Professional Documents
Culture Documents
PRODUCTION SCHEDULING
Syllabus
2 Marks
Loading may be defined as the assignment of work to a facility without specifying when the work is
done and in what sequence.
Scheduling refers to the setting of operation start dates so that jobs will be completed by
their due date.
The master schedule, also known as master production schedule (MPS), formalize the production
plan and translates it into specific end-item requirements over a short to immediate planning
horizon.
1
4. What are Gantt charts?
Gantt charts are usual aids used to depict the sequencing, load on facilities, or progress associated
with work effort over a well defined time period.
Priority sequencing is a systematic procedure for assigning priorities to waiting jobs thereby
determining the sequence in which the jobs will be performed.
Dispatching rules, also known as priority rules or sequencing rules or scheduling rules, are the
rules used in obtaining a job sequence.
Priority sequencing is a systematic procedure for assigning priorities to waiting jobs thereby
determining the sequence in which the jobs will be performed.
EBQ scheduling is nothing but the economic batch quantity scheduling that can be performed by
using aggregate run-out method.
Line-of-balance is a charting technique that uses lead times and assembling sequencing to
compare planned component completion with actual component completions
10. List the various charts that are used in line-of-balance analysis.
2. Objective chart
3. Progress chart
The objective chart shows the contrast between expected completion schedule of production and
the actual performance.
2
12. When do you use progress chart?
The progress chart is a bar type chart which shows the actual number of items produced at each
operation stage against the quantities that should have been produced as indicated by line of
balance.
Materials requirements planning (MRP) is a computational technique that converts the master
schedule for final products into a detailed schedule for the raw materials and parts used in the final
products.
14. List the various inputs required for MRP (May 2011) (May 2009) (Nov/ Dec 2017)
1. Material requisitions
3. Labour cards/Tickets
4. Move cards/Tickets
5. Inspection cards/Tickets
Expediting, also known as follow-up or progressing, is a control function that keeps track of the
‘progresses’ of work in accordance with planned schedule.
17. List the various recording methods for the progressing purpose.
1. Gantt charts
2. Visual charts
3
18. What do you mean by dispatching? (Nov/Dec 2018)
Dispatching is the routine of setting productive activities in motion through the release of orders and
instructions, in accordance with previously planned times and sequences, embodied in route sheets
and schedule.
19. What is meant by kanban system? (May 2013) (April/ May 2017)
A Kanban is a card that is attached to a storage & transport container. It identifies the
• Part number
• Container capacity
• Other informations
• Status reporting
• Attending to bottle neck or holdups in production & removing the same
• Controlling variations or deviations from planned performance levels
• Following up & monitoring progress at work through all stages of production
• Co-ordinating with purchase, stores, tool room & maintenance department
• Modifying the production plan & re-plan if necessary
21. Distinguish between production planning & production control. (May 2010)
Production Planning: It means management decision to produce the product, pre production
activity
4
23. List the key functions of the production scheduling and control. (May 2009)
24. How do you represent the mathematically the manufacturing lead time? (May 2009)
25. Compare & contrast flow production scheduling & batch production scheduling. (May
2009)
Change over time & cost Change over time & cost
26. Distinguish between single machine scheduling & flow shop scheduling. (May 2012
Regulation 2004)
Dispatching is the routine of setting productive activities in motion through the release of
orders and instructions, in accordance with previously planned times and sequences, embodied in
route sheets and schedule.
28. Distinguish between master scheduling & operation scheduling? (May 2011 Regulation
2004) What is master scheduling? (April/ May 2017)
Master Scheduling : The master schedule, also known as master production schedule (MPS),
formalize the production plan and translates it into specific end-item requirements over a short to
immediate planning horizon.
Operation Scheduling: It expresses the overall plan in terms of specific end item to produce and
dates to produce them. It uses information from both forecast and orders on hand & it is the major
drivers for all major products.
29. Write any two ways reducing the problems in scheduling. (May 2011)
Loading Techniques:
6
16 marks
Production control through control mechanism, tries to take corrective action to match the planned
and actual production. Thus production control reviews the progress of the work and takes corrective steps in
order to ensure that programmed production takes places.
