You are on page 1of 280

Besi Kg/M' Besi Kg/M' Kg/Btg'

D 10 0.617 D 10 0.617 7.400


D 12 0.888 D 12 0.892 10.700
D 13 1.042 D 13 1.040 12.480
D 16 1.578 D 16 1.583 19.000
D 19 2.226 D 19 2.233 26.800
D 22 2.984 D 22 2.983 35.800
D 25 3.850 46.200

Besi ULIR Berat


Harga / Btng Hrg / Kg
SNI batang
D 10 7.40 - -
D 12 10.70 225,200 21,046.73
D 13 12.48 - -
D 16 19.00 370,700 19,510.53
D 19 26.80 - -
D 22 35.80 - -
D 25 46.20 - -
20,278.63

16,350.00 3920
Besi Kg/M' Kg/Btg'
D6 0.222 2.660
D7 0.303 3.630
D8 0.395 4.740
D9 0.500 6.000
D10 0.617 7.400
D12 0.892 10.700
D16 1.583 19.000
D19 2.233 26.800
D22 2.983 35.800
D25 3.850 46.200

Besi POLOS Berat


SNI
Harga / Btng Hrg / Kg
batang
D8 4.74 60,500 12,763.71
D10 7.40 90,800 12,270.27
D12 10.70 170,500 15,934.58
D16 19.00 197,800 10,410.53
D19 26.80 493,700 18,421.64
D22 35.80 612,000 17,094.97
D25 46.20 - -
14,482.62

15,400.00 30 14,450.00
DAFTAR HARGA SATUAN UPAH
Basic Price Semester II Tahun 2022 - Provinsi Maluku
( Update : 01 September 2022 )

Kode Region IV

NO URAIAN SATUAN UPAH (Rp.) KETERANGAN

1 Mandor Org/hr 200,000.00 On Site


2 Kepala Tukang Org/hr 175,000.00 On Site
3 Kepala Tukang Batu Org/hr 175,000.00 On Site
4 Kepala Tukang Kayu Org/hr 175,000.00 On Site
5 Kepala Tukang Besi Org/hr 175,000.00 On Site
6 Kepala Tukang Cat Org/hr 175,000.00 On Site
7 Kepala Tukang Listrik Org/hr 175,000.00 On Site
8 Tukang Org/hr 164,000.00 On Site
9 Tukang Batu Org/hr 164,000.00 On Site
10 Tukang Kayu Org/hr 164,000.00 On Site
11 Tukang Besi Org/hr 164,000.00 On Site
12 Tukang Cat Org/hr 164,000.00 On Site
13 Tukang Listrik Org/hr 164,000.00 On Site
14 Tukang Pipa Org/hr 164,000.00 On Site
15 Tukang Plitur Org/hr 164,000.00 On Site
16 Tukang Taman Org/hr 164,000.00 On Site
17 Pembantu Tukang Org/hr 120,000.00 On Site
18 Pekerja Org/hr 120,000.00 On Site
19 Buruh Lapangan Terlatih Org/hr - On Site
20 Buruh Lapangan Tidak Terlatih Org/hr - On Site
21 Penjaga Malam Org/hr - On Site
22 Sopir Org/hr 204,000.00 On Site
23 Operator Org/hr 225,000.00 On Site
24 Mekanik Org/hr 204,000.00 On Site
25 Pembantu Sopir Org/hr 133,000.00 On Site
26 Pembantu Operator Org/hr 133,000.00 On Site
27 Pembantu Mekanik Org/hr 133,000.00 On Site

harga belum termasuk PPN dan keuntungan


DAFTAR HARGA SATUAN BAHAN BANGUNAN
Basic Price Semester II Tahun 2022 - Provinsi Maluku
( Update : 01 September 2022 )

NO MATERIAL SAT HARGA (Rp) KETERANGAN

A. AGREGAT KASAR,BAHAN PEREKAT & BAHAN JADINYA


1 Pasir Urug m3 326,000.00 On Site
2 Tanah Urug m3 400,000.00 On Site
3 Sirtu Gunung m3 450,000.00 On Site
5 Pasir Pasang Kali m3 450,000.00 On Site
6 Pasir Beton m3 450,000.00 On Site
Pasir Pantai / Pasir Lokal m3 456,000.00 On Site
7 Abu Batu m3 634,000.00 On Site
9 Batu Pecah 1/2 (split SC/mesin) m3 550,000.00 On Site
10 Batu Pecah 2/3 (split SC/mesin) m3 550,000.00 On Site
11 Batu Pecah 3/5 (macadam) m3 500,000.00 On Site
12 Batu Pecah 5/7 (macadam) m3 500,000.00 On Site
13 Batu Belah Pondasi / Batu Kali / Batu Karang m3 450,000.00 On Site
14 Batu Bronjol (Untuk Bronjong) / Batu Kali / Batu Karang m3 450,000.00 On Site
15 Batu Koral Beton Kali / Kerikil Sungai (Cor) / Kerikil Pantai (kacang) / Kerikil Karang m3 450,000.00 On Site
20 Batako Kecil 8 x 10 x 20 bh 4,000.00 On Site
21 Batako Besar 8 x 20 x 30 bh 13,000.00 On Site
22 Con Blok 10 x 15 x 40 bh 10,000.00 On Site
23 Bata Merah Bakar kelas I bh 6,000.00 On Site
24 Bata Merah Bakar kelas II bh 6,000.00 On Site
25 Bata Merah Oven ( Klingker ) bh 6,000.00 On Site
26 Bata Ringan 10 x 20 x 60 bh 22,000.00 On Site
27 Roster Beton 20 x 20 bh 45,000.00 On Site
28 Roster Beton 30 x 30 bh 91,000.00 On Site
29 Grass Blok 20 x 20 bh 94,000.00 On Site
30 Grass Blok 30 x 30 bh 104,000.00 On Site
31 Paving Blok Segi Empat Natural 6 cm (50 bh/M2) m2 350,000.00 On Site
32 Paving Blok Segi Empat Warna 6 cm (50 bh/M2) m2 350,000.00 On Site
33 Paving Blok Segi Enam Natural 8 cm (30 bh/M2) m2 210,000.00 On Site
34 Paving Blok Segi Enam Warna 8 cm (30 bh/M2) m2 210,000.00 On Site
36 Semen PC /50 kg zak 150,000.00 On Site
37 Semen PC / kg / kg 3,000.00 On Site
38 Semen Putih Tiga Roda (40 kg) zak 260,000.00 On Site
Semen Putih Tiga Roda (per Kg) / kg 6,500.00 On Site
46 Kapur Pasang / Kapur Tembok kg 28,000.00 On Site
48 Semen Warna kg 30,000.00 On Site
50 Air ltr 200.00 On Site
52 Hollow/Con Blok 8 x 20 x 40 bh 10,000.00 On Site
53 Hollow/Con Blok 8 x 15 x 40 bh 10,000.00 On Site
54 Hollow/Con Blok 8 x 10 x 40 bh 10,000.00 On Site

B. LABURAN,PENGISI DAN ALATNYA


1 Plamir Tembok Big Lion (5 kg) bks 37,000.00 On Site
2 Cat Tembok ICI Eksterior / Dulux Eksterior (Beton) kg 88,333.33 On Site
3 Cat Tembok ICI Interior / Dulux Interior (Plafon & Dinding) kg 60,000.00 On Site
4 Cat Tembok Metrolite kg 67,200.00 On Site
7 Cat Dasar kg 44,000.00 On Site
9 Pelapis Alkali ICI ( Cat Dasar Beton Ekterior ) kg 83,000.00 On Site
11 Water Profing Emulsion kg 83,000.00 On Site
13 Rool Cat Tembok bh 76,000.00 On Site
20 Kwas 3" bh 24,000.00 On Site
33 Tiner Avia Biru lt 62,000.00 On Site
34 Tiner Super lt 87,000.00 On Site
39 Ampelas lbr 16,000.00 On Site
41 Meni Kayu / Besi kg 68,000.00 On Site
43 Cat Kayu (Glotex) lt 96,000.00 On Site
44 Cat Besi lt 96,000.00 On Site

Page 4 BHN
NO MATERIAL SAT HARGA (Rp) KETERANGAN

47 Karet lis bh 5,000.00 On Site


48 Minyak cat lt 74,500.00 On Site
50 Residu lt 23,000.00 On Site

C. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Bambu 5 s.d 7 bt 45,000.00 On Site
2 Bambu 7 s.d 10 bt 57,000.00 On Site
11 Kayu Balok Kamper Samarinda m3 8,484,000.00 On Site
12 Kayu Papan Kamper Samarinda m3 8,484,000.00 On Site
21 Dolken 5 s/d 7 bt 55,000.00 On Site
22 Dolken 7 s/d 10 bt 60,000.00 On Site
26 List Profil Kamper 5 cm m1 12,500.00 On Site
27 List Profil Kamper 10 cm m1 23,500.00 On Site
31 Kayu Kaso 5/7 Kamper Medan m3 4,848,000.00 On Site
34 Kayu Reng 3/4 Kamper Medan m3 4,848,000.00 On Site
35 Kayu Papan Terentang m3 3,121,000.00 On Site
36 Kayu Balok Terentang m3 3,121,000.00 On Site

D. BAHAN PENUTUP RANGKA PLAFOND


2 Plafond Exaboard / Kalsiboard 5 mm 120 x 240 lbr 195,980.00 On Site
3 Plafond Asbes Semen 5 mm (Exaboard) m2 68,050.00 On Site
4 Plafond Asbes Semen 3,5 mm (Exaboard) m2 62,550.00 On Site
5 Gypsum 120 x 240 t= 9 mm ex DN lbr 173,000.00 On Site
6 Gypsum 120 x 240 t= 9 mm ex Luar lbr 183,000.00 On Site
7 Tepung gypsum kg - On Site
10 GRC Board (122 x 244) cm, t = 4 mm lbr - On Site
11 Papan GRC Board, t = 4 mm (Lisplank) lbr 90,000.00 On Site
12 Papan GRC board 20 cm x 400 cm, t = 9 mm lbr 85,000.00 On Site
13 Papan GRC board 30 cm x 400 cm, t = 9 mm lbr 95,000.00 On Site
15 List gypsum m' 22,000.00 On Site

E. BAHAN KAYU LAPIS


1 Triplek 3 mm 120 x 240 lbr 311,000.00 On Site
2 Triplek 4 mm 120 x 240 lbr 243,000.00 On Site
3 Triplek 5 mm 120 x 240 lbr 263,000.00 On Site
4 Triplek 6 mm 120 x 240 lbr 339,000.00 On Site
5 Triplek 9 mm 120 x 240 lbr 571,000.00 On Site
Triplek 12 mm 120 x 240 lbr 625,000.00 On Site
6 Jabar Wood 4 mm lbr 183,000.00 On Site
10 Wall paper m2 38,000.00 On Site
11 MultiPlek 9 mm 120 x 240 lbr 571,000.00 On Site
12 MultiPlek 12 mm 120 x 240 lbr 625,000.00 On Site
15 Ply Wood 9 mm 120 x 240 lbr 571,000.00 On Site
16 Ply Wood 4 mm 120 x 240 lbr 183,000.00 On Site
17 Teak Wood 3 mm 120 x 240 lbr 479,000.00 On Site
18 Teak Wood 4 mm 120 x 240 lbr 183,000.00 On Site
19 Teak Wood 3 mm 120 x 240 ukuran Pintu lbr 98,000.00 On Site
20 Teak Wood 4 mm 120 x 240 ukuran Pintu lbr 128,000.00 On Site
23 Melamin 4 mm 120 x 240 lbr 156,000.00 On Site
24 Melamin TOK 4 mm lbr 156,000.00 On Site
25 Formika 120 x 240 lbr 98,000.00 On Site
26 Formika ukuran Pintu lbr 138,000.00 On Site
27 Formika Warna 4" x 8" lbr 235,000.00 On Site

F. BAHAN LANTAI DAN PELAPIS DINDING


16 Keramik 20 x 20 (KM) KW I DN Corak/Warna /Anti Slip Mulia (25 bh) dos 183,000.00 On Site
17 Keramik 20 x 20 (KM) KW I DN Putih Polos Mulia (25 bh) dos 173,000.00 On Site
18 Keramik 20 x 25 Dinding KM KW I DN Corak Mulia (20bh) dos 277,000.00 On Site
19 Keramik 30 x 30 KWI DN Putih Polos Mulia (11 bh) dos 104,000.00 On Site
20 Keramik 30 x 30 KWI DN Warna/Corak (ANTI SLIP) Mulia (11 bh) dos 114,000.00 On Site
21 Keramik 40 x 40 KWI DN Putih Polos Mulia (6 bh) dos 173,000.00 On Site
22 Keramik 40 x 40 KWI DN Warna/Corak (ANTI SLIP) Mulia (6 bh) dos 183,000.00 On Site
25 Keramik 20 x 20 (KM) KW I DN Corak/Warna/Anti Slip Roman (25 bh) dos 183,000.00 On Site
26 Keramik 20 x 20 (KM) KW I DN Putih Polos Roman (25 bh) dos 173,000.00 On Site

Page 5 BHN
NO MATERIAL SAT HARGA (Rp) KETERANGAN

27 Keramik 20 x 25 Dinding KM KW I DN Corak Roman (20 bh) dos 277,000.00 On Site


28 Keramik 20 x 25 KW I DN Putih Polos Roman (20 bh) dos 267,000.00 On Site
29 Keramik 30 x 30 KW I DN Polos Roman (11 bh) dos 104,000.00 On Site
30 Keramik 30 x 30 KW I DN Warna/Corak (ANTI SLIP) Roman (11 bh) dos 114,000.00 On Site
31 Keramik 40 x 40 KW I DN Polos Roman (6 bh) dos 173,000.00 On Site
32 Keramik 40 x 40 KW I DN Warna/Corak (ANTI SLIP) Roman (6 bh) dos 183,000.00 On Site
Keramik 60 x 60 KW I DN Polos Roman (4 bh) dos 653,000.00 On Site
Keramik 60 x 60 KW I DN Warna/Corak (ANTI SLIP) Roman (4bh) dos 829,000.00 On Site
61 Plint keramik 10 x 30 bh 4,750.00 On Site
62 Plint keramik 10 x 40 bh 7,625.00 On Site
69 Pengisi Nat Keramik Semen Instan kg 31,000.00 On Site
70 Nat Keramik (Warna) bks 131,000.00 On Site
71 Nat Keramik (Putih) bks 131,000.00 On Site
72 Penutup Keramik / Kuku Keramik bh 22,000.00 On Site

G. BAHAN SALURAN AIR KOTOR / BERSIH


15 Injuk kg 22,000.00 On Site

H. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata kg 16,475.00 On Site
2 Besi Beton U-39 / U-32 Rata-rata kg 17,840.00 On Site
4 Bondek 0,80 mm / 0,75 x 6 m' m2 268,880.00 On Site
Bondek 0,60 mm / 0,75 x 6 m' m2 257,770.00 On Site
11 Kawat Beton kg 41,000.00 On Site
12 Kawat Duri (Pjg. 35 m') m1 19,420.00 On Site
14 Kawat Bronjong 4 mm uk. 1 x 2 x 0,5 bh 445,000.00 On Site
15 Kawat Bronjong 3 mm uk. 1 x 2 x 0,5 bh 406,000.00 On Site
17 Ram Nyamuk Hijau m2 48,000.00 On Site
18 Ram Kawat 1 x 1 cm m2 48,000.00 On Site
19 Ram Ayam m2 30,000.00 On Site
23 Kawat Las Listrik kg 58,000.00 On Site
24 Wiremesh M8 m2 - On Site
25 Wiremesh M6 m2 - On Site
28 Ram nyamuk Alumunium m2 48,000.00 On Site
31 Plat Strip bt 75,000.00 On Site
32 Besi Strip kg 28,000.00 On Site
35 Plat Alumunium 0.3 mm m2 135,000.00 On Site
36 Plat Alumunium 0.4 mm m2 160,000.00 On Site
37 Plat Alumunium 0.5 mm m2 225,000.00 On Site
38 Plat Alumunium 0.6 mm m2 336,000.00 On Site
39 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 4 " ) m1 105,000.00 On Site
40 Kusen Alumunium Warna 1.3 mm t= 1,3 mm ( 4 " ) m1 185,000.00 On Site
41 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 3 " ) m1 96,500.00 On Site
42 Kusen Alumunium Warna 1.3 mm t= 1,3 mm ( 3 " ) m1 164,000.00 On Site
49 Karet Asisoris Kusen / Pintu Alumunium m1 10,000.00 On Site
66 Besi Hallow 2 x 4 x 400 cm (Plafond) btg 48,000.00 On Site
67 Besi Hallow 4 x 4 x 400 cm (Plafond) btg 70,000.00 On Site

I. BAHAN KACA
2 Kaca Polos 3 mm ( ASAHI ) m2 - On Site
3 Kaca Polos 5 mm ( ASAHI ) m2 174,000.00 On Site
4 Kaca Polos 8 mm ( ASAHI ) m2 434,000.00 On Site
5 Kaca Rayband 3 mm ( ASAHI ) m2 - On Site
6 Kaca Rayband 5 mm ( ASAHI ) m2 979,000.00 On Site
7 Kaca Rayband 8 mm ( ASAHI ) m2 - On Site
9 Kaca cermin 5 mm m2 - On Site
10 Kaca cermin 6 mm m2 - On Site
11 Kaca cermin 8 mm m2 - On Site
15 Glass Block DN 20 x 20 ( Kedawung ) bh 65,000.00 On Site
16 Glass Block DN 20 x 20 Ex LN bh 65,000.00 On Site
17 Sealant kg 55,000.00 On Site

J. BAHAN PAKU DAN MUR BAUT


1 Paku 1/2" s/d 2" kg 42,000.00 On Site

Page 6 BHN
NO MATERIAL SAT HARGA (Rp) KETERANGAN

2 Paku 2" s/d 5" kg 42,000.00 On Site


3 Paku 8 cm s/d 15 cm kg 42,000.00 On Site
4 Paku Beton 2 cm s/d 5 cm dos 51,000.00 On Site
6 Paku Cacing kg 280,000.00 On Site
12 Piser dia.12 s/d 20 cm bh 20,000.00 On Site
13 Paku skrup 3" bh 580.00 On Site
14 Ramset / Dinabolt bh 9,000.00 On Site
15 Baut Besar bh 1,300.00 On Site
16 Baut Kecil bh 1,300.00 On Site
Baut (Screw Driver) utk. Rangka Atap Baja Ringan bh 1,150.00 On Site
17 Paku GRC / Paku Asbes kg 280,000.00 On Site
18 Paku gypsum kg 450,000.00 On Site
19 Sekrup fixer bh 580.00 On Site
20 Besi Root (penggantung plafond) bh 10,000.00 On Site
21 Paku Seng kg 129,000.00 On Site
22 Paku Campur kg 42,000.00 On Site
23 Paku Sekrup dos 58,000.00 On Site
24 Paku Triplek kg 42,000.00 On Site

K. BAHAN PERPIPAAN
14 Pipa GIP Medium A 1/2" ( 6 m1 ) bt 388,000.00 On Site
15 Pipa GIP Medium A 3/4" ( 6 m1 ) bt 416,000.00 On Site
16 Pipa GIP Medium A 1" ( 6 m1 ) bt - On Site
20 Pipa GIP Medium A 2" ( 6 m1 ) bt - On Site
34 Pipa PVC WAVIN type AW 1/2" x 4 m' bt 104,000.00 On Site
35 Pipa PVC WAVIN type AW 3/4" x 4 m' bt 121,000.00 On Site
39 Pipa PVC WAVIN type AW 2" x 4 m' bt 287,000.00 On Site
40 Pipa PVC WAVIN type AW 2 1/2" x 4 m' bt 392,000.00 On Site
41 Pipa PVC WAVIN type AW 3" x 4 m' bt 287,000.00 On Site
42 Pipa PVC WAVIN type AW 4" x 4 m' bt 287,000.00 On Site
45 Pipa PVC MASPION ABU ( AW ) 1/2" bt 104,000.00 On Site
46 Pipa PVC MASPION ABU ( AW ) 3/4" bt 121,000.00 On Site
50 Pipa PVC MASPION ABU ( AW ) 2" bt 287,000.00 On Site
51 Pipa PVC MASPION ABU ( AW ) 2 1/2" bt 392,000.00 On Site
52 Pipa PVC MASPION ABU ( AW ) 3" bt 400,000.00 On Site
53 Pipa PVC MASPION ABU ( AW ) 4" bt 526,000.00 On Site

L. BAHAN SANITAIR
1 Stop Kran Hendel 3/4" KIT bh 118,000.00 On Site
11 Saringan Air Lt. KM Stainless Steel bh 41,000.00 On Site
Saringan Air Lt. KM Plastik bh 35,000.00 On Site
13 Kran Stainless Lokal Kait bh 42,000.00 On Site
16 Kran Tembok Sun Eui dia. 3/4" bh 42,000.00 On Site
17 Kran Tembok ITAP dia. 1/2" bh 42,000.00 On Site
18 Kran Bebek Sun Eui 1/2" bh 45,000.00 On Site
19 Kran Bebek ITAP 1/2" bh 89,000.00 On Site
23 Wastafel Lengkap TOTO LW 230 unit - On Site
24 Wastafel Amerika Standard (Kecil) unit 410,000.00 On Site
25 Wastafel Amerika Standard (Besar) unit 1,899,000.00 On Site
26 Closet Jongkok Poslin Warna TOTO unit 270,000.00 On Site
27 Closet Jongkok Putih Poslin Amerikan Standard unit 460,000.00 On Site
28 Closet Jongkok Poslin Merk CONTINENTAL unit 257,000.00 On Site
29 Closet Jongkok Lengkap Sistem Jet TOTO unit - On Site
30 Closet Duduk Warna Standard TOTO C 240 Lengkap unit 2,171,000.00 On Site
31 Closet Duduk Warna Amerika Standard Lengkap unit 2,132,000.00 On Site
32 Closet Duduk Warna Standard PARMA bh 1,642,000.00 On Site
33 Urinoir Lengkap TOTO Warna Standard Lengkap unit 3,207,000.00 On Site
34 Penyekat Poslin Urinoar TOTO lbr 590,000.00 On Site
Urinoir Lokal Putih Standard Lengkap unit 780,000.00 On Site
35 Kitchen Zink Stainless Standard Lokal ( 1 Lubang ) bh 226,000.00 On Site
Kitchen Zink Stainless Standard Lokal ( 2 Lubang ) bh 765,000.00 On Site
36 Kitchen Zink Stainless Non Standard Franke ( 1 Lubang ) bh 765,000.00 On Site
Kitchen Zink Stainless Non Standard Franke ( 2 Lubang ) bh 865,000.00 On Site
37 Talang PVC U - 15 cm m' 104,000.00 On Site

Page 7 BHN
NO MATERIAL SAT HARGA (Rp) KETERANGAN

38 Kaca Cermin 5 mm bh 165,000.00 On Site


39 Water Tank Plastik 1200 ltr (Indo tank) bh 2,940,000.00 On Site
Water Tank Stainlees Teel 1100 ltr bh 5,078,000.00 On Site
Profil Tank Kav. 2200 ltr bh 4,851,000.00 On Site
Tanki Air Stailees Teel Maspion Kav. 2000 ltr bh 9,760,000.00 On Site
Tanki Air Penguin / VIP / Aqua Tank Kav. 650 ltr bh 1,755,000.00 On Site
Tanki Air Penguin / VIP / Aqua Tank Kav. 1100 ltr bh 2,125,000.00 On Site
Tanki Air Penguin / VIP / Aqua Tank Kav. 2200 ltr bh 3,168,000.00 On Site
Tanki Air Penguin / VIP / Aqua Tank Kav. 5000 ltr bh 6,748,000.00 On Site
Bak mandi Oval Fiber 65cm t = 68cm bh 868,000.00 On Site
40 Mesin Air Zimitzu PS-135 BIT 125 Watt bh 675,000.00 On Site
41 Mesin Air Zimitzu PS-226 BIT 200 Watt bh 758,000.00 On Site
42 Mesin Air Zimitzu Jet-100 BIT 100 Watt bh 675,000.00 On Site
43 Pompa Air Listrik SANYO (otomatis), 125 Watt bh 1,567,000.00 On Site
44 Pintu Plastik Kamar Mandi (66 cm x 182 cm) bh 1,176,000.00 On Site
45 Pintu Aluminium Kamar Mandi Dolphin (70 x 7 x 201 cm) bh 1,680,000.00 On Site
46 Kusen Kayu Pintu Siap Pasang (Kls.I) bh 860,000.00 On Site
47 Kusen Kayu Jendela Siap Pasang (Kls.I) bh 860,000.00 On Site
48 Daun Pintu Kayu Siap Pasang (Kls.I) bh 1,600,000.00 On Site
49 daun Jendela Kayu Siap Pasang (Kls.I) bh 800,000.00 On Site
50 Titik Air bersih ttk 250,000.00 On Site
51 TBA roll 225,000.00 On Site

M. BAHAN PENUTUP ATAP


4 Atap Alumunium / Spandek 0,30 mm x 3 m' lbr 219,000.00 On Site
5 Atap Alumunium / Spandek 0,30 mm x 4 m' lbr 257,000.00 On Site
8 Atap Seng Gelombang BJLS 0,25 90 cm x 180 cm lbr 113,000.00 On Site
9 Atap Seng Gelombang BJLS 0,30 90 cm x 180 cm lbr 113,000.00 On Site
19 Alumunium Foile m2 35,000.00 On Site
26 Genteng Metal (Prima Roof) 87 x 83 x 0,25 mm lbr 52,000.00 On Site
28 Nok Atas Metal (Prima Roof) lbr 78,000.00 On Site
51 Nok Atap Seng Plat 45 x 183 x 0,20 mm lbr 42,000.00 On Site
52 Nok standar 40 cm 18, SWG 22 (Bumbungan Spandek) m2 68,000.00 On Site
55 Trusses ZAM-75 t=0.8 Rangka Utama m1 46,660.00 On Site
56 Trusses ZAM-75 t=0.5 Rangka Utama m1 30,000.00 On Site
57 Reng 16-DB Roof Battens t=0.48 mm m1 14,580.00 On Site
62 Seng Datar / Seng Plat BJLS 0,25 lbr 72,000.00 On Site
63 Seng Talang 45 cm x 183 cm x 0,20 mm m1 42,000.00 On Site
64 Seng Talang 85 cm x 183 cm x 0,20 mm m1 48,000.00 On Site

N. BAHAN MEKANIKAL

O. BAHAN ELEKTRIKAL
1 Kabel NYA 1 x 1.5 Eterna/Prima ( 1 rol = 50 m' ) ROLL - On Site
2 Kabel NYA 1 x 2.5 Eterna/Prima ( 1 rol = 50 m' ) ROLL - On Site
3 Kabel NYM 2 x 1.5 Eterna/Prima ( 1 rol = 50 m' ) m' 15,000.00 On Site
4 Kabel NYM 2 x 2.5 Eterna/Prima ( 1 rol = 50 m' ) m' 17,000.00 On Site
5 Kabel NYM 3 x 1.5 Eterna/Prima ( 1 rol = 50 m' ) m' 16,000.00 On Site
6 Kabel NYM 3 x 2.5 Eterna/Prima ( 1 rol = 50 m' ) m' 23,000.00 On Site
7 Kabel NYM 4 x 2.5 Eterna/Prima ( 1 rol = 50 m' ) m' 29,000.00 On Site
10 Kabel NYM 4 x 4 Eterna/Prima ( 1 rol = 50 m' ) m' 42,000.00 On Site
18 Kabel NYY 2 x 1,5 Eterna ( 1 rol = 50 m' ) m' 15,000.00 On Site
19 Kabel NYY 2 x 2,5 Eterna ( 1 rol = 50 m' ) m' 17,000.00 On Site
20 Kabel NYY 3 x 1,5 Eterna ( 1 rol = 50 m' ) m' 16,000.00 On Site
21 Kabel NYY 3 x 2,5 Eterna ( 1 rol = 50 m' ) m' 23,000.00 On Site
22 Kabel NYY 4 x 2,5 Eterna ( 1 rol = 50 m' ) m' 29,000.00 On Site
23 Kabel NGA 1,5 mm m' 11,500.00 On Site
24 Kabel NGA 2,5 mm m' 12,500.00 On Site
25 Kabel NYA warna 1 x 2,5 mm Supreme ( 1 rol = 50 m' ) m' 14,700.00 On Site
28 Kabel Feeder NFGBY 4 x 6 mm m' 88,000.00 On Site
31 Rumah Panel 30 x 60 cm ( Kosong ) unt 180,000.00 On Site
32 Skring Kas 2 grop Biasa unt 208,000.00 On Site
33 Skring Kas 3 grop Biasa unt 226,000.00 On Site
34 Skring Kas 5 grop Biasa unt 468,000.00 On Site

Page 8 BHN
NO MATERIAL SAT HARGA (Rp) KETERANGAN

35 MCB 1 PAS bh 58,000.00 On Site


36 MCB 3 PAS bh 110,000.00 On Site
37 Tahanan 50 A Merk Fuji bh 522,000.00 On Site
38 Saklar Broko Tunggal Inbow Standard ( 1 Phase ) bh 31,000.00 On Site
39 Saklar Broko Seri/Double Inbow Standard ( 1 Phase ) bh 31,000.00 On Site
Saklar Broko Triple Inbow Standard ( 1 Phase ) bh 50,000.00 On Site
40 Stop Kontak Broko Inbow Standard ( 1 Phase ) bh 28,000.00 On Site
41 Stop Kontak Tutup Broko (Inbow) bh 64,000.00 On Site
42 Stop Kontak Arde Broko bh 64,000.00 On Site
43 Stop Kontak AC 220/13A bh 45,000.00 On Site
44 Instalas Titik Lampu / Stop Kontak (Upah dan Alat) ttk 200,000.00 On Site
45 Lampu pijar 25 Watt s/d 100 Watt bh 71,000.00 On Site
46 Lampu Neon Phillips 20 Watt bh 38,000.00 On Site
47 Lampu Neon Phillips 40 Watt bh 42,000.00 On Site
48 Lampu SL esensial Phillips 11 Watt bh 31,000.00 On Site
49 Lampu SL esensial Phillips 18 Watt bh 43,000.00 On Site
50 Lampu SL esensial Phillips 10 Watt (LED) bh - On Site
51 Trapo TL 20 W (Phillips) bh 50,000.00 On Site
52 Trapo TL 40 W (Phillips) bh 47,000.00 On Site
53 Trapo TL 20 W (Sinar) bh 51,000.00 On Site
54 Trapo TL 40 W (sinar) bh 51,000.00 On Site
55 Stater Neon Phillips bh 14,500.00 On Site
56 Stater Neon Biasa bh 11,500.00 On Site
57 Rumah TL In Bow / Out Bow 2 x 20 W (kosongan) bh 153,000.00 On Site
58 Down Light + SL 25 W bh 318,000.00 On Site
59 Lampu SL Philip 25 W bh 318,000.00 On Site
60 Lampu Sirkel TL 20 W Lengkap bh 76,000.00 On Site
61 Lampu Mercuri 80 W bh 158,000.00 On Site
62 Lampu Taman + Tiang + Lampu 1 Buah bh 318,000.00 On Site
63 Lampu Baret 30 cm + Neon bh 238,000.00 On Site
64 Lampu Neon Arcrilik 2 x 40 W Lengkap bh 745,000.00 On Site
65 Jarum Penangkal Petir 16 bh 109,000.00 On Site
66 Kawat BC ( Tembaga ) kg 71,000.00 On Site
67 Pentanahan Penangkal Petir ttk 428,000.00 On Site
68 Pentanahan Panel ttk 301,000.00 On Site
69 Pipa Listrik 5/8" x 4 m' staf 15,000.00 On Site
70 Tee doz bh 6,000.00 On Site
71 Lasdop bh 1,500.00 On Site
72 Benang Tukang bh 9,000.00 On Site
73 Isolasi bh 16,000.00 On Site
74 Fitting tempel plafond bh 47,000.00 On Site

P. BAHAN ALAT PENGANTUNG DAN KUNCI


7 Kunci 2 Slaag Ancor Asli / Union Elite (Komplit) bh 267,000.00 On Site
8 Kunci 2 Slaag YALE bh 191,000.00 On Site
9 Kunci KM Bulat Kualitas Biasa bh 69,000.00 On Site
10 Kunci KM Bulat ALFA bh 110,000.00 On Site
11 Kunci 2 Slaag Silinder Utama Standard bh 380,000.00 On Site
13 Kunci 2 Slaag Kuda Terbang bh 148,000.00 On Site
15 Espangolet bh 170,000.00 On Site
16 Grendel 15 cm (Pintu) bh 57,000.00 On Site
17 Grendel 5 cm (Jendela) bh 13,000.00 On Site
18 Hak Angin Kait Jendela Biasa bh 41,000.00 On Site
19 Hak Angin Jendela Antik bh 33,000.00 On Site
23 Engsel Pintu Unilon Standard ps 90,000.00 On Site
24 Engsel Jendela Unilon ps 69,000.00 On Site
25 Engsel Patrun ps 51,000.00 On Site
26 Engsel Harmonika / Engsel Garasi m1 45,000.00 On Site
27 Door Closer Kelas Standard ( Kelas Sedang ) unt 369,000.00 On Site
28 Door Closer Kelas Standard ( Kelas Baik ) unt 670,000.00 On Site
30 Door Holder / Hendel Pintu 300 mm solid Stainlees P91.02 unt 170,000.00 On Site
31 Door Stoper unt 315,000.00 On Site
33 Seng BJLS 30 Lebar 60 cm ( 1 rol 50 m' ) m1 48,000.00 On Site
34 Seng BJLS 30 Lebar 90 cm ( 1 rol 50 m' ) m1 58,000.00 On Site

Page 9 BHN
NO MATERIAL SAT HARGA (Rp) KETERANGAN

35 Seng Plat Licin BJLS 0,25 lbr 72,000.00 On Site


36 Seng Plat Licin BJLS 0,30 lbr 82,000.00 On Site

Q. BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN

R. BAHAN PENGISAP AIR SUMUR DALAM

S. BAHAN PENAMPUNG AIR

T. ALAT TUKANG

U. BAHAN BAKAR DAN PELUMAS


1 Minyak Tanah lt 23,000.00 On Site
3 Bahan Bakar Residu / Buker Oil lt 60,000.00 On Site
4 Minyak Solar lt 14,000.00 On Site
5 Bensin Premium / Pertalite lt 15,000.00 On Site
7 Oil Mesran 40 SAE lt 45,000.00 On Site
12 Minyak Bekisting ltr 12,500.00 On Site
18 Perlengkapan / Alat bantu LS 25,000.00 On Site
19 Sewa Generator 5 KVA Jam 350,000.00 On Site

