BILL OF QUANTITY AND COST ESTIMATION

PROJECT: BUSINESS VILLA MANSION

LOCATION: CHROY CHONGVA CITY


D. Landscape + Infrastructure Work
Material Cost (USD) Labor Cost (USD) Total Cost (USD)
Item Description Unit Quantity Remark
Unit Price Total Unit Price Total Unit Price Total

D-II Infrastructure work

D-II-12 Concrete for 12m street C28 (thk=0.15mm) Sq.m 3,017.83 25.00 75,445.75 10.00 30,178.30 35.00 105,624.05
D-II-13 Concrete Curb for sidewalk 3m m 504.95 5.00 2,524.75 2.00 1,009.90 7.00 3,534.65
D-II-14 Soil Compaction for sidewalk 3m Sq.m 567.89 0.50 283.95 0.50 283.95 1.00 567.89
D-II-15 Paving tile for sidewalk 3m Sq.m 567.89 7.00 3,975.23 3.50 1,987.62 10.50 5,962.85

Total for Landscape + Infrastructure Work $ 82,229.68 - $ 33,459.76 - $ 115,689.44