1. List out the functions of production scheduling and control.
The six key functions of the production scheduling and the control are;
➢ Release orders to the system in accordance with the priority plan.
➢ Assign jobs to specific work centers (including machine loading, or shop loading).
➢ Provide sequencing priorities to specify the order in which jobs are to be processed.
➢ Control the manufacturing lead time by tracking and expediting jobs if necessary.
➢ Monitor the priority status of the job via summary, scrap, reworks, and other reports.
➢ Monitor the capacity status of facilities via input/output reports of the workload versus capacity.
Output plan
Master schedule
Material requirements plan
Loading
Assigning specific jobs to each work
centre for the planning period
Sequencing
Determining the order of processing
of all jobs at each work centre
Scheduling
Establishing start and finish times of
all jobs at each work centres
Expediting
Monitoring progress, taking
corrective actions to minimize
deviations
➢ The above load chart should be prepared for each machine or a group of similar machines
available. However, now- a- days load charts are not commonly used since they are combined
with scheduled charts.
8
PRODUCTION SCHEDULING:
3. Discuss in detail about flow production scheduling and master production scheduling.(Nov/Dec
2012) (Nov/ Dec 2017)
A production schedule is like a time table that tells us what machine or department
should be doing what and when.
➢ The production schedule should be formulated for the method which satisfactorily matches the
systems requirements with the available resources.
SCHEDULING:
➢ Scheduling refers to the setting of operation start dates so that jobs will be completed by their
due date.
➢ Scheduling establishes the timing of productive activities that use the firm’s human and
equipment resources to serve its customers.
➢ Scheduling is used to allocate workloads to specific work-centres and to determine the sequence
in which operations are to be performed within the available capacity.
➢ Scheduling deals with:
✓ Which work centre will do which job?
✓ When should an operation/ job to be started and when should it end?
✓ On which equipment should it be done and by whom
✓ What is the sequence in which jobs/operations needed to be handled?
➢ The various functions of an effective production scheduling system includes:
i. Allocating jobs to facilities.
ii. Establishing a set of rules of priorities to sequence the activities on the facilities.
iii. Dispatching job orders as per the schedule to initiate loading of jobs to facilities.
iv. Reviewing the status of jobs as they are loaded and processed in the facilities
v. Expediting the critical jobs.
Objectives of the production scheduling;
✓ To meet the due dates
✓ To minimize lead time
✓ To minimize lead time
✓ To minimize setup time or cost
✓ To minimize work in process inventory
✓ To maximize machine or labour utilization.
Data Requirements for Scheduling
✓ The current status of jobs (what orders are in process and where);
✓ What upcoming jobs are available?
✓ The adequacy of materials and capabilities
9
✓ Equipment and labour utilization
✓ Job progress and efficiency
In addition, the system database must contain information on current inventory levels, lot
sizes, lead times, work-center capacities, set-up and run times, scrap rates, due dates, etc.
4. Discuss in detail the method of obtaining Master production schedule for a system with
examples. Suitable assumptions can be made.(Nov/Dec 2015)
Types of scheduling tools/techniques:
Mater schedule
Month Jan Feb Mar Apr May Jun Jul Aug Sep
AC motors:
15 - 30 - - 30 - - 10
5 hp
AC motors:
20 25 25 15 15 15 20 30 20
25 hp
DC motors:
20 hp - - - - - - 10 10 -
WR motors:
5 - - 15 15 5 - 20
10 hp 10
10
Inputs to MPS:
✓ Forecasts of demand of end items
✓ Customer orders
✓ Inventory on hand from the previous period.
Determining the Planning Horizon Length of a Master schedule:
✓ The planning horizon length (time span) of a master schedule depends on
• The type of product
• Volume of production
• Component lead times of the product being produced.
• The time horizon can be weeks, months, or some combinations, but the schedule
should encompass the lead times for all purchased and assembled components.
Functions of MPS:
▪ To translate aggregate plans into specific end items.
▪ To evaluate alternative schedules
▪ To generate material requirements
▪ To generate capacity requirements
▪ To facilitate information processing
▪ To maintain valid priorities
▪ To utilize capacity effectively
Master production scheduling process
12
2. Gantt scheduling chart
➢ A Gantt scheduling chart is used to track the progress of jobs as they pass through
departments in an organization.