V. BAHAN PAGAR

W. BIDANG PERTAMANAN

X. BIDANG BAHAN MEUBELAIR SEKOLAH


1 Meja Tunggal + Kursi Siswa SMA (M-02/K-02), model ; 1mj + 1kr Set 954,496.40 On Site
2 Meja Ganda + Kursi Siswa SMA (M-02/K-02), model ; 1mj + 2kr Set 1,743,549.60 On Site
3 Meja Guru / Meja Kerja (M-01), model ; 1/5 biro Bh 3,586,450.40 On Site
4 Meja Siswa Ganda (M-02) Bh 1,048,304.40 On Site
5 Meja Siswa Tunggal (M-02) Bh 524,152.20 On Site
6 Meja Laboratorium (M-03) Bh 2,758,808.00 On Site
7 Meja Persiapan & Meja Demonstrasi (M-10) Bh 2,482,927.20 On Site
8 Meja Praktek / Serbaguna (M-10) Bh 2,482,927.20 On Site
9 Meja Lab Bahasa / Meja Baca Individu (M-14), model ; meja tunggal sekat Bh 1,103,523.20 On Site
10 Kursi Guru & Siswa (K-01), bahan ; kombinasi besi, plastik, spons, pakai sandaran Bh 827,642.40 On Site
11 Kursi Guru & Siswa (K-02), bahan ; kayu, spons, pakai sandaran Bh 695,138.60 On Site
12 Kursi Guru & Siswa (K-03), bahan ; kombinasi besi, plastik, spons tanpa sandaran Bh 662,092.60 On Site
13 Kursi Guru & Siswa (K-03), bahan ; kombinasi besi, plastik tanpa sandaran Bh 529,588.80 On Site
14 Kursi Tamu (K-11), model ; tunggal / 1 dudukan Bh 937,973.40 On Site
15 Kursi Tamu (K-12), model ; ganda / 2 dudukan Bh 1,765,615.80 On Site
16 Lemari Simpan (L-01) Bh 4,193,324.20 On Site
17 Lemari Simpan (L-02) Bh 3,807,112.40 On Site
18 Rak Penyimpanan Buku Perpustakaan (L-06) Bh 3,476,012.80 On Site
19 Papan Tulis White Board (P-01) Bh 1,820,728.00 On Site
20 Papan Tulis White Board (P-02) Bh 1,820,728.00 On Site
21 Tempat Sampah Bh 341,120.00 On Site

harga belum termasuk PPN dan keuntungan

Page 10 BHN
DAFTAR HARGA
UPAH DAN BAHAN

OVERHEAD
KWARI/CHK. ONGKS.ANGKU GALIAN "C" HARGA DI ASTEK
10% - 15% TOTAL HARGA DIBULATKAN
T KE PROYEK 20% LOKASI 5%
(Rp) (Rp)
NO. JENIS MATERIAL YANG DIPAKAI SATUAN (Rp) (Rp) (Rp) (Rp) (Rp)
(Rp)
(1) (2) (3) (4) (5) (6) (7) (8)
(1)+(2)+(3) 5% x (4) 10% x (4) (4)+(5)+(6)

I SATUAN UPAH
1 Pekerja / Hari 120,000.00 120,000.00 - - 120,000.00 120,000.00
2 Tukang Batu, Kayu, Besi, Cat, Listrik, Pipa, Alluminium / Hari 164,000.00 164,000.00 - - 164,000.00 150,000.00
3 Kepala tukang / Hari 175,000.00 175,000.00 - - 175,000.00 175,000.00
4 Mandor / Hari 200,000.00 200,000.00 - - 200,000.00 200,000.00

II SATUAN BAHAN

A. Batu kali
1 Batu Belah Pondasi / Batu Kali / Batu Karang / M3 450,000.00 - 450,000.00 - 450,000.00 450,000.00
2 Batu Pecah Mesin 1/2 cm (m3) / M3 550,000.00 - 550,000.00 - 550,000.00 550,000.00
3 Batu Pecah Mesin 1/2 cm (Kg) / Kg 407.41 - 407.41 - 407.41 407.00
4 Batu Pecah 2/3 cm (m3) / M3 550,000.00 - 550,000.00 - 550,000.00 550,000.00
5 Batu Pecah 2/3 cm (Kg) / Kg 407.41 - 407.41 - 407.41 407.00
6 Batu Kerikil Sungai (m3) / M3 450,000.00 - 450,000.00 - 450,000.00 450,000.00
7 Batu Kerikil Sungai (Kg) / Kg 333.33 - 333.33 - 333.33 333.00
8 Batu Bata merah / Bh 3,300.00 - 3,300.00 - 3,300.00 3,300.00
9 Batu Bataco Semen uk. 23 x 12 x 8 Bh 4,000.00 - 4,000.00 - 4,000.00 4,000.00
10 Batu Conblock HB10 uk. 30 x 13 x 9 Bh 10,000.00 - 10,000.00 - 10,000.00 10,000.00

B. Pasir/ Tanah
1 Pasir Urug / M3 326,000.00 - 326,000.00 - 326,000.00 326,000.00
2 Pasir Pasir Pasang / Kali / Pantai (M3) / M3 450,000.00 - 450,000.00 - 450,000.00 450,000.00
3 Pasir Pasir Pasang / Kali / Pantai (Kg) / Kg 321.43 - 321.43 - 321.43 321.00
4 Pasir Beton / M3 / M3 450,000.00 - 450,000.00 - 450,000.00 450,000.00
5 Pasir Beton / Kg / Kg 321.43 - 321.43 - 321.43 321.00
6 Tanah Urug / Timbunan Biasa / M3 400,000.00 - 400,000.00 - 400,000.00 400,000.00
7 Tanah Urug / Sirtu Padat / M3 450,000.00 - 450,000.00 - 450,000.00 450,000.00

C. Semen & Compound


1 Semen Tonasa 50 Kg / Sak 150,000.00 150,000.00 - 150,000.00 150,000.00
2 Semen Tonasa / Kg 3,000.00 3,000.00 - 3,000.00 3,000.00
3 Semen Warna / Kg 30,000.00 30,000.00 - 30,000.00 30,000.00

D. Bahan Atap
1 Bumbungan Genteng Metal / Lbr 78,000.00 78,000.00 - 78,000.00 78,000.00
2 Zink datar BJLS 0.25 (914 x 1829 mm) / Lbr 72,000.00 72,000.00 - 72,000.00 72,000.00
3 Zink datar BJLS 0.30 (914 x 1829 mm) / Lbr 82,000.00 82,000.00 - 82,000.00 82,000.00
4 Zink gelombang BJLS 0.25 (914 x 1829 mm) / Lbr 113,000.00 113,000.00 - 113,000.00 113,000.00
5 Zink gelombang BJLS 0.30 (914 x 1829 mm) / Lbr 113,000.00 113,000.00 - 113,000.00 113,000.00
6 Atap Zincalum Almunium/Spandek, tbl. 0,25 mm / Lbr 238,000.00 238,000.00 - 238,000.00 238,000.00
7 Atap Zincalum Almunium/Spandek, tbl. 0,25 mm / M2 90,666.67 90,666.67 - 90,666.67 90,600.00
8 Nok standar 40 cm 18, SWG 22 / M2 68,000.00 68,000.00 - 68,000.00 68,000.00
OVERHEAD
KWARI/CHK. ONGKS.ANGKU GALIAN "C" HARGA DI ASTEK
10% - 15% TOTAL HARGA DIBULATKAN
T KE PROYEK 20% LOKASI 5%
(Rp) (Rp)
NO. JENIS MATERIAL YANG DIPAKAI SATUAN (Rp) (Rp) (Rp) (Rp) (Rp)
(Rp)
(1) (2) (3) (4) (5) (6) (7) (8)
(1)+(2)+(3) 5% x (4) 10% x (4) (4)+(5)+(6)
E. Bahan Kayu, Gipsum & Wallpaper
1 Kayu Kls. I (5/10, 6/12, 10/10) / M3 8,484,000.00 8,484,000.00 - 8,484,000.00 8,480,000.00
2 Kayu papan Kls. I semua ukuran / M3 8,484,000.00 8,484,000.00 - 8,484,000.00 8,480,000.00
3 Kayu Kls. II semua ukuran (Kayu makila, meranti) / M3 4,848,000.00 4,848,000.00 - 4,848,000.00 4,840,000.00
4 Kayu papan Kls. II semua ukuran / M3 4,848,000.00 4,848,000.00 - 4,848,000.00 4,840,000.00
5 Kayu Kls. III semua ukuran / M3 3,121,000.00 3,121,000.00 - 3,121,000.00 3,120,000.00
6 Kayu papan Kls. III semua ukuran / M3 3,121,000.00 3,121,000.00 - 3,121,000.00 3,120,000.00
7 Tripleks tebal 4 mm / Lbr 243,000.00 243,000.00 - 243,000.00 243,000.00
8 Tripleks tebal 9 mm / Lbr 571,000.00 571,000.00 - 571,000.00 571,000.00
9 List kayu klas I profil lebar 8 cm / M' 23,500.00 23,500.00 - 23,500.00 23,500.00
10 Kalsiboard, tebal 5 mm / Lbr 195,980.00 195,980.00 - 195,980.00 195,900.00
11 Gypsum board, t=9 mm / Lbr 183,000.00 183,000.00 - 183,000.00 183,000.00
12 Papan GRC Board 30 cm, t = 9 mm (400 cm) / Lbr 90,000.00 90,000.00 - 90,000.00 90,000.00
13 Dolken kayu Ø8-10 mm / 4 m / Btg 60,000.00 60,000.00 - 60,000.00 60,000.00

F. Kawat
1 Kawat bendrat / KG 41,000.00 41,000.00 - 41,000.00 41,000.00
2 Kawat Las 3.2 mm / KG 58,000.00 58,000.00 - 58,000.00 58,000.00

G. Tegel Keramik & Batu Alam


1 Tegel keramik 40/40 cm, polos / Bh 27,680.00 27,680.00 - 27,680.00 27,600.00
2 Tegel keramik 40/40 cm, unpolos / Bh 29,280.00 29,280.00 - 29,280.00 29,200.00
3 Tegel keramik 60/60 cm, unpolos / Bh 163,250.00 163,250.00 - 163,250.00 163,200.00
4 Tegel keramik 20/20 cm, polos / Bh 8,784.00 8,784.00 - 8,784.00 8,700.00
5 Tegel keramik 20/25 cm, polos / Bh 16,620.00 16,620.00 - 16,620.00 16,600.00
6 Plint Keramik 10 x 40 cm, Polis / Bh 7,625.00 7,625.00 - 7,625.00 7,600.00
7 Pengisi Nat Keramik Semen Instan / Kg 31,000.00 31,000.00 - 31,000.00 31,000.00
8 Nat Keramik (Warna) / Bks 131,000.00 131,000.00 - 131,000.00 131,000.00
9 Nat Keramik (Putih) / Bks 131,000.00 131,000.00 - 131,000.00 131,000.00
10 Penutup Keramik / Kuku Keramik / Bh 22,000.00 22,000.00 - 22,000.00 22,000.00

H. Bahan Kaca
1 Kaca Bening 5 mm / M2 174,000.00 174,000.00 - 174,000.00 174,000.00
2 Kaca Raibend 5 mm / M2 979,000.00 979,000.00 - 979,000.00 979,000.00

I. Bahan Listrik
1 Titik Cahaya / Ttk 200,000.00 200,000.00 - 200,000.00 200,000.00
2 Titik Stop Kontak / Ttk 200,000.00 200,000.00 - 200,000.00 200,000.00
3 Saklar tunggal inbow broco / Bh 31,000.00 31,000.00 - 31,000.00 31,000.00
4 Saklar ganda inbouw broco / Bh 31,000.00 31,000.00 - 31,000.00 31,000.00
5 Stop kontak inbouw broco / Bh 28,000.00 28,000.00 - 28,000.00 28,000.00
6 Lampu SL esensial Phillips 11 Watt / Bh 31,000.00 31,000.00 - 31,000.00 31,000.00
7 Lampu SL esensial Phillips 18 Watt / Bh 43,000.00 43,000.00 - 43,000.00 43,000.00
8 Lampu SL esensial Phillips 10 Watt (LED) / Bh 45,000.00 45,000.00 - 45,000.00 45,000.00
9 Lampu philips SL 25 Watt feting tempel (lengkap) / Bh 318,000.00 318,000.00 - 318,000.00 318,000.00
10 Lampu philips SL 18 Watt feting tempel (lengkap) / Bh 286,200.00 286,200.00 - 286,200.00 286,200.00
11 Kabel NYM 3 x 2,5mm (1 rol = 50 M') / Roll 1,150,000.00 1,150,000.00 - 1,150,000.00 1,150,000.00
12 Kabel NYM 3 x 2,5mm /M 23,000.00 23,000.00 - 23,000.00 23,000.00
13 T doz / Bh 6,000.00 6,000.00 - 6,000.00 6,000.00
14 Lasdop / Bh 1,500.00 1,500.00 - 1,500.00 1,500.00
15 Benang Tukang / Bh 9,000.00 9,000.00 - 9,000.00 9,000.00
16 Isolasi / Bh 16,000.00 16,000.00 - 16,000.00 16,000.00
17 Fitting tempel plafond / Bh 47,000.00 47,000.00 - 47,000.00 47,000.00
OVERHEAD
KWARI/CHK. ONGKS.ANGKU GALIAN "C" HARGA DI ASTEK
10% - 15% TOTAL HARGA DIBULATKAN
T KE PROYEK 20% LOKASI 5%
(Rp) (Rp)
NO. JENIS MATERIAL YANG DIPAKAI SATUAN (Rp) (Rp) (Rp) (Rp) (Rp)
(Rp)
(1) (2) (3) (4) (5) (6) (7) (8)
(1)+(2)+(3) 5% x (4) 10% x (4) (4)+(5)+(6)
J. Alat Penggantun / Pengunci
1 Kunci pintu tanam kaca 2 slag / Bh 267,000.00 267,000.00 - 267,000.00 267,000.00
2 Engsel pintu nilon 4" / Psg 90,000.00 90,000.00 - 90,000.00 90,000.00
3 Engsel jendela nilon 3" / Psg 69,000.00 69,000.00 - 69,000.00 69,000.00
4 Engsel pintu angin 4" / Psg 51,000.00 51,000.00 - 51,000.00 51,000.00
5 Grendel Pintu / Bh 57,000.00 57,000.00 - 57,000.00 57,000.00
6 Grendel jendela, ventilasi / Bh 13,000.00 13,000.00 - 13,000.00 13,000.00
7 Kait angin 4" jendela/ ventilasi / Bh 41,000.00 41,000.00 - 41,000.00 41,000.00

K. Bahan Paku
1 Paku Semua Ukuran / KG 42,000.00 42,000.00 - 42,000.00 42,000.00
2 Paku Genteng / KG 280,000.00 280,000.00 - 280,000.00 280,000.00
3 Paku Skrup (bh) / Bh 580.00 580.00 - 580.00 500.00
4 Paku Skrup (kg) / KG 280,000.00 280,000.00 - 280,000.00 280,000.00
5 Skrup fixer / Bh 580.00 580.00 - 580.00 500.00
6 Paku beton semua ukuran / Dos 51,000.00 51,000.00 - 51,000.00 51,000.00

L. Bahan Besi
1 Besi Beton U-24 Rata-rata (polos) / KG 16,475.00 16,475.00 - 16,475.00 16,400.00
2 Besi Beton U-39 / U-32 Rata-rata (ulir) / KG 17,840.00 17,840.00 - 17,840.00 17,800.00
3 Besi strip 5 mm / Btng 168,750.00 168,750.00 - 168,750.00 168,700.00
4 Besi strip 5 mm / Kg 28,000.00 28,000.00 - 28,000.00 28,000.00
5 Baja Ringan Canai Dingin C 75 x 35,5 x 0.75 mm / M' 38,330.00 38,330.00 - 38,330.00 38,300.00
6 Baten / Reng U 50 x 30 x 0,5 / M' 14,580.00 14,580.00 - 14,580.00 14,500.00
7 Baut Dril Skrel dia. 12 mm 14 x 16 / Bh 1,150.00 1,150.00 - 1,150.00 1,100.00
8 Baut Dril Skrel dia. 12 mm 16 x 20 / Bh 1,150.00 1,150.00 - 1,150.00 1,100.00
9 Dinabold/Fisher Beton dia. 10 mm / Bh 9,000.00 9,000.00 - 9,000.00 9,000.00
10 Talang / Jurai Canai Dingin / M' 104,000.00 104,000.00 - 104,000.00 104,000.00

M. Bahan Finishing/ Cat/ Minyak


1 Amplas kayu / Lbr 16,000.00 16,000.00 - 16,000.00 16,000.00
2 Plamir tembok biglion / 5 KG 37,000.00 37,000.00 - 37,000.00 37,000.00
3 Plamir tembok biglion / KG 7,400.00 7,400.00 - 7,400.00 7,400.00
4 Cat dasar kayu kembang / KG 68,000.00 68,000.00 - 68,000.00 68,000.00
5 Minyak cat (Tineer) / Ltr 74,500.00 74,500.00 - 74,500.00 74,500.00
6 Cat Glotex / Kg 96,000.00 96,000.00 - 96,000.00 96,000.00
7 Cat tembok Meterolite / KG 67,200.00 67,200.00 - 67,200.00 67,200.00
8 Cat Batu Cotting/ Propan / KG 83,000.00 83,000.00 - 83,000.00 83,000.00
9 Cat menie / KG 44,000.00 44,000.00 - 44,000.00 44,000.00
10 Water Proofing 2 Komponen (Liquid+Bubuk). Ex. Lemkra / KG 83,000.00 83,000.00 - 83,000.00 83,000.00
11 Minyak Bakesting / Ltr 12,500.00 12,500.00 - 12,500.00 12,500.00
12 Solar / Ltr 14,000.00 14,000.00 - 14,000.00 14,000.00
13 Minyak Pelumas/ Olie / Ltr 45,000.00 45,000.00 - 45,000.00 45,000.00
14 Kuas / Bh 24,000.00 24,000.00 - 24,000.00 24,000.00
15 Air / Ltr 200.00 200.00 - 200.00 200.00
OVERHEAD
KWARI/CHK. ONGKS.ANGKU GALIAN "C" HARGA DI ASTEK
10% - 15% TOTAL HARGA DIBULATKAN
T KE PROYEK 20% LOKASI 5%
(Rp) (Rp)
NO. JENIS MATERIAL YANG DIPAKAI SATUAN (Rp) (Rp) (Rp) (Rp) (Rp)
(Rp)
(1) (2) (3) (4) (5) (6) (7) (8)
(1)+(2)+(3) 5% x (4) 10% x (4) (4)+(5)+(6)
N. Bahan Pipa & Sanitair
1 Titik Air bersih / Ttk 250,000.00 250,000.00 - 250,000.00 250,000.00
2 Pipa Listrik 5/8" / Stap 15,000.00 15,000.00 - 15,000.00 15,000.00
3 Pipa Listrik 5/8" / M' 6,000.00 6,000.00 - 6,000.00 6,000.00
4 Pipa PVC dia. 3" (AW) / M' 71,750.00 71,750.00 - 71,750.00 71,700.00
5 Pipa PVC dia. 2" (AW) / M' 71,750.00 71,750.00 - 71,750.00 71,700.00
6 Pipa PVC dia. 1/2" (AW) / M' 26,000.00 26,000.00 - 26,000.00 26,000.00
7 Pipa GIP Medium "A" dia. 3/4" / M' 69,333.33 69,333.33 - 69,333.33 69,300.00
8 Pipa GIP Medium "A" dia. 1/2" / M' 64,666.67 64,666.67 - 64,666.67 64,600.00
9 Floor Drine Stainless steel / Bh 41,000.00 41,000.00 - 41,000.00 41,000.00
10 TBA / Roll 225,000.00 225,000.00 - 225,000.00 225,000.00
11 Keran Air 1/2" / Bh 42,000.00 42,000.00 - 42,000.00 42,000.00
12 Keran Air 3/4" / Bh 42,000.00 42,000.00 - 42,000.00 42,000.00
13 Wastafel Porselin Standard / Bh 410,000.00 410,000.00 - 410,000.00 410,000.00
14 Kitchen Zink Stainless Standard Lokal ( 1 Lubang ) / Bh 226,000.00 226,000.00 - 226,000.00 226,000.00
15 Pipa GIP Medium "A" dia. 2,0" / Stap - - - - -
16 Pipa GIP Medium "A" dia. 2,0" / M' - - - - -
17 Closet Jongkok Poslin (INA) / Bh 257,000.00 257,000.00 - 257,000.00 257,000.00
18 Closet Duduk Pakai Tabung (INA) / Bh 2,132,000.00 2,132,000.00 - 2,132,000.00 2,132,000.00
19 Bak mandi Oval Fiber 65cm t = 68cm / Bh 868,000.00 868,000.00 - 868,000.00 868,000.00

0. Bahan Alluminium & PVC


1 Alluminium strip / M' 75,000.00 75,000.00 - 75,000.00 75,000.00
2 Rangka plafond Hollow / M' 14,750.00 14,750.00 - 14,750.00 14,700.00
3 Karet penjepit (gasket) / M' 10,000.00 10,000.00 - 10,000.00 10,000.00
4 Ramset / Dinabolt / Bh 9,000.00 9,000.00 - 9,000.00 9,000.00
5 Sealent / Karet / Kg 55,000.00 55,000.00 - 55,000.00 55,000.00
6 Perlengkapan/ Alat bantu / LS 25,000.00 25,000.00 - 25,000.00 25,000.00
7 Sewa Generator 5 KVA / Jam 350,000.00 350,000.00 - 350,000.00 350,000.00
8 Besi Hollow 20 x 40 / 4 M', (plafond) / Btg 48,000.00 48,000.00 - 48,000.00 48,000.00
9 Besi Hollow 40 x 40 / 4 M', (plafond) / Btg 70,000.00 70,000.00 - 70,000.00 70,000.00
10 Sekrup Hollow / Bh 580.00 580.00 - 580.00 500.00
11 Screw Gipsum / Bh 10,000.00 10,000.00 - 10,000.00 10,000.00
12 Besi Root (penggantung plafond) / Bh 10,000.00 10,000.00 - 10,000.00 10,000.00

P. BAHAN MEUBELAIR SEKOLAH ( SMA / SMU / MA )


1 Meja Tunggal + Kursi Siswa (M-02/K-02), model ; 1mj + 1kr (M-02/K-02) / Set 954,496.40 75,000.00 1,029,496.40 - 1,029,496.40 1,029,400.00
2 Meja Ganda + Kursi Siswa (M-02/K-02), model ; 1mj + 2kr (M-02/K-02) / Set 1,743,549.60 75,000.00 1,818,549.60 - 1,818,549.60 1,818,500.00
3 Meja Guru / Meja Kerja (M-01), model ; 1/5 biro (M-01) / Bh 3,586,450.40 50,000.00 3,636,450.40 - 3,636,450.40 3,636,400.00
4 Meja Siswa Ganda (M-02) (M-02), ganda / Bh 1,048,304.40 50,000.00 1,098,304.40 - 1,098,304.40 1,098,300.00
5 Meja Siswa Tunggal (M-02) (M-02), tunggal / Bh 524,152.20 50,000.00 574,152.20 - 574,152.20 574,100.00
6 Meja Laboratorium (M-03) (M-03) / Bh 2,758,808.00 50,000.00 2,808,808.00 - 2,808,808.00 2,808,800.00
7 Meja Persiapan & Meja Demonstrasi (M-10) (M-10) / Bh 2,482,927.20 50,000.00 2,532,927.20 - 2,532,927.20 2,532,900.00
8 Meja Praktek / Serbaguna (M-10) (M-10) / Bh 2,482,927.20 50,000.00 2,532,927.20 - 2,532,927.20 2,532,900.00
9 Meja Lab Bahasa / Meja Baca Individu (M-14), model ; meja tunggal sekat (M-14) / Bh 1,103,523.20 50,000.00 1,153,523.20 - 1,153,523.20 1,153,500.00
10 Kursi Guru & Siswa (K-01), bahan ; kombinasi besi, plastik, spons pakai sandaran (K-01) / Bh 827,642.40 25,000.00 852,642.40 - 852,642.40 852,600.00
11 Kursi Guru & Siswa (K-02), bahan ; kayu kls 1 pakai sandaran (K-02) / Bh 695,138.60 25,000.00 720,138.60 - 720,138.60 720,100.00
12 Kursi Guru & Siswa (K-03), bahan ; kombinasi besi, plastik, spons tanpa sandaran (K-03), bulat / Bh 662,092.60 25,000.00 687,092.60 - 687,092.60 687,000.00
13 Kursi Guru & Siswa (K-03), bahan ; kombinasi besi, plastik tanpa sandaran (K-03), segi 3 / Bh 529,588.80 25,000.00 554,588.80 - 554,588.80 554,500.00
14 Kursi Tamu (K-11), model ; tunggal / 1 dudukan (K-11) / Bh 937,973.40 25,000.00 962,973.40 - 962,973.40 962,900.00
15 Kursi Tamu (K-12), model ; ganda / 2 dudukan (K-12) / Bh 1,765,615.80 25,000.00 1,790,615.80 - 1,790,615.80 1,790,600.00
16 Lemari Simpan (L-01) (L-01) / Bh 4,193,324.20 50,000.00 4,243,324.20 - 4,243,324.20 4,243,300.00
17 Lemari Simpan (L-02) (L-02) / Bh 3,807,112.40 50,000.00 3,857,112.40 - 3,857,112.40 3,857,100.00
18 Rak Penyimpanan Buku Perpustakaan (L-06) (L-06) / Bh 3,476,012.80 50,000.00 3,526,012.80 - 3,526,012.80 3,526,000.00
19 Papan Tulis White Board (P-01) (P-01) / Bh 1,820,728.00 50,000.00 1,870,728.00 - 1,870,728.00 1,870,700.00
20 Papan Tulis White Board (P-02) (P-02) / Bh 1,820,728.00 50,000.00 1,870,728.00 - 1,870,728.00 1,870,700.00
21 Tempat Sampah / Bh 341,120.00 5,000.00 346,120.00 - 346,120.00 346,100.00
22 Meja Kerja (M-07) (M-07) /Bh 3,744,000.00 50,000.00 3,794,000.00 - 3,794,000.00 3,790,000.00
OVERHEAD
KWARI/CHK. ONGKS.ANGKU GALIAN "C" HARGA DI ASTEK
10% - 15% TOTAL HARGA DIBULATKAN
T KE PROYEK 20% LOKASI 5%
(Rp) (Rp)
NO. JENIS MATERIAL YANG DIPAKAI SATUAN (Rp) (Rp) (Rp) (Rp) (Rp)
(Rp)
(1) (2) (3) (4) (5) (6) (7) (8)
(1)+(2)+(3) 5% x (4) 10% x (4) (4)+(5)+(6)
23 Meja Tamu (M-09B) (M-09B) /Bh 806,400.00 50,000.00 856,400.00 - 856,400.00 850,000.00
24 Kursi Kerja Staf (K-08C) (K-08C) /Bh 1,152,000.00 25,000.00 1,177,000.00 - 1,177,000.00 1,170,000.00
25 Kursi Hadap/Rapat (K-09B) (K-09B) /Bh 783,360.00 25,000.00 808,360.00 - 808,360.00 800,000.00
26 Lemari Simpan Pintu Solid (L-11) (L-11) /Bh 2,188,800.00 50,000.00 2,238,800.00 - 2,238,800.00 2,230,000.00
27 Papan Tulis Putih uk. 120 x 240 cm (P-03) (P-03) /Bh 1,843,200.00 50,000.00 1,893,200.00 - 1,893,200.00 1,890,000.00
28 Papan Presensi uk. 60 x 60 cm (P-04) (P-04) /Bh 614,400.00 50,000.00 664,400.00 - 664,400.00 660,000.00
29 Papan Pengumuman uk. 90 x 90 cm (P-05) (P-05) /Bh 857,302.33 50,000.00 907,302.33 - 907,302.33 900,000.00
Lembaran -16

DAFTAR ANALISA HARGA SATUAN


I. HARGA SATUAN PEKERJAAN PERSIAPAN
A.2.2.1.4. Pengukuran dan pamasangan 1 M' Bouwplank
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.100 120,000.00 12,000.00
Tukang L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 29,750.00
B. BAHAN
Kayu balok 5/7 M3 0.120 3,120,000.00 374,400.00
Paku 2-3" Kg 0.020 42,000.00 840.00
Kayu papan 3/20 M3 0.007 3,120,000.00 21,840.00
JUMLAH HARGA BAHAN 397,080.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 426,830.00
E. Overhead & Profit 12% x D 51,219.60
F. Harga Satuan Pekerjaan (D+E) 478,049.00

A.2.2.1.7. Pembuatan 1 M2 gudang semen dan peralatan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.000 120,000.00 120,000.00
Tukang L.02 Oh 2.000 150,000.00 300,000.00
Kepala Tukang L.03 Oh 0.200 175,000.00 35,000.00
Mandor L.04 Oh 0.050 200,000.00 10,000.00
JUMLAH TENAGA KERJA 465,000.00
B. BAHAN
Dolken kayu dia. 8-10/ 400 cm Batang 1.700 60,000.00 102,000.00
Kayu Kls. III M3 0.210 3,120,000.00 655,200.00
Paku biasa Kg 0.300 42,000.00 12,600.00
Semen portland Kg 10.500 3,000.00 31,500.00
Pasir beton M3 0.030 450,000.00 13,500.00
Kerikil beton M3 0.050 450,000.00 22,500.00
Seng gelombang Lbr 1.500 113,000.00 169,500.00
Seng plat Lbr 0.250 72,000.00 18,000.00
JUMLAH HARGA BAHAN 1,024,800.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,489,800.00
E. Overhead & Profit 12% x D 178,776.00
F. Harga Satuan Pekerjaan (D+E) 1,668,576.00

II. HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 M3 tanah biasa sedalam 1 m
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.750 120,000.00 90,000.00
Mandor L.04 Oh 0.025 200,000.00 5,000.00
JUMLAH TENAGA KERJA 95,000.00
B. BAHAN -
JUMLAH HARGA BAHAN -
C. PERALATAN -
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 95,000.00
E. Overhead & Profit 12% x D 11,400.00
F. Harga Satuan Pekerjaan (D+E) 106,400.00

A.2.3.1.9. Pengurugan kembali1M3 galian dihitung dari 1/3kali dari koefisien pekerjaan galian
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.500 120,000.00 60,000.00
Mandor L.04 Oh 0.050 200,000.00 10,000.00
JUMLAH TENAGA KERJA 70,000.00
B. BAHAN -
JUMLAH HARGA BAHAN -
C. PERALATAN -
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 70,000.00
Lembaran -17

E. Overhead & Profit 12% x D 8,400.00


F. Harga Satuan Pekerjaan (D+E) 78,400.00
Lembaran -18

A.2.3.1.11. Pengurugan 1M3 dengan pasir urug


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Mandor L.04 Oh 0.010 200,000.00 2,000.00
JUMLAH TENAGA KERJA 38,000.00
B. BAHAN -
Pasir urug M3 1.200 326,000.00 391,200.00
JUMLAH HARGA BAHAN 391,200.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 429,200.00
E. Overhead & Profit 12% x D 51,504.00
F. Harga Satuan Pekerjaan (D+E) 480,704.00

A.2.3.1.14. Pengurugan 1M3 sirtu padat


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.250 120,000.00 30,000.00
Mandor L.04 Oh 0.025 200,000.00 5,000.00
JUMLAH TENAGA KERJA 35,000.00
B. BAHAN -
Tanah Sirtu Padat M3 1.200 450,000.00 540,000.00
JUMLAH HARGA BAHAN 540,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 575,000.00
E. Overhead & Profit 12% x D 69,000.00
F. Harga Satuan Pekerjaan (D+E) 644,000.00

A.2.3.1.15. Pengurugan 1 M3 dengan Tanah Timbunan Biasa


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.250 120,000.00 30,000.00
Mandor L.04 Oh 0.025 200,000.00 5,000.00
JUMLAH TENAGA KERJA 35,000.00
B. BAHAN -
Tanah Urug/Timbunan Biasa M3 1.200 400,000.00 480,000.00
JUMLAH HARGA BAHAN 480,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 515,000.00
E. Overhead & Profit 12% x D 61,800.00
F. Harga Satuan Pekerjaan (D+E) 576,800.00

III. HARGA SATUAN PEKERJAAN PONDASI


A.2.3.1.9. Pemasangan 1 M3 batu kosong (anstambing)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.780 120,000.00 93,600.00
Tukang Batu L.02 Oh 0.390 150,000.00 58,500.00
Kepala Tukang L.03 Oh 0.039 175,000.00 6,825.00
Mandor L.04 Oh 0.039 200,000.00 7,800.00
JUMLAH TENAGA KERJA 166,725.00
B. BAHAN
Batu belah M3 1.200 450,000.00 540,000.00
Pasir urug M3 0.432 326,000.00 140,832.00
JUMLAH HARGA BAHAN 680,832.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 847,557.00
E. Overhead & Profit 12% x D 101,706.84
F. Harga Satuan Pekerjaan (D+E) 949,263.00

A.3.2.1.3. Pemasangan 1 M3 pondasi batu belah campuran 1SP : 5PP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.500 120,000.00 180,000.00
Tukang Batu L.02 Oh 0.750 150,000.00 112,500.00
Kepala Tukang L.03 Oh 0.075 175,000.00 13,125.00
Mandor L.04 Oh 0.075 200,000.00 15,000.00
JUMLAH TENAGA KERJA 320,625.00
B. BAHAN
Lembaran -19

Batu belah M3 1.200 450,000.00 540,000.00


Semen portland Kg 136.000 3,000.00 408,000.00
Pasir pasang M3 0.544 450,000.00 244,800.00
JUMLAH HARGA BAHAN 1,192,800.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,513,425.00
E. Overhead & Profit 12% x D 181,611.00
F. Harga Satuan Pekerjaan (D+E) 1,695,036.00
Lembaran -20

IV. HARGA SATUAN PEKERJAAN DINDING


A.4.4.1.7. Pemasangan 1 M2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 55,750.00
B. BAHAN
Bata merah M3 70.000 3,300.00 231,000.00
Semen portland Kg 18.950 3,000.00 56,850.00
Pasir pasang M3 0.038 450,000.00 17,100.00
JUMLAH HARGA BAHAN 304,950.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 360,700.00
E. Overhead & Profit 12% x D 43,284.00
F. Harga Satuan Pekerjaan (D+E) 403,984.00

A.4.4.1.10. Pemasangan 1 M2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 5PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 55,750.00
B. BAHAN
Bata merah M3 70.000 3,300.00 231,000.00
Semen portland Kg 9.680 3,000.00 29,040.00
Pasir pasang M3 0.045 450,000.00 20,250.00
JUMLAH HARGA BAHAN 280,290.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 336,040.00
E. Overhead & Profit 12% x D 40,324.80
F. Harga Satuan Pekerjaan (D+E) 376,364.00

A.4.4.1.21. Pemasangan 1 M2 dinding Conblock HB10 campuran 1SP : 4PP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 55,750.00
B. BAHAN
Conblock HB10 M3 12.500 10,000.00 125,000.00
Semen portland Kg 12.130 3,000.00 36,390.00
Pasir pasang M3 0.388 450,000.00 174,600.00
Besi angker dia. 8 Kg 0.280 16,400.00 4,592.00
JUMLAH HARGA BAHAN 335,990.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 391,740.00
E. Overhead & Profit 12% x D 47,008.80
F. Harga Satuan Pekerjaan (D+E) 438,748.00

A.4.4.1.22. Pemasangan 1 M2 dinding Bataco Semen (uk. 23 x 12 x 8) campuran 1SP : 4PP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 55,750.00
B. BAHAN
Batu Bataco Semen uk. 23 x 12 x 8 m3 28.000 4,000.00 112,000.00
Semen portland kg 11.500 3,000.00 34,500.00
Pasir pasang M3 0.043 450,000.00 19,350.00
Besi angker dia. 8 Kg 0.280 16,400.00 4,592.00
JUMLAH HARGA BAHAN 165,850.00
C. PERALATAN
Lembaran -21

JUMLAH HARGA ALAT -


D. JUMLAH (A+B+C) 221,600.00
E. Overhead & Profit 12% x D 26,592.00
F. Harga Satuan Pekerjaan (D+E) 248,192.00
Lembaran -22

V. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2. Pemasangan 1 M2 plesteran 1SP : 2PP tebal 15 mm.
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.150 150,000.00 22,500.00
Kepala Tukang L.03 Oh 0.015 175,000.00 2,625.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 64,125.00
B. BAHAN
Semen portland Kg 10.224 3,000.00 30,672.00
Pasir pasang M3 0.020 450,000.00 9,000.00
JUMLAH HARGA BAHAN 39,672.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 103,797.00
E. Overhead & Profit 12% x D 12,455.64
F. Harga Satuan Pekerjaan (D+E) 116,252.00

A.4.4.2.4. Pemasangan 1 M2 plesteran 1SP : 4PP tebal 15 mm.


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.150 150,000.00 22,500.00
Kepala Tukang L.03 Oh 0.015 175,000.00 2,625.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 64,125.00
B. BAHAN
Semen portland Kg 6.240 3,000.00 18,720.00
Pasir pasang M3 0.024 450,000.00 10,800.00
JUMLAH HARGA BAHAN 29,520.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 93,645.00
E. Overhead & Profit 12% x D 11,237.40
F. Harga Satuan Pekerjaan (D+E) 104,882.00

A.4.4.2.27. Pemasangan 1 M2 acian.


