Business Project - Project Plan (IMask)
Business Project - Project Plan (IMask)
IMask
I. INTRODUCTION
II. Objectives
It will be hard to find all the good materials in Medium In order to have a good materials, we will try to
order to make the mask contact the company that have the same
product with us & we will act like a customer, so
we will try to get what materials did they use
and where it came from
The machine and the other stuff that we Medium We will try to find a way to get contact with the
need in order to make the item will not be seller and ask for corporation (if our product is
cheap booming, we will make a discount for the seller
of the companies family if they want to buy)
It will be hard to found the people who have Medium In order to fix this problem , we will try to make
a good skill in making a mask & face shield a good relationship with them, also we will
discuss about the high salary for the workers
The training style will be a little bit different Low We will try to make a group for the workers
because there is still pandemic about the training, example in Monday group 1
will be the one get train, etc.
It will be so hard to finding the perfect place Hard Not really sure about we fixing this but we will
for build the workplace, because we need to make a border house for the workers, so they
make sure that the place had everything that can live in there
they need (such as, if the person live to far
away from work place, its mean they need to
find an Apartment).
III.6 Milestones (Link with Project Scope)
Intitiating
Planning
All the materials & etc. 03/06/20 Completed Vyona Echaristy The materials is really
hard to find but it’s done
All the machines 04/06/20 Completed Immanuel Lasut All the Machines is
expensive but it’s done
Workers / Employees _ Progress Jeremy Teneh _
All the teams are ready to do their part which is Ressa as the president with a big responsibilities. Vyona as a
vice president & she already got all the materials, WBS/OBS/RAM. Mario Tampi as a Manager that will train
the workers in order to keep them in the company goals. Imanuel as a Assistant Manager that will help manager
on everything & Jeremy as a director of finance that will control all the money.
V. Constraints
Step 1 : The Manager Shall document all changes to the project scope, schedule, workforce, or cost as soon
as they are discovered.
Step 2 : The Project Manager will evaluate the change and determine the impact on a project before reporting
the issue.
Step 3 : After reviewing and determining the impact, the manager will find a way to fix the problem
Step 4 : After that the manager will meet and discuss the method he got earlier with the president and vice
president
Step 5 : After that the manager will apply the method that has been obtained earlier in order to meet the
deficiencies or problems that were previously agreed upon by the president and vice president.
I had already read and agree to the terms and conditions of the aforementioned Project Plan, and I guarantee
my complete dedication and support for the Project Plan.