➢ The vertical axis usually represents the departments in the sequence that jobs flow, and the
horizontal axis represents time.
➢ A job cannot be started in the next department until it is finished in the previous
department.
➢ Thus the chart makes easy to see the time required for and the current status of each job.
➢ Industrial engineers should always try to minimize the unassigned periods (in figure) to
make the best use of existing capacity and improve efficiency.
15
➢ SOT (Shortest time operating) - Run the job with the shortest completion time first, next
shortest second and so on. This is identical to SPT.
➢ Due data – earliest due date first – Run the job with the earliest due date first.
➢ Start date-due date minus normal lead time –Run the job with the earliest start date first.
➢ STR (Slack time remaining) – Difference between the time remaining before the due date
minus the processing time remaining. Orders with the shortest STR are run first.
➢ STR/OR (Slack time remaining per operation) – orders with shortest STR/OP are run first.
STR/OP is calculated as follows:
𝑆𝑇𝑅 𝑇𝑖𝑚𝑒 𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑔 𝑏𝑒𝑓𝑜𝑟𝑒 𝑑𝑢𝑒 𝑑𝑎𝑡𝑒 − 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑝𝑟𝑜𝑐𝑒𝑠𝑠𝑖𝑛𝑔 𝑡𝑖𝑚𝑒
=
𝑂𝑃 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛
➢ CR(critical ratio) – Orders with the smallest CR runs first. CR is calculated as the difference
between the due date and the current date divided by the number of work days remaining.
➢ QR(queue ratio) – Orders with the smallest QR is first run. QR is calculated as the slack time
remaining in the schedule divided by the planned schedule remaining queue in time.
➢ LCFS (last come, first served) – As orders arrive, they are placed on the top of the stack, the
operator usually picks up the order on top to run first.
➢ Random order or whim – The operators usually select whichever job they feel like running.
9. A manufacturing facility has five jobs to be scheduled on a machine. Their sequence of arrival,
processing time, and due-date are given in the table below.
16
Solution:
(i) FCFS (first-come first-served) rule: In this, the job which arrives first is scheduled first,
and so on, the FCFS rules results are shown below:
Flow time Lateness of job
Processing times Due date
Job sequence (Fi=Fi-1+ pi) Li= Fi - di ,
(pi ) days di (days)
(days) If Fi> di, otherwise zero
A 7 8 0+7=7 0
B 4 3 7+4=11 8
C 5 7 11+5=16 9
D 2 9 16+2=18 9
E 6 6 18+6=24 18
76 44
Mean flow time = 76/5 = 15.2 days
This rule gives top priority to that job which has shortest processing time. The resulting flow
times are as below.
17
iii) D Date (or earliest due- date) rule:
This rules gives top priority to the having earliest due-date as below.
This rule gives top priority to that job, which has arrived most recently, as below.
18
v) STR (Slack time remaining) rule:
The following table summarizes the results for the given problem.
It is observed mathematically that SPT rule yields an optimum solution for the n/l scheduling
problem than problem than other rules in minimizing average flow time, and average job lateness.
19
Scheduling n jobs on two machines (Johnson’s Rule)
Product sequencing
➢ Where n jobs must be processed by two machines, M1 followed by M2. The processing times
of all jobs on M1 and M2 are known and deterministic.
➢ It is required to find the sequence which minimizes the time to complete all jobs.
Johnson’s rule:
➢ The objective of Johnson’s rule is to minimize the flow time. From the beginning of the first
job until the finish of the last. In other words, this rule tries to maximize the concurrent
operating time both the machines.
Problem Content:
The n job 2 machine sequencing problem is completely described
➢ Only two machines are involved say M1, M2
➢ Each job is processed in the order M1, M2
➢ The exact or expected processing times for all jobs on both machines are known.
The problem is to determine the sequence (order) of jobs that minimizes the total completion
time.
Rules steps
➢ Step 1: List the operation time, each job on both machines
➢ Step 2: Select the shortest operations time.