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.200 120,000.00 24,000.00
Tukang Batu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.010 200,000.00 2,000.00
JUMLAH TENAGA KERJA 42,750.00
B. BAHAN
Semen portland Kg 3.250 3,000.00 9,750.00
JUMLAH HARGA BAHAN 9,750.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 52,500.00
E. Overhead & Profit 12% x D 6,300.00
F. Harga Satuan Pekerjaan (D+E) 58,800.00
Lembaran -23

VI. HARGA SATUAN PEKERJAAN BETON


Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.6500 120,000.00 198,000.00
Tukang Batu L.02 Oh 0.2750 150,000.00 41,250.00
Kepala Tukang L.03 Oh 0.0280 175,000.00 4,900.00
Mandor L.04 Oh 0.0830 200,000.00 16,600.00
JUMLAH TENAGA KERJA 260,750.00
B. BAHAN
Semen portland kg 247.000 3,000.00 741,000.00
Pasir beton kg 869.000 321.00 278,949.00
Kerikil (Maks 30mm) kg 999.000 407.00 406,593.00
Air Liter 215.000 200.00 43,000.00
JUMLAH HARGA BAHAN 1,469,542.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,730,292.00
E. Overhead & Profit 12% x D 207,635.04
F. Harga Satuan Pekerjaan (D+E) 1,937,927.00
*) Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.6500 120,000.00 198,000.00
Tukang Batu L.02 Oh 0.2750 150,000.00 41,250.00
Kepala Tukang L.03 Oh 0.0280 175,000.00 4,900.00
Mandor L.04 Oh 0.0830 200,000.00 16,600.00
JUMLAH TENAGA KERJA 260,750.00
B. BAHAN
Semen portland kg 299.000 3,000.00 897,000.00
Pasir beton kg 799.000 321.00 256,479.00
Kerikil (Maks 30mm) kg 1,017.000 407.00 413,919.00
Air Liter 215.000 200.00 43,000.00
JUMLAH HARGA BAHAN 1,610,398.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,871,148.00
E. Overhead & Profit 12% x D 224,537.76
F. Harga Satuan Pekerjaan (D+E) 2,095,685.00
*) Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

A.4.1.1.5. Membuat 1 M3 beton mutu f'c = 14,5 Mpa (K 175), slump (12 · ·2) cm, w/c = 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.6500 120,000.00 198,000.00
Tukang Batu L.02 Oh 0.2750 150,000.00 41,250.00
Kepala Tukang L.03 Oh 0.0280 175,000.00 4,900.00
Mandor L.04 Oh 0.0830 200,000.00 16,600.00
JUMLAH TENAGA KERJA 260,750.00
B. BAHAN
Semen portland kg 326.000 3,000.00 978,000.00
Pasir beton kg 760.000 321.00 243,960.00
Kerikil (Maks 30mm) kg 1,029.000 407.00 418,803.00
Air Liter 215.000 200.00 43,000.00
JUMLAH HARGA BAHAN 1,683,763.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,944,513.00
E. Overhead & Profit 12% x D 233,341.56
F. Harga Satuan Pekerjaan (D+E) 2,177,854.00
*) Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.070 120,000.00 8,400.00
Tukang Besi L.02 Oh 0.070 150,000.00 10,500.00
Kepala Tukang L.03 Oh 0.007 175,000.00 1,225.00
Mandor L.04 Oh 0.004 200,000.00 800.00
JUMLAH TENAGA KERJA 20,925.00
B. BAHAN
Besi beton (Polos/ulir) Kg 10.500 16,400.00 172,200.00
Lembaran -24

Kawat beton Kg 0.150 41,000.00 6,150.00


JUMLAH HARGA BAHAN 178,350.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 199,275.00
E. Overhead & Profit 12% x D 23,913.00
F. Harga Satuan Pekerjaan (D+E) 10 Kg 223,188.00
Harga Satuan Pekerjaan 1 Kg 22,318.80
Lembaran -25

A.4.1.1.21. Pemasangan 1 M2 bekisting untuk sloof


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.520 120,000.00 62,400.00
Tukang Kayu L.02 Oh 0.260 150,000.00 39,000.00
Kepala Tukang L.03 Oh 0.026 175,000.00 4,550.00
Mandor L.04 Oh 0.026 200,000.00 5,200.00
JUMLAH TENAGA KERJA 111,150.00
B. BAHAN
Kayu kelas III M3 0.045 3,120,000.00 140,400.00
Paku 5 cm - 10 cm Kg 0.300 42,000.00 12,600.00
Minyak bekisting Liter 0.100 12,500.00 1,250.00
JUMLAH HARGA BAHAN 154,250.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 265,400.00
E. Overhead & Profit 12% x D 31,848.00
F. Harga Satuan Pekerjaan (D+E) 297,248.00

A.4.1.1.22. Pemasangan 1 M2 bekisting untuk kolom


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.660 120,000.00 79,200.00
Tukang Kayu L.02 Oh 0.330 150,000.00 49,500.00
Kepala Tukang L.03 Oh 0.033 175,000.00 5,775.00
Mandor L.04 Oh 0.033 200,000.00 6,600.00
JUMLAH TENAGA KERJA 141,075.00
B. BAHAN
Kayu kelas III M3 0.040 3,120,000.00 124,800.00
Paku 5 cm - 10 cm Kg 0.400 42,000.00 16,800.00
Minyak bekisting Liter 0.200 12,500.00 2,500.00
Balok kayu kelas II M3 0.015 4,840,000.00 72,600.00
Plywood tebal 9 mm Lbr 0.350 571,000.00 199,850.00
Dolken kayu ø 8 - 10 cm/ 4 m Batang 2.000 60,000.00 120,000.00
JUMLAH HARGA BAHAN 536,550.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 677,625.00
E. Overhead & Profit 12% x D 81,315.00
F. Harga Satuan Pekerjaan (D+E) 758,940.00

A.4.1.1.23. Pemasangan 1 M2 bekisting untuk balok


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.660 120,000.00 79,200.00
Tukang Kayu L.02 Oh 0.330 150,000.00 49,500.00
Kepala Tukang L.03 Oh 0.033 175,000.00 5,775.00
Mandor L.04 Oh 0.033 200,000.00 6,600.00
JUMLAH TENAGA KERJA 141,075.00
B. BAHAN
Kayu kelas III M3 0.040 3,120,000.00 124,800.00
Paku 5 cm - 12 cm Kg 0.400 42,000.00 16,800.00
Minyak bekisting Liter 0.200 12,500.00 2,500.00
Balok kayu kelas II M3 0.018 4,840,000.00 87,120.00
Plywood tebal 9 mm Lbr 0.350 571,000.00 199,850.00
Dolken kayu ø 8 - 10 cm/ 4 m Batang 2.000 60,000.00 120,000.00
JUMLAH HARGA BAHAN 551,070.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 692,145.00
E. Overhead & Profit 12% x D 83,057.40
F. Harga Satuan Pekerjaan (D+E) 775,202.00

A.4.1.1.23. Pemasangan 1 M2 bekisting untuk lantai


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.660 120,000.00 79,200.00
Tukang Kayu L.02 Oh 0.330 150,000.00 49,500.00
Kepala Tukang L.03 Oh 0.033 175,000.00 5,775.00
Mandor L.04 Oh 0.033 200,000.00 6,600.00
JUMLAH TENAGA KERJA 141,075.00
B. BAHAN
Kayu kelas III M3 0.040 3,120,000.00 124,800.00
Paku 5 cm - 12 cm Kg 0.400 42,000.00 16,800.00
Lembaran -26

Minyak bekisting Liter 0.200 12,500.00 2,500.00


Balok kayu kelas II M3 0.015 4,840,000.00 72,600.00
Plywood tebal 9 mm Lbr 0.350 571,000.00 199,850.00
Dolken kayu ø 8 - 10 cm/ 4 m Batang 6.000 60,000.00 360,000.00
JUMLAH HARGA BAHAN 776,550.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 917,625.00
E. Overhead & Profit 12% x D 110,115.00
F. Harga Satuan Pekerjaan (D+E) 1,027,740.00
Lembaran -27

(RSNI 2002, 6.13) 1 M3 Bongkar beton


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 6.667 120,000.00 800,040.00
Mandor L.04 Oh 0.333 200,000.00 66,600.00
JUMLAH TENAGA KERJA 866,640.00
B. BAHAN
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 866,640.00
E. Overhead & Profit 12% x D 103,996.80
F. Harga Satuan Pekerjaan (D+E) 970,636.00

(SNI 03 3434-2002, 6.13) 1 M3 Beton 1 PC : 2 PS : 3 KR


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 3.400 120,000.00 408,000.00
Tukang Batu L.02 Oh 0.850 150,000.00 127,500.00
Kepala Tukang L.03 Oh 0.085 175,000.00 14,875.00
Mandor L.04 Oh 0.170 200,000.00 34,000.00
JUMLAH TENAGA KERJA 584,375.00
B. BAHAN
Semen PC Kg 194.000 3,000.00 582,000.00
Pasir beton M3 0.312 450,000.00 140,400.00
Batu pecah/koral M3 0.480 550,000.00 264,000.00
JUMLAH HARGA BAHAN 986,400.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,570,775.00
E. Overhead & Profit 12% x D 188,493.00
F. Harga Satuan Pekerjaan (D+E) 1,759,268.00

Untuk 1 M3 Pekerjaan Sloof (Beton K-175)


Berat Besi Harga Beton Harga Bakesting Harga Siram/ Jumlah Harga
Harga Pembesian (Rp)
(Kg/m3) (Rp) (Rp) Bongkar (Rp) (Rp)
110 2,455,068.00 2,177,854.00 297,248.00 970,636.00 5,900,806.00
150 3,347,820.00 2,177,854.00 297,248.00 970,636.00 6,793,558.00

Untuk 1 M3 Pekerjaan Balok (Beton K-175)


Berat Besi Harga Beton Harga Bakesting Harga Siram/ Jumlah Harga
Harga Pembesian (Rp)
(Kg/m3) (Rp) (Rp) Bongkar (Rp) (Rp)
110 2,455,068.00 2,177,854.00 775,202.00 970,636.00 6,378,760.00
150 3,347,820.00 2,177,854.00 775,202.00 970,636.00 7,271,512.00

Untuk 1 M3 Pekerjaan Kolom (Beton K-175)


Berat Besi Harga Beton Harga Bakesting Harga Siram/ Jumlah Harga
Harga Pembesian (Rp)
(Kg/m3) (Rp) (Rp) Bongkar (Rp) (Rp)
110 2,455,068.00 2,177,854.00 758,940.00 970,636.00 6,362,498.00
150 3,347,820.00 2,177,854.00 758,940.00 970,636.00 7,255,250.00

Untuk 1 M3 Pekerjaan Plat Lantai (Beton K-175)


Berat Besi Harga Beton Harga Bakesting Harga Siram/ Jumlah Harga
Harga Pembesian (Rp)
(Kg/m3) (Rp) (Rp) Bongkar (Rp) (Rp)
110 2,455,068.00 2,177,854.00 1,027,740.00 970,636.00 6,631,298.00
150 3,347,820.00 2,177,854.00 1,027,740.00 970,636.00 7,524,050.00
Lembaran -28

VII. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING


A.4.4.3.34. Pemasangan 1 M2 Lantai Keramik Ukuran 40 cm x 40 cm polish
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.250 120,000.00 30,000.00
Tukang Batu L.02 Oh 0.125 150,000.00 18,750.00
Kepala Tukang L.03 Oh 0.013 175,000.00 2,275.00
Mandor L.04 Oh 0.013 200,000.00 2,600.00
JUMLAH TENAGA KERJA 53,625.00
B. BAHAN
Keramik 40 cm x 40 cm polish Bh 6.630 27,600.00 182,988.00
Semen portland Kg 9.800 3,000.00 29,400.00
Semen warna / Pengisi Nat Keramik Semen Instan Kg 1.300 31,000.00 40,300.00
Pasir pasang M3 0.045 450,000.00 20,250.00
JUMLAH HARGA BAHAN 272,938.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 326,563.00
E. Overhead & Profit 12% x D 39,187.56
F. Harga Satuan Pekerjaan (D+E) 365,750.00

A.4.4.3.34. Pemasangan 1 M2 Lantai Keramik Ukuran 40 cm x 40 cm unpolish


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.250 120,000.00 30,000.00
Tukang Batu L.02 Oh 0.125 150,000.00 18,750.00
Kepala Tukang L.03 Oh 0.013 175,000.00 2,275.00
Mandor L.04 Oh 0.013 200,000.00 2,600.00
JUMLAH TENAGA KERJA 53,625.00
B. BAHAN
Keramik 40 cm x 40 cm unpolish Bh 6.630 29,200.00 193,596.00
Semen portland Kg 9.800 3,000.00 29,400.00
Semen warna / Pengisi Nat Keramik Semen Instan Kg 1.300 31,000.00 40,300.00
Pasir pasang M3 0.045 450,000.00 20,250.00
JUMLAH HARGA BAHAN 283,546.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 337,171.00
E. Overhead & Profit 12% x D 40,460.52
F. Harga Satuan Pekerjaan (D+E) 377,631.00

A.4.4.3.34. Pemasangan 1 M2 Lantai Keramik Ukuran 60 cm x 60 cm unpolish


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.240 120,000.00 28,800.00
Tukang Batu L.02 Oh 0.120 150,000.00 18,000.00
Kepala Tukang L.03 Oh 0.012 175,000.00 2,100.00
Mandor L.04 Oh 0.012 200,000.00 2,400.00
JUMLAH TENAGA KERJA 51,300.00
B. BAHAN
Keramik 60 cm x 60 cm unpolish Bh 3.100 163,200.00 505,920.00
Semen portland Kg 9.600 3,000.00 28,800.00
Semen warna / Pengisi Nat Keramik Semen Instan Kg 1.500 31,000.00 46,500.00
Pasir pasang M3 0.045 450,000.00 20,250.00
JUMLAH HARGA BAHAN 601,470.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 652,770.00
E. Overhead & Profit 12% x D 78,332.40
F. Harga Satuan Pekerjaan (D+E) 731,102.00

A.4.4.3.35. Pemasangan 1 M2 Dinding Keramik 20 cm x 25 cm Polis


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.700 120,000.00 84,000.00
Tukang Batu L.02 Oh 0.350 150,000.00 52,500.00
Kepala Tukang L.03 Oh 0.035 175,000.00 6,125.00
Mandor L.04 Oh 0.035 200,000.00 7,000.00
JUMLAH TENAGA KERJA 149,625.00
B. BAHAN
Keramik 20 cm x 25 cm polish m2 1.100 8,700.00 9,570.00
Semen portland Kg 9.300 3,000.00 27,900.00
Semen warna Kg 1.940 31,000.00 60,140.00
Pasir pasang M3 0.018 450,000.00 8,100.00
Lembaran -29

JUMLAH HARGA BAHAN 105,710.00


C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 255,335.00
E. Overhead & Profit 12% x D 30,640.20
F. Harga Satuan Pekerjaan (D+E) 285,975.00

A.4.4.3.36. Pemasangan 1 M2 Dinding Keramik 20 cm x 20 cm Polis


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.700 120,000.00 84,000.00
Tukang Batu L.02 Oh 0.350 150,000.00 52,500.00
Kepala Tukang L.03 Oh 0.035 175,000.00 6,125.00
Mandor L.04 Oh 0.035 200,000.00 7,000.00
JUMLAH TENAGA KERJA 149,625.00
B. BAHAN
Keramik 20 cm x 20 cm polish m2 1.100 8,700.00 9,570.00
Semen portland Kg 10.400 3,000.00 31,200.00
Semen warna Kg 0.500 31,000.00 15,500.00
Pasir pasang M3 0.045 450,000.00 20,250.00
JUMLAH HARGA BAHAN 76,520.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 226,145.00
E. Overhead & Profit 12% x D 27,137.40
F. Harga Satuan Pekerjaan (D+E) 253,282.00

A.4.4.3.36. Pemasangan 1 M2 Lantai Keramik 20 cm x 20 cm Polis


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.270 120,000.00 32,400.00
Tukang Batu L.02 Oh 0.135 150,000.00 20,250.00
Kepala Tukang L.03 Oh 0.014 175,000.00 2,450.00
Mandor L.04 Oh 0.014 200,000.00 2,800.00
JUMLAH TENAGA KERJA 57,900.00
B. BAHAN
Keramik 20 cm x 20 cm polish Bh 26.500 8,700.00 230,550.00
Semen portland Kg 10.400 3,000.00 31,200.00
Semen warna Kg 1.000 31,000.00 31,000.00
Pasir pasang M3 0.045 450,000.00 20,250.00
JUMLAH HARGA BAHAN 313,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 370,900.00
E. Overhead & Profit 12% x D 44,508.00
F. Harga Satuan Pekerjaan (D+E) 415,408.00

A.4.4.3.18. Pemasangan 1 M' Plin Keramik 10 cm x 40 cm, Polis


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.090 120,000.00 10,800.00
Tukang Batu L.02 Oh 0.090 150,000.00 13,500.00
Kepala Tukang L.03 Oh 0.009 175,000.00 1,575.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 26,875.00
B. BAHAN
Plint Keramik 10 x 40 cm, Polis bh 3.530 7,600.00 26,828.00
Semen portland Kg 1.140 3,000.00 3,420.00
Semen warna Kg 0.100 31,000.00 3,100.00
Pasir pasang M3 0.003 450,000.00 1,350.00
JUMLAH HARGA BAHAN 34,698.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 61,573.00
E. Overhead & Profit 12% x D 7,388.76
F. Harga Satuan Pekerjaan (D+E) 68,961.00
Lembaran -30

VIII. HARGA SATUAN PEKERJAAN KAYU


A.4.6.1.1. Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela, kayu klas I
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 7.000 120,000.00 840,000.00
Tukang Kayu L.02 Oh 21.000 150,000.00 3,150,000.00
Kepala Tukang L.03 Oh 2.100 175,000.00 367,500.00
Mandor L.04 Oh 0.350 200,000.00 70,000.00
JUMLAH TENAGA KERJA 4,427,500.00
B. BAHAN
Balok kayu kls 1 M3 1.100 8,480,000.00 9,328,000.00
Paku 10 cm Kg 1.250 42,000.00 52,500.00
Lem kayu Kg 1.000 55,000.00 55,000.00
JUMLAH HARGA BAHAN 9,435,500.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 13,863,000.00
E. Overhead & Profit 12% x D 1,663,560.00
F. Harga Satuan Pekerjaan (D+E) 15,526,560.00

A.4.6.1.5. Pembuatan dan pemasangan 1 M2 daun pintu panel, kayu klas I atau II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.000 120,000.00 120,000.00
Tukang Kayu L.02 Oh 3.000 150,000.00 450,000.00
Kepala Tukang L.03 Oh 0.300 175,000.00 52,500.00
Mandor L.04 Oh 0.050 200,000.00 10,000.00
JUMLAH TENAGA KERJA 632,500.00
B. BAHAN
Papan Kayu Kelas I M3 0.040 8,480,000.00 339,200.00
Lem kayu Kg 0.500 55,000.00 27,500.00
JUMLAH HARGA BAHAN 366,700.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 999,200.00
E. Overhead & Profit 12% x D 119,904.00
F. Harga Satuan Pekerjaan (D+E) 1,119,104.00

A.4.6.1.6. Pembuatan dan pemasangan 1 M2 pintu dan jendela kaca, kayu klas I atau II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.800 120,000.00 96,000.00
Tukang Kayu L.02 Oh 2.400 150,000.00 360,000.00
Kepala Tukang L.03 Oh 0.240 175,000.00 42,000.00
Mandor L.04 Oh 0.040 200,000.00 8,000.00
JUMLAH TENAGA KERJA 506,000.00
B. BAHAN
Papan Kayu Kelas I M3 0.024 8,480,000.00 203,520.00
Lem kayu Kg 0.300 55,000.00 16,500.00
JUMLAH HARGA BAHAN 220,020.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 726,020.00
E. Overhead & Profit 12% x D 87,122.40
F. Harga Satuan Pekerjaan (D+E) 813,142.00

A.4.6.1.8. Pembuatan 1 M2 daun pintu plywood rangkap, rangka kayu klas II tertutup (lebar sampai 90 cm)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.700 120,000.00 84,000.00
Tukang Kayu L.02 Oh 2.100 150,000.00 315,000.00
Kepala Tukang L.03 Oh 0.210 175,000.00 36,750.00
Mandor L.04 Oh 0.035 200,000.00 7,000.00
JUMLAH TENAGA KERJA 442,750.00
B. BAHAN
Papan Kayu Kelas II M3 0.025 4,840,000.00 121,000.00
Paku 1 cm - 2,5 cm Kg 0.030 42,000.00 1,260.00
Lem kayu Kg 0.500 55,000.00 27,500.00
Plywood tebal 4 mm ukuran (90 x 220) cm Lembar 1.000 243000 243,000.00
JUMLAH HARGA BAHAN 392,760.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 835,510.00
E. Overhead & Profit 12% x D 100,261.20
Lembaran -31

F. Harga Satuan Pekerjaan (D+E) 935,771.00


Lembaran -32

A.4.6.1.9. Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.670 120,000.00 80,400.00
Tukang Kayu L.02 Oh 2.000 150,000.00 300,000.00
Kepala Tukang L.03 Oh 0.200 175,000.00 35,000.00
Mandor L.04 Oh 0.335 200,000.00 67,000.00
JUMLAH TENAGA KERJA 482,400.00
B. BAHAN
Papan Kayu Kelas II M3 0.060 4,840,000.00 290,400.00
Paku uk. 1 cm - 4 cm kg 0.150 42,000.00 6,300.00
JUMLAH HARGA BAHAN 296,700.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 779,100.00
E. Overhead & Profit 12% x D 93,492.00
F. Harga Satuan Pekerjaan (D+E) 872,592.00

SNI A.4.6.1.13. Pembuatan 1 M3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 4.000 120,000.00 480,000.00
Tukang Kayu L.02 Oh 12.000 150,000.00 1,800,000.00
Kepala Tukang L.03 Oh 1.200 175,000.00 210,000.00
Mandor L.04 Oh 0.200 200,000.00 40,000.00
JUMLAH TENAGA KERJA 2,530,000.00
B. BAHAN
Balok kayu M3 1.100 8,480,000.00 9,328,000.00
Besi strip tebal 5mm Kg 15.000 28,000.00 420,000.00
Paku 12 cm Kg 5.600 42,000.00 235,200.00
JUMLAH HARGA BAHAN 9,983,200.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 12,513,200.00
E. Overhead & Profit 12% x D 1,501,584.00
F. Harga Satuan Pekerjaan (D+E) 14,014,784.00

A.4.6.1.15. Pemasangan 1 M3 konstruksi gordeng, kayu kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 6.700 120,000.00 804,000.00
Tukang Kayu L.02 Oh 20.100 150,000.00 3,015,000.00
Kepala Tukang L.03 Oh 2.010 175,000.00 351,750.00
Mandor L.04 Oh 0.335 200,000.00 67,000.00
JUMLAH TENAGA KERJA 4,237,750.00
B. BAHAN
Balok kayu M3 1.100 4,840,000.00 5,324,000.00
Besi strip tebal 5mm Kg 15.000 28,000.00 420,000.00
Paku 12 cm Kg 3.000 42,000.00 126,000.00
JUMLAH HARGA BAHAN 5,870,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 10,107,750.00
E. Overhead & Profit 12% x D 1,212,930.00
F. Harga Satuan Pekerjaan (D+E) 11,320,680.00

A.4.6.1.22. Pemasangan 1 M' listplank ukuran (3 x 30) cm, kayu kelas I atau kelas II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.100 120,000.00 12,000.00
Tukang Kayu L.02 Oh 0.200 150,000.00 30,000.00
Kepala Tukang L.03 Oh 0.020 175,000.00 3,500.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 46,500.00
B. BAHAN
Papan kayu Kls.2 M3 0.011 4,840,000.00 53,240.00
Paku 5 dan 7 cm Kg 0.050 42,000.00 2,100.00
JUMLAH HARGA BAHAN 55,340.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 101,840.00
E. Overhead & Profit 12% x D 12,220.80
F. Harga Satuan Pekerjaan (D+E) 114,060.00
Lembaran -33

A.4.6.1.20. Pemasangan 1 M2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.200 120,000.00 24,000.00
Tukang Kayu L.02 Oh 0.300 150,000.00 45,000.00
Kepala Tukang L.03 Oh 0.030 175,000.00 5,250.00
Mandor L.04 Oh 0.010 200,000.00 2,000.00
JUMLAH TENAGA KERJA 76,250.00
B. BAHAN
Kaso-kaso 5 x 7 cm M3 0.016 4,840,000.00 78,892.00
Paku 7 - 10 cm Kg 0.250 42,000.00 10,500.00
JUMLAH HARGA BAHAN 89,392.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 165,642.00
E. Overhead & Profit 12% x D 19,877.04
F. Harga Satuan Pekerjaan (D+E) 185,519.00

A.4.5.1.5. Pemasangan 1 M2 langit-langit tripleks (120 x 240) cm, tebal 3mm, 4mm & 6 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.100 120,000.00 12,000.00
Tukang Kayu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 29,750.00
B. BAHAN
Tripleks Lembar 0.375 243,000.00 91,125.00
Paku tripleks Kg 0.030 42,000.00 1,260.00
JUMLAH HARGA BAHAN 92,385.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 122,135.00
E. Overhead & Profit 12% x D 14,656.20
F. Harga Satuan Pekerjaan (D+E) 136,791.00

A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.350 120,000.00 42,000.00
Tukang Kayu L.02 Oh 0.350 150,000.00 52,500.00
Kepala Tukang L.03 Oh 0.035 175,000.00 6,125.00
Mandor L.04 Oh 0.018 200,000.00 3,600.00
JUMLAH TENAGA KERJA 104,225.00
B. BAHAN
Rangka metal hollow 40.40.2 mm & 20.40.2 mm M1 4.000 14,700.00 58,800.00
Assesoris (perkuatan, las dll), 60% x rangka % 0.600 58,800.00 35,280.00
JUMLAH HARGA BAHAN 94,080.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 198,305.00
E. Overhead & Profit 12% x D 23,796.60
F. Harga Satuan Pekerjaan (D+E) 222,101.00

A.4.5.1.5. Pemasangan 1 M2 langit-langit KALSIBOARD (120 x 240) cm, tebal 4mm & 6 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.100 120,000.00 12,000.00
Tukang Kayu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 29,750.00
B. BAHAN
Kalsiboard, tebal 5 mm Lembar 0.375 195,900.00 73,462.50
Paku tripleks Kg 0.030 42,000.00 1,260.00
JUMLAH HARGA BAHAN 74,722.50
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 104,472.50
E. Overhead & Profit 12% x D 12,536.70
F. Harga Satuan Pekerjaan (D+E) 117,009.00
Lembaran -34

A.4.5.1.6. Pemasangan 1 m’ list langit-langit kayu profil


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.050 120,000.00 6,000.00
Tukang Kayu L.02 Oh 0.050 150,000.00 7,500.00
Kepala Tukang L.03 Oh 0.005 175,000.00 875.00
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 14,975.00
B. BAHAN
List kayu klas I profil lebar 8 cm m' 1.050 23,500.00 24,675.00
Paku Campur kg 0.010 42,000.00 420.00
JUMLAH HARGA BAHAN 25,095.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 40,070.00
E. Overhead & Profit 12% x D 4,808.40
F. Harga Satuan Pekerjaan (D+E) 44,878.00

A.4.5.2.38. Pemasangan 1 M2 atap seng gelombang


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.120 120,000.00 14,400.00
Tukang Kayu L.02 Oh 0.060 150,000.00 9,000.00
Kepala Tukang L.03 Oh 0.006 175,000.00 1,050.00
Mandor L.04 Oh 0.006 200,000.00 1,200.00
JUMLAH TENAGA KERJA 25,650.00
B. BAHAN
Seng gelombang 3" x 6" Lembar 0.700 113,000.00 79,100.00
Paku biasa 1/2" - 1" Kg 0.020 42,000.00 840.00
JUMLAH HARGA BAHAN 79,940.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 105,590.00
E. Overhead & Profit 12% x D 12,670.80
F. Harga Satuan Pekerjaan (D+E) 118,260.00

A.4.5.2.36. Pemasangan 1 m’ nok atap seng


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.150 120,000.00 18,000.00
Tukang Kayu L.02 Oh 0.070 150,000.00 10,500.00
Kepala Tukang L.03 Oh 0.007 175,000.00 1,225.00
Mandor L.04 Oh 0.006 200,000.00 1,200.00
JUMLAH TENAGA KERJA 30,925.00
B. BAHAN
Zink Plat 3" x 6" BJLS 25 Lbr 0.300 72,000.00 21,600.00
Paku Zink Kg 0.040 42,000.00 1,680.00
JUMLAH HARGA BAHAN 23,280.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 54,205.00
E. Overhead & Profit 12% x D 6,504.60
F. Harga Satuan Pekerjaan (D+E) 60,709.00

A.4.5.2.36. Pemasangan 1 m2 nok alumunium [Spandek]


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.100 120,000.00 12,000.00
Tukang Kayu L.02 Oh 1.000 150,000.00 150,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.010 200,000.00 2,000.00
JUMLAH TENAGA KERJA 165,750.00
B. BAHAN
Nok standar 40 cm 18, swg 22 M2 1.200 68,000.00 81,600.00
Paku hak panjang 15 cm Kg 0.040 42,000.00 1,680.00
JUMLAH HARGA BAHAN 83,280.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 249,030.00
E. Overhead & Profit 12% x D 29,883.60
F. Harga Satuan Pekerjaan (D+E) 278,913.00
Lembaran -35

A.4.5.2.38. Pemasangan 1 m2 Atap Zincalum Almunium/Spandek, tbl. 0,25 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.120 120,000.00 14,400.00
Tukang Kayu L.02 Oh 0.060 150,000.00 9,000.00
Kepala Tukang L.03 Oh 0.006 175,000.00 1,050.00
Mandor L.04 Oh 0.006 200,000.00 1,200.00
JUMLAH TENAGA KERJA 25,650.00
B. BAHAN
Atap Zincalum Almunium/Spandek, tbl. 0,25 mm m2 1.050 90,600.00 95,130.00
Paku sekrup bh 8.000 500.00 4,000.00
JUMLAH HARGA BAHAN 99,130.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 124,780.00
E. Overhead & Profit 12% x D 14,973.60
F. Harga Satuan Pekerjaan (D+E) 139,753.00

A.4.2.1.22. Pemasangan 1 m² Kuda - Kuda Baja Ringan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.200 120,000.00 24,000.00
Tukang Besi L.02 Oh 0.450 150,000.00 67,500.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.050 200,000.00 10,000.00
JUMLAH TENAGA KERJA 103,250.00
B. BAHAN
Baja Ringan Canai Dingin C75 m' 3.720 38,300.00 142,476.00
Baut (Screw Driver) Bh 28.000 1,100.00 30,800.00
Dynabol dia 12 x 120 mm Bh 2.000 9,000.00 18,000.00
Reng Canai Dingin m' 5.400 14,500.00 78,300.00
Talang /Jurai Canai Dingin m' 0.000 104,000.00 -
JUMLAH HARGA BAHAN 269,576.00
C. PERALATAN
Alat Rangka Atap Baja Canai Dingin 10% 0.100 269,576.00 26,957.60
JUMLAH HARGA ALAT 26,957.60
D. JUMLAH (A+B+C) 399,783.60
E. Overhead & Profit 12% x D 47,974.03
F. Harga Satuan Pekerjaan (D+E) 447,757.00

A.4.6.1.22. Pemasangan 1 m’ lisplank lebar 30 cm, bahan GRC board 9 mm, 12 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.1000 120,000.00 12,000.00
Tukang Kayu L.02 Oh 0.2000 150,000.00 30,000.00
Kepala Tukang L.03 Oh 0.0200 175,000.00 3,500.00
Mandor L.04 Oh 0.0050 200,000.00 1,000.00
JUMLAH TENAGA KERJA 46,500.00
B. BAHAN
Papan GRC board 9 mm M2 0.3300 90,000.00 29,700.00
Paku skrup GRC kg 0.0500 280,000.00 14,000.00
JUMLAH HARGA BAHAN 43,700.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 90,200.00
E. Overhead & Profit 12% x D 10,824.00
F. Harga Satuan Pekerjaan (D+E) 101,024.00
Lembaran -36

IX. HARGA SATUAN PEKERJAAN KUNCI, PENGGANTUNG DAN KACA


A.4.6.2.1. Pemasangan 1 buah kunci tanam antik
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.060 120,000.00 7,200.00
Tukang Kayu L.02 Oh 0.060 150,000.00 9,000.00
Kepala Tukang L.03 Oh 0.060 175,000.00 10,500.00
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 27,300.00
B. BAHAN
Kunci tanam antik Bh 1.000 267,000.00 267,000.00
JUMLAH HARGA BAHAN 267,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 294,300.00
E. Overhead & Profit 12% x D 35,316.00
F. Harga Satuan Pekerjaan (D+E) 329,616.00

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.010 120,000.00 1,200.00
Tukang Kayu L.02 Oh 0.500 150,000.00 75,000.00
Kepala Tukang L.03 Oh 0.050 175,000.00 8,750.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 85,950.00
B. BAHAN
Kunci tanam biasa Bh 1.000 267,000.00 267,000.00
JUMLAH HARGA BAHAN 267,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 352,950.00
E. Overhead & Profit 12% x D 42,354.00
F. Harga Satuan Pekerjaan (D+E) 395,304.00

A.4.6.2.5. Pemasangan 1 buah engsel pintu


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.015 120,000.00 1,800.00
Tukang Kayu L.02 Oh 0.150 150,000.00 22,500.00
Kepala Tukang L.03 Oh 0.015 175,000.00 2,625.00
Mandor L.04 Oh 0.0008 200,000.00 160.00
JUMLAH TENAGA KERJA 27,085.00
B. BAHAN
Engsel pintu Bh 1.000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 72,085.00
E. Overhead & Profit 12% x D 8,650.20
F. Harga Satuan Pekerjaan (D+E) 80,735.00

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.010 120,000.00 1,200.00
Tukang Kayu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.0005 200,000.00 100.00
JUMLAH TENAGA KERJA 18,050.00
B. BAHAN
Engsel kupu-kupu Bh 1.000 34,500.00 34,500.00
JUMLAH HARGA BAHAN 34,500.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 52,550.00
E. Overhead & Profit 12% x D 6,306.00
F. Harga Satuan Pekerjaan (D+E) 58,856.00

A.4.6.2.8. Pemasangan 1 buah spring knip


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.015 120,000.00 1,800.00
Tukang Kayu L.02 Oh 0.150 150,000.00 22,500.00
Kepala Tukang L.03 Oh 0.015 175,000.00 2,625.00
Mandor L.04 Oh 0.008 200,000.00 1,600.00
JUMLAH TENAGA KERJA 28,525.00
B. BAHAN
Lembaran -37

Spring knip Bh 1.000 13,000.00 13,000.00


JUMLAH HARGA BAHAN 13,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 41,525.00
E. Overhead & Profit 12% x D 4,983.00
F. Harga Satuan Pekerjaan (D+E) 46,508.00
Lembaran -38

A.4.6.2.9. Pemasangan 1 buah kait angin


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.015 120,000.00 1,800.00
Tukang Kayu L.02 Oh 0.150 150,000.00 22,500.00
Kepala Tukang L.03 Oh 0.015 175,000.00 2,625.00
Mandor L.04 Oh 0.008 200,000.00 1,600.00
JUMLAH TENAGA KERJA 28,525.00
B. BAHAN
Kait angin Bh 1.000 41,000.00 41,000.00
JUMLAH HARGA BAHAN 41,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 69,525.00
E. Overhead & Profit 12% x D 8,343.00
F. Harga Satuan Pekerjaan (D+E) 77,868.00

