You are on page 1of 2

GNQ INDUSTRIAL &

Date Prepared: ___________


CONTRACTING CORPORATION
Project:

Client Name: AMMONIA PUMP


Page __1__ of ____ page/s
PRE-COMMISSIONING CHECKLIST

Unit Designation: End User Name:


Project Name: Contact Number:
Project Number: Address:

Pump Motor
Model HP/KW Phase
Make FLA Make
Serial No: Motor No: Model
TDH (FT): Voltage Frequency (Hz)
Flow rate: Speed (RPM) Efficiency (%)

Mechanical Check Remarks


1. Check the external cleanliness of the pumps, remove and clean replace all strainers
2. Check that flow direction is correct
3. Check that all components, bolts, fixing, tie bars, etc., are secured
4. Check that the impellers are free to rotate
5. Check the level and plumb of pump and motor shaft and slide rails; (direct drive pumps
require particular attention in this respect)
6. Check the anti-vibration mountings for correct deflection
7. Check that the correct drivers are fitted
8. Check that the pipe work imposes no strain on the pump connections
Operational Check
9. Check pump-separator elevation.
10. Check actual motor load is lower than FLA rating
Starting The Pump
Adjust the valves in following order:
1. Close drain valve
2. Open vent valve
3. Open valve in discharge line one quarter.
4. Slowly open valve in suction line fully.
5. Open suction vent valve (if present) fully.
6. Fill pump with liquid.
7. Open valve in bypass line.
8. Check wiring of motor and heater. Make sure that once liquid is admitted to pump,
Prepared by: __ s T Accepted by:

GNQ Representative Owner / Representative


(Signature of Over Printed Name) (Signature of Over Printed Name)

Ammonia Pump Pre-commissioning Checklist Form-GNQ-18 Rev 1


GNQ INDUSTRIAL &
Date Prepared: ___________
CONTRACTING CORPORATION
Project:

Client Name: AMMONIA PUMP


Page __1__ of ____ page/s
PRE-COMMISSIONING CHECKLIST

heater is on.
9. Allow pump to cool down for approximately one hour.
On any subsequent start-up of the pump, after it has been shut down for one or more days,
The oil reservoir should be vented of any vapor accumulation, and oil should be added as
necessary.

10. Start the Pump.


START-UP DATA
Insulation Testing Rotation
G-L1 G-L2 G-L3 L1-L2 L2-L3 L1-L3 Clockwise Counter Clockwise

Prepared by: __ s T Accepted by:

GNQ Representative Owner / Representative


(Signature of Over Printed Name) (Signature of Over Printed Name)

Ammonia Pump Pre-commissioning Checklist Form-GNQ-18 Rev 1

You might also like