➢ Step 3: If the shortest time for first machine, do the job first, if it is for second machine , do
the job last. Break any ties between jobs by sequencing the job on the first machine earliest
and that on the second machine latest. Jobs having the same time at both machines can be
assigned at either end of the available sequence.
➢ Step 4: Repeat the step 2 and 3 for each remaining job until the schedule is complete.
10. Processing time of five jobs on two machines are given below. Using Johnson’s rules, schedule
these jobs. Also find the minimum total flow time.
A B C D E
Machine M1 5 4 8 7 6
Machine M2 3 9 2 4 10
20
Solution: The sequence of jobs can be obtained as below.
i) The shortest time is for job c in machine M2 (2hours). So Place job C as late as possible
C
ii) The next shortest time is for job a in machine M2. So place job A as late as possible.
A C
iii) The next shortest time is a tie between jobs on the first machine M1 (job B) as early as
possible.
B A C
iv) The next shortest time is for job Din machine M2. So place the job as late as possible.
B D A C
We can get
State the steps in Johnson’s algorithm for solving sequencing problems of n jobs and 3 or 4 machines.
(April/May 2018)
Scheduling n jobs on three machines (n/3 scheduling)
Johnson’s method can be extended to yield an optimal solution for the n/3 scheduling problems.
21
➢ No passing of jobs is permitted (the same order over each machine is maintained)
➢ The exact or expected processing times on tree machines are known.
The method consists of replacing the given problem by an equivalent problem involving n
jobs and two machines. These two hypothetical machines are denoted by G and H and their
corresponding processing times are given by
Gi = M 1 i + M 2 i
Hi = M 2i + M 3i
11. Five jobs are to be processed on three machines. The processing times in hours are given
below. Find the optimal-sequence of jobs so that total elapsed time (i.e., total flow time) is
minimised.
JOB J1 J2 J3 J4 J5
A 5 7 6 9 5
B 2 1 4 5 3
C 3 7 5 6 7
Solution: Here minimum processing time on A is 5 hours and maximum processing time on B is 5
hours. Since minimum of A ≥Maximum of B, we can proceed the extended johnson’s method.
Now let us consider two fictitious machines G and H, and the processing times on them are given
below.
PROCESSING TIMES
Job G= A+B H=B+C
J1 7 5
22
J2 8 8
J3 10 9
J4 14 11
J5 8 10
Now using the original Johnson’s rule, the optimal sequence can be obtained as
J2 J5 J4 J3 J1
= 25 hours
= 12 hours Ans.
23
When there are two jobs each having its own processing sequence on m machines, the optimal
sequence of these jobs on the m machines to minimize the total processing time can be obtained by
using a graphical procedure.
➢ STEP 1: Construct a two – dimensional graph where x-axis represents the processing time and
the sequence of job 1 on the m machines while y-axis represents those of job 2 (use the same
scale for both x and y)
➢ STEP 2: Shade the areas where a machine would be occupied by the two jobs at the same time.
➢ STEP 3: The processing of both jobs can be represented by a continuous path which consists of
horizontal, vertical and 450 diagonal segments.
12. Two major parts P1 and P2 for a product require processing through five machine centres. The
technological sequence of these parts on the six machines and the manufacturing times on each
machine are given below:
Part P1 Part P2
Sequence of machines Times (Hours) Sequence of machines Times (Hours)
A 3 B 5
B 4 C 4
C 2 A 3
D 6 D 2
E 2 E 6
Using the graphical method, determine the optimal scheduling to minimize the total processing time
for these two parts.
Solution:
24
1. Draw lines (horizontal and vertical) OX and OY representing the processing time of job 1 and
job 2 respectively.
2. Then mark the processing times of the jobs on the machines in the given order as shown in
figure.
3. Then draw shaded rectangular blocks corresponding to each machine.
4. Now starting from starting point O, move on doing jobs avoiding the shaded rectangular
blocks until the finish point is reached. Here it is important to note that we should try to move
as much as we can, along a line inclined at angle 450 to the horizontal, wherever movement
along this line is not possible we shall move only horizontally or vertically.