A.4.6.2.17. Pemasangan 1 M2 kaca tebal 5 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.015 120,000.00 1,800.00
Tukang Kayu L.02 Oh 0.150 150,000.00 22,500.00
Kepala Tukang L.03 Oh 0.015 175,000.00 2,625.00
Mandor L.04 Oh 0.0008 200,000.00 160.00
JUMLAH TENAGA KERJA 27,085.00
B. BAHAN
Kaca tebal 5 mm M2 1.100 174,000.00 191,400.00
Sealant Kg 0.050 55,000.00 2,750.00
JUMLAH HARGA BAHAN 194,150.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 221,235.00
E. Overhead & Profit 12% x D 26,548.20
F. Harga Satuan Pekerjaan (D+E) 247,783.00
Lembaran -39

X. HARGA SATUAN PEKERJAAN SANITAIR


A.5.1.1.20. Pemasangan 1 M' pipa galvanis dia. 3/4"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.054 120,000.00 6,480.00
Tukang Kayu L.02 Oh 0.090 150,000.00 13,500.00
Kepala Tukang L.03 Oh 0.009 175,000.00 1,575.00
Mandor L.04 Oh 0.027 200,000.00 5,400.00
JUMLAH TENAGA KERJA 26,955.00
B. BAHAN
Pipa galvanis 3/4" M 1.200 69,300.00 83,160.00
Perlengkapan 35% % 0.350 83,160.00 29,106.00
JUMLAH HARGA BAHAN 112,266.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 139,221.00
E. Overhead & Profit 12% x D 16,706.52
F. Harga Satuan Pekerjaan (D+E) 155,927.00

(RSNIT 2002 6.31) 1 Titik air kotor


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.000 120,000.00 120,000.00
Tukang Pipa L.02 Oh 0.100 150,000.00 15,000.00
JUMLAH TENAGA KERJA 135,000.00
B. BAHAN
Pipa PVC AW 3" M' 1.100 71,700.00 78,870.00
Perlengkapan 6% % 0.060 78,870.00 4,732.20
JUMLAH HARGA BAHAN 83,602.20
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 218,602.20
E. Overhead & Profit 12% x D 26,232.26
F. Harga Satuan Pekerjaan (D+E) 244,834.00

A.5.1.1.18. Pemasangan 1 Buah Kran Air diameter 1/2" atau 3/4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.010 120,000.00 1,200.00
Tukang Kayu L.02 Oh 0.400 150,000.00 60,000.00
Kepala Tukang L.03 Oh 0.040 175,000.00 7,000.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 69,200.00
B. BAHAN
Kran air 1/2" Bh 1.000 42,000.00 42,000.00
Perlengkapan 35% % 0.350 42,000.00 14,700.00
JUMLAH HARGA BAHAN 56,700.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 125,900.00
E. Overhead & Profit 12% x D 15,108.00
F. Harga Satuan Pekerjaan (D+E) 141,008.00

A.5.1.1 22. Pemasangan 1 m’ pipa galvanis diameter 1 ½” & 2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.200 120,000.00 24,000.00
Tukang Kayu L.02 Oh 0.200 150,000.00 30,000.00
Kepala Tukang L.03 Oh 0.020 175,000.00 3,500.00
Mandor L.04 Oh 0.001 200,000.00 200.00
JUMLAH TENAGA KERJA 57,700.00
B. BAHAN
Pipa galvanis 2" M' 1.200 0.00 -
Perlengkapan 35% % 0.350 0.00 -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 57,700.00
E. Overhead & Profit 12% x D 6,924.00
F. Harga Satuan Pekerjaan (D+E) 64,624.00
Lembaran -40

A.5.1.1.26. Pemasangan 1 M' Pipa PVC tipe AW 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.036 120,000.00 4,320.00
Tukang Kayu L.02 Oh 0.060 150,000.00 9,000.00
Kepala Tukang L.03 Oh 0.006 175,000.00 1,050.00
Mandor L.04 Oh 0.002 200,000.00 400.00
JUMLAH TENAGA KERJA 14,770.00
B. BAHAN
Pipa PVC dia. 1/2" M' 1.200 26,000.00 31,200.00
Perlengkapan 35% % 0.350 31,200.00 10,920.00
JUMLAH HARGA BAHAN 42,120.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 56,890.00
E. Overhead & Profit 12% x D 6,826.80
F. Harga Satuan Pekerjaan (D+E) 63,716.00

A.5.1.1.29. Pemasangan 1 M' Pipa PVC tipe AW 2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.054 120,000.00 6,480.00
Tukang Kayu L.02 Oh 0.090 150,000.00 13,500.00
Kepala Tukang L.03 Oh 0.009 175,000.00 1,575.00
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 22,155.00
B. BAHAN
Pipa PVC dia. 2" M' 1.200 71,700.00 86,040.00
Perlengkapan 35% % 0.350 86,040.00 30,114.00
JUMLAH HARGA BAHAN 116,154.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 138,309.00
E. Overhead & Profit 12% x D 16,597.08
F. Harga Satuan Pekerjaan (D+E) 154,906.00

A.5.1.1.31. Pemasangan 1 M' Pipa PVC tipe AW diameter 3"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.081 120,000.00 9,720.00
Tukang Kayu L.02 Oh 0.135 150,000.00 20,250.00
Kepala Tukang L.03 Oh 0.014 175,000.00 2,362.50
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 32,932.50
B. BAHAN
Pipa PVC dia. 3" M' 1.200 71,700.00 86,040.00
Perlengkapan 35% % 0.350 86,040.00 30,114.00
JUMLAH HARGA BAHAN 116,154.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 149,086.50
E. Overhead & Profit 12% x D 17,890.38
F. Harga Satuan Pekerjaan (D+E) 166,976.00

A.5.1.1 4a. (K3) Pemasangan 1 buah klosed duduk pakai tabung komplit.
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.200 120,000.00 144,000.00
Tukang Batu L.02 Oh 1.450 150,000.00 217,500.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.060 200,000.00 12,000.00
JUMLAH TENAGA KERJA 375,250.00
B. BAHAN
klosed Duduk Pakai Tabung (komplit) Unit 1.000 2,132,000.00 2,132,000.00
Semen Portland Kg 6.000 3,000.00 18,000.00
Pasir pasang M3 0.010 450,000.00 4,500.00
Perlengkapan 12% % 0.120 2,154,500.00 258,540.00
JUMLAH HARGA BAHAN 2,413,040.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 2,788,290.00
E. Overhead & Profit 12% x D 334,594.80
Lembaran -41

F. Harga Satuan Pekerjaan (D+E) 3,122,884.00

A.5.1.1 5. (K3) Pemasangan 1 buah wastafel keramik.


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.200 120,000.00 144,000.00
Tukang Kayu L.02 Oh 1.450 150,000.00 217,500.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.060 200,000.00 12,000.00
JUMLAH TENAGA KERJA 375,250.00
B. BAHAN
Wastafel Unit 1.000 410,000.00 410,000.00
Semen Portland Kg 6.000 3,000.00 18,000.00
Pasir pasang M3 0.010 450,000.00 4,500.00
Perlengkapan 12% % 0.120 432,500.00 51,900.00
JUMLAH HARGA BAHAN 484,400.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 859,650.00
E. Overhead & Profit 12% x D 103,158.00
F. Harga Satuan Pekerjaan (D+E) 962,808.00

A.5.1.1.5a. (K3) Pemasangan 1 buah Wastafel Kitchen Zink Metalco Single Bowls
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 1.200 120,000.00 144,000.00
Tukang Kayu L.02 Oh 1.450 150,000.00 217,500.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.060 200,000.00 12,000.00
JUMLAH TENAGA KERJA 375,250.00
B. BAHAN
Kitchen Zink Metalco Single Bowls MS42/20 Unit 1.000 226,000.00 226,000.00
Semen Portland Kg 6.000 1,690.00 10,140.00
Pasir pasang M3 0.010 255,000.00 2,550.00
Perlengkapan 12% % 0.120 238,690.00 28,642.80
JUMLAH HARGA BAHAN 267,332.80
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 642,582.80
E. Overhead & Profit 12% x D 77,109.94
F. Harga Satuan Pekerjaan (D+E) 719,692.00

A.5.1.1.10. Pemasangan 1 buah bak air fiberglass vol. m3


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.300 120,000.00 36,000.00
Tukang Batu L.02 Oh 0.450 150,000.00 67,500.00
Kepala Tukang L.03 Oh 0.045 175,000.00 7,875.00
Mandor L.04 Oh 0.015 200,000.00 3,000.00
JUMLAH TENAGA KERJA 114,375.00
B. BAHAN
buah bak air fiberglass Unit 1.000 868,000.00 868,000.00
Perlengkapan 12% % 0.120 868,000.00 104,160.00
JUMLAH HARGA BAHAN 972,160.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 1,086,535.00
E. Overhead & Profit 12% x D 130,384.20
F. Harga Satuan Pekerjaan (D+E) 1,216,919.00

A.5.1.1.14. Pemasangan 1 buah floor drain


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.010 120,000.00 1,200.00
Tukang Batu L.02 Oh 0.100 150,000.00 15,000.00
Kepala Tukang L.03 Oh 0.010 175,000.00 1,750.00
Mandor L.04 Oh 0.005 200,000.00 1,000.00
JUMLAH TENAGA KERJA 18,950.00
B. BAHAN
Floor drain Unit 1.000 41,000.00 41,000.00
JUMLAH HARGA BAHAN 41,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
Lembaran -42

D. JUMLAH (A+B+C) 59,950.00


E. Overhead & Profit 12% x D 7,194.00
F. Harga Satuan Pekerjaan (D+E) 67,144.00

(RSNIT 2002 6.32) Memasang 1m' Saluran Keliling Bangunan ukuran (25 x 40) cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
B. BAHAN
Galian tanah m³ 0.1650 106,400.00 17,556.00
Urugan Pasir tbl. 5 cm dibawah rabat saluran m³ 0.0138 480,704.00 6,633.72
Rabat Beton 1 : 3 : 5, tbl. 8 cm (K-100) m³ 0.0220 1,759,268.00 38,703.90
Pasangan bata semen ad. 1pc : 4ps m² 0.0990 438,748.00 43,436.05
Plesteran 1 pc : 2 Ps m² 1.5400 116,252.00 179,028.08
JUMLAH HARGA BAHAN 285,357.74
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 285,357.74
E. Overhead & Profit 12% x D 34,242.93
F. Harga Satuan Pekerjaan (D+E) 319,600.00
Lembaran -43

XI. HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.10. Pengecatan 1 M2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.020 120,000.00 2,400.00
Tukang Cat L.02 Oh 0.063 150,000.00 9,450.00
Kepala Tukang L.03 Oh 0.0063 175,000.00 1,102.50
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 13,552.50
B. BAHAN
Plamuur Kg 0.100 7,400.00 740.00
Cat dasar Kg 0.100 44,000.00 4,400.00
Cat penutup Kg 0.260 67,200.00 17,472.00
JUMLAH HARGA BAHAN 22,612.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 36,164.50
E. Overhead & Profit 12% x D 4,339.74
F. Harga Satuan Pekerjaan (D+E) 40,504.00

A.4.7.1.4. 1 M2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.070 120,000.00 8,400.00
Tukang Cat L.02 Oh 0.009 150,000.00 1,350.00
Kepala Tukang L.03 Oh 0.006 175,000.00 1,050.00
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 11,400.00
B. BAHAN
Cat menie Kg 0.200 68,000.00 13,600.00
Plamuur Kg 0.150 7,400.00 1,110.00
Cat penutup Kg 0.260 96,000.00 24,960.00
Kuas Bh 0.010 24,000.00 240.00
Pengencer Kg 0.030 74,500.00 2,235.00
Amplas Lbr 0.200 16,000.00 3,200.00
JUMLAH HARGA BAHAN 26,070.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 37,470.00
E. Overhead & Profit 12% x D 4,496.40
F. Harga Satuan Pekerjaan (D+E) 41,966.00

(SNI 2002) 1 M2 Mengecat plafon


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.0200 120,000.00 2,400.00
Tukang Cat L.02 Oh 0.0630 150,000.00 9,450.00
Kepala Tukang L.03 Oh 0.0063 175,000.00 1,102.50
Mandor L.04 Oh 0.0030 200,000.00 600.00
JUMLAH TENAGA KERJA 13,552.50
B. BAHAN
Cat dasar Kg 0.1000 44,000.00 4,400.00
Cat metrolite penutup 2 kali (Kualitas "A") Kg 0.2600 67,200.00 17,472.00
JUMLAH HARGA BAHAN 21,872.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 35,424.50
E. Overhead & Profit 12% x D 4,250.94
F. Harga Satuan Pekerjaan (D+E) 39,675.00

(SNI 2002) 1 M2 mengecat dengan Waterproofing


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 Oh 0.020 120,000.00 2,400.00
Tukang Cat L.02 Oh 0.063 150,000.00 9,450.00
Kepala Tukang L.03 Oh 0.006 175,000.00 1,102.50
Mandor L.04 Oh 0.003 200,000.00 600.00
JUMLAH TENAGA KERJA 13,552.50
B. BAHAN
Water Proofing 2 Komponen - Kg 1.300 83,000.00 107,900.00
- (Liquid+Bubuk). Ex. Lemkra
JUMLAH HARGA BAHAN 107,900.00
C. PERALATAN
JUMLAH HARGA ALAT -
Lembaran -44

D. JUMLAH (A+B+C) 121,452.50


E. Overhead & Profit 12% x D 14,574.30
F. Harga Satuan Pekerjaan (D+E) 136,026.00
Lembaran -45

XII. HARGA SATUAN PEKERJAAN LISTRIK


An. 1 Titik lampu/Instalasi lampu
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Tukang Listrik L.02 Oh 1.000 150,000.00 150,000.00
JUMLAH TENAGA KERJA 150,000.00
B. BAHAN
Kabel NYM 3 x 2,5 mm M' 8.000 23,000.00 184,000.00
Pipa PVC 3/4", 5/8" M' 8.000 6,000.00 48,000.00
Lasdop Bh 3.000 1,500.00 4,500.00
Benang Bh 1.000 9,000.00 9,000.00
T doss Bh 1.000 6,000.00 6,000.00
Isolasi Bh 2.000 16,000.00 32,000.00
Paku Kg 0.300 42,000.00 12,600.00
JUMLAH HARGA BAHAN 296,100.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 446,100.00
E. Overhead & Profit 12% x D 53,532.00
F. Harga Satuan Pekerjaan (D+E) 499,632.00

An. Memasang Stop Kontak


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Tukang Listrik L.02 Oh 0.300 150,000.00 45,000.00
JUMLAH TENAGA KERJA 45,000.00
B. BAHAN
Stop kontak Bh 1.000 28,000.00 28,000.00
JUMLAH HARGA BAHAN 28,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 73,000.00
E. Overhead & Profit 12% x D 8,760.00
F. Harga Satuan Pekerjaan (D+E) 81,760.00

An. Memasang Saklar Ganda


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Tukang Listrik L.02 Oh 0.300 150,000.00 45,000.00
JUMLAH TENAGA KERJA 45,000.00
B. BAHAN
Saklar ganda Bh 1.000 31,000.00 31,000.00
JUMLAH HARGA BAHAN 31,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 76,000.00
E. Overhead & Profit 12% x D 9,120.00
F. Harga Satuan Pekerjaan (D+E) 85,120.00

An. Memasang Saklar Tunggal


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Tukang Listrik L.02 Oh 0.300 150,000.00 45,000.00
JUMLAH TENAGA KERJA 45,000.00
B. BAHAN
Saklar tunggal Bh 1.000 31,000.00 31,000.00
JUMLAH HARGA BAHAN 31,000.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 76,000.00
E. Overhead & Profit 12% x D 9,120.00
F. Harga Satuan Pekerjaan (D+E) 85,120.00

An. Memasang lampu philips SL 18 watt feting tempel


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Tukang Listrik L.02 Oh 0.300 150,000.00 45,000.00
JUMLAH TENAGA KERJA 45,000.00
B. BAHAN
Lampu philips SL 18 watt feting tempel Bh 1.000 43,000.00 43,000.00
Fitting tempel plafond Bh 1.000 47,000.00 47,000.00
Bahan lainnya 2% dari harga material Bh 0.020 90,000.00 1,800.00
JUMLAH HARGA BAHAN 91,800.00
Lembaran -46

C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 136,800.00
E. Overhead & Profit 12% x D 16,416.00
F. Harga Satuan Pekerjaan (D+E) 153,216.00
Lembaran -47

An. Memasang lampu philips SL 11 watt feting tempel


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Tukang Listrik L.02 Oh 0.300 150,000.00 45,000.00
JUMLAH TENAGA KERJA 45,000.00
B. BAHAN
Lampu philips SL 11 watt feting tempel Bh 1.000 31,000.00 31,000.00
Fitting tempel plafond Bh 1.000 47,000.00 47,000.00
Bahan lainnya 2% dari harga material Bh 0.020 78,000.00 1,560.00
JUMLAH HARGA BAHAN 79,560.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. JUMLAH (A+B+C) 124,560.00
E. Overhead & Profit 12% x D 14,947.20
F. Harga Satuan Pekerjaan (D+E) 139,507.00

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
EGINEER ESTIMATE (EE)

PEKERJAAN :

PEMBANGUNAN RUANG KELAS BARU (RKB) BESERTA


PERABOTNYA

LOKASI :
SMA NEGERI 4 SERAM BAGIAN TIMUR
( Kabupaten Maluku Tengah )

SUMBER DANA :
Dana Alokasi Khusus (DAK)
Tahun Anggaran 2022

Konsultan Perencana

CV. PESONA CONSULTAN


Konsultaan - Manajemen - Supervisi - Disain
Jln. Hative Kecil RT.002/RW.04, Kec. Sirimau - Ambon
TOTAL REKAPITULASI BIAYA

INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU


KEGIATAN : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN
TIMUR BESERTA PERABOTNYA
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
NO. JENIS PEKERJAAN
(Rp)

I. PEMBANGUNAN ASRAMA SISWA BESERTA PERABOTNYA Rp 1,027,438,000.00


II. PEMBANGUNAN RUANG TATA USAHA BESERTA PERABOTNYA Rp 397,500,000.00
III. PEMBANGUNAN RUANG BIMBINGAN KONSELING BESERTA PERABOTNYA Rp 429,300,000.00
IV. PEMBANGUNAN RUANG OSIS BESERTA PERABOTNYA Rp 429,300,000.00
V. PEMBANGUNAN RUANG LABORATORIUM KOMPUTER BESERTA PERABOTNYA Rp 429,300,000.00
VI. PEMBANGUNAN RUANG UNIT KESEHATAN SEKOLAH BESERTA PERABOTNYA Rp 397,500,000.00
VII. PEMBANGUNAN TOILET/JAMBAN BESERTA PERABOTNYA Rp 537,788,000.00
VIII. REHABILITASI LABORATORIUM FISIKA BESERTA PERABOTNYA Rp 357,750,000.00
IX. REHABILITASI LABORATORIUM KIMIA BESERTA PERABOTNYA Rp 357,750,000.00
X. REHABILITASI RUANG KELAS BESERTA PERABOTNYA Rp 2,575,800,000.00
XI. PEMBANGUNAN RUMAH DINAS GURU BESERTA PERABOTNYA Rp 525,600,000.00
XII. REHABILITASI RUANG IBADAH BESERTA PERABOTNYA (SATU RUANG) Rp 129,850,000.00
XIII. REHABILITASI RUANG KEPALA SEKOLAH BESERTA PERABOTNYA (SATU RUANG) Rp 198,748,000.00

A. Jumlah Total Rp 7,793,624,000.00


C. Total (D + E) Rp 7,793,624,000.00
D. PEMBULATAN Rp 7,793,624,000.00

#NAME?

Keterangan : Harga Tersebut sudah termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU (RKB) BESERTA PERABOTNYA
VOLUME : 3 RKB
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PEMBANGUNAN 3 RKB Rp 1,136,658,493.19


I. PEKERJAAN TANAH Rp 87,011,472.30
II. PEKERJAAN PASANGAN BATU & BETON Rp 313,511,956.79
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 97,449,650.05
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 61,210,627.64
V. PEKERJAAN KERAMIK Rp 96,248,530.80
VI. PEKERJAAN KACA Rp 4,404,342.83
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 369,930,658.03
VIII. PEKERJAAN LISTRIK Rp 21,634,802.00
IX. PEKERJAAN PENGECATAN Rp 42,243,107.05
X. PEKERJAAN SANITAIR Rp 26,654,640.00
XI. PEKERJAAN TEMPAT CUCI TANGAN ( Vol = 03 Bh ) Rp 16,358,705.72

B. PEKERJAAN PENGADAAN PERABOT RKB - 3 RKB Rp 149,634,600.00

C. Jumlah Rp 1,286,293,093.19
D. PPn 11% Rp 141,492,240.25
E. Total (D + E) Rp 1,427,785,333.44
PEMBULATAN Rp 1,427,785,000.00
Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU (RKB) BESERTA PERABOTNYA
VOLUME : 3 RKB
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

B. PEMBANGUNAN RUANG KELAS BARU (RKB) BESERTA PERABOTNYA (3 RKB)


HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PEMBANGUNAN 3 RKB
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 61.71 106,400.00 6,565,944.00
2 Pek. Urugan tanah kembali M3 18.51 78,400.00 1,451,419.20
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 120.30 576,800.00 69,390,424.32
4 Pek. Urugan pasir dibawah pondasi, tbl = 5 cm M3 4.84 480,704.00 2,326,607.36
5 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 15.14 480,704.00 7,277,077.42
Jumlah - A.1 87,011,472.30
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Batu Kosong / Aanstamping M3 14.52 949,263.00 13,783,298.76
2 Pas. Pondasi Batu Kali ad. 1:5 M3 60.58 1,695,036.00 102,685,280.88
3 Pas. Dinding Batu Bata Semen ad. 1:4 M2 270.55 248,192.00 67,149,536.92
4 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm, (ruangan) (150 kg/m3) M3 2.45 6,793,558.00 16,630,629.98
- Beton Sloof 15/20 cm, (teras depan) (150 kg/m3) M3 1.30 6,793,558.00 8,804,451.17
- Beton Kolom 20/20 cm, (ruangan) (150 kg/m3) M3 3.12 7,255,250.00 22,636,380.00
- Beton Kolom 20/20 cm, (teras depan) (150 kg/m3) M3 1.56 7,255,250.00 11,318,190.00
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.40 6,362,498.00 2,565,359.19
- Beton Ring Balok 15/20 cm, (ruangan) (150 kg/m3) M3 2.45 7,271,512.00 17,800,661.38
- Beton Ring Balok 15/20 cm, (teras depan) (150 kg/m3) M3 1.30 7,271,512.00 9,423,879.55
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.52 7,271,512.00 3,769,551.82
- Ring Balok Kuda Kuda 12/15 cm, (gewel / ddg KK) (150 kg/m3) M3 0.42 7,271,512.00 3,062,760.85
- Kolom Praktis 12/12 cm, (gewel / ddg kuda kuda) (110 kg/m3) M3 0.12 6,362,498.00 732,959.77
5 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Bawah Lantai, tbl = 5 cm M3 12.85 1,937,927.00 24,902,749.54
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 4.26 1,937,927.00 8,246,266.97
Jumlah - A.2 313,511,956.79
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran Dinding ad. 1 : 4 M2 541.11 104,882.00 56,752,657.07
2 Pek. Plesteran Kolom ad. 1 : 4 M2 54.25 104,882.00 5,689,848.50
3 Pek. Acian Dinding dan Kolom M2 595.36 58,800.00 35,007,144.48
Jumlah - A.3 97,449,650.05
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 1.14 15,526,560.00 17,651,369.74
2 Kosen Manumata Atap/Gewel/Sopi sopi, kayu kls. I M3 0.07 15,526,560.00 1,062,327.24
3 Daun Pintu Panel, kayu kls. I M2 8.78 1,119,104.00 9,823,494.91
4 Daun Jendela / Kom Jendela, kayu kls.I M2 5.85 813,142.00 4,756,880.70
5 Jalusi Kusen Pintu & Jendela, kayu kls.II M2 15.66 872,592.00 13,660,602.28
6 Jalusi Manumata Atap/Gewel/Sopi sopi, kayu kls. II M2 2.31 872,592.00 2,018,130.78
7 Engsel Pintu 4" Bh 18.00 80,735.00 1,453,230.00
8 Engsel Jendela Bh 60.00 58,856.00 3,531,360.00
9 Grendel Jendela Bh 30.00 46,508.00 1,395,240.00
10 Kunci Tanam Bh 3.00 395,304.00 1,185,912.00
11 Kait Angin Bh 60.00 77,868.00 4,672,080.00
Jumlah - A.4 61,210,627.64
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 207.09 365,750.00 75,743,167.50
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 54.30 377,631.00 20,505,363.30
Jumlah - A.5 96,248,530.80
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 9.90 247,783.00 2,453,051.70
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 7.88 247,783.00 1,951,291.13
Jumlah - A.6 4,404,342.83
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 408.10 447,757.00 182,729,631.70
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 408.10 139,753.00 57,033,199.30
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 11.70 278,913.00 3,263,282.10
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 85.60 101,024.00 8,647,654.40
5 Pek. Rangka Plafond Hollow 2/4 & 4/4 M2 317.59 222,101.00 70,536,501.34
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 317.59 117,009.00 37,160,595.79
7 Pek. Lis Plafond Kayu Profil, lbr = 8 cm (ruang & teras muka) M' 157.40 44,878.00 7,063,797.20
8 Pek. Lis Plafond Kayu Profil, lbr = 8 cm (tirisan luar) M' 77.90 44,878.00 3,495,996.20
Jumlah - A.7 369,930,658.03
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 31.00 499,632.00 15,488,592.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 18.00 153,216.00 2,757,888.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 6.00 139,507.00 837,042.00
4 Pas. Stop kontak broco BH 6.00 81,760.00 490,560.00
5 Pas. Saklar ganda broco BH 3.00 85,120.00 255,360.00
6 Pas. Saklar tunggal broco BH 3.00 85,120.00 255,360.00
7 Pas. MCB 6 A (lengkap) BH 6.00 150,000.00 900,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 1.00 650,000.00 650,000.00
Jumlah - A.8 21,634,802.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 595.36 40,504.00 24,114,445.24
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 317.59 39,675.00 12,600,284.06
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 18.82 41,966.00 789,967.98
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 60.26 41,966.00 2,529,018.04
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 26.97 41,966.00 1,131,704.84
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 25.68 41,966.00 1,077,686.88
Jumlah - A.9 42,243,107.05
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 83.40 319,600.00 26,654,640.00
Jumlah - A.10 26,654,640.00
XI. PEKERJAAN TEMPAT CUCI TANGAN ( Vol = 03 Bh )
1 Pek. Dinding Beton ad. 1Pc : 2Ps : 3Kr
- Bekisting M2 5.04 1,027,740.00 5,179,809.60
- Beton tidak bertulang ad. 1Pc : 2Ps : 3Kr M3 0.27 1,759,268.00 475,002.36
2 Pek. Plesteran dinding ad. 1 : 4 M2 5.22 104,882.00 547,484.04
3 Pek. Acian dinding M2 5.22 58,800.00 306,936.00
4 Pek. Pengecatan waterproofing M2 5.22 136,026.00 710,055.72
5 Pas. Wastafel Keramik Bh 3.00 962,808.00 2,888,424.00
6 Pas. Kran air 1/2" + Asesories Bh 3.00 141,008.00 423,024.00
7 Pas. Pipa PVC tipe AW 1/2" + Asesories M' 55.00 63,716.00 3,504,380.00
8 Pas. Pipa PVC tipe AW 2" + Asesories M' 15.00 154,906.00 2,323,590.00
Jumlah - A.11 16,358,705.72
B. PEKERJAAN PENGADAAN PERABOT RKB - 3 RKB
1 Meja + Kursi Siswa SMA (tunggal) (M-02/K02) Unit 108.00 1,029,400.00 111,175,200.00
2 Meja Guru (M-01) (M-01) Bh 3.00 3,636,400.00 10,909,200.00
3 Kursi Guru (K-01) (K-01) Bh 3.00 852,600.00 2,557,800.00
4 Papan Tulis Dorong (White Board P-01) (P-01) Bh 6.00 1,870,700.00 11,224,200.00
5 Lemari Penyimpanan (L-01) (L-01) Bh 3.00 4,243,300.00 12,729,900.00
6 Tempat Sampah Bh 3.00 346,100.00 1,038,300.00
JUMLAH - B 149,634,600.00

REKAPITULASI BIAYA
A. PEKERJAAN PEMBANGUNAN 3 RKB Rp. 1,136,658,493.19
I. PEKERJAAN TANAH Rp. 87,011,472.30
II. PEKERJAAN PASANGAN BATU & BETON Rp. 313,511,956.79
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 97,449,650.05
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 61,210,627.64
V. PEKERJAAN KERAMIK Rp. 96,248,530.80
VI. PEKERJAAN KACA Rp. 4,404,342.83
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 369,930,658.03
VIII. PEKERJAAN LISTRIK Rp. 21,634,802.00
IX. PEKERJAAN PENGECATAN Rp. 42,243,107.05
X. PEKERJAAN SANITAIR Rp. 26,654,640.00
XI. PEKERJAAN TEMPAT CUCI TANGAN ( Vol = 03 Bh ) Rp. 16,358,705.72
B. PEKERJAAN PENGADAAN PERABOT RKB - 3 RKB Rp. 149,634,600.00
JUMLAH Rp. 1,286,293,093.19
PEMBULATAN Rp 1,286,293,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM FISIKA BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp 732,576,681.28


I. PEKERJAAN TANAH Rp 59,597,047.27
II. PEKERJAAN PASANGAN BATU & BETON Rp 205,485,414.40
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 62,570,652.67
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 41,818,009.89
V. PEKERJAAN KERAMIK Rp 53,270,943.15
VI. PEKERJAAN KACA Rp 2,049,165.41
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 218,762,384.48
VIII. PEKERJAAN LISTRIK Rp 15,475,625.00
IX. PEKERJAAN PENGECATAN Rp 26,662,623.78
X. PEKERJAAN SANITAIR Rp 27,356,400.00
XI. PEKERJAAN MEJA BETON Rp 19,528,415.24

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 27,689,700.00

C. Jumlah Rp 760,266,381.28
D. PPn 11% Rp 83,629,301.94
E. Total (D + E) Rp 843,895,683.22
PEMBULATAN Rp 843,895,000.00
Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM FISIKA BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

C. PEMBANGUNAN RUANG LABORATORIUM FISIKA BESERTA PERABOTNYA (1 RUANG)


HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PEMBANGUNAN 1 RUANG
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 38.76 106,400.00 4,124,064.00
2 Pek. Urugan tanah kembali M3 11.63 78,400.00 911,635.20
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 84.46 576,800.00 48,713,644.00
4 Pek. Urugan pasir dibawah pondasi, tbl = 5 cm M3 3.04 480,704.00 1,461,340.16
5 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 9.12 480,704.00 4,386,363.91
Jumlah - A.1 59,597,047.27
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Batu Kosong / Aanstamping M3 9.12 949,263.00 8,657,278.56
2 Pas. Pondasi Batu kali ad. 1:5 M3 42.66 1,695,036.00 72,317,015.90
3 Pas. Dinding Batu Bata Semen ad. 1:4 M2 184.69 248,192.00 45,839,771.80
4 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm, (ruangan) (150 kg/m3) M3 1.63 6,793,558.00 11,046,325.31
- Beton Sloof 15/20 cm, (teras depan) (150 kg/m3) M3 0.64 6,793,558.00 4,320,702.89
- Beton Kolom 20/20 cm, (ruangan) (150 kg/m3) M3 1.87 7,255,250.00 13,581,828.00
- Beton Kolom 20/20 cm, (teras depan) (150 kg/m3) M3 0.94 7,255,250.00 6,790,914.00
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.30 6,362,498.00 1,924,019.40
- Beton Ring Balok 15/20 cm, (ruangan) (150 kg/m3) M3 1.63 7,271,512.00 11,823,478.51
- Beton Ring Balok 15/20 cm, (teras depan) (150 kg/m3) M3 0.64 7,271,512.00 4,624,681.63
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.32 7,271,512.00 2,303,615.00
- Ring Balok Kuda Kuda 12/15 cm, (gewel / ddg KK) (150 kg/m3) M3 0.42 7,271,512.00 3,062,760.85
- Kolom Praktis 12/12 cm, (gewel / ddg kuda kuda) (110 kg/m3) M3 0.12 6,362,498.00 732,959.77
5 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Bawah Lantai, tbl = 5 cm M3 7.09 1,937,927.00 13,733,458.82
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.44 1,937,927.00 4,726,603.95
Jumlah - A.2 205,485,414.40
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 369.39 104,882.00 38,742,320.03
2 Pek. Plesteran kolom ad. 1 : 4 M2 12.88 104,882.00 1,350,880.16
3 Pek. Acian dinding dan kolom M2 382.27 58,800.00 22,477,452.48
Jumlah - A.3 62,570,652.67
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.71 15,526,560.00 11,067,331.97
2 Kosen Manumata Atap/Gewel/Sopi sopi, kayu kls. I M3 0.07 15,526,560.00 1,062,327.24
3 Daun Pintu Panel, kayu kls. I M2 7.94 1,119,104.00 8,887,923.97
4 Daun Jendela / Kom Jendela, kayu kls.I M2 3.00 813,142.00 2,439,426.00
5 Jalusi Kusen Pintu, Jendela & Ventilasi, kayu kls.II M2 9.66 872,592.00 8,431,332.94
6 Jalusi Manumata Atap/Gewel/Sopi sopi, kayu kls. II M2 2.31 872,592.00 2,018,130.78
7 Engsel pintu 4" Bh 15.00 80,735.00 1,211,025.00
8 Engsel jendela Bh 32.00 58,856.00 1,883,392.00
9 Grendel jendela Bh 16.00 46,508.00 744,128.00
10 Kunci tanam Bh 4.00 395,304.00 1,581,216.00
11 Kait Angin Bh 32.00 77,868.00 2,491,776.00
Jumlah - A.4 41,818,009.89
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 114.26 365,750.00 41,790,960.75
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 30.40 377,631.00 11,479,982.40
Jumlah - A.5 53,270,943.15
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 4.84 247,783.00 1,199,269.72
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 3.43 247,783.00 849,895.69
Jumlah - A.6 2,049,165.41
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 240.10 447,757.00 107,506,455.70
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 240.10 139,753.00 33,554,695.30
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 6.90 278,913.00 1,924,499.70
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 62.42 101,024.00 6,305,918.08
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 184.56 222,101.00 40,990,627.41
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 184.56 117,009.00 21,595,005.53
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 99.52 44,878.00 4,466,258.56
8 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 53.90 44,878.00 2,418,924.20
Jumlah - A.7 218,762,384.48
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 23.00 499,632.00 11,491,536.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 8.00 153,216.00 1,225,728.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 11.00 81,760.00 899,360.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 2.00 85,120.00 170,240.00
7 Pas. MCB 6 A (lengkap) BH 3.00 150,000.00 450,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 1.00 650,000.00 650,000.00
Jumlah - A.8 15,475,625.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 382.27 40,504.00 15,483,447.88
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 184.56 39,675.00 7,322,358.49
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 12.27 41,966.00 515,073.90
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 39.06 41,966.00 1,639,233.93
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 21.84 41,966.00 916,654.27
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 18.73 41,966.00 785,855.32
Jumlah - A.9 26,662,623.78
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 59.00 319,600.00 18,856,400.00
2 Pek. Tanki Limbah & Resapan uk. (120cm x 280cm), H = (140/100) cm Unit 1.00 8,500,000.00 8,500,000.00
Jumlah - A.10 27,356,400.00
XI. PEKERJAAN MEJA BETON
1 Pas. Batu Bata Semen ad. 1:4 M2 4.20 248,192.00 1,042,406.40
2 Pekerjaan Beton Bertulang (K-175) :
- Pelat Lantai Meja Beton, tbl = 8 cm (110 kg/m3) M3 0.92 6,631,298.00 6,111,404.24
3 Pek. Plesteran dinding ad. 1 : 4 M2 3.15 104,882.00 330,378.30
4 Pas. Keramik 40 x 40 cm Meja Beton (polos) M2 16.21 365,750.00 5,928,807.50
5 Pas. Bak cuci tangan lapis keramik (uk. 40cm x 40cm x 20cm) Bh 3.00 215,907.60 647,722.80
6 Pas. Keran Air Bh 3.00 141,008.00 423,024.00
7 Pas. Pipa PVC tipe AW 1/2" M' 50.00 63,716.00 3,185,800.00
8 Pas. Pipa PVC tipe AW 2" M' 12.00 154,906.00 1,858,872.00
Jumlah - A.11 19,528,415.24
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Laboratorium (M-03) (M-03) Bh 2.00 2,808,800.00 5,617,600.00
2 Kursi Laboratorium (K-03) (K-03) Bh 12.00 687,000.00 8,244,000.00
3 Meja Guru (M-01) (M-01) Bh 1.00 3,636,400.00 3,636,400.00
4 Kursi Guru (K-01) (K-01) Bh 1.00 852,600.00 852,600.00
5 Meja Demonstrasi (M-10) (M-10) Bh 1.00 2,532,900.00 2,532,900.00
6 Papan Tulis Dorong (White Board P-01) (P-01) Bh 1.00 1,870,700.00 1,870,700.00
7 Lemari Penyimpanan Alat (L-01) (L-01) Bh 1.00 4,243,300.00 4,243,300.00
8 Tempat Sampah Bh 2.00 346,100.00 692,200.00
JUMLAH - B 27,689,700.00

