Professional Documents
Culture Documents
FOR
PROJECT :
Lot G-71 Rollney @ Aeon Seri Manjung, Perak
Note:
- SCOPE OF WORK
- METHOD OF WORK
- INSPECTION
Project:
2.0 SPECIFICATION
The raised floor system shall consist of nominal 600mm or 24 inch square,
modular panels supported on pedestals that are secured to the structural floor
Panel shall be easily removable by one person with suction lifting cups, and
shall be interchangeable except where cut for special conditions.
Unless otherwise specified, performance of the access floor system shall comply
fully with :
ORGANIZATION CHART
Main Contractor
JUSO LIVING ENTERPRISE
Sub Contractor
CONFIDENTIAL
012-236 5689
Project Manager
4.0 METHOD OF WORK
The quality and efficiency of an installation is reflected in the tools chosen for
performing the works. The following tools and suppliers should be considered
for use on access floor installation projects.
Before taking possession of site, floor area must be clear of debris, floor surface
also to be smooth and ceiling works must be completed first to avoid from being
damaged later.
(Protection and learning of raised floor shall be done by others after completion
installation)
4.5 INSTALLATION
In the installation of an acces floor, there are certain criteria that should be
followed. These are listed in the general order of sequence.
4.5.1 Step 1
Verify The Room Dimension
4.5.2 Step 2
Determine Starting Points
4.5.3 Step 3
Layout Grid
Find the starting point in the room as shown on the
drawings. Seek approval to change the starting point
if cut panels at the perimeter will be too small to allow
proper support. Recommended minimum size of the
cut panels for proper support is 6inches wide.
NOTE: When starting the installation in the corner of
a room, stretch a dry line for line "B" before laying
down chalk. Check the distance from "B" line and the
"A" chalk line to the walls. If the distance to the walls
is over 24 inches at any point, move the entire line
closer to the wall so that the greatest distance is 24
inches or less.
4.5.4 Step 4
Check Control Line
4.5.5 Step 5
Target Finished Floor Height
4.5.6 Step 6
Glue Pedestal
.
4.5.7 Step 7
Bolt Stringers
4.5.8 Step 8
Lay Panels in one Direction
4.5.9 Step 9
Check for Rocking Panels
If a panel rocks diagonally when placed in the
system, turn it one quarter (90°) turn and
check it again. If the panel continues to rock
when rotated, some debris may be between
the panel bottom and the pedestal head or
stringer.
4.5.11 Step 11
Align Grid
After the first section of a floor is installed, check
to see that all the grid lines are straight. If the
grid is not square, you can make them square by
bumping the rows of installed panel with your
foot. If this fails, take up every third or fourth row
of panels and tap the bases in the direction of
the panels that have to be moved. All grid lines
should be straight before cutting in the perimeter
panels.
***Caution
Be sure not to create a lightness problem
that will result in difficult removal and
reinstallation of panels.
4.5.12 Step 12 After installing the first section of A/F, only one chalked
Proceed With Next Row control line along the long wall needs to be used for the
remainder of the floor. The initial section of floor
normally dictates the square ness and location of the
rest of the floor. However, it is possible in a long room
to allow a curve to develop in small increments in the
grid. Therefore, a dry line should be kept stretched
along the short wall until at least a four-panel-wide
section of the floor is installed the entire length of the
room.
In setting this dry line, secure one end at the starting
point on the grid line between the first two panels.
Raise the line about one inch off the panel, then stretch
the line to the other end of the floor and do the same
there. The line should not override the panel edges.
5.0 INSPECTION AND TEST PLAN
Examine structural floor for unevenness, irregularities and dampness that would
affect the quality and execution of the work. Do not proceed with installation
until the structural floor surface are level, clean and dry.
Please follow the below term & condition in order to prevent the condition in protect
the Raised Floor System;
6.1 Prior to allowing other trades on the access floor, the general contractor
and/or owner shall access the floor system.
6.2 When replacing or removing panels after initial installations, extreme care must
be taken not to chip or damage the edging. The tapered edging has been
designed to allow cays removal and installation with the proper tools. Do not
handle without using the special lifter. Do not drop or kick panels into position.
FORCE MUST NOT BE USED IN REPLACING PANELS.
6.4 When installing cable, no more than 5 panels or approximately 3 meters should
be removed at one time to avoid misalignment of the floor when re-installing.
This applies to all types of understructure.
6.5 The installer should exercise caution when pulling cable to not loosen the
adjusting nuts on the pedestals. This can happen when cables rub against the
nut and sufficient friction will tend to loose the nut
6.6 NEVER flood panels with water or a cleaning agent. This could cause damage
to the panels and affect electrical communication wiring underneath.
Aluminium Chequer Plate Panel & selected and approved floor tile requires
little maintenance and can be easily cleaned by dry mopping and
periodically damp mopping with mild detergent when necessary. Use of strong
cleaning agents, waxing, bugging or refinishing is not needed. Under normal
environmental conditions, do not clean floor surface with steel wool, nylon
pads or abrasive of any kind, manually or with power equipment.
6.7 Owner should clean the panels twice yearly and vacuum of understructure
and subfloor at least two times a year.
6.8 In the busy area such as corridor, gateway etc. excessive load shall be
avoided. Otherwise the floor will be easily damaged.
6.9 Areas for storage and installation must be clean, dry, ventilated and free from
both excessive and rapid variations of temperature and humidity.
If necessary, you can spot clean stubborn stains with a non-flammable organic
cleaner. But if you do, take care that the cleaner does not get into cracks between
the support panel and the laminate where it could adversely affect the bond.
DO NOT clean with mop saturated with oils or chemicals. A film on the floor will affect
performance