13. Elaborate the procedure involved in determination of quantity, machine capacity and balancing
in batch production.(Nov/Dec 2015)
How to determine the economic order quantity in batch production? (Nov/Dec 2012)
14. Explain in detail about Aggregate run out method (Nov/Dec 2009)
Batch production scheduling:
➢ Batch production is preferred when a variety of products are to be made and the volumes are
not large enough to demand a separate line for each product.
➢ In batch production output is inventoriable and be produced in sustainable volume. It is
necessary to determine the lot size for a batch to be produced at one time in addition to
scheduling the batch on the facilities.
➢ The decision to be taken in these processes
✓ The economic batch size decision
✓ The scheduling decision.(regarding when to begin the processing of the batch)
1. Determination of economic batch quantity (EBQ)
25
The concept important and expressions of economic batch quantity have been discussed already.
1. Constant costs per piece C
2. Setup costs per batch S
3. Carrying cost
4. Storage carrying cost
2. Batch scheduling
Batch scheduling, also known as EBQ scheduling, can be performed by using aggregate
run out method.
a. Aggregate run out method
➢ Aggregate run-out method also known as aggregate run-out time (AROT) can be
used to determine production runs for a group of items that requires the same
production facilities. This methods computes run out time which along with inventory
- on hand will satisfy future demand for an item.
➢ The objective of run out method is to balance the utilization of production capacity so
that run out time for all the items must be same.
Procedure:
1. Compute the aggregate run-out time (AROT) of each item required for a product.
𝑴𝒂𝒄𝒉𝒊𝒏𝒆 𝒉𝒐𝒖𝒓𝒔 𝒊𝒏𝒗𝒆𝒏𝒕𝒐𝒓𝒚 𝒇𝒐𝒓 𝒂𝒍𝒍 𝒊𝒕𝒆𝒎𝒔 + 𝑻𝒐𝒕𝒂𝒍 𝒂𝒗𝒂𝒊𝒍𝒂𝒃𝒍𝒆 𝒎𝒂𝒄𝒉𝒊𝒏𝒆 𝒉𝒐𝒖𝒓𝒔
AROT =
𝑴𝒂𝒄𝒉𝒊𝒏𝒆 𝒉𝒐𝒖𝒓𝒔 𝒓𝒆𝒒𝒖𝒊𝒓𝒆𝒎𝒆𝒏𝒕𝒔 𝒇𝒐𝒓𝒆𝒄𝒂𝒔𝒕𝒆𝒅 𝒇𝒐𝒓 𝒂𝒍𝒍 𝒕𝒉𝒆 𝒊𝒕𝒆𝒎𝒔
2. Rank the items in the in the ascending order of their run-out times (ROT’S)
3. Schedule the item with the lowest ROT first, followed by the item with the next lowest
ROT.
15. The table below gives the data on the current inventory, production lot sizes, and standard
hours per unit and the forecast of demand for all items required for a product. Determine the
sequence of production (production schedule) using the aggregate run-out (AROT) method.
The available production capacity is 320 hours. Also analyse the effect of the capacity on the
schedule.
26
Item Standard Lot size Forecast Current Machine
hours per demand/week inventory hour per
unit order
A 0.20 200 70 200 40
B 0.40 300 100 240 120
C 0.30 200 80 260 60
D 0.40 400 120 160 160
Total = 380
Solution:
STEP 1: calculate AROT as shown in table below
Table: AROT determination
Standard Forecast Machine hours for Current Machine hours
Item hours demand the forecast demand inventory inventory
per unit per unit
A 0.20 70 70 × 0.2 = 14 200 0.20 × 200 =40
B 0.40 100 100 × 0.4 = 40 240 0.40 × 240= 96
C 0.30 80 80 × 0.3 = 24 260 0.30 × 260= 78
D 0.40 120 120 × 0.4 = 48 160 0.40 × 160= 64
Total = 126 hrs Total=278 hrs
278+320
AROT = = 4.746
126
STEP 2: Calculation of schedule requirements is shown below in the table
Gross requirements = forecast demand per week × AROT
Net requirements = gross requirements – current inventory
Table: schedule requirements
Item Standard Forecast AROT Gross inventory Current Net requirements
hours demand per inventory
per unit unit
A 0.20 70 4.746 4.746 × 70 = 332 200 332 – 200 =132
B 0.40 100 4.746 4.746 × 100 = 474 240 474 -240 = 234
C 0.30 80 4.746 4.746 × 380 = 380 260 380 – 260 = 120
D 0.40 120 4.746 4.746 × 570 = 570 160 570 – 160 = 410
28
Various charts used in LOB
➢ Operation program chart or assembly chart
➢ Objective chart
➢ Progress chart
➢ Line of balance chart
29
➢ If the LOB line is higher than the progress chart, the schedule is taken as delayed; otherwise
the production is well in advanced of plan.