REKAPITULASI BIAYA
A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp. 732,576,681.28
I. PEKERJAAN TANAH Rp. 59,597,047.27
II. PEKERJAAN PASANGAN BATU & BETON Rp. 205,485,414.40
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 62,570,652.67
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 41,818,009.89
V. PEKERJAAN KERAMIK Rp. 53,270,943.15
VI. PEKERJAAN KACA Rp. 2,049,165.41
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 218,762,384.48
VIII. PEKERJAAN LISTRIK Rp. 15,475,625.00
IX. PEKERJAAN PENGECATAN Rp. 26,662,623.78
X. PEKERJAAN SANITAIR Rp. 27,356,400.00
XI. PEKERJAAN MEJA BETON Rp. 19,528,415.24
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 27,689,700.00
JUMLAH Rp. 760,266,381.28
PEMBULATAN Rp 760,266,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM BILOGI BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp 722,591,314.64


I. PEKERJAAN TANAH Rp 59,641,170.62
II. PEKERJAAN PASANGAN BATU & BETON Rp 199,960,820.45
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 59,924,733.14
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 38,761,808.79
V. PEKERJAAN KERAMIK Rp 53,416,877.40
VI. PEKERJAAN KACA Rp 2,245,533.44
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 218,654,450.61
VIII. PEKERJAAN LISTRIK Rp 14,809,113.00
IX. PEKERJAAN PENGECATAN Rp 25,792,575.00
X. PEKERJAAN SANITAIR Rp 27,356,400.00
XI. PEKERJAAN MEJA BETON Rp 22,027,832.19

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 27,689,700.00

C. Jumlah Rp 750,281,014.64
D. PPn 11% Rp 82,530,911.61
E. Total (D + E) Rp 832,811,926.25
PEMBULATAN Rp 832,811,000.00
Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM BILOGI BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

D. PEMBANGUNAN RUANG LABORATORIUM BILOGI BESERTA PERABOTNYA (1 RUANG)


HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PEMBANGUNAN 1 RUANG
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 37.23 106,400.00 3,961,272.00
2 Pek. Urugan tanah kembali M3 11.17 78,400.00 875,649.60
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 84.96 576,800.00 49,007,379.40
4 Pek. Urugan pasir dibawah pondasi, tbl = 5 cm M3 2.92 480,704.00 1,403,655.68
5 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 9.14 480,704.00 4,393,213.94
Jumlah - A.1 59,641,170.62
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Batu Kosong / Aanstamping M3 8.76 949,263.00 8,315,543.88
2 Pas. Pondasi Batu kali ad. 1:5 M3 41.46 1,695,036.00 70,282,972.70
3 Pas. Dinding Batu Bata Semen ad. 1:4 M2 176.61 248,192.00 43,833,759.96
4 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm, (ruangan) (150 kg/m3) M3 1.54 6,793,558.00 10,475,666.44
- Beton Sloof 15/20 cm, (teras depan) (150 kg/m3) M3 0.64 6,793,558.00 4,320,702.89
- Beton Kolom 20/20 cm, (ruangan) (150 kg/m3) M3 1.87 7,255,250.00 13,581,828.00
- Beton Kolom 20/20 cm, (teras depan) (150 kg/m3) M3 0.94 7,255,250.00 6,790,914.00
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.30 6,362,498.00 1,924,019.40
- Beton Ring Balok 15/20 cm, (ruangan) (150 kg/m3) M3 1.54 7,271,512.00 11,212,671.50
- Beton Ring Balok 15/20 cm, (teras depan) (150 kg/m3) M3 0.64 7,271,512.00 4,624,681.63
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.32 7,271,512.00 2,303,615.00
- Ring Balok Kuda Kuda 12/15 cm, (gewel / ddg KK) (150 kg/m3) M3 0.42 7,271,512.00 3,062,760.85
- Kolom Praktis 12/12 cm, (gewel / ddg kuda kuda) (110 kg/m3) M3 0.12 6,362,498.00 732,959.77
5 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Bawah Lantai, tbl = 5 cm M3 7.11 1,937,927.00 13,772,120.47
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.44 1,937,927.00 4,726,603.95
Jumlah - A.2 199,960,820.45
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 353.22 104,882.00 37,046,902.50
2 Pek. Plesteran kolom ad. 1 : 4 M2 12.88 104,882.00 1,350,880.16
3 Pek. Acian dinding dan kolom M2 366.10 58,800.00 21,526,950.48
Jumlah - A.3 59,924,733.14
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.68 15,526,560.00 10,623,272.35
2 Kosen Manumata Atap/Gewel/Sopi sopi, kayu kls. I M3 0.07 15,526,560.00 1,062,327.24
3 Daun Pintu Panel, kayu kls. I M2 6.27 1,119,104.00 7,016,782.08
4 Daun Jendela / Kom Jendela, kayu kls.I M2 3.19 813,142.00 2,591,890.13
5 Jalusi Kusen Pintu & Jendela, kayu kls.II M2 9.00 872,592.00 7,855,422.22
6 Jalusi Manumata Atap/Gewel/Sopi sopi, kayu kls. II M2 2.31 872,592.00 2,018,130.78
7 Engsel pintu 4" Bh 12.00 80,735.00 968,820.00
8 Engsel jendela Bh 34.00 58,856.00 2,001,104.00
9 Grendel jendela Bh 17.00 46,508.00 790,636.00
10 Kunci tanam Bh 3.00 395,304.00 1,185,912.00
11 Kait Angin Bh 34.00 77,868.00 2,647,512.00
Jumlah - A.4 38,761,808.79
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 114.66 365,750.00 41,936,895.00
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 30.40 377,631.00 11,479,982.40
Jumlah - A.5 53,416,877.40
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 5.14 247,783.00 1,274,224.08
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 3.92 247,783.00 971,309.36
Jumlah - A.6 2,245,533.44
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 240.10 447,757.00 107,506,455.70
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 240.10 139,753.00 33,554,695.30
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 6.90 278,913.00 1,924,499.70
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 62.42 101,024.00 6,305,918.08
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 184.96 222,101.00 41,079,245.71
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 184.96 117,009.00 21,641,692.12
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 94.10 44,878.00 4,223,019.80
8 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 53.90 44,878.00 2,418,924.20
Jumlah - A.7 218,654,450.61
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 22.00 499,632.00 10,991,904.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 8.00 153,216.00 1,225,728.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 10.00 81,760.00 817,600.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 1.00 85,120.00 85,120.00
7 Pas. MCB 6 A (lengkap) BH 3.00 150,000.00 450,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 1.00 650,000.00 650,000.00
Jumlah - A.8 14,809,113.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 366.10 40,504.00 14,828,700.72
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 184.96 39,675.00 7,338,188.81
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 11.84 41,966.00 496,877.44
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 37.63 41,966.00 1,579,222.55
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 18.20 41,966.00 763,730.17
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 18.73 41,966.00 785,855.32
Jumlah - A.9 25,792,575.00
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 59.00 319,600.00 18,856,400.00
2 Pek. Tanki Limbah & Resapan uk. (120cm x 280cm), H = (140/100) cm Unit 1.00 8,500,000.00 8,500,000.00
Jumlah - A.10 27,356,400.00
XI. PEKERJAAN MEJA BETON
1 Pas. Batu Bata Semen ad. 1:4 M2 4.20 248,192.00 1,042,406.40
2 Pekerjaan Beton Bertulang (K-175) :
- Pelat Lantai Meja Beton, tbl = 8 cm (110 kg/m3) M3 0.88 6,631,298.00 5,856,762.39
3 Pek. Plesteran dinding ad. 1 : 4 M2 3.15 104,882.00 330,378.30
4 Pas. Keramik 40 x 40 cm Meja Beton (polos) M2 15.73 365,750.00 5,753,247.50
5 Pas. Bak cuci tangan lapis keramik (uk. 40cm x 40cm x 20cm) Bh 6.00 215,907.60 1,295,445.60
6 Pas. Keran Air Bh 6.00 141,008.00 846,048.00
7 Pas. Pipa PVC tipe AW 1/2" M' 50.00 63,716.00 3,185,800.00
8 Pas. Pipa PVC tipe AW 2" M' 24.00 154,906.00 3,717,744.00
Jumlah - A.11 22,027,832.19
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Laboratorium (M-03) (M-03) Bh 2.00 2,808,800.00 5,617,600.00
2 Kursi Laboratorium (K-03) (K-03) Bh 12.00 687,000.00 8,244,000.00
3 Meja Guru (M-01) (M-01) Bh 1.00 3,636,400.00 3,636,400.00
4 Kursi Guru (K-01) (K-01) Bh 1.00 852,600.00 852,600.00
5 Meja Demonstrasi (M-10) (M-10) Bh 1.00 2,532,900.00 2,532,900.00
6 Papan Tulis Dorong (White Board P-01) (P-01) Bh 1.00 1,870,700.00 1,870,700.00
7 Lemari Penyimpanan Alat (L-01) (L-01) Bh 1.00 4,243,300.00 4,243,300.00
8 Tempat Sampah Bh 2.00 346,100.00 692,200.00
JUMLAH - B 27,689,700.00

REKAPITULASI BIAYA
A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp. 722,591,314.64
I. PEKERJAAN TANAH Rp. 59,641,170.62
II. PEKERJAAN PASANGAN BATU & BETON Rp. 199,960,820.45
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 59,924,733.14
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 38,761,808.79
V. PEKERJAAN KERAMIK Rp. 53,416,877.40
VI. PEKERJAAN KACA Rp. 2,245,533.44
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 218,654,450.61
VIII. PEKERJAAN LISTRIK Rp. 14,809,113.00
IX. PEKERJAAN PENGECATAN Rp. 25,792,575.00
X. PEKERJAAN SANITAIR Rp. 27,356,400.00
XI. PEKERJAAN MEJA BETON Rp. 22,027,832.19
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 27,689,700.00
JUMLAH Rp. 750,281,014.64
PEMBULATAN Rp 750,281,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KIMIA BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp 721,391,569.91


I. PEKERJAAN TANAH Rp 59,641,170.62
II. PEKERJAAN PASANGAN BATU & BETON Rp 200,817,082.85
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 61,054,138.94
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 35,966,929.84
V. PEKERJAAN KERAMIK Rp 53,416,877.40
VI. PEKERJAAN KACA Rp 1,702,888.67
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 218,654,450.61
VIII. PEKERJAAN LISTRIK Rp 14,809,113.00
IX. PEKERJAAN PENGECATAN Rp 25,944,685.79
X. PEKERJAAN SANITAIR Rp 27,356,400.00
XI. PEKERJAAN MEJA BETON Rp 22,027,832.19

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 27,689,700.00

C. Jumlah Rp 749,081,269.91
D. PPn 11% Rp 82,398,939.69
E. Total (D + E) Rp 831,480,209.60
PEMBULATAN Rp 831,480,000.00
Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KIMIA BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

E. PEMBANGUNAN RUANG LABORATORIUM KIMIA BESERTA PERABOTNYA (1 RUANG)


HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PEMBANGUNAN 1 RUANG
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 37.23 106,400.00 3,961,272.00
2 Pek. Urugan tanah kembali M3 11.17 78,400.00 875,649.60
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 84.96 576,800.00 49,007,379.40
4 Pek. Urugan pasir dibawah pondasi, tbl = 5 cm M3 2.92 480,704.00 1,403,655.68
5 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 9.14 480,704.00 4,393,213.94
Jumlah - A.1 59,641,170.62
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Batu Kosong / Aanstamping M3 8.76 949,263.00 8,315,543.88
2 Pas. Pondasi Batu kali ad. 1:5 M3 41.46 1,695,036.00 70,282,972.70
3 Pas. Dinding Batu Bata Semen ad. 1:4 M2 180.06 248,192.00 44,690,022.36
4 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm, (ruangan) (150 kg/m3) M3 1.54 6,793,558.00 10,475,666.44
- Beton Sloof 15/20 cm, (teras depan) (150 kg/m3) M3 0.64 6,793,558.00 4,320,702.89
- Beton Kolom 20/20 cm, (ruangan) (150 kg/m3) M3 1.87 7,255,250.00 13,581,828.00
- Beton Kolom 20/20 cm, (teras depan) (150 kg/m3) M3 0.94 7,255,250.00 6,790,914.00
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.30 6,362,498.00 1,924,019.40
- Beton Ring Balok 15/20 cm, (ruangan) (150 kg/m3) M3 1.54 7,271,512.00 11,212,671.50
- Beton Ring Balok 15/20 cm, (teras depan) (150 kg/m3) M3 0.64 7,271,512.00 4,624,681.63
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.32 7,271,512.00 2,303,615.00
- Ring Balok Kuda Kuda 12/15 cm, (gewel / ddg KK) (150 kg/m3) M3 0.42 7,271,512.00 3,062,760.85
- Kolom Praktis 12/12 cm, (gewel / ddg kuda kuda) (110 kg/m3) M3 0.12 6,362,498.00 732,959.77
5 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Bawah Lantai, tbl = 5 cm M3 7.11 1,937,927.00 13,772,120.47
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.44 1,937,927.00 4,726,603.95
Jumlah - A.2 200,817,082.85
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 360.12 104,882.00 37,770,588.30
2 Pek. Plesteran kolom ad. 1 : 4 M2 12.88 104,882.00 1,350,880.16
3 Pek. Acian dinding dan kolom M2 373.00 58,800.00 21,932,670.48
Jumlah - A.3 61,054,138.94
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.63 15,526,560.00 9,718,073.90
2 Kosen Manumata Atap/Gewel/Sopi sopi, kayu kls. I M3 0.07 15,526,560.00 1,062,327.24
3 Daun Pintu Panel, kayu kls. I M2 6.27 1,119,104.00 7,016,782.08
4 Daun Jendela / Kom Jendela, kayu kls.I M2 2.44 813,142.00 1,982,033.63
5 Jalusi Kusen Pintu, Jendela & Ventilasi, kayu kls.II M2 9.00 872,592.00 7,855,422.22
6 Jalusi Manumata Atap/Gewel/Sopi sopi, kayu kls. II M2 2.31 872,592.00 2,018,130.78
7 Engsel pintu 4" Bh 12.00 80,735.00 968,820.00
8 Engsel jendela Bh 26.00 58,856.00 1,530,256.00
9 Grendel jendela Bh 13.00 46,508.00 604,604.00
10 Kunci tanam Bh 3.00 395,304.00 1,185,912.00
11 Kait Angin Bh 26.00 77,868.00 2,024,568.00
Jumlah - A.4 35,966,929.84
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 114.66 365,750.00 41,936,895.00
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 30.40 377,631.00 11,479,982.40
Jumlah - A.5 53,416,877.40
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 3.93 247,783.00 974,406.65
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 2.94 247,783.00 728,482.02
Jumlah - A.6 1,702,888.67
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 240.10 447,757.00 107,506,455.70
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 240.10 139,753.00 33,554,695.30
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 6.90 278,913.00 1,924,499.70
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 62.42 101,024.00 6,305,918.08
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 184.96 222,101.00 41,079,245.71
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 184.96 117,009.00 21,641,692.12
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 94.10 44,878.00 4,223,019.80
8 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 53.90 44,878.00 2,418,924.20
Jumlah - A.7 218,654,450.61
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 22.00 499,632.00 10,991,904.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 8.00 153,216.00 1,225,728.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 10.00 81,760.00 817,600.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 1.00 85,120.00 85,120.00
7 Pas. MCB 6 A (lengkap) BH 3.00 150,000.00 450,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 1.00 650,000.00 650,000.00
Jumlah - A.8 14,809,113.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 373.00 40,504.00 15,108,178.32
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 184.96 39,675.00 7,338,188.81
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 11.84 41,966.00 496,877.44
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 34.72 41,966.00 1,456,891.66
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 18.08 41,966.00 758,694.25
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 18.73 41,966.00 785,855.32
Jumlah - A.9 25,944,685.79
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 59.00 319,600.00 18,856,400.00
2 Pek. Tanki Limbah & Resapan uk. (120cm x 280cm), H = (140/100) cm Unit 1.00 8,500,000.00 8,500,000.00
Jumlah - A.10 27,356,400.00
XI. PEKERJAAN MEJA BETON
1 Pas. Batu Bata Semen ad. 1:4 M2 4.20 248,192.00 1,042,406.40
2 Pekerjaan Beton Bertulang (K-175) :
- Pelat Lantai Meja Beton, tbl = 8 cm (110 kg/m3) M3 0.88 6,631,298.00 5,856,762.39
3 Pek. Plesteran dinding ad. 1 : 4 M2 3.15 104,882.00 330,378.30
4 Pas. Keramik 40 x 40 cm Meja Beton (polos) M2 15.73 365,750.00 5,753,247.50
5 Pas. Bak cuci tangan lapis keramik (uk. 40cm x 40cm x 20cm) Bh 6.00 215,907.60 1,295,445.60
6 Pas. Keran Air Bh 6.00 141,008.00 846,048.00
7 Pas. Pipa PVC tipe AW 1/2" M' 50.00 63,716.00 3,185,800.00
8 Pas. Pipa PVC tipe AW 2" M' 24.00 154,906.00 3,717,744.00
Jumlah - A.11 22,027,832.19
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Laboratorium (M-03) (M-03) Bh 2.00 2,808,800.00 5,617,600.00
2 Kursi Laboratorium (K-03) (K-03) Bh 12.00 687,000.00 8,244,000.00
3 Meja Guru (M-01) (M-01) Bh 1.00 3,636,400.00 3,636,400.00
4 Kursi Guru (K-01) (K-01) Bh 1.00 852,600.00 852,600.00
5 Meja Demonstrasi (M-10) (M-10) Bh 1.00 2,532,900.00 2,532,900.00
6 Papan Tulis Dorong (White Board P-01) (P-01) Bh 1.00 1,870,700.00 1,870,700.00
7 Lemari Penyimpanan Alat (L-01) (L-01) Bh 1.00 4,243,300.00 4,243,300.00
8 Tempat Sampah Bh 2.00 346,100.00 692,200.00
JUMLAH - B 27,689,700.00

REKAPITULASI BIAYA
A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp. 721,391,569.91
I. PEKERJAAN TANAH Rp. 59,641,170.62
II. PEKERJAAN PASANGAN BATU & BETON Rp. 200,817,082.85
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 61,054,138.94
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 35,966,929.84
V. PEKERJAAN KERAMIK Rp. 53,416,877.40
VI. PEKERJAAN KACA Rp. 1,702,888.67
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 218,654,450.61
VIII. PEKERJAAN LISTRIK Rp. 14,809,113.00
IX. PEKERJAAN PENGECATAN Rp. 25,944,685.79
X. PEKERJAAN SANITAIR Rp. 27,356,400.00
XI. PEKERJAAN MEJA BETON Rp. 22,027,832.19
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 27,689,700.00
JUMLAH Rp. 749,081,269.91
PEMBULATAN Rp 749,081,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
REKAPITULASI BIAYA

INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KOMPUTER BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp 468,059,325.67


I. PEKERJAAN TANAH Rp 37,439,964.30
II. PEKERJAAN PASANGAN BATU & BETON Rp 135,539,731.85
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 41,969,636.15
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 26,613,651.80
V. PEKERJAAN KERAMIK Rp 32,196,132.90
VI. PEKERJAAN KACA Rp 1,356,611.93
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 142,747,150.03
VIII. PEKERJAAN LISTRIK Rp 11,466,374.00
IX. PEKERJAAN PENGECATAN Rp 17,667,523.48
X. PEKERJAAN SANITAIR Rp 15,021,200.00
XI. PEKERJAAN TEMPAT CUCI TANGAN ( Vol = 01 Bh ) Rp 6,041,349.24
XII. PEKERJAAN RAMP (Akses Disabilitas/Tuna Daksa) Rp -

B. PEKERJAAN PENGADAAN PERABOT LAB KOMPUTER Rp 30,911,000.00

C. Jumlah Rp 498,970,325.67
D. PPn 11% Rp 54,886,735.82
E. Total (D + E) Rp 553,857,061.49
PEMBULATAN Rp 553,857,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KOMPUTER BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

E. PEMBANGUNAN RUANG LABORATORIUM KOMPUTER BESERTA PERABOTNYA (1 RUANG)


HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PEMBANGUNAN 1 RUANG
I. PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi M3 23.97 106,400.00 2,550,408.00
2 Pek. Urugan tanah kembali M3 7.19 78,400.00 563,774.40
3 Pek. Timbunan tanah bawah lantai M3 53.49 576,800.00 30,853,176.20
4 Pek. Urugan pasir dibawah pondasi, tbl = 5 cm M3 2.12 480,704.00 1,016,688.96
5 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 5.11 480,704.00 2,455,916.74
Jumlah - A.1 37,439,964.30
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Batu Kosong / Aanstamping M3 5.64 949,263.00 5,353,843.32
2 Pas. Pondasi Batu kali ad. 1:5 M3 28.54 1,695,036.00 48,383,107.58
3 Pas. Dinding Batu Bata Semen ad. 1:4 M2 123.72 248,192.00 30,707,505.56
4 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm, (ruangan) (150 kg/m3) M3 0.97 6,793,558.00 6,603,338.38
- Beton Sloof 15/20 cm, (teras depan) (150 kg/m3) M3 0.36 6,793,558.00 2,445,680.88
- Beton Kolom 20/20 cm, (ruangan) (150 kg/m3) M3 1.25 7,255,250.00 9,054,552.00
- Beton Kolom 20/20 cm, (teras depan) (150 kg/m3) M3 0.62 7,255,250.00 4,527,276.00
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.20 6,362,498.00 1,282,679.60
- Beton Ring Balok 15/20 cm, (ruangan) (150 kg/m3) M3 0.97 7,271,512.00 7,067,909.66
- Beton Ring Balok 15/20 cm, (teras depan) (150 kg/m3) M3 0.36 7,271,512.00 2,617,744.32
- Ring Balok Latei 12/15 cm, (teras depan) (110 kg/m3) M3 0.22 7,271,512.00 1,570,646.59
- Ring Balok Kuda Kuda 12/15 cm, (gewel / ddg KK) (150 kg/m3) M3 0.42 7,271,512.00 3,062,760.85
- Kolom Praktis 12/12 cm, (gewel / ddg kuda kuda) (110 kg/m3) M3 0.12 6,362,498.00 732,959.77
5 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Bawah Lantai, tbl = 5 cm M3 4.27 1,937,927.00 8,275,190.53
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 1.99 1,937,927.00 3,854,536.80
Jumlah - A.2 135,539,731.85
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 247.45 104,882.00 25,953,008.95
2 Pek. Plesteran kolom ad. 1 : 4 M2 8.96 104,882.00 939,742.72
3 Pek. Acian dinding dan kolom M2 256.41 58,800.00 15,076,884.48
Jumlah - A.3 41,969,636.15
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.51 15,526,560.00 7,946,120.77
2 Kosen Manumata Atap/Gewel/Sopi sopi, kayu kls. I M3 0.07 15,526,560.00 1,062,327.24
3 Daun Pintu Panel, kayu kls. I M2 3.00 1,119,104.00 3,353,059.40
4 Daun Jendela / Kom Jendela, kayu kls.I M2 1.88 813,142.00 1,524,641.25
5 Jalusi Kusen Pintu & Jendela, kayu kls.II M2 5.76 872,592.00 5,030,318.36
6 Jalusi Manumata Atap/Gewel/Sopi sopi, kayu kls. II M2 2.31 872,592.00 2,018,130.78
7 Engsel pintu 4" Bh 6.00 80,735.00 484,410.00
8 Engsel jendela Bh 30.00 58,856.00 1,765,680.00
9 Grendel jendela Bh 15.00 46,508.00 697,620.00
10 Kunci tanam Bh 1.00 395,304.00 395,304.00
11 Kait Angin Bh 30.00 77,868.00 2,336,040.00
Jumlah - A.4 26,613,651.80
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 69.03 365,750.00 25,247,722.50
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 18.40 377,631.00 6,948,410.40
Jumlah - A.5 32,196,132.90
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 3.03 247,783.00 749,543.58
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 2.45 247,783.00 607,068.35
Jumlah - A.6 1,356,611.93
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 156.10 447,757.00 69,894,867.70
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 156.10 139,753.00 21,815,443.30
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 4.50 278,913.00 1,255,108.50
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 49.60 101,024.00 5,010,790.40
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 119.23 222,101.00 26,480,546.98
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
6 Pek. Penutup plafond Kalsiboard 5 mm M2 119.23 117,009.00 13,950,690.55
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 54.80 44,878.00 2,459,314.40
8 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 41.90 44,878.00 1,880,388.20
Jumlah - A.7 142,747,150.03
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 17.00 499,632.00 8,493,744.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 2.00 139,507.00 279,014.00
4 Pas. Stop kontak broco BH 8.00 81,760.00 654,080.00
5 Pas. Saklar ganda broco BH 1.00 85,120.00 85,120.00
6 Pas. Saklar tunggal broco BH 1.00 85,120.00 85,120.00
7 Pas. MCB 6 A (lengkap) BH 2.00 150,000.00 300,000.00
8 Panel MCB 3 grup lengkap pemasangannya Unit 1.00 650,000.00 650,000.00
Jumlah - A.8 11,466,374.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 256.41 40,504.00 10,385,614.44
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 119.23 39,675.00 4,730,351.06
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 7.74 41,966.00 324,648.98
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 29.01 41,966.00 1,217,425.27
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 9.17 41,966.00 385,029.66
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 14.88 41,966.00 624,454.08
Jumlah - A.9 17,667,523.48
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 47.00 319,600.00 15,021,200.00
Jumlah - A.10 15,021,200.00
XI. PEKERJAAN TEMPAT CUCI TANGAN ( Vol = 01 Bh )
1 Pek. Dinding Beton ad. 1Pc : 2Ps : 3Kr
- Bekisting M2 1.68 1,027,740.00 1,726,603.20
- Beton tidak bertulang ad. 1Pc : 2Ps : 3Kr M3 0.09 1,759,268.00 158,334.12
2 Pek. Plesteran dinding ad. 1 : 4 M2 1.74 104,882.00 182,494.68
3 Pek. Acian dinding M2 1.74 58,800.00 102,312.00
4 Pek. Pengecatan waterproofing M2 1.74 136,026.00 236,685.24
5 Pas. Wastafel Keramik Bh 1.00 962,808.00 962,808.00
6 Pas. Kran air 1/2" + Asesories Bh 1.00 141,008.00 141,008.00
7 Pas. Pipa PVC tipe AW 1/2" + Asesories M' 30.00 63,716.00 1,911,480.00
8 Pas. Pipa PVC tipe AW 2" + Asesories M' 4.00 154,906.00 619,624.00
Jumlah - A.11 6,041,349.24
B. PEKERJAAN PENGADAAN PERABOT LAB KOMPUTER
1 Meja Siswa Ganda (M-02) (M-02) Bh 6.00 1,098,300.00 6,589,800.00
2 Meja Komputer Server (M-02) (M-02) Bh 2.00 1,098,300.00 2,196,600.00
3 Kursi Siswa (K-02) (K-02) Bh 16.00 720,100.00 11,521,600.00
4 Meja Laboran (M-01) (M-01) Bh 1.00 3,636,400.00 3,636,400.00
5 Kursi Laboran (K-01) (K-01) Bh 1.00 852,600.00 852,600.00
6 Papan Tulis (White Board P-01) (P-01) Bh 1.00 1,870,700.00 1,870,700.00
7 Lemari Penyimpanan (L-01) (L-01) Bh 1.00 4,243,300.00 4,243,300.00
8 Tempat Sampah Bh 0.00 346,100.00 0.00
JUMLAH - B 30,911,000.00

REKAPITULASI BIAYA
A. PEKERJAAN PEMBANGUNAN 1 RUANG Rp. 468,059,325.67
I. PEKERJAAN TANAH Rp. 37,439,964.30
II. PEKERJAAN PASANGAN BATU & BETON Rp. 135,539,731.85
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 41,969,636.15
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 26,613,651.80
V. PEKERJAAN KERAMIK Rp. 32,196,132.90
VI. PEKERJAAN KACA Rp. 1,356,611.93
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 142,747,150.03
VIII. PEKERJAAN LISTRIK Rp. 11,466,374.00
IX. PEKERJAAN PENGECATAN Rp. 17,667,523.48
X. PEKERJAAN SANITAIR Rp. 15,021,200.00
XI. PEKERJAAN TEMPAT CUCI TANGAN ( Vol = 01 Bh ) Rp. 6,041,349.24
B. PEKERJAAN PENGADAAN PERABOT LAB KOMPUTER Rp. 30,911,000.00
JUMLAH Rp. 498,970,325.67
PEMBULATAN Rp 498,970,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
REKAPITULASI BIAYA

INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUMAH DINAS GURU BESERTA PERABOTNYA
VOLUME : 1 KOPEL / 2 LOKAL
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 56 MALUKU TENGAH

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 9,800,000
B. PEKERJAAN PEMBANGUNAN 2 (DUA) LOKAL Rp 520,541,542.87
I. PEKERJAAN TANAH Rp 10,628,181.20
II. PEKERJAAN PASANGAN BATU & BETON Rp 179,254,960.42
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 59,925,127.80
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 50,547,976.89
V. PEKERJAAN KERAMIK Rp 33,499,563.64
VI. PEKERJAAN KACA Rp 1,642,801.29
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 117,566,586.29
VIII. PEKERJAAN LISTRIK Rp 13,526,840.00
IX. PEKERJAAN PENGECATAN Rp 40,751,863.33
X. PEKERJAAN SANITAIR Rp 13,197,642.00

C. PENGADAAN PERABOT - RMH DINAS GURU ( 2 LOKAL ) Rp 25,731,600.00

C. Jumlah ( A ) + ( B x 2 Lokal ) Rp 546,273,142.87


D. PPn 11% Rp 60,090,045.72
E. Total (D + E) Rp 606,363,188.58
PEMBULATAN Rp 606,363,000.00

#NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Wakil Direktur
RENCANA ANGGARAN BIAYA (RAB)
INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUMAH DINAS GURU BESERTA PERABOTNYA
VOLUME : 1 KOPEL / 2 LOKAL
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 56 MALUKU TENGAH

J. PEMBANGUNAN RUMAH DINAS GURU BESERTA PERABOTNYA (1 KOPEL / 2 LOKAL)


HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI
1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 9,800,000.00
B. PEKERJAAN PEMBANGUNAN 2 (DUA) LOKAL
I. PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi M3 23.43 106,400.00 2,492,420.00
2 Pek. Urugan Tanah Kembali M3 5.86 78,400.00 459,130.00
3 Pek. Timbunan Tanah Bawah Lantai (Timbunan Biasa) M3 13.31 576,800.00 7,676,631.20
Jumlah - A.1 10,628,181.20
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu Kali / Karang ad. 1:5 M3 26.70 1,695,036.00 45,265,088.86
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 320.38 248,192.00 79,515,455.13
3 Pekerjaan Beton Bertulang :
- Beton Sloof 15/20 cm (110 kg/m3) M3 4.50 5,900,806.00 26,539,465.07
- Kolom Praktis 15/15 cm, atas sloof (110 kg/m3) M3 0.53 5,391,724.00 2,838,548.58
- Kolom Praktis 15/15 cm, atas ring balok (110 kg/m3) M3 0.09 5,391,724.00 481,373.12
- Beton Ring Balok 15/20 cm (110 kg/m3) M3 2.25 6,378,760.00 14,344,555.49
- Beton Ring Balok Praktis 15/15 cm, sisi miring (110 kg/m3) M3 0.79 6,378,760.00 5,036,668.90
- Beton Ring Balok Praktis 15/15 cm, Latei (110 kg/m3) M3 0.07 6,378,760.00 459,270.72
- Plat atap /DAK (110 kg/m3) M3 0.72 6,631,298.00 4,774,534.56
Jumlah - A.2 179,254,960.42
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran Dinding ad. 1 : 4 M2 571.36 104,882.00 59,925,127.80
2 Pek. Acian Dinding dan Kolom M2 0.00 58,800.00 0.00
Jumlah - A.3 59,925,127.80
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 1.24 15,526,560.00 19,227,781.37
2 Daun Pintu Panel, kayu kls. I M2 16.38 1,119,104.00 18,330,923.52
3 Daun Jendela Panil Kaca, kayu kls.I M2 6.00 813,142.00 4,878,852.00
4 Pas. Engsel Pintu 4" Bh 20.00 80,735.00 1,614,700.00
5 Pas. Engsel Jendela Bh 20.00 58,856.00 1,177,120.00
6 Pas. Grendel Jendela Bh 10.00 46,508.00 465,080.00
7 Pas. Kunci Tanam (Pintu Panel) Bh 10.00 329,616.00 3,296,160.00
0.00
8 Pas. Kait Angin Bh 20.00 77,868.00 1,557,360.00
Jumlah - A.4 50,547,976.89
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Dalam (polos) M2 62.84 365,750.00 22,983,730.00
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 9.96 377,631.00 3,761,204.76
3 Pas. Lantai Keramik 20x20 cm Toilet (anti slip) M2 4.86 415,408.00 2,018,882.88
4 Pas. Dinding Keramik 20x25 cm Toilet, H=1,5 m' (polos) M2 16.56 285,975.00 4,735,746.00
Jumlah - A.5 33,499,563.64
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 6.63 247,783.00 1,642,801.29
Jumlah - A.6 1,642,801.29
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pas. Kuda-Kuda Kayu 6/12, Klas I M2 0.86 14,014,784.00 11,990,712.84
2 Pas. Gording Kayu 5/10, Klas II M2 0.52 11,320,680.00 5,909,394.96
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 230.54 139,753.00 32,218,321.21
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 27.08 60,709.00 1,643,999.72
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 22.00 114,060.00 2,509,320.00
6 Pek. Rangka plafond kayu klas II M2 195.32 185,519.00 36,235,571.08
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 195.32 117,009.00 22,854,197.88
8 Pek. Lis plafond Kayu Profil, lbr = 8 cm (dalam ruang) M' 93.70 44,878.00 4,205,068.60
Jumlah - A.7 117,566,586.29
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VIII. PEKERJAAN LISTRIK
1 Pek. Titik Instalasi Lampu TTK 20.00 499,632.00 9,992,640.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 4.00 153,216.00 612,864.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 8.00 139,507.00 1,116,056.00
4 Pas. Stop kontak broco BH 8.00 81,760.00 654,080.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 8.00 85,120.00 680,960.00
7 Pas. MCB 6 A (lengkap) BH 2.00 150,000.00 300,000.00

