TASK Task Duration Start Date End Date

Site Preparation

Construction of Billboard 1 3-Jun 4-Jun

Construction of Facilities
4 3-Jun 7-Jun
for engineers

Prov. Of Furniture, Equipment


2 3-Jun 5-Jun
& Appliances for Field Engineers
Hiring of Manpower and
1 3-Jun 4-Jun
Equipments
Purchase of Materials 1 3-Jun 4-Jun
Mobilization 1 3-Jun 4-Jun
Planting
Digging Holes 1 7-Jun 8-Jun
Placing Trees and Backfilling 2 8-Jun 10-Jun
Closing
Clearing 7 10-Jun 17-Jun
Inspection 1 17-Jun 18-Jun
Handover 1 18-Jun 19-Jun
Task
TASK Task Duration Start Date End Date

3-Jun
4-Jun
5-Jun
6-Jun
7-Jun
No.

1 Construction of Billboard 1 3-Jun 4-Jun X X


2 Construction of Facilities 4 3-Jun 7-Jun
for engineers X X X X X
3 Prov. Of Furniture, Equipment 2 3-Jun 5-Jun
& Appliances for Field Engineers X X X
4 Hiring of Manpower and 1 3-Jun 4-Jun
Equipments X X
5 Purchase of Materials 1 3-Jun 4-Jun X X
6 Mobilization 1 3-Jun 4-Jun X X
7 Digging Holes 1 7-Jun 8-Jun X
8 Laying Trees and Backfilling 2 8-Jun 10-Jun
12 Clearing 7 10-Jun 17-Jun
13 Inspection 1 17-Jun 18-Jun
14 Handover 1 18-Jun 19-Jun
X
8-Jun
9-Jun

X X X
10-Jun
11-Jun
12-Jun
13-Jun
14-Jun
15-Jun
16-Jun

X X X X X X X X
17-Jun

X X
18-Jun

X X
19-Jun