➢ Thus management can take corrective action based on the information from LOB chart for
those components that lagging and causing production to fall behind of schedule.
17. List out the inputs required for MRP. Also explain the concept of MRP with neat sketch.
(Nov/Dec 2012)(May/June 2012) How MRP works? (May/June 2012) (Nov/Dec 2015)(April/May
2017) What are the components of MRP? (Nov/Dec 2017)
18. What are the Inputs to MRP? Explain them. (Nov/Dec 2011)
MATERIAL REQUIREMENTS PLANNING (MRP)
➢ Material requirements planning (MRP) is a computational technique that converts the master
schedule for final products into a detailed schedule for the raw materials and parts used in the
final products.
➢ The detailed schedule identifies the quantities of each raw material and part item.
➢ It also indicates when each item must be ordered and delivered so as to meet the master
schedule for the final products.
➢ MRP is a computerized system for managing dependent-demand inventory, scheduling
replenishment orders, and meeting demand for end items as given in the master production
schedule.
Basic characteristics of MRP
Two basic characteristics of MRP are
1. MRP drives demand for components, subassemblies, materials, etc., from demand for and
production schedules of parent items.
2. MRP offsets replenishment orders (purchase orders or production schedules) relative to the
date when replenishment is needed.
Information need for MRP:
➢ Demand for all products.
➢ Lead time for all finished goods, components, parts and raw materials.
➢ Lot sizing policies for all parts.
➢ Opening inventory levels.
➢ Safety stock requirements.
➢ Any order previously placed but which have not arrived yet.
Inputs to MRP:
1. Master production schedule
2. Bill of materials file
3. Inventory record file.
30
Structure of a material requirements planning (MRP) system
1. Master production schedule (MPS)
Master production schedule is a detailed plan that states how many end items (i.e final
product to be sold to customer) will be available for sale/distribution during specific periods.
Purpose of the master production schedule:
i. To set due dates for the availability of the end items.
ii. To provide the information regarding resources and the materials required to support
to support the aggregate plan.
iii. As an input to MRP, this will set specific production schedules for parts and
components used in end items.
Inputs to MPS
i. Market requirements.
ii. Production plan from aggregate planning.
iii. Resources available
MPS Output
The output of the MRP is the list of end items available every period that is feasible
with respect to demand and capacity.
Product structure:
➢ The structure of an assembly product in the form of a pyramid can be depicted as shown in
figure
➢ It can be seen from figure that the product P1 is the parent of subassemblies S1, S2. Similarly
S1 is the parent material of components C1, C2, and C3 and so on.
Working of MRP:
MPS provides a period-by-period list of final products required. The BOM defines what
materials and components are needed for each product. Then the inventory record file contains
information on the current and future inventory status of each component. By using these three
inputs, the MRP processor computes the number of each component and raw material required for the
given final product.
MRP Output reports
i. Primary outputs include:
i. Order release notice, to place orders that have been planned by the MRP system.
ii. Report of planned order releases in future periods.
iii. Rescheduling notice, to indicate the changes in due dates for open orders.
32
iv. Cancellation notices, to indicate the cancellation of open orders because of changes in the
master schedule.
v. Reports on inventory status.
ii. Secondary outputs include:
i. Performance reports of various types, to indicate costs, item usage, etc.
ii. Expectation reports, to show deviations from schedule, orders that are overdue, scrap and so
on.
iii. Inventory forecasts, to indicate the projected inventory levels in future periods.
Benefits of MRP
➢ Reduction in inventory,
➢ Quicker response to changes in demand,
➢ Reduced setup and changeover costs,
➢ Better machine utilization,
➢ Better production scheduling,
➢ Reduce production lead time
➢ Improved product quality.
