings successfully In near future more Safety Meeting s wll be organied.
reports after visit of Grid Stations under this office. TSG Technical Audit teams also visit the sites to Management HSE Walk-through/ Site Tours assess implementation related to safety of workers 2 and equipment. In addition to this DM (Safety) provided assistance to the Grid and T/L staff regarding Health Satefy and Environment. In near future more site tours will be arranged.
3 Asset Integrity Management N/A
During the visit of Deputy Manager (Safety) NTDC
Quetta, it reveals that there is huge shortage of T&P 4 PPE & T&P at every Grid Station However, Personal Protective Equipments (PPE) are available at all Grid Stations. List of PPE & T&P attached as Annex-A.
Electrical and Mechanical isolations system is being
implemented thoroughly as it is vital for safety of the workers. PTW is issued/cancelled after confirmation Electrical and Mechanical Isolation 5 from site that the electrical equipment has been completely isolated and ready to perform work.Temporary Ground and PPE is used while working on equipment. A well defined WAPDA’s Permit to Work system is implemented in NTDC. Permit to work (PTW) is issued by control room operator with the approval from NPCC /RCC as per approved format which shows nature of work, start & end timings , signatures of issuer and receiver. Only authorized Permit to Work 6 persons i.e SSO-I are allowed to issue permit and Test Inspectors /Foremans / LS-I are allowed to take permit for annual maintenance /Emergent shut situations in the presence of Assistant manager/Deputy Manager following all the SOPs. 1. Sample attached as Annex-B 2. PTW Documents attached as Annex-C
Performance Assessment Department and TSG
Department have visited Grid Stations under GM HSE Audit AM South Office. The Audit conducted by these two 7 department are properly reported and compliance of the same is submitted to track progress pertaining to recommendations.
No such emission of haramful chemical/gases which
Waste Disposal System cause hazard to anyone life so 8
First aid boxes are available at each Grid Station.
First Aid Facilities Inspection and refilling is carried out on monthly 9 basis to have sufficient First Aid Facility available at sites.
Emergency Drill performed at 500kV Grid Station
NTDC Jamshoro, 500kV Grid Station NTDC NKI, Emergency Management 10 220kV Grid Station NTDC Hala Road Hyderabad, 220kV Grid Station NTDC TM Khan and 220kV Gird Station NTDC Jhampir I,220kV Daharki. Incidents are reported accurately in minimum possible time and subsequently investigated on top Incident Reporting and Investigation priority. The finding/recommendations of 11 Investigation Reports are circulated to all offices with strict instruction for implemention of recommendations to avoid any mishaps in future.