You are on page 1of 3

PC/OP/CC

Brian E. Rawling, Brian E. Rawling & Associates

Many contracts in Hong Kong link the Department, the Water Services Department,
achievement of practical completion under and the Drainage Services Department, to
the contract to obtaining an occupation name just three. The main contractor and
permit (OP) from the Building Authority or subcontractors therefore not only have to
a certificate of compliance (CC) from the satisfy the Building Authority and
Lands Department. This is inherently wrong Authorized Person that the building has
as different authorities are involved in been satisfactorily constructed and
obtaining the OP and CC to those involved completed to OP standard as, before that can
in determining when a building has been be done, other authorities have to be dealt
completed to the standard of practical with and satisfied that parts of the building,
completion. Therefore, anyone drafting a e.g. fire services, plumbing and drainage,
contract to include reference to an OP or CC have also been satisfactorily installed,
should consider the different authorities completed and tested.
involved and the respective obligations
established by the Buildings Ordinance The works, which have to be completed, are
(Cap. 123). those parts of the building for which an
application for an OP is being made and
Practical Completion those works should have been constructed to
comply with Cap. 123. In addition, there
For practical completion, it is the architect must be a set of drawings and plans
under the main building contract who has to prepared by the Authorized Person, which
be satisfied that the building has "been are approved by both the Building Authority
substantially completed and shall have and the Fire Department. This approval is
satisfactorily passed any tests that may be necessary before the Form 516 for the fire
prescribed by the Contract, and/or any services inspection can be issued.
Named Sub-Contract, to be carried out
before Practical Completion" (i.e. clause When he is satisfied that the building
15(1) of the Swire Standard Form of complies with Cap. 123 and the approved
Building Contract for use in Hong Kong). drawings and plans, the Registered Building
Clause 15(1) of the HKIS Standard Form of Contractor has to submit, to the Authorized
Building Contract (May 1979 Revision) has Person, a completed and signed Form BA13
a similar provision without the requirement to signify that the building has been
for tests. The work, which has to be constructed in accordance with Cap. 123,
substantially completed, is usually defined the drawings and plans approved by the
as the Works, or a Section thereof, and it Building Authority and the Fire Department,
should have been constructed in accordance and has been completed to the standard
with the Contract. required for an OP.

Occupation Permit The Authorized Person then endorses the


Form BA13 if he is satisfied that the
For the OP, it is the Building Authority that building has been constructed in accordance
has to be satisfied that the building (or a part with Cap. 123, the approved drawings and
thereof if a temporary occupation permit plans and has been completed to OP
(TOP) is being sought) has been constructed standard. It is then the Authorized Person
in accordance with the Buildings Ordinance who is finally responsible, in accordance
(Cap. 123). Obtaining an OP also involves with Hong Kong law, for obtaining an OP, it
several other authorities such as the Fire is the Fire Department who decides if the
building complies with fire regulations relating to the OP are, therefore,
(similarly, the Water and Drainage Services unnecessary as the obligations are already
departments decide on compliance for defined in the Buildings Ordinance and exist
plumbing and drainage) and the Building at law.
Authority decides if the OP can be issued
and, if not, what work has to be done before Why should a contract refer to obtaining an
it can be issued. OP at all when participation in the OP
process and compliance with the Buildings
Hence, it is clear that the authorities Ordinance is part of the contractor's
concerned with obtaining an OP are obligations at law? The answer is (or should
different to the authorities concerned with be) timing. A developer may wish to obtain
practical completion. an OP at an early stage so that whilst the
main contractor completes finishings and
Certificate of Compliance non-essential building services (for OP
purposes) in one part of the building, the
Similarly, where a developer has to apply developer's tenants can commence their
for a CC before a development can be sold fitting out works in another part of the same
or used (irrespective of the OP having been building and vice versa.
obtained), then, again, it is a different
authority, usually the Lands Department, Further, in a residential development, sale
that has to be satisfied with the status of and purchase agreements may have
construction work. provisions relating to the OP being obtained
by a certain date. In such circumstances, a
OP - Timing developer will want his building contract to
reflect the provisions in the sale and
Obviously, for every development, the purchase agreements.
Authorized Person has to obtain an OP
before the building can be occupied but in Substantial Completion
the building contract there is no need to link
this requirement to practical completion. An What is the meaning of "substantially
OP can be obtained at a date relatively completed" as referred to in Clause 15(1) of
earlier than the date on which practical the HKIS and Swire Standard Forms?
completion is achieved as finishes and
passenger lifts (to name just two items) do One of the tests for substantial completion is
not have to be completed to obtain an OP that the building should be suitable for its
but they would have to be completed, and intended purpose. That would obviously
the lifts successfully tested, to achieve include obtaining an OP, as, without such
practical completion. permit, the building is not suitable for its
intended purpose as it cannot be occupied.
The main contractor, and certain specialist
subcontractors, has obligations under Cap. Therefore, where the standard form of
123 regarding compliance with building contract requires the building to be
regulations. Under Clause 4 of both the "substantially completed" before an
HKIS and the Swire Standard Forms of architect issues the practical completion
Contract, the main contractor is obliged to certificate, it is obvious that the obligation
carry out the works in accordance with would also include the Registered Building
building regulations (BERA consider that Contractor's issue of a valid Form BA13 and
this part of Clause 4 is unnecessary as participation in obtaining the fire services
contractors have this obligation at law in certificate (Form 172) and the OP.
any case). Further, contractual provisions
OP and LAD's Building Contractor or a specialist
subcontractor; e.g.:
The recovery of liquidated and ascertained
damages should not be linked to the OP as it Form 501 - for fire service;
is not wholly the contractor's responsibility Form FX172 - for ventilation;
to obtain the OP. The Authorized Person has Form H - for plumbing;
to prepare and submit to the Building Form 5 - for lifts.
Authority plans and drawings to obtain the OP and General Damages
Building Authority's approval thereof and
then he has to monitor the progress of Swire Properties Limited deal with the OP
construction and decide when to issue the procedures by including an item in the
Form BA13 to the Building Authority. This Preliminaries Bill which sets out separate
process can cause delay to the date when the obligations for the main contractor divorced
OP can be obtained. Therefore, if liquidated from his performance obligations under the
and ascertained damages were linked conditions of contract.
obtaining to the OP, they would become
void if it can be shown that delay in The preliminaries item refers to the OP
obtaining the OP was caused by anyone procedures, which the main contractor has
other than the main contractor. The main to participate in and ends with the issue of a
contractor, as the Registered Building valid Form BA13.91.
Contractor, is responsible for issuing a valid
Form BA13, but the issue of the Form Not only are these obligations additional to
BA13 may be delayed because of the main contractor's performance
amendments made by the Authorized obligations under the conditions of contract,
Person to previously approved drawings so but general damages for delay are also
that the final approved drawings depict what linked with the separate obligations in the
is built. event that the main contractor fails to
comply therewith.
Although the foregoing refers solely to the
Form BA13, the same applies to other (adopted from the HKIS Newsletter 10(7)b August
submissions which have to be made by 2001)
either the Authorised Person, the Registered

You might also like