DISPATCHING AND EXPEDITING:
19. Explain in detail about dispatching (May /June 2012)
What is meant by dispatching? Enumerate and list the various functions of dispatching.
Explain the various documents raised by the dispatcher. (April/May 2019)
Dispatching
➢ Dispatching is the routine of setting productive activities in motion the through the release
order and instructions, in accordance with previously planned times and sequences, embodied
in route sheets and scheduled charts.
➢ Once the production order is complete and the schedules are planned, then it is the
responsibility of the dispatching function to trigger off the flow of information and instruction
and with them the issue of materials, tools, production aids, drawing and specifications,
inspection orders, etc.
DISPATCHING ACTIVITIES
1. Movement of material from stores to the first process and from process to process.
2. Issues of tool orders instructing the tool department to collect and make ready tools, jigs and
fixtures in advance of the time at which the operation will start.
3. Issues of job order authorizing operations, in accordance with the dates and times previously
planned and entered on the machine loading charts, route sheets and progress control boards.
33
4. Issue of time tickets, drawings, instruction cards and other necessary information to personnel
performing the work.
5. Issue of inspection orders after each operation to determine the result in number of pieces good
and bad and the causes of spoilage.
6. Issue of move orders and collection of time tickets, drawings and instruction cards for all
completed operations.
Finally the dispatching function is responsible for keeping records of actual operations time, idle
man and machine times, length and causes of breakdowns, and any other relevant information about
reality keeping within schedule or deviating from it.
21. Explain the procedure for dispatching and explain the dispatching rules.(April/May 2011)
Dispatching rules
1. FCFS (first-come, first-served)
2. SOT (shortest operation time)
3. Earliest due date
4. Slack time remaining (STR)
5. Critical ratio (CR)
6. Queue ratio (QR)
7. Slack time remaining per operation (STR/OR)
Functions of expediting
The various functions/activities/duties of expediting include;
▪ Status reporting
▪ Attending to bottlenecks or hold up in production
35
▪ Controlling the variations or deviations from planned performance
▪ Follow up and monitoring progress at work through all stage of production
▪ Coordinating with purchase, stores, and tool room and maintenance departments.
▪ Modifying the production plans and re-plans if necessary
Types of progressing
The five types of progressing are given
▪ Programmed control
▪ Order progressing
▪ Shortage chasing
▪ Daily plan progressing
▪ Departmental progress control
Programmed control
➢ It is the task of comparing the actual production output with the production programme
and reporting deviations from plan to the line management for consideration and
correction.
➢ The different recording tools used for this purpose include Gantt charts, tabulated records.
Order progressing
➢ It is concerned with the control of internal orders and purchase requisitions.
➢ The four main progress record systems used for this purpose are
i. Due date filling
ii. Order delivery records
iii. Operation progress records
iv. List orders progress
Shortage chasing
➢ It is the task of comparing the actual availability of materials and parts with the
quantities required for production and of reporting any shortages so that they can be
produced quickly.
Daily plan progressing
➢ It is the control used to ensure that the daily plans made during dispatching are
achieved
➢ The general method used for this purpose is to have daily and weekly departmental
meetings.
Departmental progress control
➢ It is s method used to access the efficiency of the different production departments in a
factory.
36
➢ This is calculated by recording number of failures to complete orders by due-date in
each department at regular intervals and by comparing these quantities with the
prescribed limits of performance.
Recording progress
There are many recording tools available; the most widely used progress recording methods
are as follows:
1. Gantt charts:
➢ Gantt charts are used to provide an immediate comparison between schedule and
reality.
➢ This is achieved simply by marking on the schedule the actual progress of the
work.
2. Visual charts:
➢ Visual charts are nothing but variations of the Gantt chart, for example, a visual
control chart using a pin board.
➢ These charts present a current picture of the situation but leave no record of past
events.
➢ Visual charts often make use of colored bars, strings, moveable rulers, and meters
with numbers.
3. Cumulative and weekly charts:
➢ The cumulative chart shows how much we have managed to produce so far. The
weekly output charts depict the weekly fluctuations in production.
37