Jumlah - A.8 13,526,840.00


IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 571.36 40,504.00 23,142,268.23
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 195.32 39,675.00 7,749,321.00
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 195.32 41,966.00 8,196,799.12
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 0.28 41,966.00 11,693.22
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 32.76 41,966.00 1,374,806.16
6 Pek. Cat Lisplank papan Kayu dengan cat Glotex M2 6.60 41,966.00 276,975.60
Jumlah - A.9 40,751,863.33
X. PEKERJAAN SANITAIR
1 Pas. Klosed Jongkok Keramik + Acc Bh 2.00 3,122,884.00 6,245,768.00
2 Pas. Keran Air 1/2" + Asesories Bh 4.00 141,008.00 564,032.00
3 Pas. Floor Drine Stainless steel Bh 2.00 244,834.00 489,668.00
4 Pipa PVC tipe AW 1/2" M' 15.00 63,716.00 955,740.00
5 Pipa PVC tipe AW 2" M' 5.00 154,906.00 774,530.00
6 Pipa PVC tipe AW 3" M' 4.00 166,976.00 667,904.00
7 Pek. Septik Tank & Resapan (Konpensional-Tipe Kecil) Unit 1.00 3,500,000.00 3,500,000.00
Jumlah - A.10 13,197,642.00
C. PENGADAAN PERABOT - RMH DINAS GURU ( 2 LOKAL )
1 Tempat Tidur (ketersediaan) Bh 2.00 4,000,000.00 8,000,000.00
2 Kasur, Bantal, Seprei, Selimut (ketersediaan) Set 2.00 2,500,000.00 5,000,000.00
3 Meja Kerja & Kursi Kerja (M-01 & K-02) Set 2.00 3,588,100.00 7,176,200.00
4 Meja Makan & Kursi Makan (M-10 & K-02) Set 2.00 1,044,000.00 2,088,000.00
5 Meja Tamu & Kursi Tamu (2-1) (K-11 & K-12) Set 2.00 1,733,700.00 3,467,400.00
JUMLAH - B 25,731,600.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 9,800,000.00


B. PEKERJAAN PEMBANGUNAN 2 (DUA) LOKAL Rp. 520,541,542.87
I. PEKERJAAN TANAH Rp. 10,628,181.20
II. PEKERJAAN PASANGAN BATU & BETON Rp. 179,254,960.42
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 59,925,127.80
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 50,547,976.89
V. PEKERJAAN KERAMIK Rp. 33,499,563.64
VI. PEKERJAAN KACA Rp. 1,642,801.29
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 117,566,586.29
VIII. PEKERJAAN LISTRIK Rp. 13,526,840.00
IX. PEKERJAAN PENGECATAN Rp. 40,751,863.33
X. PEKERJAAN SANITAIR Rp. 13,197,642.00
C. PENGADAAN PERABOT - RMH DINAS GURU ( 2 LOKAL ) Rp. 25,731,600.00
JUMLAH Rp. 556,073,142.87
PEMBULATAN Rp 556,073,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
GALIAN TANAH PONDASI
Rumus Panjang Lebar Tinggi Volume x2

V=PxLxT 46.85 1.00 0.50 23.43 46.85

Jumlah total 23.43 m3


SKETSA

URGAN KEMBALI
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 1.00 0.70 5.86 m3

Jumlah total 5.86 m3


SKETSA

TIMBUNAN TANAH BAWAH LANTAI


Rumus Luas Lebar Tinggi Volume x2

Teras 1.66 0.15 0.25 0.50


Ruang Tamu 12.28 0.20 2.46 4.91
Kamar 1 7.59 0.20 1.52 3.04
Kamar 2 6.69 0.20 1.34 2.68
WC 2.43 0.15 0.36 0.73
Ruang Masak 4.86 0.15 0.73 1.46

Jumlah total 6.65 13


SKETSA

PASANG BATU KALI


Rumus Panjang Lebar Tinggi Volume Satuan

46.85 0.48 0.60 13.35 26.70

Jumlah total - 27
SKETSA

BATU KOSONG
Rumus Panjang Lebar Tinggi Volume Satuan

46.85 0.80 0.15 5.62 11.24

Jumlah total - 11
SKETSA
URUG PASIR BAWAH PONDASI
Rumus Panjang Lebar Tinggi Volume Satuan

46.85 0.80 0.05 1.87 3.75

Jumlah total - 4
SKETSA

URUG PASIR BAWAH LANTAI


Rumus Luasan Lebar Tinggi Volume Satuan

Teras 1.66 0.05 0.08 0.17


Ruang Tamu 12.28 0.05 0.61 1.23
Kamar 1 7.59 0.05 0.38 0.76
Kamar 2 6.69 0.05 0.33 0.67
WC 2.43 0.05 0.12 0.24
Ruang Masak 4.86 0.05 0.24 0.49
Jumlah total 1.78 4
SKETSA

DINDING BATA SEMEN


Rumus Panjang Lebar Pintu Jendela Satuan

Depan 1 3.20 2.85 2.33 2.00 4.78


Depan 2 3.73 2.85 - 2.00 8.63
Belakang 1 3.65 2.85 2.33 - 10.40
Belakang 2 4.00 2.85 - - 11.40
Samping kiri 34.70 1.00 - 34.70
Samping kanan 42.00 1.00 - 42.00
Tengah/pembagi ruangan 18.00 3.20 9.32 48.28

Jumlah total 320


Jumlah total X 2

SLOOF15/20
Rumus Panjang Lebar tebal Vol x2

V= Panjang Pondasi 46.85 0.12 0.20 1.12 2.25

Jumlah total 4
SKETSA

KOLOM 15/15
Rumus Tinggi Lebar tebal jml x2

Kolom 1 4.10 0.12 0.12 0.059 0.118


Kolom 2 3.73 0.12 0.12 0.054 0.107
Kolom3 3.20 0.12 0.12 0.046 0.092
Kolom4 3.40 0.12 0.12 0.049 0.098
Kolom5 3.85 0.12 0.12 0.055 0.111

Jumlah total 0.263 0.526


SKETSA
KOLOM GEWEL
Rumus Tinggi Lebar tebal jml x2

Kolom 1 1.78 0.12 0.12 0.026 0.051


Kolom 2 1.32 0.12 0.12 0.019 0.038

Jumlah total 0.045 0.089


SKETSA

BALOK 15/20
Rumus Panjang Lebar tebal jml x2

Balok 1 46.85 0.12 0.20 1.12 2.25


Jumlah total 2.249

Balok Latei 1.50 0.12 0.20 0.04 0.07


Jumlah total 0.072

Kuda-kuda Gewel1 8.45 0.12 0.20 0.20 0.41


Kuda-kuda Gewel 2 8.00 0.12 0.20 0.19 0.38
Jumlah total 0.790

PLAT ATAP
Rumus Tinggi Lebar tebal jml x2

DAK 6.00 0.50 0.12 0.360 0.720


Jumlah total 0.720

ACIAN
Rumus Panjang Lebar Pintu Jendela Satuan

Depan 1 3.20 2.85 2.33 2.00 4.78


Depan 2 3.73 2.85 - 2.00 8.63
Belakang 1 3.65 2.85 2.33 - 10.40
Belakang 2 4.00 2.85 - - 11.40
Samping kiri 17.35 1.00 - 17.35
Samping kanan 42.00 1.00 - 42.00
Tengah/pembagi ruangan 18.00 3.20 9.32 48.28

Jumlah total 286


Jumlah total X 2 571
X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN ASRAMA SISWA BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 15,275,000.00


B. PEKERJAAN PEMBANGUNAN Rp 780,161,942.66
I. PEKERJAAN TANAH Rp 26,518,246.85
II. PEKERJAAN PASANGAN BATU & BETON Rp 157,792,959.51
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 83,066,127.03
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 59,996,123.80
V. PEKERJAAN KERAMIK Rp 99,973,489.98
VI. PEKERJAAN KACA Rp 3,421,189.44
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 230,638,311.75
VIII. PEKERJAAN LISTRIK Rp 24,233,533.00
IX. PEKERJAAN PENGECATAN Rp 32,905,143.40
X. PEKERJAAN SANITAIR Rp 59,203,260.00
XII. PEKERJAAN MEJA BETON DAPUR Rp 2,413,557.89

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 130,183,300.00

C. Jumlah Rp 925,620,242.66
D. PPn 11% Rp 101,818,226.69
E. Total (D + E) Rp 1,027,438,469.35
PEMBULATAN Rp 1,027,438,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN ASRAMA SISWA BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.00 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.00 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.00 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.00 11,325,000.00 11,325,000.00
5 Air kerja dan listrik Ls 1.00 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.00 750,000.00 750,000.00
Jumlah - A.1 15,275,000.00
B. PEKERJAAN PEMBANGUNAN
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 29.56 106,400.00 3,145,077.60
2 Pek. Urugan tanah kembali M3 0.00 78,400.00 0.00
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 30.43 576,800.00 17,551,086.70
4 Pek. Urugan pasir dibawah pondasi, tbl = 5 cm M3 3.94 480,704.00 1,894,550.60
5 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 8.17 480,704.00 3,927,531.94
Jumlah - A.1 26,518,246.85
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Batu Kosong / Aanstamping M3 11.82 949,263.00 11,223,706.01
2 Pas. Pondasi Batu kali ad. 1:5 M3 22.17 1,695,036.00 37,577,676.84
3 Pas. Dinding Batu Bata Semen ad. 1:4 M2 233.94 248,192.00 58,062,632.14
4 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 12/15 cm, (pembangian ruangan) (150 kg/m3) M3 0.67 6,793,558.00 4,536,738.03
- Beton Sloof 15/20 cm, (keliling ruangan) (150 kg/m3) M3 1.56 6,793,558.00 10,597,950.48
- Beton Sloof 15/20 cm, (teras depan) (150 kg/m3) M3 0.18 6,793,558.00 1,222,840.44
- Beton Kolom 20/20 cm, (ruangan) (150 kg/m3) M3 1.19 7,255,250.00 8,619,237.00
- Beton Kolom 20/20 cm, (teras depan) (150 kg/m3) M3 0.15 7,255,250.00 1,077,404.63
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.43 5,900,806.00 2,531,445.77
- Beton Ring Balok 12/15 cm, (pembagian ruangan) (150 kg/m3) M3 0.67 7,271,512.00 4,855,915.71
- Beton Ring Balok 15/20 cm, (Keliling ruangan) (150 kg/m3) M3 1.56 7,271,512.00 11,343,558.72
- Beton Ring Balok 15/20 cm, (teras depan) (150 kg/m3) M3 0.18 7,271,512.00 1,308,872.16
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.10 7,271,512.00 738,203.90
5 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.11 1,937,927.00 4,096,777.68
Jumlah - A.2 157,792,959.51
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 467.88 104,882.00 49,072,693.59
2 Pek. Plesteran kolom ad. 1 : 4 M2 39.60 104,882.00 4,153,327.20
3 Pek. Acian dinding dan kolom M2 507.48 58,800.00 29,840,106.24
Jumlah - A.3 83,066,127.03
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.82 15,526,560.00 12,683,025.80
2 Daun Pintu Panel, kayu kls. I M2 21.00 1,119,104.00 23,501,184.00
3 Daun Jendela kaca kayu kla I M2 11.00 813,142.00 8,944,562.00
4 Jalusi Kusen Pintu, Jendela & Ventilasi, kayu kls.II M2 0.00 872,592.00 0.00
5 Jalusi Manumata Atap/Gewel/Sopi sopi, kayu kls. II M2 0.00 872,592.00 0.00
6 Engsel pintu 4" Bh 48.00 80,735.00 3,875,280.00
7 Engsel jendela Bh 44.00 58,856.00 2,589,664.00
8 Grendel jendela Bh 22.00 46,508.00 1,023,176.00
9 Kunci tanam Bh 10.00 395,304.00 3,953,040.00
10 Kait Angin Bh 44.00 77,868.00 3,426,192.00
Jumlah - A.4 59,996,123.80
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 60x60 cm Rg. Kelas (polos) M2 124.62 731,102.00 91,107,737.93
2 Pas. Lantai Keramik 60x60 cm Teras Depan (anti slip) M2 4.00 731,102.00 2,924,408.00
3 Pas. Lantai Keramik 20x20 cm WC/KM (anti slip) M2 8.38 377,631.00 3,165,756.20
4 Pas. Dinding Keramik 20x40 cm WC/KM (polos) M2 7.35 377,631.00 2,775,587.85
Jumlah - A.5 99,973,489.98
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 6.81 247,783.00 1,687,699.57
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 7.00 247,783.00 1,733,489.87
Jumlah - A.6 3,421,189.44
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 248.85 447,757.00 111,422,986.18
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 248.85 139,753.00 34,777,114.79
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 17.77 278,913.00 4,955,726.18
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 64.09 101,024.00 6,474,628.16
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 189.77 222,101.00 42,148,550.97
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 189.77 117,009.00 22,205,031.95
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 192.84 44,878.00 8,654,273.52
8 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 0.00 44,878.00 0.00
Jumlah - A.7 230,638,311.75
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 36.00 499,632.00 17,986,752.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 11.00 153,216.00 1,685,376.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 15.00 139,507.00 2,092,605.00
4 Pas. Stop kontak broco BH 10.00 81,760.00 817,600.00
5 Pas. Saklar ganda broco BH 4.00 85,120.00 340,480.00
6 Pas. Saklar tunggal broco BH 6.00 85,120.00 510,720.00
7 Pas. MCB 6 A (lengkap) BH 1.00 150,000.00 150,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 1.00 650,000.00 650,000.00
Jumlah - A.8 24,233,533.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 502.73 40,504.00 20,362,689.33
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 189.77 39,675.00 7,529,204.10
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 19.28 41,966.00 809,272.34
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 34.90 41,966.00 1,464,705.73
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 45.55 41,966.00 1,911,702.38
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 19.72 41,966.00 827,569.52
Jumlah - A.9 32,905,143.40
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 56.00 319,600.00 17,897,600.00
2 Pek. Tanki Limbah & Resapan uk. (120cm x 280cm), H = (140/100) cm Unit 1.00 8,500,000.00 8,500,000.00
3 Pek. Septink 2,5 x 1,5 meter t = 2 Unit 2.00 5,000,000.00 10,000,000.00
4 Pas. Bak Mandi Fiberglass uk. 65 cm, t = 68 cm Unit 4.00 1,216,919.00 4,867,676.00
5 Pas. Closet duduk + tabung Unit 4.00 3,122,884.00 12,491,536.00
6 Pas. Kran air Bh 4.00 141,008.00 564,032.00
7 Pas. Floor drain Bh 4.00 67,144.00 268,576.00
8 Pas. Pipa air kotor PVC AW 3" M' 20.00 166,976.00 3,339,520.00
9 Pas. Pipa air bersih PVC AW 1/2" M' 20.00 63,716.00 1,274,320.00

Jumlah - A.10 59,203,260.00


XII. PEKERJAAN MEJA BETON DAPUR
1 Pas. Batu Bata Semen ad. 1:4 M2 1.26 248,192.00 312,721.92
2 Pekerjaan Beton Bertulang (K-175) :
- Pelat Lantai Meja Beton, tbl = 7 cm (110 kg/m3) M3 0.13 6,631,298.00 840,185.46
3 Pek. Plesteran dinding ad. 1 : 4 M2 1.68 104,882.00 176,201.76
4 Pas. Keramik 40 x 40 cm Meja Beton (polos) M2 2.97 365,750.00 1,084,448.75
Jumlah - A.11 2,413,557.89
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Belajar (M-03) (M-03) Bh 4.00 2,808,800.00 11,235,200.00
2 Kursi siswa tunggal (K-01) (K-03) Bh 20.00 852,600.00 17,052,000.00
3 Tempat tidur tingkat + kasur spons satu badan (20 bh) (K-01) Bh 10.00 3,600,000.00 36,000,000.00
4 Tempat tidur Pengelola + Kasur Bh 1.00 2,800,000.00 2,800,000.00
5 Meja Tamu + Kursi tamu (K-01) Set 1.00 10,250,000.00 10,250,000.00
6 Lemari pakaian 2 Pintu Bh 21.00 2,500,000.00 52,500,000.00
7 Tempat Sampah Bh 1.00 346,100.00 346,100.00
JUMLAH - B 130,183,300.00

REKAPITULASI BIAYA

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 15,275,000.00


B. PEKERJAAN PEMBANGUNAN Rp. 780,161,942.66

I. PEKERJAAN TANAH Rp. 26,518,246.85


II. PEKERJAAN PASANGAN BATU & BETON Rp. 157,792,959.51
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 83,066,127.03
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 59,996,123.80
V. PEKERJAAN KERAMIK Rp. 99,973,489.98
VI. PEKERJAAN KACA Rp. 3,421,189.44
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 230,638,311.75


VIII. PEKERJAAN LISTRIK Rp. 24,233,533.00
IX. PEKERJAAN PENGECATAN Rp. 32,905,143.40
X. PEKERJAAN SANITAIR Rp. 59,203,260.00
XI. PEKERJAAN MEJA BETON DAPUR Rp. 2,413,557.89
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 130,183,300.00
JUMLAH Rp. 925,620,242.66
PEMBULATAN Rp 925,620,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 25.00 Bh 100,000.00 2,500,000.00
2 Sarung Tangan (Safeti Gloves) 25.00 Psg 15,000.00 375,000.00
3 Sepatu Keselamatan (Safety Shoes) 25.00 Psg 200,000.00 5,000,000.00
4 Rompi Keselamatan (Safety Vest) 25.00 Bh 50,000.00 1,250,000.00
sub total 9,125,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 11,325,000.00
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG TATA USAHA BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 9,800,000.00


B. PEMBANGUNAN FISIK 1 (RUANG) Rp 334,808,359.56
I. PEKERJAAN TANAH Rp 12,135,470.48
II. PEKERJAAN PASANGAN BATU & BETON Rp 73,690,443.82
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 46,858,337.24
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 27,032,226.00
V. PEKERJAAN KERAMIK Rp 30,206,319.72
VI. PEKERJAAN KACA Rp 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 104,623,149.11
VIII. PEKERJAAN LISTRIK Rp 7,333,417.00
IX. PEKERJAAN PENGECATAN Rp 18,816,025.80
X. PEKERJAAN SANITAIR Rp 9,740,348.00
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp 1,147,280.63

C. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 13,500,000.00

D. Jumlah Rp 358,108,359.56
E. PPn 11% Rp 39,391,919.55
F. Total (D + E) Rp 397,500,279.11
PEMBULATAN Rp 397,500,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG TATA USAHA BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.00 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.00 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.00 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.00 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.00 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.00 750,000.00 750,000.00
Jumlah - A.1 9,800,000.00
B. PEMBANGUNAN FISIK 1 (RUANG)
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 13.25 106,400.00 1,409,800.00
2 Pek. Urugan tanah kembali M3 (13.25) 78,400.00 (1,038,800.00)
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 20.40 576,800.00 11,764,470.48
Jumlah - A.1 12,135,470.48
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu kali ad. 1:5 M3 9.94 1,695,036.00 16,844,420.25
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 135.09 248,192.00 33,527,347.16
3 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm (150 kg/m3) M3 0.95 6,793,558.00 6,481,054.33
- Beton Kolom 15/20 cm (150 kg/m3) M3 0.38 7,255,250.00 2,758,155.84
- Beton Kolom 15/15 cm, (teras depan) (150 kg/m3) M3 0.30 7,255,250.00 2,176,575.00
- Beton Ring Balok 15/20 cm (150 kg/m3) M3 0.95 7,271,512.00 6,937,022.45
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.12 7,271,512.00 869,091.11
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.11 1,937,927.00 4,096,777.68
Jumlah - A.2 73,690,443.82
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 270.17 104,882.00 28,336,249.56
2 Pek. Plesteran kolom ad. 1 : 4 M2 16.10 104,882.00 1,689,019.73
3 Pek. Acian dinding dan kolom M2 286.28 58,800.00 16,833,067.96
Jumlah - A.3 46,858,337.24
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.45 15,526,560.00 6,917,082.48
2 Daun Pintu Panel, kayu kls. I M2 6.93 1,119,104.00 7,755,390.72
3 Daun Jendela kaca kayu kla I M2 8.40 813,142.00 6,830,392.80
6 Engsel pintu 4" Bh 8.00 80,735.00 645,880.00
7 Engsel jendela Bh 8.00 58,856.00 470,848.00
8 Grendel jendela Bh 14.00 46,508.00 651,112.00
9 Kunci tanam Bh 4.00 395,304.00 1,581,216.00
10 Kait Angin Bh 28.00 77,868.00 2,180,304.00
Jumlah - A.4 27,032,226.00
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 63.13 365,750.00 23,090,090.10
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 6.00 377,631.00 2,265,786.00
3 Pas. Lantai Keramik 20x20 cm WC/KM (anti slip) M2 3.28 377,631.00 1,240,291.26
4 Pas. Dinding Keramik 20x40 cm WC/KM (polos) M2 9.56 377,631.00 3,610,152.36
Jumlah - A.5 30,206,319.72
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 5.54 247,783.00 1,372,321.37
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 7.48 247,783.00 1,853,020.39
Jumlah - A.6 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Kuda-kuda kayu Kls I Uk. 6/12 M2 1.03 14,014,784.00 14,449,242.30
2 Pek. Rangka Gording kayu Kls II uk. 5/10 M2 1.18 11,320,680.00 13,358,402.40
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 141.24 139,753.00 19,738,755.65
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 38.82 278,913.00 10,827,402.66
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 51.04 101,024.00 5,156,264.96
6 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 105.13 222,101.00 23,349,655.81
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 105.13 117,009.00 12,301,249.78
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 121.27 44,878.00 5,442,175.55
Jumlah - A.7 104,623,149.11
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 10.00 499,632.00 4,996,320.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 5.00 81,760.00 408,800.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 2.00 85,120.00 170,240.00
7 Pas. Box MCB 4 grup (tutup transparan + MCB 6A 2buh) Unit 1.00 250,000.00 250,000.00
Jumlah - A.8 7,333,417.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 302.38 40,504.00 12,247,626.50
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 105.13 39,675.00 4,171,064.49
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 21.20 41,966.00 889,679.20
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 0.30 41,966.00 12,692.41
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 20.31 41,966.00 852,379.82
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 15.31 41,966.00 642,583.39
Jumlah - A.9 18,816,025.80
X. PEKERJAAN SANITAIR
1 Pek. Septink 2,5 x 1,5 meter t = 2 Unit 1.00 3,500,000.00 3,500,000.00
2 Pas. Closet duduk + tabung Unit 1.00 3,122,884.00 3,122,884.00
3 Pas. Kran air Bh 2.00 141,008.00 282,016.00
4 Pas. Floor drain Bh 1.00 67,144.00 67,144.00
5 Pas. Pipa air kotor PVC AW 3" M' 12.00 166,976.00 2,003,712.00
6 Pas. Pipa air bersih PVC AW 1/2" M' 12.00 63,716.00 764,592.00

Jumlah - A.10 9,740,348.00


XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING
1 Pas. Batu Bata Semen ad. 1:4 M2 0.10 248,192.00 23,826.43
2 Pekerjaan Beton Bertulang (K-175) :
- Pelat Lantai Meja Beton, tbl = 7 cm (110 kg/m3) M3 0.06 6,631,298.00 375,596.72
3 Pek. Plesteran dinding ad. 1 : 4 M2 0.84 104,882.00 88,100.88
4 Pas. Keramik 40 x 40 cm Meja Beton (polos) M2 0.83 365,750.00 302,841.00
5 Pas. Kitchen Zink 1 lubang dan sayap (uk. 82cm x 38cm) Bh 1.00 215,907.60 215,907.60
6 Pas. Keran Air Bh 1.00 141,008.00 141,008.00
Jumlah - A.11 1,147,280.63
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja & Kursi - Kepala TU (M-01 & K-02) (M-01 & K-02) set 1.00 3,500,000.00 3,500,000.00
2 Meja & Kursi - Staf TU (M-01 & K-02) (M-01 & K-02) set 2.00 3,500,000.00 7,000,000.00
3 Lemari Penyimpanan (L-01) unit 1.00 3,000,000.00 3,000,000.00
JUMLAH - B 13,500,000.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 9,800,000.00

B. PEMBANGUNAN FISIK 1 (RUANG) Rp. 334,808,359.56


I. PEKERJAAN TANAH Rp. 12,135,470.48
II. PEKERJAAN PASANGAN BATU & BETON Rp. 73,690,443.82
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 46,858,337.24
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 27,032,226.00
V. PEKERJAAN KERAMIK Rp. 30,206,319.72
VI. PEKERJAAN KACA Rp. 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 104,623,149.11
VIII. PEKERJAAN LISTRIK Rp. 7,333,417.00
IX. PEKERJAAN PENGECATAN Rp. 18,816,025.80
X. PEKERJAAN SANITAIR Rp. 9,740,348.00
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp. 1,147,280.63
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 13,500,000.00
JUMLAH Rp. 358,108,359.56
PEMBULATAN Rp 358,108,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 53.00 0.50 0.50 13.25 m3

Jumlah total 13.25 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.49 0.40 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 13.25 26.50 - - (13.25) m3

Jumlah total (13.25) m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 2.88 1.88 0.15 0.81 m3


Lantai selasar 56.00 0.75 0.15 6.30 m3
Lantai ruang tamu 5.38 2.88 0.20 3.10 m3
Lantai ruang Rawat Putri 3.88 2.88 0.20 2.23 m3
Lantai ruang Rawat Putra 3.88 2.88 0.20 2.23 m3
Lantai ruang Periksa 4.00 3.00 0.20 2.40 m3
Lantai ruang Hall 2.88 1.38 0.20 0.79 m3
Lantai ruang Dokter 2.88 2.38 0.20 1.37 m3
Lantai WC/KM 2.38 1.38 0.15 0.49 m3
Lantai Pentry 2.38 1.38 0.20 0.66 m3
Jumlah total 20 m3
SKETSA

5. Pekerjaan urug pasir bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 2.88 1.88 0.05 0.27 m3


Lantai selasar 56.00 0.75 0.05 2.10 m3
Lantai ruang tamu 5.38 2.88 0.05 0.77 m3
Lantai ruang Rawat Putri 3.88 2.88 0.05 0.56 m3
Lantai ruang Rawat Putra 3.88 2.88 0.05 0.56 m3
Lantai ruang Periksa 4.00 3.00 0.20 2.40 m3
Lantai ruang Hall 2.88 1.38 0.05 0.20 m3
Lantai ruang Dokter 2.88 2.38 0.05 0.34 m3
Lantai WC/KM 2.38 1.38 0.05 0.16 m3
Lantai Pentry 2.38 1.38 0.05 0.16 m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 53.00 0.50 0.05 1.33 m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 53.00 0.50 0.15 3.98 m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 53.00 0.25 0.50 0.50 9.94 m3

Jumlah total 9.94 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 45.76 0.45 - 20.59 m2

Jumlah total 20.59 m2


SKETSA
4. Pekerjaan pasangan dinding batu bata semen
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 8.64 3.30 2.59 7.97 7.87 m2
Dinding Belakang 8.52 3.30 6.65 21.47 m2
Dinding Samping kiri 7.76 3.30 - - 25.61 m2
Dinding Samping Kanan 7.76 3.30 2.33 - 23.28 m2
Dinding pembagi ruangan 18.16 3.30 6.38 - 53.55 m2
Dinding atas teras 6.64 0.50 3.32 m2

Jumlah total 135.09 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 15/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 8.00 0.38 m3

Jumlah total 0.380 m3


- Pekerjaan Kolom 15/15 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 2.00 0.10 m3

Jumlah total 0.095 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.30 6.00 0.20 m3

Jumlah total 0.198 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 53.00 0.12 0.15 1.00 0.95 m3

Jumlah total 0.954 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3


Jumlah total - m3
- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 53.00 0.12 0.15 1.00 0.95 m3

Jumlah total 0.954 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.64 0.12 0.15 1.00 0.12 m3

Jumlah total 0.120 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Rumus Luas Pas. Bata Luas Lubangan Volume Satuan

V = (Luas pas Batu - Luas


lubangan Pintu Jendela) x 2 135 270

Jumlah total x 2 sisi 270.17 m2


SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah
Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2
Plesteran Kolom teras 0.60 3.30 2.00 3.96 m2

Jumlah total 16.104 m2

3. Pekerjaan Acian dinding


Rumus Volume Satuan

V = Luas plesteran dinding + Luas Pleteran Kolom 286.28 m2

Jumlah total x 2 sisi 286.28 m2


SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 2.00 3.96 m2

Jumlah total 16.104 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

JV1 9.690 0.110 0.05 4.00 0.213 m3


JV2 8.250 0.110 0.05 2.00 0.091 m3
P1 6.980 0.110 0.05 2.00 0.077 m3
P2 6.780 0.110 0.05 1.00 0.037 m3
P3 5.000 0.110 0.05 1.00 0.028 m3

Jumlah total 0.45 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

P1 0.900 2.100 - 2.00 3.780 m2


P2 0.800 2.100 - 1.00 1.680 m2
P3 0.700 2.100 - 1.00 1.470 m2

Jumlah total 6.93 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

JV1 1.000 0.600 - 12.00 7.200 m2


JV2 1.000 0.600 - 2.00 1.200 m2

Jumlah total 8.40 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

P1 2.00 2.00 4.00 Buah


P2 1.00 2.00 2.00 Buah
P3 1.00 2.00 2.00 Buah

Jumlah total 8.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan

P1 2.00 2.00 4.00


P2 1.00 2.00 2.00 Buah
P3 1.00 2.00 2.00 Buah

Jumlah total 8.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan

P1 2.00 1.00 2.00


P2 1.00 1.00 1.00 Buah
P3 1.00 1.00 1.00 Buah

Jumlah total 4.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

JV1 12.00 1.00 12.00 Buah


JV2 2.00 1.00 2.00 Buah

Jumlah total 14.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1
P1 2.00 1.00 2.00 Buah
P2 1.00 1.00 1.00 Buah
P3 1.00 1.00 1.00 Buah

Jumlah total 4.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan

JV1 12.00 2.00 24.00 Buah


JV2 2.00 2.00 4.00 Buah

Jumlah total 28.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai ruang tamu 5.38 2.88 - 15.49 m3


Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 63.13 m2


SKETSA

2. Pekerjaan keramik lantai teras 60/60 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 2.00 3.00 - 6.00 m2

Jumlah total 6.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL
Lantai WC/KM 2.38 1.38 - 3.28 m3

m2

Jumlah total 3.28 m2


SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Keramik dinding WC/KM

Sekmen I 2.38 1.50 1.00 1.85 m2


Sekmen II 2.38 1.50 1.00 3.57 m2
Sekmen III 1.38 1.50 1.00 2.07 m2
Sekmen IV 1.38 1.50 1.00 2.07 m2

Jumlah total x 4 ruang 9.56 m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

J1 0.86 0.46 12.00 4.75 m2


J2 0.86 0.46 2.00 0.79 m2

Jumlah total 5.538 m2

Kaca Mati
Rumus Panjang Lebar Jumlah Volume Satuan

J1 0.86 0.48 12.00 4.95 m2


J2 0.86 0.48 2.00 0.83 m2

p1 0.88 0.48 2.00 0.84 m2


p2 0.78 0.48 1.00 0.37 m2

V1 0.60 0.40 2.00 0.48

Jumlah total 7.478 m2


VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND
1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2

Jumlah total 141.240 m2


SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2
Jumlah total 141.240 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 38.82 M'

Jumlah total x 2 sisi 38.82 M'


SKETSA
4. Pasang Lisplank GRC/ Calsiboard
Rumus Volume Satuan

V = panjang Nok 51.04 M'

Jumlah total x 2 sisi 51.04 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 - - 56.00 m2


Lantai ruang tamu 16.52 - - 16.52 m2
Lantai ruang Rawat Putri 10.93 - - 10.93 m2
Lantai ruang Rawat Putra 10.93 - - 10.93 m2
Lantai ruang Periksa 7.00 - - 7.00 m2
Lantai ruang Hall 9.37 - - 9.37 m2
Lantai ruang Dokter 10.52 - - 10.52 m2
Lantai Pentry - - - m2

Jumlah total 121.27 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 36 Titik
Pas. Lampu down ligth LED 18 watt 11.00 bh
Pas. Lampu down ligth LED 11 watt 15.00 bh
Pas. Stop kontak panasonic 10.00 bh
Pas. saklar ganda panasonic 4.00 bh
Pas. saklar ganda panasonic 6.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Acian
Rumus Volume Satuan
Dinding Kolom

V = Vol Acian dinding + Acian Kolom 286.28 16.10 302.38 m2

Jumlah total 302.38 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 113.50 0.10 1.00 11.35 m2


Lantai ruang tamu 16.52 0.10 1.00 1.65 m2
Lantai ruang Rawat Putri 13.52 0.10 1.00 1.35 m2
Lantai ruang Rawat Putra 13.52 0.10 1.00 1.35 m2
Lantai ruang Periksa 7.00 0.10 1.00 0.70 m2
Lantai ruang Hall 8.52 0.10 4.00 3.41 m2
Lantai ruang Dokter 10.52 0.10 1.00 1.05 m2
Lantai Pentry 2.38 0.10 1.00 0.24 m2

Jumlah total 21.10 m2


SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

JV1 9.690 0.235 0.05 4.00 0.455


JV2 8.250 0.235 0.05 2.00 0.194
P1 6.980 0.235 0.05 2.00 0.164 m2
P2 6.780 0.235 0.05 1.00 0.080 m2
P3 5.000 0.235 0.05 1.00 0.059 m2
m2
m2
m2

Jumlah total 0.30 m2


SKETSA

5. Pekerjaan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

J1 2.880 0.080 2.00 12.00 5.530 m2


J2 2.880 0.080 2.00 2.00 0.922 m2

P1 2.100 0.900 2.00 2.00 7.560 m2


P2 2.100 0.800 2.00 1.00 3.360 m2
P3 2.100 0.700 2.00 1.00 2.940 m2

Jumlah total 20.31 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 51.04 0.30 15.312

Jumlah total 15.31 m2


SKETSA

Meja beton

1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL - 0.30 - -

Jumlah total - m2
SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG BIMBINGAN KONSELING BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 10,500,000.00


B. PEMBANGUNAN FISIK 1 (RUANG) Rp 356,061,745.78
I. PEKERJAAN TANAH Rp 15,799,130.48
II. PEKERJAAN PASANGAN BATU & BETON Rp 95,162,304.75
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 56,368,261.44
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 27,032,226.00
V. PEKERJAAN KERAMIK Rp 25,355,876.10
VI. PEKERJAAN KACA Rp 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 104,623,149.11
VIII. PEKERJAAN LISTRIK Rp 7,333,417.00
IX. PEKERJAAN PENGECATAN Rp 21,162,039.15

C. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 20,195,080.00

D. Jumlah Rp 386,756,825.78
E. PPn 11% Rp 42,543,250.84
F. Total (D + E) Rp 429,300,076.62
PEMBULATAN Rp 429,300,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG BIMBINGAN KONSELING BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.00 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.00 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.00 1,200,000.00 1,200,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.00 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.00 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.00 750,000.00 750,000.00
Jumlah - A.1 10,500,000.00
B. PEMBANGUNAN FISIK 1 (RUANG)
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 33.08 106,400.00 3,519,180.00
2 Pek. Urugan tanah kembali M3 6.58 78,400.00 515,480.00
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 20.40 576,800.00 11,764,470.48
Jumlah - A.1 15,799,130.48
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu kali ad. 1:5 M3 16.03 1,695,036.00 27,173,545.88
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 164.14 248,192.00 40,737,324.76
3 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm (150 kg/m3) M3 1.22 6,793,558.00 8,254,172.97
- Beton Kolom 15/20 cm (150 kg/m3) M3 0.38 7,255,250.00 2,758,155.84
- Beton Kolom 15/15 cm, (teras depan) (150 kg/m3) M3 0.30 7,255,250.00 2,176,575.00
- Beton Ring Balok 15/20 cm (150 kg/m3) M3 1.22 7,271,512.00 8,834,887.08
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.16 7,271,512.00 1,130,865.55
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.11 1,937,927.00 4,096,777.68
Jumlah - A.2 95,162,304.75
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 328.27 104,882.00 34,429,893.76
2 Pek. Plesteran kolom ad. 1 : 4 M2 16.10 104,882.00 1,689,019.73
3 Pek. Acian dinding dan kolom M2 344.38 58,800.00 20,249,347.96
Jumlah - A.3 56,368,261.44
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.45 15,526,560.00 6,917,082.48
2 Daun Pintu Panel, kayu kls. I M2 6.93 1,119,104.00 7,755,390.72
3 Daun Jendela kaca kayu kla I M2 8.40 813,142.00 6,830,392.80
6 Engsel pintu 4" Bh 8.00 80,735.00 645,880.00
7 Engsel jendela Bh 8.00 58,856.00 470,848.00
8 Grendel jendela Bh 14.00 46,508.00 651,112.00
9 Kunci tanam Bh 4.00 395,304.00 1,581,216.00
10 Kait Angin Bh 28.00 77,868.00 2,180,304.00
Jumlah - A.4 27,032,226.00
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 63.13 365,750.00 23,090,090.10
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 6.00 377,631.00 2,265,786.00
Jumlah - A.5 25,355,876.10
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 5.54 247,783.00 1,372,321.37
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 7.48 247,783.00 1,853,020.39
Jumlah - A.6 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Kuda-kuda kayu Kls I Uk. 6/12 M2 1.03 14,014,784.00 14,449,242.30
2 Pek. Rangka Gording kayu Kls II uk. 5/10 M2 1.18 11,320,680.00 13,358,402.40
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 141.24 139,753.00 19,738,755.65
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 38.82 278,913.00 10,827,402.66
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 51.04 101,024.00 5,156,264.96
6 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 105.13 222,101.00 23,349,655.81
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 105.13 117,009.00 12,301,249.78
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 121.27 44,878.00 5,442,175.55
Jumlah - A.7 104,623,149.11
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 10.00 499,632.00 4,996,320.00
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 5.00 81,760.00 408,800.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 2.00 85,120.00 170,240.00
7 Pas. Box MCB 4 grup (tutup transparan + MCB 6A 2buh) Unit 1.00 250,000.00 250,000.00
Jumlah - A.8 7,333,417.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 360.40 40,504.00 14,597,668.58
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 105.13 39,675.00 4,171,064.49
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 21.10 41,966.00 885,650.46
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 0.30 41,966.00 12,692.41
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 20.31 41,966.00 852,379.82
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 15.31 41,966.00 642,583.39
Jumlah - A.9 21,162,039.15
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Kerja (M-07) (M-07) set 3.00 3,790,000.00 11,370,000.00
2 Kursi Kerja Staf (K-08C) (K-08C) set 3.00 1,170,000.00 3,510,000.00
3 Kursi Hadap (K-09B) (K-0B) unit 3.00 808,360.00 2,425,080.00
4 Lemari Simpan Pintu Solid (L-11) (L-11) Unit 1.00 2,230,000.00 2,230,000.00
5 Papan Presensi (P-04) (P-04) Bh 1.00 660,000 660,000.00
JUMLAH - B 20,195,080.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 10,500,000.00

B. PEMBANGUNAN FISIK 1 (RUANG) Rp. 356,061,745.78


I. PEKERJAAN TANAH Rp. 15,799,130.48
II. PEKERJAAN PASANGAN BATU & BETON Rp. 95,162,304.75
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 56,368,261.44
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 27,032,226.00
V. PEKERJAAN KERAMIK Rp. 25,355,876.10
VI. PEKERJAAN KACA Rp. 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 104,623,149.11
VIII. PEKERJAAN LISTRIK Rp. 7,333,417.00
IX. PEKERJAAN PENGECATAN Rp. 21,162,039.15
X. PEKERJAAN SANITAIR Rp. -
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp. -
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 20,195,080.00
JUMLAH Rp. 386,756,825.78
PEMBULATAN Rp 386,756,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN RUANG BIMBINGAN KONSELING BESERTA PERABOTNYA
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 67.50 0.70 0.70 33.08 m3

Jumlah total 33.08 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.49 0.40 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 33.08 26.50 - - 6.58 m3

Jumlah total 6.58 m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 2.88 1.88 0.15 0.81 m3


Lantai selasar 56.00 0.75 0.15 6.30 m3
Lantai ruang tamu 5.38 2.88 0.20 3.10 m3
Lantai ruang Rawat Putri 3.88 2.88 0.20 2.23 m3
Lantai ruang Rawat Putra 3.88 2.88 0.20 2.23 m3
Lantai ruang Periksa 4.00 3.00 0.20 2.40 m3
Lantai ruang Hall 2.88 1.38 0.20 0.79 m3
Lantai ruang Dokter 2.88 2.38 0.20 1.37 m3
Lantai WC/KM 2.38 1.38 0.15 0.49 m3
Lantai Pentry 2.38 1.38 0.20 0.66 m3
Jumlah total 20 m3
SKETSA

5. Pekerjaan urug pasir bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 2.88 1.88 0.05 0.27 m3


Lantai selasar 56.00 0.75 0.05 2.10 m3
Lantai ruang tamu 5.38 2.88 0.05 0.77 m3
Lantai ruang Rawat Putri 3.88 2.88 0.05 0.56 m3
Lantai ruang Rawat Putra 3.88 2.88 0.05 0.56 m3
Lantai ruang Periksa 4.00 3.00 0.20 2.40 m3
Lantai ruang Hall 2.88 1.38 0.05 0.20 m3
Lantai ruang Dokter 2.88 2.38 0.05 0.34 m3
Lantai WC/KM 2.38 1.38 0.05 0.16 m3
Lantai Pentry 2.38 1.38 0.05 0.16 m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 67.50 0.70 0.05 2.36 m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 67.50 0.70 0.15 7.09 m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 67.50 0.25 0.70 0.50 16.03 m3

Jumlah total 16.03 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 45.76 0.45 - 20.59 m2

Jumlah total 20.59 m2


SKETSA
4. Pekerjaan pasangan dinding batu bata semen
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 8.64 3.30 2.59 7.97 7.87 m2
Dinding Belakang 8.52 3.30 6.65 21.47 m2
Dinding Samping kiri 7.76 3.30 - - 25.61 m2
Dinding Samping Kanan 7.76 3.30 2.33 - 23.28 m2
Dinding pembagi ruangan 26.66 3.30 6.38 - 81.60 m2
Dinding atas Latei 8.64 0.50 4.32 m2

Jumlah total 164.14 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 15/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 8.00 0.38 m3

Jumlah total 0.380 m3


- Pekerjaan Kolom 15/15 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 2.00 0.10 m3

Jumlah total 0.095 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.30 10.00 0.33 m3

Jumlah total 0.330 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 67.50 0.12 0.15 1.00 1.22 m3

Jumlah total 1.215 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3


Jumlah total - m3
- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 67.50 0.12 0.15 1.00 1.22 m3

Jumlah total 1.215 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 8.64 0.12 0.15 1.00 0.16 m3

Jumlah total 0.156 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Rumus Luas Pas. Bata Luas Lubangan Volume Satuan

V = (Luas pas Batu - Luas


lubangan Pintu Jendela) x 2 164 328

Jumlah total x 2 sisi 328.27 m2


SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah
Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2
Plesteran Kolom teras 0.60 3.30 2.00 3.96 m2

Jumlah total 16.104 m2

3. Pekerjaan Acian dinding


Rumus Volume Satuan

V = Luas plesteran dinding + Luas Pleteran Kolom 344.38 m2

Jumlah total x 2 sisi 344.38 m2


SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 2.00 3.96 m2

Jumlah total 16.104 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

JV1 9.690 0.110 0.05 4.00 0.213 m3


JV2 8.250 0.110 0.05 2.00 0.091 m3
P1 6.980 0.110 0.05 2.00 0.077 m3
P2 6.780 0.110 0.05 1.00 0.037 m3
P3 5.000 0.110 0.05 1.00 0.028 m3

Jumlah total 0.45 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

P1 0.900 2.100 - 2.00 3.780 m2


P2 0.800 2.100 - 1.00 1.680 m2
P3 0.700 2.100 - 1.00 1.470 m2

Jumlah total 6.93 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

JV1 1.000 0.600 - 12.00 7.200 m2


JV2 1.000 0.600 - 2.00 1.200 m2

Jumlah total 8.40 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

P1 2.00 2.00 4.00 Buah


P2 1.00 2.00 2.00 Buah
P3 1.00 2.00 2.00 Buah

Jumlah total 8.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan

P1 2.00 2.00 4.00


P2 1.00 2.00 2.00 Buah
P3 1.00 2.00 2.00 Buah

Jumlah total 8.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan

P1 2.00 1.00 2.00


P2 1.00 1.00 1.00 Buah
P3 1.00 1.00 1.00 Buah

Jumlah total 4.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

JV1 12.00 1.00 12.00 Buah


JV2 2.00 1.00 2.00 Buah

Jumlah total 14.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1
P1 2.00 1.00 2.00 Buah
P2 1.00 1.00 1.00 Buah
P3 1.00 1.00 1.00 Buah

Jumlah total 4.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan

JV1 12.00 2.00 24.00 Buah


JV2 2.00 2.00 4.00 Buah

Jumlah total 28.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai ruang tamu 5.38 2.88 - 15.49 m3


Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 63.13 m2


SKETSA

2. Pekerjaan keramik lantai teras 60/60 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 2.00 3.00 - 6.00 m2

Jumlah total 6.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL
Lantai WC/KM 2.38 1.38 - 3.28 m3

m2

Jumlah total 3.28 m2


SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Keramik dinding WC/KM

Sekmen I 2.38 1.50 1.00 1.85 m2


Sekmen II 2.38 1.50 1.00 3.57 m2
Sekmen III 1.38 1.50 1.00 2.07 m2
Sekmen IV 1.38 1.50 1.00 2.07 m2

Jumlah total x 4 ruang 9.56 m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

J1 0.86 0.46 12.00 4.75 m2


J2 0.86 0.46 2.00 0.79 m2

Jumlah total 5.538 m2

Kaca Mati
Rumus Panjang Lebar Jumlah Volume Satuan

J1 0.86 0.48 12.00 4.95 m2


J2 0.86 0.48 2.00 0.83 m2

p1 0.88 0.48 2.00 0.84 m2


p2 0.78 0.48 1.00 0.37 m2

V1 0.60 0.40 2.00 0.48

Jumlah total 7.478 m2


VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND
1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2

Jumlah total 141.240 m2


SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2
Jumlah total 141.240 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 38.82 M'

Jumlah total x 2 sisi 38.82 M'


SKETSA
4. Pasang Lisplank GRC/ Calsiboard
Rumus Volume Satuan

V = panjang Nok 51.04 M'

Jumlah total x 2 sisi 51.04 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 - - 56.00 m2


Lantai ruang tamu 16.52 - - 16.52 m2
Lantai ruang Rawat Putri 10.93 - - 10.93 m2
Lantai ruang Rawat Putra 10.93 - - 10.93 m2
Lantai ruang Periksa 7.00 - - 7.00 m2
Lantai ruang Hall 9.37 - - 9.37 m2
Lantai ruang Dokter 10.52 - - 10.52 m2
Lantai Pentry - - - m2

Jumlah total 121.27 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 36 Titik
Pas. Lampu down ligth LED 18 watt 11.00 bh
Pas. Lampu down ligth LED 11 watt 15.00 bh
Pas. Stop kontak panasonic 10.00 bh
Pas. saklar ganda panasonic 4.00 bh
Pas. saklar ganda panasonic 6.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Acian
Rumus Volume Satuan
Dinding Kolom

V = Vol Acian dinding + Acian Kolom 344.38 16.10 360.48 m2

Jumlah total 360.48 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 113.50 0.10 1.00 11.35 m2


Lantai ruang tamu 16.52 0.10 1.00 1.65 m2
Lantai ruang Rawat Putri 13.52 0.10 1.00 1.35 m2
Lantai ruang Rawat Putra 13.52 0.10 1.00 1.35 m2
Lantai ruang Periksa 7.00 0.10 1.00 0.70 m2
Lantai ruang Hall 8.52 0.10 4.00 3.41 m2
Lantai ruang Dokter 10.52 0.10 1.00 1.05 m2
Lantai Pentry 2.38 0.10 1.00 0.24 m2

Jumlah total 21.10 m2


SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

JV1 9.690 0.235 0.05 4.00 0.455


JV2 8.250 0.235 0.05 2.00 0.194
P1 6.980 0.235 0.05 2.00 0.164 m2
P2 6.780 0.235 0.05 1.00 0.080 m2
P3 5.000 0.235 0.05 1.00 0.059 m2
m2
m2
m2

Jumlah total 0.30 m2


SKETSA

5. Pekerjaan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

J1 2.880 0.080 2.00 12.00 5.530 m2


J2 2.880 0.080 2.00 2.00 0.922 m2

P1 2.100 0.900 2.00 2.00 7.560 m2


P2 2.100 0.800 2.00 1.00 3.360 m2
P3 2.100 0.700 2.00 1.00 2.940 m2

Jumlah total 20.31 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 51.04 0.30 15.312

Jumlah total 15.31 m2


SKETSA

Meja beton

1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL - 0.30 - -

Jumlah total - m2
SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG OSIS BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 10,500,000.00


B. PEMBANGUNAN FISIK 1 (RUANG) Rp 346,505,678.70
I. PEKERJAAN TANAH Rp 17,053,904.00
II. PEKERJAAN PASANGAN BATU & BETON Rp 86,873,652.89
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 47,768,954.88
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 26,343,883.68
V. PEKERJAAN KERAMIK Rp 31,752,480.50
VI. PEKERJAAN KACA Rp 3,320,292.20
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 107,560,149.42
VIII. PEKERJAAN LISTRIK Rp 7,914,809.00
IX. PEKERJAAN PENGECATAN Rp 17,917,552.13

C. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 29,751,300.00

D. Jumlah Rp 386,756,978.70
E. PPn 11% Rp 42,543,267.66
F. Total (D + E) Rp 429,300,246.35
PEMBULATAN Rp 429,300,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG OSIS BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 1,200,000.00 1,200,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 10,500,000.00
B. PEMBANGUNAN FISIK 1 (RUANG)
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 32.830 106,400.00 3,493,112.00
2 Pek. Urugan tanah kembali M3 6.330 78,400.00 496,272.00
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 22.650 576,800.00 13,064,520.00
Jumlah - A.1 17,053,904.00
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu kali ad. 1:5 M3 15.910 1,695,036.00 26,968,022.76
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 135.870 248,192.00 33,721,847.04
3 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm (150 kg/m3) M3 1.200 6,793,558.00 8,152,269.60
- Beton Kolom 15/20 cm (150 kg/m3) M3 0.380 7,255,250.00 2,758,155.84
- Beton Kolom 15/15 cm, (teras depan) (150 kg/m3) M3 0.300 7,255,250.00 2,176,575.00
- Beton Ring Balok 15/20 cm (150 kg/m3) M3 1.200 7,271,512.00 8,725,814.40
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.220 7,271,512.00 1,599,732.64
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 1.430 1,937,927.00 2,771,235.61
Jumlah - A.2 86,873,652.89
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 271.740 104,882.00 28,500,634.68
2 Pek. Plesteran kolom ad. 1 : 4 M2 20.100 104,882.00 2,108,128.20
3 Pek. Acian dinding dan kolom M2 291.840 58,800.00 17,160,192.00
Jumlah - A.3 47,768,954.88
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.400 15,526,560.00 6,210,624.00
2 Daun Pintu Panel, kayu kls. I M2 5.670 1,119,104.00 6,345,319.68
3 Daun Jendela kaca kayu kla I M2 9.000 813,142.00 7,318,278.00
6 Engsel pintu 4" Bh 6.000 80,735.00 484,410.00
7 Engsel jendela Bh 30.000 58,856.00 1,765,680.00
8 Grendel jendela Bh 15.000 46,508.00 697,620.00
9 Kunci tanam Bh 3.000 395,304.00 1,185,912.00
10 Kait Angin Bh 30.000 77,868.00 2,336,040.00
Jumlah - A.4 26,343,883.68
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 68.230 365,750.00 24,955,122.50
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 18.000 377,631.00 6,797,358.00
Jumlah - A.5 31,752,480.50
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 5.940 247,783.00 1,471,831.02
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 7.460 247,783.00 1,848,461.18
Jumlah - A.6 3,320,292.20
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Kuda-kuda kayu Kls I Uk. 6/12 M2 1.200 14,014,784.00 16,817,740.80
2 Pek. Rangka Gording kayu Kls II uk. 5/10 M2 1.320 11,320,680.00 14,943,297.60
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 137.260 139,753.00 19,182,496.78
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 23.080 278,913.00 6,437,312.04
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 44.640 101,024.00 4,509,711.36
6 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 117.460 222,101.00 26,087,983.46
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 117.460 117,009.00 13,743,877.14
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 130.080 44,878.00 5,837,730.24
Jumlah - A.7 107,560,149.42
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 11.000 499,632.00 5,495,952.00
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.000 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.000 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 6.000 81,760.00 490,560.00
5 Pas. Saklar ganda broco BH 2.000 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 2.000 85,120.00 170,240.00
7 Pas. Box MCB 4 grup (tutup transparan + MCB 6A 2buh) Unit 1.000 250,000.00 250,000.00
Jumlah - A.8 7,914,809.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 242.600 40,504.00 9,826,270.40
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 117.460 39,675.00 4,660,225.50
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 13.008 41,966.00 545,893.73
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 37.100 41,966.00 1,556,938.60
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 18.250 41,966.00 765,879.50
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 13.400 41,966.00 562,344.40
Jumlah - A.9 17,917,552.13
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Siswa Ganda (M-02) (M-02) ganda set 6.000 1,098,300.00 6,589,800.00
2 Kursi Guru & Siswa (K-02), bahan ; kayu kls 1 pakai sandaran (K-02) set 15.000 720,100.00 10,801,500.00
3 Papan Tulis Putih uk. 120 x 240 cm (P-03) (P-03) unit 3.000 1,890,000.00 5,670,000.00
4 Lemari Simpan Pintu Solid (L-11) (L-11) Unit 3.000 2,230,000.00 6,690,000.00

JUMLAH - B 29,751,300.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 10,500,000.00

B. PEMBANGUNAN FISIK 1 (RUANG) Rp. 346,505,678.70


I. PEKERJAAN TANAH Rp. 17,053,904.00
II. PEKERJAAN PASANGAN BATU & BETON Rp. 86,873,652.89
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 47,768,954.88
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 26,343,883.68
V. PEKERJAAN KERAMIK Rp. 31,752,480.50
VI. PEKERJAAN KACA Rp. 3,320,292.20
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 107,560,149.42
VIII. PEKERJAAN LISTRIK Rp. 7,914,809.00
IX. PEKERJAAN PENGECATAN Rp. 17,917,552.13
X. PEKERJAAN SANITAIR Rp. -
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp. -
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 29,751,300.00
JUMLAH Rp. 386,756,978.70
PEMBULATAN Rp 386,756,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 67.00 0.70 0.70 32.83 m3

Jumlah total 32.83 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.49 0.40 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 32.83 15.91 - - 16.92 m3

Jumlah total 16.92 m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 8.88 1.88 0.20 3.34 m3


Lantai selasar 38.00 0.75 0.20 5.70 m3
Ruang Osis 7.88 2.88 0.20 4.54 m3
Ruang Pramuka 7.88 2.88 0.20 4.54 m3
Ruang PMR 7.88 2.88 0.20 4.54 m3
Jumlah total 23 m3
SKETSA

5. Pekerjaan urug pasir bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 8.88 1.88 0.05 0.83 m3


Lantai selasar 38.00 0.75 0.05 1.43 m3
Ruang Osis 7.88 2.88 0.05 1.13 m3
Ruang Pramuka 7.88 2.88 0.05 1.13 m3
Ruang PMR 7.88 2.88 0.05 1.13 m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 67.00 0.70 0.05 2.35 m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 67.00 0.70 0.15 7.04 m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 67.00 0.25 0.70 0.50 15.91 m3

Jumlah total 15.91 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 45.76 0.45 - 20.59 m2

Jumlah total 20.59 m2


SKETSA
4. Pekerjaan pasangan dinding batu bata semen
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 8.64 3.30 7.77 11.98 8.76 m2
Dinding Belakang 8.64 3.30 8.95 19.56 m2
Dinding Samping kiri 7.76 3.30 - - 25.61 m2
Dinding Samping Kanan 7.76 3.30 - - 25.61 m2
Dinding pembagi ruangan 15.76 3.30 - - 52.01 m2
Dinding atas Latei 8.64 0.50 4.32 m2

Jumlah total 135.87 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 15/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 8.00 0.38 m3

Jumlah total 0.380 m3


- Pekerjaan Kolom 15/15 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 4.00 0.19 m3

Jumlah total 0.190 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.30 4.00 0.13 m3

Jumlah total 0.132 m3

- Pekerjaan Sloof 15/20


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 67.00 0.12 0.15 1.00 1.21 m3

Jumlah total 1.206 m3


- Pekerjaan Balok 15/20
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 67.00 0.12 0.15 1.00 1.21 m3

Jumlah total 1.206 m3


- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 12.40 0.12 0.15 1.00 0.22 m3


Jumlah total 0.223 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 38.00 0.75 0.05 1.00 1.43 m3

Jumlah total 1.425 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Rumus Luas Pas. Bata Luas Lubangan Volume Satuan

V = (Luas pas Batu - Luas


lubangan Pintu Jendela) x 2 136 272

Jumlah total x 2 sisi 271.74 m2


SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 4.00 7.92 m2

Jumlah total 20.064 m2

3. Pekerjaan Acian dinding


Rumus Volume Satuan

V = Luas plesteran dinding + Luas Pleteran Kolom 291.80 m2

Jumlah total x 2 sisi 291.80 m2


SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan
V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 4.00 7.92 m2

Jumlah total 20.064 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar tebal jumlah Volume Satuan

V=PxLxT

JV1 9.690 0.110 0.05 3.00 0.160 m3


JV2 8.250 0.110 0.05 3.00 0.136 m3
P1 6.980 0.110 0.05 3.00 0.115 m3

Jumlah total 0.41 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

P1 0.900 2.100 - 3.00 5.670 m2


P2 0.000 0.000 - 1.00 - m2
P3 0.000 0.000 - 1.00 - m2

Jumlah total 5.67 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

JV1 1.000 0.600 - 6.00 3.600 m2


JV2 1.000 0.600 - 9.00 5.400 m2

Jumlah total 9.00 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

P1 2.00 3.00 6.00 Buah


P2 - - - Buah
P3 - - - Buah
Jumlah total 6.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan

J1 6.00 2.00 12.00


J2 9.00 2.00 18.00 Buah
Buah

Jumlah total 30.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan

P1 3.00 1.00 3.00


Buah
Buah

Jumlah total 3.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

JV1 6.00 1.00 6.00 Buah


JV2 9.00 1.00 9.00 Buah

Jumlah total 15.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

P1 3.00 1.00 3.00 Buah


P2 Buah
P3 Buah

Jumlah total 3.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan

JV1 6.00 2.00 12.00 Buah


JV2 9.00 2.00 18.00 Buah

Jumlah total 30.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL
Ruang Pramuka 7.88 2.88 - 22.69 m3
Ruang Osis 7.88 2.88 - 22.69 m3
Ruang PMR 7.88 2.88 - 22.69 m3

Jumlah total 68.08 m2


SKETSA

2. Pekerjaan keramik lantai teras 60/60 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 9.00 2.00 - 18.00 m2

Jumlah total 18.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Lantai WC/KM m3

m2

Jumlah total - m2
SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Keramik dinding WC/KM

Sekmen I m2
Sekmen II m2
Sekmen III m2
Sekmen IV m2

Jumlah total x 4 ruang - m2


SKETSA
VII. PEKERJAAN KACA
1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

J1 0.86 0.46 6.00 2.37 m2


J2 0.86 0.46 9.00 3.56 m2

Jumlah total 5.934 m2

Kaca Mati
Rumus Panjang Lebar Jumlah Volume Satuan

J1 0.86 0.48 6.00 2.48 m2


J2 0.86 0.48 9.00 3.72 m2

p1 0.88 0.48 3.00 1.27 m2

Jumlah total 7.459 m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2
Jumlah total 141.240 m2
SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 1.00 11.00 7.49 1.00 44.94 m2

Sekmen II
v = 1/2 (a+b) x t 1.00 11.00 5.77 1.00 34.62 m2

Sekmen III
v = 1/2 (a) x t 10.00 5.77 2.00 57.70 m2

Jumlah total 137.260 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 23.08 M'

Jumlah total x 2 sisi 23.08 M'


SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus Volume Satuan

V = panjang Nok 44.64 M'

Jumlah total x 2 sisi 44.64 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Selasar 38.00 0.75 - 28.50 m3


Ruang Pramuka 7.88 2.88 - 22.69 m3
Ruang Osis 7.88 2.88 - 22.69 m3
Ruang PMR 7.88 2.88 - 22.69 m3
TERAS 8.88 2.40 21.31
Jumlah total 117.90 m2
SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Selasar 38.00 0.75 - 28.50 m3


Ruang Pramuka 7.88 2.88 - 22.69 m3
Ruang Osis 7.88 2.88 - 22.69 m3
Ruang PMR 7.88 2.88 - 22.69 m3
TERAS 8.70 2.40 20.88 m3
m3
m3
m3

Jumlah total 117.46 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

Selasar 46.00 1.00 46.00 m2


Ruang Pramuka 21.52 1.00 21.52 m2
Ruang Osis 21.52 1.00 21.52 m2
Ruang PMR 21.52 1.00 21.52 m2
TERAS 19.52 1.00 19.52 m2
m2
m2
m2

Jumlah total 130.08 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 11 Titik
Pas. Lampu down ligth LED 18 watt 6.00 bh
Pas. Lampu down ligth LED 11 watt 2.00 bh
Pas. Stop kontak panasonic 3.00 bh
Pas. saklar tunggal panasonic - bh
Pas. saklar ganda panasonic 3.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


4. Pekerjaan pasangan dinding batu bata semen
Luas
Rumus Labar Tinggi Volume Satuan
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 8.64 3.00 7.77 11.98 6.17 m2
Dinding Belakang 8.64 3.00 8.95 16.97 m2
Dinding Samping kiri 7.76 3.00 - - 23.28 m2
Dinding Samping Kanan 7.76 3.00 - - 23.28 m2
Dinding pembagi ruangan 15.76 3.00 - - 47.28 m2
Dinding atas Latei 8.64 0.50 4.32 m2

Jumlah total 242.60 m2


2. Pekerjaan Pengecatan Plafond
Rumus Panjang Lebar jml ruang Volume Satuan

m3
m3
V= luas plafond 117.46 m3
m3
m3
m3
m3
m3

Jumlah total 117.46 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

m2
m2
m2
Panjang list x lebar 130.08 0.10 13.01 m2
m2
m2
m2
m2

Jumlah total 13.01 m2


SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

JV1 9.690 0.235 - 9.00 20.494


JV2 8.250 0.235 - 6.00 11.633
P1 6.980 0.235 - 3.00 4.921 m2

m2
m2
m2
Jumlah total 37.05 m2
SKETSA

5. Pekerjaan pengecatan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

J1 2.880 0.080 2.00 9.00 4.147 m2


J2 2.880 0.080 2.00 6.00 2.765 m2

P1 2.100 0.900 2.00 3.00 11.340 m2


m2
m2

Jumlah total 18.25 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 44.64 0.30 13.392

Jumlah total 13.39 m2


SKETSA

Meja beton

1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL - 0.30 - -

Jumlah total - m2
SKETSA
X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KOMPUTER BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 10,500,000.00


B. PEMBANGUNAN FISIK 1 (RUANG) Rp 339,581,999.96
I. PEKERJAAN TANAH Rp 16,098,451.94
II. PEKERJAAN PASANGAN BATU & BETON Rp 69,972,161.62
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 32,651,088.94
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 21,923,938.33
V. PEKERJAAN KERAMIK Rp 32,390,494.80
VI. PEKERJAAN KACA Rp 3,719,222.83
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 114,429,257.90
VIII. PEKERJAAN LISTRIK Rp 9,570,505.00
IX. PEKERJAAN PENGECATAN Rp 14,945,278.59
X. PEKERJAAN SANITAIR Rp 14,701,600.00
XI. PEKERJAAN TERALIS PENGAMAN Rp 9,180,000.00

C. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 36,674,900.00

D. Jumlah Rp 386,756,899.96
E. PPn 11% Rp 42,543,259.00
F. Total (D + E) Rp 429,300,158.95
PEMBULATAN Rp 429,300,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KOMPUTER BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.00 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.00 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.00 1,200,000.00 1,200,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.00 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.00 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.00 750,000.00 750,000.00
Jumlah - A.1 10,500,000.00
B. PEMBANGUNAN FISIK 1 (RUANG)
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 23.03 106,400.00 2,450,392.00
2 Pek. Urugan tanah kembali M3 7.40 78,400.00 580,356.00
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 22.66 576,800.00 13,067,703.94
Jumlah - B.1 16,098,451.94
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu kali ad. 1:5 M3 15.63 1,695,036.00 26,489,175.09
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 89.71 248,192.00 22,264,659.02
3 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm (150 kg/m3) M3 0.85 6,793,558.00 5,747,350.07
- Beton Kolom 15/20 cm (150 kg/m3) M3 0.38 7,255,250.00 2,758,155.84
- Beton Kolom 15/15 cm, (teras depan) (150 kg/m3) M3 0.30 7,255,250.00 2,176,575.00
- Beton Ring Balok 15/20 cm (150 kg/m3) M3 0.85 7,271,512.00 6,151,699.15
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.22 7,271,512.00 1,623,001.48
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 1.43 1,937,927.00 2,761,545.98
Jumlah - B.2 69,972,161.62
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 179.41 104,882.00 18,817,383.05
2 Pek. Plesteran kolom ad. 1 : 4 M2 20.06 104,882.00 2,104,352.45
3 Pek. Acian dinding dan kolom M2 199.48 58,800.00 11,729,353.44
Jumlah - B.3 32,651,088.94
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.35 15,526,560.00 5,438,022.37
2 Daun Pintu Panel, kayu kls. I M2 1.89 1,119,104.00 2,115,106.56
3 Daun Jendela kaca kayu kla I M2 10.20 813,142.00 8,294,048.40
6 Engsel pintu 4" Bh 3.00 80,735.00 242,205.00
7 Engsel jendela Bh 34.00 58,856.00 2,001,104.00
8 Grendel jendela Bh 17.00 46,508.00 790,636.00
9 Kunci tanam Bh 1.00 395,304.00 395,304.00
10 Kait Angin Bh 34.00 77,868.00 2,647,512.00
Jumlah - B.4 21,923,938.33
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 69.97 365,750.00 25,593,136.80
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 18.00 377,631.00 6,797,358.00
Jumlah - B.5 32,390,494.80
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 6.73 247,783.00 1,666,390.23
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 8.28 247,783.00 2,052,832.60
Jumlah - B.6 3,719,222.83
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Kuda-kuda kayu Kls I Uk. 6/12 M2 1.25 14,014,784.00 17,518,480.00
2 Pek. Rangka Gording kayu Kls II uk. 5/10 M2 1.30 11,320,680.00 14,716,884.00
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 152.00 139,753.00 21,242,456.00
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 38.82 278,913.00 10,827,402.66
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 46.00 101,024.00 4,647,104.00
6 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 119.79 222,101.00 26,604,679.23
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 111.40 117,009.00 13,034,521.78
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 130.08 44,878.00 5,837,730.24
Jumlah -B.7 114,429,257.90
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 14.00 499,632.00 6,994,848.00
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 10.00 81,760.00 817,600.00
5 Pas. Saklar ganda broco BH 1.00 85,120.00 85,120.00
6 Pas. Saklar tunggal broco BH 1.00 85,120.00 85,120.00
7 Pas. Box MCB 4 grup (tutup transparan + MCB 6A 2buh) Unit 1.00 250,000.00 250,000.00
Jumlah - B.8 9,570,505.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 166.29 40,504.00 6,735,604.58
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 119.79 39,675.00 4,752,525.42
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 13.28 41,966.00 557,308.48
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 37.05 41,966.00 1,554,745.88
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 18.25 41,966.00 765,963.43
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 13.80 41,966.00 579,130.80
Jumlah - B.9 14,945,278.59
X. PEKERJAAN SANITAIR
1 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 46.00 319,600.00 14,701,600.00
Jumlah - B.10 14,701,600.00
XI. PEKERJAAN TERALIS PENGAMAN
Pek. Teralis pengaman jendela (bahan besi kotak) Bh 17.00 540,000.00 9,180,000.00
Jumlah - B.11 9,180,000.00
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Siswa Ganda (M-02) (M-02) Bh 6.00 574,100.00 3,444,600.00
2 Meja Komputer Server (M-02) (M-02) Bh 2.00 574,100.00 1,148,200.00
3 Kursi Siswa (K-02) (K-02) Bh 20.00 720,100.00 14,402,000.00
4 Meja Laboran (M-01) (M-01) Bh 2.00 2,808,800.00 5,617,600.00
5 Kursi Laboran (K-01) (K-01) Bh 2.00 852,600.00 1,705,200.00
6 Papan Tulis (White Board P-01) (P-01) Bh 1.00 1,870,700.00 1,870,700.00
7 Lemari Penyimpanan (L-01) (L-01) Bh 2.00 4,243,300.00 8,486,600.00

JUMLAH - C 36,674,900.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 10,500,000.00

B. PEMBANGUNAN FISIK 1 (RUANG) Rp. 330,401,999.96


I. PEKERJAAN TANAH Rp. 16,098,451.94
II. PEKERJAAN PASANGAN BATU & BETON Rp. 69,972,161.62
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 32,651,088.94
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 21,923,938.33
V. PEKERJAAN KERAMIK Rp. 32,390,494.80
VI. PEKERJAAN KACA Rp. 3,719,222.83
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 114,429,257.90
VIII. PEKERJAAN LISTRIK Rp. 9,570,505.00
IX. PEKERJAAN PENGECATAN Rp. 14,945,278.59
X. PEKERJAAN SANITAIR Rp. 14,701,600.00
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp. -
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 36,674,900.00
JUMLAH Rp. 377,576,899.96
PEMBULATAN Rp 377,576,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 47.00 0.70 0.70 23.03 m3

Jumlah total 23.03 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.49 0.40 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 23.03 15.63 - - 7.40 m3

Jumlah total 7.40 m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 8.88 1.88 0.20 3.34 m3


Lantai selasar 38.00 0.75 0.20 5.70 m3
Ruang Osis 7.88 2.88 0.20 4.54 m3
Ruang Pramuka 7.88 2.88 0.20 4.54 m3
Ruang PMR 7.88 2.88 0.20 4.54 m3
Jumlah total 23 m3
SKETSA

5. Pekerjaan urug pasir bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 8.88 1.88 0.05 0.83 m3


Lantai selasar 38.00 0.75 0.05 1.43 m3
Ruang Osis 7.88 2.88 0.05 1.13 m3
Ruang Pramuka 7.88 2.88 0.05 1.13 m3
Ruang PMR 7.88 2.88 0.05 1.13 m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 47.00 0.70 0.05 1.65 m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 47.00 0.70 0.15 4.94 m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 47.00 0.25 0.70 0.70 15.63 m3

Jumlah total 15.63 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 45.76 0.45 - 20.59 m2

Jumlah total 20.59 m2


SKETSA
4. Pekerjaan pasangan dinding batu bata semen
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 8.64 3.30 2.59 6.99 18.93 m2
Dinding Belakang 8.64 3.30 8.95 19.56 m2
Dinding Samping kiri 7.76 3.30 - - 25.61 m2
Dinding Samping Kanan 7.76 3.30 - - 25.61 m2
Dinding pembagi ruangan - - - - - m2
Dinding atas Latei - m2

Jumlah total 89.71 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 15/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 8.00 0.38 m3

Jumlah total 0.380 m3


- Pekerjaan Kolom 15/15 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 4.00 0.19 m3

Jumlah total 0.190 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 4.00 0.19 m3

Jumlah total 0.190 m3

- Pekerjaan Sloof 15/20


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 47.00 0.12 0.15 1.00 0.85 m3

Jumlah total 0.846 m3


- Pekerjaan Balok 15/20
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 47.00 0.12 0.15 1.00 0.85 m3

Jumlah total 0.846 m3


- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 12.40 0.12 0.15 1.00 0.22 m3


Jumlah total 0.223 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 38.00 0.75 0.05 1.00 1.43 m3

Jumlah total 1.425 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Rumus Luas Pas. Bata Luas Lubangan Volume Satuan

V = (Luas pas Batu - Luas


lubangan Pintu Jendela) x 2 90 179

Jumlah total x 2 sisi 179.41 m2


SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 4.00 7.92 m2

Jumlah total 20.064 m2

3. Pekerjaan Acian dinding


Rumus Volume Satuan

V = Luas plesteran dinding + Luas Pleteran Kolom 199.48 m2

Jumlah total x 2 sisi 199.48 m2


SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan
V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 4.00 7.92 m2

