Professional Documents
Culture Documents
1
University of Petroleum and Energy Studies, Dehradun, 248007, India
Abstract: Gas processing plant is having many hazards which are inherent to the facility.
Even though gas processing installations are generally located in remote areas,
experience shows that residential/industrial units come up in close proximity
with the passage of time. Hence, these installations which store, process and
handle large quantity of flammable materials, pose threat to surroundings as
well, in addition to their own safety. Such conditions, therefore, necessitate the
introduction of in-built fire protection facilities. It is impossible to design the
fire protection facility to control catastrophic fires. Normally fire protection
systems will prevent the spread of fire and to prevent emergencies so the
installations and surrounding can be protected. So designing an effective
firewater network plays an important role in controlling the spread of fire. This
paper deals about the design and analysis of firewater network for a typical
onshore gas processing plant based on OISD - 116.
Application rate:
As required by OISD-116, application rate
to be considered for each fire zone area is
1
l/min/m².
Allowance:
An allowance of 372 m3/hr shall be
considered for supplementary hose stream
protection and/or use of mobile fire-
FIRE ZONE DELIANETION fighting equipment to protect adjacent
equipment.
A Fire zone is a geographical area of the
plant, where certain minimum
requirements shall be respected so that in
case of fire occurring within a fire zone,
Alternative-2: Fire water demand for Monitors shall be located at strategic
10*10 m area locations for protection of cluster of
Fire water demand is calculated by columns, heaters, gasifiers, etc., and where
consider 10*10 m area of process unit on it is not possible to approach the higher
fire & provide cover on area of 30 m x 30 levels. A minimum of 2 monitors shall be
m area. provided for the protection of each such
area. Water monitors for protection of
Application rate: heaters shall be installed so that the heater
As required by OISD-116, application rate can be isolated from the remainder of the
to be considered for each fire zone area is plant in an emergency.
10.2 l/min/m².
Monitors shall provide protection to
Allowance: firemen in case of fire and it is also placed
An allowance of 372 m3/hr shall be in such a direction to direct water on the
considered for supplementary hose stream object. The monitors should not be
protection and/or use of mobile fire- installed less than 15 M from hazardous
fighting equipment to protect adjacent equipment.
equipment.
There should be proper planning for the
Alternative-3: Fire water demand for placement of HVLRs so that it delivers its
Water Spray system (Deluge system) intended purpose. The maximum distance
Fire water demand for the deluge of monitors from equipment protected
protection for each equipment is assessed. should be 45m.
The total no. of hydrants required to The total no. of monitors required to
protect the onshore gas processing plant is protect the onshore gas processing plant is
81. 22.
Nozzle specification
Nozzle specification
REFERENCES
1) Mannan, Sam, ed. Lees' Loss
prevention in the process industries:
Hazard identification, assessment and
control. Butterworth-Heinemann,
2004.
2) OISD 116 Fire Protection Facilities
for Petroleum Refineries and Oil/Gas
Processing Plants – Second Edition,
2012
3) Gordan P. Mckinnon, Keith Tower,
Fire Prevention Handbook, National
Fire Protection Association Harry E.