General Preliminary
I Provide Provisional sum for storage facility 1 L/S 0 0
Provide Provisional sum for health and safety materials 1 L/S 0 0
Provide hand tools and Equipment 1 L/S 500 500
Profiling: Pegs (round poles): setting out of profile including all
necessary benchmarks, levels, lines and frames, layout of entire
church building
Provide for site clearance (demolition of existing market tent) / Land
scape for proposed annex and equavilent levelling including all
1 L/S 150 150
topography works. The owner will decide optionly to execute
underground excavation works by direct manpower.
Provide timbers 2'' x 2'' x 14' 25 pcs 1.5 37.5
Provide wawa 1'' x 4'' x 14', rap and dress well 25 pcs 3 75
Provide wire nails 3'' for all profiling works 6 pks 2.5 15
timber 2'' x 6'' x 14' wall plat / Bottom tie, parallel with all bearing walls,
125 pcs 5 625
properly flushed and tied in place. And ridge piece and king post
timber 2'' x 2'' x 14' - purlines @ 3' - 0'' all center 230 pcs 1.5 345
fascia board 1'' x 10'' x 14' - dressed 28 pcs 5 140
wire nails 5'' 6 carton 45 270
wire nails 4'' 8 carton 45 360
wire nails 3'' 10 carton 45 450
steel nails 4'' 20 pks 2.6 52
28 Gauge aluminium roofing sheet 27 bundles 130 3510
roofing nails - 3'' and washier 30 box 5 150
carboline (apply carboline to timbers before roofing) 2 drums 50 100
braces (assorted timbers for bracing) 1 L/S 150 150
roofing felt 2 rolls 20 40
Ridge cap 24SWG 2' - 0'' grith 46 pcs 5 230
Grand total roofing works summary 6422
4 Ceiling - Hard Board Plywood 1/4'' x 4' x 8'; ceiling panel 2' x 4'
Provide materials as indicated:
hard board plywood/ceiling tiles 1/4'' x 4' x 8' 160 pcs 10 1600
ceiling strips 1/4'' x 2'' x 14' - dressed 38 bundles 9 342
timber 2'' x 2'' x 14' 380 pcs 1.5 570
steel nail 4'' 6 pks 2.6 15.6
wire nail 4'' 3 cartons 45 135
wire nail 3'' 8 cartons 45 360
wire nail 1 1/2'' 3 cartons 45 135
Grand total ceiling works summary 3157.6
General Electrical Works
All electrical wires are AWG or approved equal. Allow for the complete electrical services including site reticulation, cabling, wiring,
5 ducting, and accessories, conduits, trenches, cable pits, power oulets, light fittings, earthing system and switchboards, fluorescent bulbs /
energy saving bulbs in and around the building and the provision of electrical wires that is required to run the entire building all in
accordance with the specifications.
Provide materials as indicated:
85 W electrical lamp 80 set 10 800
sockets 80 pcs 3 240
recepticle outlet 40 pcs 1.5 60
A/C and water heater recepticle 8 pcs 1.5 12
single switch heavy duty 18 pcs 5 90
double switch 10 pcs 5 50
4'' x 4'' junction cup 30 pcs 5 150
5-face breaker panel box - distribution - complete - harvells 2 pcs 50 100
Pvc conduit - 1/2'' flexible tube 20 rolls 10 200
AWG 6mm 2 rolls 100 200
AWG 2.5mm 8 rolls 50 400
AWG 1.5mm 10 rolls 35 350
electrical tape 33+ 8 rolls 4 32
grounding rod - 24'' 2 pcs 75 150
Grand total electrical works summary 2834
General Doors. Fixed panel over doors made of 4'' x 1'' tongued and grooved boards on 4'' x 2'' ledges and braces fixed to 4'' x 2'' frame,
including one pair of 12'' galvanized steel ''T'' hinges and 1 No 6'' pad bolt and approved lack with minimum of 3 keys. Fixed panel over
6 door of 3 No 4'' x 1'' board fixed to frame with equal gaps.
Doors - Panel - & Plywood - all doors shall be finished products prior to installation. All timbers for wooden doors should be produced
from lovoa.
Provide materials as indicated:
Finished panel door (3'-0'' x 6'-9'' including frames) 15 sets 75 1125
Finished plywood door (3'-0'' x 6'-9'' including frames) for toilet 5 sets 75 375
Provide pairs of 4'' hinges to all doors frames 28 sets 2.6 72.8
yale lock - complete (cylinder lock set), that includes the cylinder, lock,
body and handle 20 sets 25 500
Bill of Quantity and Scope of work for the construction of an Annex for first Assembly Of God High School
Summary of estimate for the proposed annex
Section No.
I General Preliminary works 1375.2
1 Substructure and Foundation 65321.1
2 Superstructure - wall elevation 17593
3 Roofing works 6422
4 Ceiling works 3157.6
5 General Electrical works 2834
6 Door works 2072.8
7 Window works 2404.38
8 Tiling works 1133.3
9 Construction of General Septic Tank 1501.64
10 Plumbing works 1252.5
11 Painting works 3295
12 Finishing and Demobilization works 75
PROJECT SUMMARY
I General Preliminary Cost 1450.2
II Total Labor Cost @ 20% of materior Cost 21397.46
III Total Transportation Cost @ 10% of materials Cost 10698.73
Administrative Cost @ 1% of materials Cost 1069.87
IV Total Materials Cost 106987.32
Total Project inplementation Cost 141603.59
`