Jumlah total 20.064 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

JV1 9.690 0.110 0.05 5.00 0.266 m3


JV2 8.250 0.110 0.05 1.00 0.045 m3
P1 6.980 0.110 0.05 1.00 0.038 m3
P2 0.000 0.110 0.05 1.00 - m3
P3 0.000 0.110 0.05 1.00 - m3

Jumlah total 0.35 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

P1 0.900 2.100 - 1.00 1.890 m2


P2 0.000 0.000 - 1.00 - m2
P3 0.000 0.000 - 1.00 - m2

Jumlah total 1.89 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

JV1 1.000 0.600 - 15.00 9.000 m2


JV2 1.000 0.600 - 2.00 1.200 m2

Jumlah total 10.20 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

P1 1.00 3.00 3.00 Buah


P2 - - - Buah
P3 - - - Buah
Jumlah total 3.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan

J1 15.00 2.00 30.00


J2 2.00 2.00 4.00 Buah
Buah

Jumlah total 34.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan

P1 1.00 1.00 1.00


Buah
Buah

Jumlah total 1.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

JV1 15.00 1.00 15.00 Buah


JV2 2.00 1.00 2.00 Buah

Jumlah total 17.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

P1 1.00 1.00 1.00 Buah


P2 Buah
P3 Buah

Jumlah total 1.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan

JV1 15.00 2.00 30.00 Buah


JV2 2.00 2.00 4.00 Buah

Jumlah total 34.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL
Ruang Pramuka 8.88 7.88 - 69.97 m3
Ruang Osis m3
Ruang PMR m3

Jumlah total 69.97 m2


SKETSA

2. Pekerjaan keramik lantai teras 60/60 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 9.00 2.00 - 18.00 m2

Jumlah total 18.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Lantai WC/KM m3

m2

Jumlah total - m2
SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Keramik dinding WC/KM

Sekmen I m2
Sekmen II m2
Sekmen III m2
Sekmen IV m2

Jumlah total x 4 ruang - m2


SKETSA
VII. PEKERJAAN KACA
1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

J1 0.86 0.46 15.00 5.93 m2


J2 0.86 0.46 2.00 0.79 m2

Jumlah total 6.725 m2

Kaca Mati
Rumus Panjang Lebar Jumlah Volume Satuan

J1 0.86 0.48 15.00 6.19 m2


J2 0.86 0.48 2.00 0.83 m2

p1 0.88 0.48 3.00 1.27 m2

Jumlah total 8.285 m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2
Jumlah total 141.240 m2
SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2
Jumlah total 141.240 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 38.82 M'

Jumlah total x 2 sisi 38.82 M'


SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus Volume Satuan

V = panjang Nok 46.00 M'

Jumlah total x 2 sisi 46.00 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Selasar 38.00 0.75 - 28.50 m3


Ruang lab 8.88 7.88 - 69.97 m3
m3
m3
TERAS 8.88 2.40 21.31
Jumlah total 119.79 m2
SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Selasar 38.00 0.75 - 28.50 m3


Ruang Pramuka 7.88 2.88 - 22.69 m3
Ruang Osis 7.88 2.88 - 22.69 m3
Ruang PMR 7.88 2.88 - 22.69 m3
TERAS 7.88 1.88 14.81 m3
m3
m3
m3

Jumlah total 111.40 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

Selasar 46.00 1.00 46.00 m2


Ruang Pramuka 21.52 1.00 21.52 m2
Ruang Osis 21.52 1.00 21.52 m2
Ruang PMR 21.52 1.00 21.52 m2
TERAS 19.52 1.00 19.52 m2
m2
m2
m2

Jumlah total 130.08 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 19 Titik
Pas. Lampu down ligth LED 18 watt 6.00 bh
Pas. Lampu down ligth LED 11 watt 3.00 bh
Pas. Stop kontak panasonic 10.00 bh
Pas. saklar tunggal panasonic 1.00 bh
Pas. saklar ganda panasonic 1.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela
V = L x T - (Luas pintu dan
jendela)
Dinding Depan 8.64 3.10 2.59 6.99 17.20 m2
Dinding Belakang 8.64 3.10 8.95 17.83 m2
Dinding Samping kiri 7.76 3.10 - - 24.06 m2
Dinding Samping Kanan 7.76 3.10 - - 24.06 m2
Dinding pembagi ruangan - - - - - m2
Dinding atas Latei - m2

Jumlah total 166.29 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

m3
m3
V= luas plafond 111.40 m3
m3
m3
m3
m3
m3

Jumlah total 111.40 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

m2
m2
m2
Panjang list x lebar 130.08 0.10 13.01 m2
m2
m2
m2
m2

Jumlah total 13.01 m2


SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

JV1 9.690 0.235 - 9.00 20.494


JV2 8.250 0.235 - 6.00 11.633
P1 6.980 0.235 - 3.00 4.921 m2

m2
m2
m2

Jumlah total 37.05 m2


SKETSA

5. Pekerjaan pengecatan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

J1 2.880 0.080 2.00 9.00 4.147 m2


J2 2.880 0.080 2.00 6.00 2.765 m2

P1 2.100 0.900 2.00 3.00 11.340 m2


m2
m2

Jumlah total 18.25 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 46.00 0.30 13.800

Jumlah total 13.80 m2


SKETSA

Meja beton

1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL - 0.30 - -

Jumlah total - m2
SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SEKOLAH BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 10,500,000.00


B. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 335,905,771.11
I. PEKERJAAN TANAH Rp 13,289,574.48
II. PEKERJAAN PASANGAN BATU & BETON Rp 75,623,708.75
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 45,050,305.87
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 27,032,226.00
V. PEKERJAAN KERAMIK Rp 29,141,618.06
VI. PEKERJAAN KACA Rp 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 106,732,850.32
VIII. PEKERJAAN LISTRIK Rp 7,333,417.00
IX. PEKERJAAN PENGECATAN Rp 17,730,108.25
X. PEKERJAAN SANITAIR Rp 9,599,340.00
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp 1,147,280.63

C. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 11,702,600.00

D. Jumlah Rp 358,108,371.11
E. PPn 11% Rp 39,391,920.82
F. Total (D + E) Rp 397,500,291.94
PEMBULATAN Rp 397,500,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUANG UNIT KESEHATAN SEKOLAH BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.00 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.00 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.00 1,200,000.00 1,200,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.00 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.00 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.00 750,000.00 750,000.00
Jumlah - A.1 10,500,000.00
B. PEKERJAAN PEMBANGUNAN
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 13.35 106,400.00 1,420,440.00
2 Pek. Urugan tanah kembali M3 1.34 78,400.00 104,664.00
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 20.40 576,800.00 11,764,470.48
Jumlah - A.1 13,289,574.48
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu kali ad. 1:5 M3 12.02 1,695,036.00 20,365,857.54
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 129.56 248,192.00 32,156,582.74
3 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm (150 kg/m3) M3 0.96 6,793,558.00 6,529,967.95
- Beton Kolom 15/20 cm (150 kg/m3) M3 0.38 7,255,250.00 2,758,155.84
- Beton Kolom 15/15 cm, (teras depan) (150 kg/m3) M3 0.10 7,255,250.00 689,538.96
- Kolom Praktis 12/12 cm, (ruangan) (110 kg/m3) M3 0.20 5,900,806.00 1,168,359.59
- Beton Ring Balok 15/20 cm (150 kg/m3) M3 0.96 7,271,512.00 6,989,377.33
- Ring Balok Latei 12/15 cm, (teras depan) (150 kg/m3) M3 0.12 7,271,512.00 869,091.11
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 2.11 1,937,927.00 4,096,777.68
Jumlah - A.2 75,623,708.75
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 259.13 104,882.00 27,177,722.98
2 Pek. Plesteran kolom ad. 1 : 4 M2 16.10 104,882.00 1,689,019.73
3 Pek. Acian dinding dan kolom M2 275.23 58,800.00 16,183,563.16
Jumlah - A.3 45,050,305.87
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.45 15,526,560.00 6,917,082.48
2 Daun Pintu Panel, kayu kls. I M2 6.93 1,119,104.00 7,755,390.72
3 Daun Jendela kaca kayu kla I M2 8.40 813,142.00 6,830,392.80
6 Engsel pintu 4" Bh 8.00 80,735.00 645,880.00
7 Engsel jendela Bh 8.00 58,856.00 470,848.00
8 Grendel jendela Bh 14.00 46,508.00 651,112.00
9 Kunci tanam Bh 4.00 395,304.00 1,581,216.00
10 Kait Angin Bh 28.00 77,868.00 2,180,304.00
Jumlah - A.4 27,032,226.00
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 63.13 365,750.00 23,090,090.10
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 6.00 377,631.00 2,265,786.00
3 Pas. Lantai Keramik 20x20 cm WC/KM (anti slip) M2 3.28 415,408.00 1,364,366.04
4 Pas. Dinding Keramik 20x40 cm WC/KM (polos) M2 9.56 253,282.00 2,421,375.92
Jumlah - A.5 29,141,618.06
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 5.54 247,783.00 1,372,321.37
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 7.48 247,783.00 1,853,020.39
Jumlah - A.6 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Kuda-kuda kayu Kls I Uk. 6/12 M2 1.23 14,014,784.00 17,238,184.32
2 Pek. Rangka Gording kayu Kls II uk. 5/10 M2 1.12 11,320,680.00 12,679,161.60
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 141.24 139,753.00 19,738,755.65
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 38.82 278,913.00 10,827,402.66
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 51.04 101,024.00 5,156,264.96
6 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 105.13 222,101.00 23,349,655.81
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 105.13 117,009.00 12,301,249.78
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 121.27 44,878.00 5,442,175.55
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
Jumlah - A.7 106,732,850.32
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 10.00 499,632.00 4,996,320.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.00 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 5.00 81,760.00 408,800.00
5 Pas. Saklar ganda broco BH 2.00 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 2.00 85,120.00 170,240.00
7 Pas. Box MCB 4 grup (tutup transparan + MCB 6A 2buh) Unit 1.00 250,000.00 250,000.00
Jumlah - A.8 7,333,417.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 275.67 40,504.00 11,165,737.68
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 105.13 39,675.00 4,171,064.49
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 21.10 41,966.00 885,650.46
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 0.30 41,966.00 12,692.41
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 20.31 41,966.00 852,379.82
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 15.31 41,966.00 642,583.39
Jumlah - A.9 17,730,108.25
X. PEKERJAAN SANITAIR
1 Pek. Septink 2,5 x 1,5 meter t = 2 Unit 1.00 3,500,000.00 3,500,000.00
2 Pas. Closet duduk + tabung Unit 1.00 3,122,884.00 3,122,884.00
3 Pas. Kran air Bh 1.00 141,008.00 141,008.00
4 Pas. Floor drain Bh 1.00 67,144.00 67,144.00
5 Pas. Pipa air kotor PVC AW 3" M' 12.00 166,976.00 2,003,712.00
6 Pas. Pipa air bersih PVC AW 1/2" M' 12.00 63,716.00 764,592.00

Jumlah - A.10 9,599,340.00


XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING
1 Pas. Batu Bata Semen ad. 1:4 M2 0.10 248,192.00 23,826.43
2 Pekerjaan Beton Bertulang (K-175) :
- Pelat Lantai Meja Beton, tbl = 7 cm (110 kg/m3) M3 0.06 6,631,298.00 375,596.72
3 Pek. Plesteran dinding ad. 1 : 4 M2 0.84 104,882.00 88,100.88
4 Pas. Keramik 40 x 40 cm Meja Beton (polos) M2 0.83 365,750.00 302,841.00
5 Pas. Kitchen Zink 1 lubang dan sayap (uk. 82cm x 38cm) Bh 1.00 215,907.60 215,907.60
6 Pas. Keran Air Bh 1.00 141,008.00 141,008.00
Jumlah - A.11 1,147,280.63
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja + kursi Staf perawat UKS (M-03) Bh 1.00 3,636,400.00 3,636,400.00
2 Bangsal + Kasur untuk Periksa (K-01) Bh 1.00 3,500,000.00 3,500,000.00
3 Bangsal + Kasur untuk Pasien (K-01) Set 1.00 3,500,000.00 3,500,000.00
4 Kusi periksa Bh 1.00 720,100.00 720,100.00
5 Tempat Sampah Bh 1.00 346,100.00 346,100.00
JUMLAH - B 11,702,600.00

REKAPITULASI BIAYA
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 347,608,371.11
I. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 10,500,000.00 Rp. 10,500,000.00

I. PEKERJAAN TANAH Rp. 13,289,574.48


II. PEKERJAAN PASANGAN BATU & BETON Rp. 75,623,708.75
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 45,050,305.87
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 27,032,226.00
V. PEKERJAAN KERAMIK Rp. 29,141,618.06
VI. PEKERJAAN KACA Rp. 3,225,341.75
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 106,732,850.32
VIII. PEKERJAAN LISTRIK Rp. 7,333,417.00
IX. PEKERJAAN PENGECATAN Rp. 17,730,108.25
X. PEKERJAAN SANITAIR Rp. 9,599,340.00
XI. PEKERJAAN MEJA BETON TEMPAT CUCI PIRING Rp. 1,147,280.63
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 11,702,600.00
JUMLAH Rp. 369,810,971.11
PEMBULATAN Rp 369,810,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 53.40 0.50 0.50 13.35 m3

Jumlah total 13.35 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.49 0.40 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 13.35 12.02 - - 1.34 m3

Jumlah total 1.34 m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 2.88 1.88 0.15 0.81 m3


Lantai selasar 56.00 0.75 0.15 6.30 m3
Lantai ruang tamu 5.38 2.88 0.20 3.10 m3
Lantai ruang Rawat Putri 3.88 2.88 0.20 2.23 m3
Lantai ruang Rawat Putra 3.88 2.88 0.20 2.23 m3
Lantai ruang Periksa 4.00 3.00 0.20 2.40 m3
Lantai ruang Hall 2.88 1.38 0.20 0.79 m3
Lantai ruang Dokter 2.88 2.38 0.20 1.37 m3
Lantai WC/KM 2.38 1.38 0.15 0.49 m3
Lantai Pentry 2.38 1.38 0.20 0.66 m3
Jumlah total 20 m3
SKETSA

5. Pekerjaan urug pasir bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 2.88 1.88 0.05 0.27 m3


Lantai selasar 56.00 0.75 0.05 2.10 m3
Lantai ruang tamu 5.38 2.88 0.05 0.77 m3
Lantai ruang Rawat Putri 3.88 2.88 0.05 0.56 m3
Lantai ruang Rawat Putra 3.88 2.88 0.05 0.56 m3
Lantai ruang Periksa 4.00 3.00 0.20 2.40 m3
Lantai ruang Hall 2.88 1.38 0.05 0.20 m3
Lantai ruang Dokter 2.88 2.38 0.05 0.34 m3
Lantai WC/KM 2.38 1.38 0.05 0.16 m3
Lantai Pentry 2.38 1.38 0.05 0.16 m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 53.40 0.80 0.05 2.14 m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 53.40 0.80 0.15 6.41 m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 53.40 0.25 0.50 0.60 12.02 m3

Jumlah total 12.02 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 45.76 0.45 - 20.59 m2

Jumlah total 20.59 m2


SKETSA
4. Pekerjaan pasangan dinding batu bata semen
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 8.64 3.30 2.59 7.97 7.87 m2
Dinding Belakang 8.52 3.30 6.65 21.47 m2
Dinding Samping kiri 7.76 3.30 - - 25.61 m2
Dinding Samping Kanan 7.76 3.30 2.33 - 23.28 m2
Dinding pembagi ruangan 15.78 3.30 4.05 - 48.02 m2
Dinding atas teras 6.64 0.50 3.32 m2

Jumlah total 129.56 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 15/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 8.00 0.38 m3

Jumlah total 0.380 m3


- Pekerjaan Kolom 15/15 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.12 0.12 3.30 2.00 0.10 m3

Jumlah total 0.095 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.30 6.00 0.20 m3

Jumlah total 0.198 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 53.40 0.12 0.15 1.00 0.96 m3

Jumlah total 0.961 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3


Jumlah total - m3
- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 53.40 0.12 0.15 1.00 0.96 m3

Jumlah total 0.961 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah - 0.12 0.15 1.00 - m3

Jumlah total - m3
- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.64 0.12 0.15 1.00 0.12 m3

Jumlah total 0.120 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Volume pas. Bata
Rumus Volume Satuan

V = L x T - (Luas pintu dan 129.56 2.00 259.13 m2


jendela)

Jumlah total x 2 sisi 259.13 m2


SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah
Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2
Plesteran Kolom teras 0.60 3.30 2.00 3.96 m2

Jumlah total 16.104 m2

3. Pekerjaan Acian dinding


Luas. Pas. Bata
Rumus Volume Satuan

V = L x T - (Luas pintu dan 129.56 2.00 259.13


jendela)
m2
m2
m2
m2
m2
Dinding atas teras - 0.75 - - - m2
Jumlah total x 2 sisi 259.13 m2
SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.46 3.30 8.00 12.14 m2


Plesteran Kolom teras 0.60 3.30 2.00 3.96 m2

Jumlah total 16.104 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

JV1 9.690 0.110 0.05 4.00 0.213 m3


JV2 8.250 0.110 0.05 2.00 0.091 m3
P1 6.980 0.110 0.05 2.00 0.077 m3
P2 6.780 0.110 0.05 1.00 0.037 m3
P3 5.000 0.110 0.05 1.00 0.028 m3

Jumlah total 0.45 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

P1 0.900 2.100 - 2.00 3.780 m2


P2 0.800 2.100 - 1.00 1.680 m2
P3 0.700 2.100 - 1.00 1.470 m2

Jumlah total 6.93 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

JV1 1.000 0.600 - 12.00 7.200 m2


JV2 1.000 0.600 - 2.00 1.200 m2

Jumlah total 8.40 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

P1 2.00 2.00 4.00 Buah


P2 1.00 2.00 2.00 Buah
P3 1.00 2.00 2.00 Buah

Jumlah total 8.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan

P1 2.00 2.00 4.00


P2 1.00 2.00 2.00 Buah
P3 1.00 2.00 2.00 Buah

Jumlah total 8.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan

P1 2.00 1.00 2.00


P2 1.00 1.00 1.00 Buah
P3 1.00 1.00 1.00 Buah

Jumlah total 4.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

JV1 12.00 1.00 12.00 Buah


JV2 2.00 1.00 2.00 Buah

Jumlah total 14.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1
P1 2.00 1.00 2.00 Buah
P2 1.00 1.00 1.00 Buah
P3 1.00 1.00 1.00 Buah

Jumlah total 4.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan

JV1 12.00 2.00 24.00 Buah


JV2 2.00 2.00 4.00 Buah

Jumlah total 28.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai ruang tamu 5.38 2.88 - 15.49 m3


Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 63.13 m2


SKETSA

2. Pekerjaan keramik lantai teras 60/60 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 2.00 3.00 - 6.00 m2

Jumlah total 6.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL
Lantai WC/KM 2.38 1.38 - 3.28 m3

m2

Jumlah total 3.28 m2


SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Keramik dinding WC/KM

Sekmen I 2.38 1.50 1.00 1.85 m2


Sekmen II 2.38 1.50 1.00 3.57 m2
Sekmen III 1.38 1.50 1.00 2.07 m2
Sekmen IV 1.38 1.50 1.00 2.07 m2

Jumlah total x 4 ruang 9.56 m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

J1 0.86 0.46 12.00 4.75 m2


J2 0.86 0.46 2.00 0.79 m2

Jumlah total 5.538 m2

Kaca Mati
Rumus Panjang Lebar Jumlah Volume Satuan

J1 0.86 0.48 12.00 4.95 m2


J2 0.86 0.48 2.00 0.83 m2

p1 0.88 0.48 2.00 0.84 m2


p2 0.78 0.48 1.00 0.37 m2

V1 0.60 0.40 2.00 0.48

Jumlah total 7.478 m2


VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND
1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2

Jumlah total 141.240 m2


SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 11.00 1.04 5.94 2.00 71.52 m2

Sekmen II
v = 1/2 (a) x t 10.27 5.85 1.00 30.04 m2

Sekmen III
v = 1/2 (a+b) x t 5.27 3.03 1.00 7.98 m2

Sekmen IV 22.06 m2
v = sekmen II-sekmen III

Sekmen V
v=axt 1.96 2.46 2.00 9.64 m2
Jumlah total 141.240 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 38.82 M'

Jumlah total x 2 sisi 38.82 M'


SKETSA
4. Pasang Lisplank GRC/ Calsiboard
Rumus Volume Satuan

V = panjang Nok 51.04 M'

Jumlah total x 2 sisi 51.04 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 - - 56.00 m2


Lantai ruang tamu 16.52 - - 16.52 m2
Lantai ruang Rawat Putri 10.93 - - 10.93 m2
Lantai ruang Rawat Putra 10.93 - - 10.93 m2
Lantai ruang Periksa 7.00 - - 7.00 m2
Lantai ruang Hall 9.37 - - 9.37 m2
Lantai ruang Dokter 10.52 - - 10.52 m2
Lantai Pentry - - - m2

Jumlah total 121.27 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 36 Titik
Pas. Lampu down ligth LED 18 watt 11.00 bh
Pas. Lampu down ligth LED 11 watt 15.00 bh
Pas. Stop kontak panasonic 10.00 bh
Pas. saklar ganda panasonic 4.00 bh
Pas. saklar ganda panasonic 6.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Acian
Rumus Volume Satuan
Dinding Kolom

V = Vol Acian dinding + Acian Kolom 259.13 16.10 275.23 m2

Jumlah total 275.23 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 56.00 0.75 - 42.00 m3


Lantai ruang tamu 5.38 2.88 - 15.49 m3
Lantai ruang Rawat Putri 3.88 2.88 - 11.17 m3
Lantai ruang Rawat Putra 3.88 2.88 - 11.17 m3
Lantai ruang Periksa 3.88 2.88 - 11.17 m3
Lantai ruang Hall 2.88 1.38 - 3.97 m3
Lantai ruang Dokter 2.88 2.38 - 6.85 m3
Lantai Pentry 2.38 1.38 - 3.28 m3

Jumlah total 105.13 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Lantai selasar 113.50 0.10 1.00 11.35 m2


Lantai ruang tamu 16.52 0.10 1.00 1.65 m2
Lantai ruang Rawat Putri 13.52 0.10 1.00 1.35 m2
Lantai ruang Rawat Putra 13.52 0.10 1.00 1.35 m2
Lantai ruang Periksa 7.00 0.10 1.00 0.70 m2
Lantai ruang Hall 8.52 0.10 4.00 3.41 m2
Lantai ruang Dokter 10.52 0.10 1.00 1.05 m2
Lantai Pentry 2.38 0.10 1.00 0.24 m2

Jumlah total 21.10 m2


SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

JV1 9.690 0.235 0.05 4.00 0.455


JV2 8.250 0.235 0.05 2.00 0.194
P1 6.980 0.235 0.05 2.00 0.164 m2
P2 6.780 0.235 0.05 1.00 0.080 m2
P3 5.000 0.235 0.05 1.00 0.059 m2
m2
m2
m2

Jumlah total 0.30 m2


SKETSA

5. Pekerjaan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

J1 2.880 0.080 2.00 12.00 5.530 m2


J2 2.880 0.080 2.00 2.00 0.922 m2

P1 2.100 0.900 2.00 2.00 7.560 m2


P2 2.100 0.800 2.00 1.00 3.360 m2
P3 2.100 0.700 2.00 1.00 2.940 m2

Jumlah total 20.31 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 51.04 0.30 15.312

Jumlah total 15.31 m2


SKETSA

Meja beton

1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL - 0.30 - -

Jumlah total - m2
SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN TOILET/JAMBAN BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 9,800,000.00


B. PEMBANGUNAN FISIK 1 (RUANG) Rp 432,767,743.09
I. PEKERJAAN TANAH Rp 12,922,058.13
II. PEKERJAAN PASANGAN BATU & BETON Rp 93,960,433.17
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 37,571,990.52
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 31,648,522.66
V. PEKERJAAN KERAMIK Rp 77,746,289.19
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 129,408,288.43
VIII. PEKERJAAN LISTRIK Rp 7,583,417.00
C. PEKERJAAN SANITAIR Rp 41,926,744.00

D. Jumlah Rp 484,494,487.09
E. PPn 11% Rp 53,294,393.58
F. Total (D + E) Rp 537,788,880.67
PEMBULATAN Rp 537,788,000.00

Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN TOILET/JAMBAN BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 9,800,000.00
B. PEMBANGUNAN FISIK 1 (RUANG)
I. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi M3 9.574 106,400.00 1,018,631.04
2 Pek. Urugan tanah kembali M3 9.574 78,400.00 750,570.24
3 Pek. Timbunan tanah bawah lantai (timbunan biasa) M3 10.031 576,800.00 5,785,736.60
4 Pek. Urugan pasir dibawah lantai, tbl = 5 cm M3 11.165 480,704.00 5,367,120.25
Jumlah - A.1 12,922,058.13
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu kali ad. 1:5 M3 7.978 1,695,036.00 13,522,997.21
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 114.330 248,192.00 28,375,791.36
3 Pekerjaan Beton Bertulang (K-175) :
- Beton Sloof 15/20 cm (150 kg/m3) M3 1.197 6,793,558.00 8,129,850.86
- Beton Kolom 15/15 cm (150 kg/m3) M3 1.150 7,255,250.00 8,341,723.69
- Beton Kolom 15/15 cm, (teras depan) (150 kg/m3) M3 0.189 7,255,250.00 1,371,242.25
- Kolom Praktis 12/12 cm, (110 kg/m3) M3 0.152 6,362,498.00 966,304.38
- Beton Ring Balok 15/20 cm (Utama) (150 kg/m3) M3 0.882 7,271,512.00 6,413,473.58
- Beton Ring Balok 12/15 cm (Praktis) (150 kg/m3) M3 0.194 7,271,512.00 1,413,581.93
- Beton Ring Balok 15/20 cm (DAK) (150 kg/m3) M3 0.348 7,271,512.00 2,530,486.18
- Plat atap/DAK (110 kg/m3) M3 3.150 6,362,498.00 20,041,868.70
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 1.472 1,937,927.00 2,853,113.03
Jumlah - A.2 93,960,433.17
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran dinding ad. 1 : 4 M2 223.199 104,882.00 23,409,557.52
2 Pek. Plesteran kolom ad. 1 : 4 M2 9.900 104,882.00 1,038,331.80
3 Pek. Acian dinding dan kolom M2 223.199 58,800.00 13,124,101.20
Jumlah - A.3 37,571,990.52
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.337 15,526,560.00 5,226,240.10
2 Daun Pintu Panel, kayu kls. I M2 17.640 1,119,104.00 19,740,994.56
3 Daun Jendela kaca kayu kla I M2 0.000 813,142.00 0.00
6 Engsel pintu 4" Bh 24.000 80,735.00 1,937,640.00
7 Engsel jendela Bh 0.000 58,856.00 0.00
8 Grendel jendela Bh 0.000 46,508.00 0.00
9 Kunci tanam Bh 12.000 395,304.00 4,743,648.00
10 Kait Angin Bh 0.000 77,868.00 0.00
Jumlah - A.4 31,648,522.66
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. WC/KM (polos) M2 43.100 365,750.00 15,763,825.00
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 24.000 377,631.00 9,063,144.00
3 Pas. Lantai Keramik 20x20 cm WC/KM (anti slip) M2 17.600 377,631.00 6,646,305.60
4 Pas. Dinding Keramik 20x40 cm WC/KM (polos) M2 122.535 377,631.00 46,273,014.59
Jumlah - A.5 77,746,289.19
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 0.000 247,783.00 0.00
2 Pemasangan Kaca Mati Jendela t= 5 mm M2 0.000 247,783.00 0.00
Jumlah - A.6 0.00
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Kuda-kuda kayu Kls I Uk. 6/12 M2 1.915 14,014,784.00 26,843,939.70
2 Pek. Rangka Gording kayu Kls II uk. 5/10 M2 1.890 11,320,680.00 21,396,085.20
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 125.440 139,753.00 17,530,616.32
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 14.000 278,913.00 3,904,782.00
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 43.660 101,024.00 4,410,707.84
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
6 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 160.043 222,101.00 35,545,599.29
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 160.043 117,009.00 18,726,412.88
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 23.400 44,878.00 1,050,145.20
Jumlah - A.7 129,408,288.43
VIII. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 10.000 499,632.00 4,996,320.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.000 153,216.00 919,296.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 3.000 139,507.00 418,521.00
4 Pas. Stop kontak broco BH 5.000 81,760.00 408,800.00
5 Pas. Saklar ganda broco BH 2.000 85,120.00 170,240.00
6 Pas. Saklar tunggal broco BH 2.000 85,120.00 170,240.00
7 Pas. Box MCB 4 grup (tutup transparan + MCB 6A 2buh) Unit 2.000 250,000.00 500,000.00
Jumlah - A.8 7,583,417.00
IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 223.199 40,504.00 9,040,452.30
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 160.043 39,675.00 6,349,686.19
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 2.340 41,966.00 98,200.44
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 14.100 41,966.00 591,720.60
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 35.280 41,966.00 1,480,560.48
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 13.098 41,966.00 549,670.67
Jumlah - A.9 18,110,290.67
C. PEKERJAAN SANITAIR
1 Pek. Septink 2,5 x 1,5 meter t = 2 Unit 1.000 3,500,000.00 3,500,000.00
2 Pas. Closet duduk + tabung Unit 10.000 3,122,884.00 31,228,840.00
3 Pas. Kran air Bh 14.000 141,008.00 1,974,112.00
4 Pas. Floor drain Bh 10.000 67,144.00 671,440.00
5 Pas. Pipa air kotor PVC AW 3" M' 12.000 166,976.00 2,003,712.00
6 Pas. Pipa air bersih PVC AW 1/2" M' 40.000 63,716.00 2,548,640.00

Jumlah - A.10 41,926,744.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 9,800,000.00

B. PEMBANGUNAN FISIK 1 (RUANG) Rp. 408,951,289.76


I. PEKERJAAN TANAH Rp. 12,922,058.13
II. PEKERJAAN PASANGAN BATU & BETON Rp. 93,960,433.17
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 37,571,990.52
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 31,648,522.66
V. PEKERJAAN KERAMIK Rp. 77,746,289.19
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 129,408,288.43
VIII. PEKERJAAN LISTRIK Rp. 7,583,417.00
IX. PEKERJAAN PENGECATAN Rp. 18,110,290.67
C. PEKERJAAN SANITAIR Rp. 41,926,744.00
JUMLAH Rp. 460,678,033.76
PEMBULATAN Rp 460,678,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
31.14 8.75
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
### sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 39.89 0.60 0.40 9.57 m3

Jumlah total 9.57 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.49 0.40 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 9.57 9.57 m3

Jumlah total 9.57 m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Jml Ruang Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 1.00 11.85 1.85 0.20 4.38 m3


Lantai Toliet 5.00 1.60 1.10 0.20 1.76 m3
Laintai R. Wastafel 2 2.85 1.85 0.25 2.64 m3
Hall 2 1.25 2.50 0.20 1.25 m3
Lantai Selasar

Jumlah total 10.03 m3


SKETSA
5. Pekerjaan urug pasir bawah lantai
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 1.00 11.85 1.85 0.20 4.38 m3


Lantai Toliet 5.00 1.60 1.10 0.20 1.76 m3
Laintai R. Wastafel 2 2.85 1.85 0.25 2.64 m3
Hall 2 1.25 2.50 0.20 1.25 m3
Lantai Selasar 1 27.50 0.83 0.05 1.13

Jumlah total 11.17 m3


SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 39.89 0.60 0.05 1.20 m3

Jumlah total 1.20 m3


SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 39.89 0.60 0.15 3.59 m3

Jumlah total 3.59 m3


SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 39.89 0.20 0.60 0.50 7.98 m3


0.40

Jumlah total 7.98 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 35.50 0.15 0.45 5.33 m2

Jumlah total 5.33 m2


SKETSA

4. Pekerjaan pasangan dinding batu bata semen


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Ventilasi
Depan 11.40 3.30 3.44 1.44 32.74 m2
Dinding Samping Kiri 5.30 3.30 0.36 17.13 m2
Dinding Samping Kanan 5.30 3.30 0.36 17.13 m2
Dinding Pembagi Ruangan 8.00 2.45 8.60 11.00 m2
4.30 3.30 14.19
Belakang 5.55 2.80 0.36 15.18
Dinding Gewel 2.18 1.60 6.96 -

Jumlah total 114.33 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 15/15 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.15 0.15 2.85 5.00 0.32 m3


0.15 0.15 3.35 11.00 0.83
-

Jumlah total 1.150 m3


- Pekerjaan Kolom 15/15 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.15 0.15 2.80 3.00 0.19 m3

Jumlah total 0.189 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.15 0.15 2.25 3.00 0.15 m3

Jumlah total 0.152 m3

- Pekerjaan Sloof 15/20


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 39.89 0.15 0.20 1.00 1.20 m3

Jumlah total 1.197 m3


Pekerjaan Balok 15/20
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

Balok 15/20

Balok Dak 14.50 0.12 0.20 1.00 0.35 m3


Jumlah total 0.348 m3

Balok dalam ruangan 8.10 0.12 0.20 1.00 0.19


Jumlah total 0.194 m3

Balok 15/15
Balok Teras 16.00 0.12 0.15 1.00 0.29
Balok Atap 33.00 0.12 0.15 1.00 0.59
Jumlah total 0.882 m3
m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 39.00 0.76 0.05 1.00 1.47 m3

Jumlah total 1.472 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Ventilasi

Depan 11.40 3.30 3.44 2.24 31.94 m2


Dinding Samping Kiri 22.85 0.36 22.49 m2
Dinding Samping Kanan 22.85 - 0.36 22.49 m2
Dinding Pembagi Ruangan 29.70 2.25 17.20 49.63 m2
Belakang 11.10 3.30 1.44 35.19 m2
- m2

Jumlah total 161.74 m2


323.47
Keramik Dinding 100.28 m2
223.20

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Teras 0.60 3.30 5.00 9.90 m2

Jumlah total 9.900 m2

3. Pekerjaan Acian dinding


1. Pekerjaan Plesteran dinding ad. 1 : 4
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Ventilasi

Depan 11.40 3.30 3.44 2.24 31.94 m2


Dinding Samping Kiri 22.85 0.36 22.49 m2
Dinding Samping Kanan 22.85 - 0.36 22.49 m2
Dinding Pembagi Ruangan 29.70 2.25 17.20 49.63 m2
Belakang 11.10 3.30 1.44 35.19 m2
- m2

Jumlah total 161.74 m2


323.47
Keramik Dinding 100.28 m2
223.20

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.60 3.30 5.00 9.90 m2


Plesteran Kolom teras - 3.30 - - m2

Jumlah total 9.900 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

P1 5.100 0.110 0.05 12.00 0.337 m3

Jumlah total 0.34 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

P1 0.700 2.100 - 12.00 17.640 m2


P2 m2
P3 m2

Jumlah total 17.64 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

JV1 0.000 0.600 - 12.00 - m2


JV2 0.000 0.600 - 2.00 - m2

Jumlah total - m2
SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3
P1 12.00 2.00 24.00 Buah
Buah
Buah

Jumlah total 24.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan

P1 - 2.00 -
- Buah
- Buah

Jumlah total - Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan

P1 1.00 1.00 1.00


Buah
Buah

Jumlah total 1.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

JV1 - 1.00 - Buah


JV2 - 1.00 - Buah

Jumlah total - Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

P1 12.00 1.00 12.00 Buah


Buah
Buah

Jumlah total 12.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan

JV1 - 2.00 - Buah


JV2 - 2.00 - Buah

Jumlah total - Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 40/40
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL
Keramik Lantai
Lantai WC Putra 23.60 m3
Lantai WC Putri 19.50 m3
Lantai Ruang Orinoir m3
m3
m3
m3

Jumlah total 43.10 m2


SKETSA

2. Pekerjaan keramik lantai teras 40/40 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 2.00 12.00 24.00 m2

Jumlah total 24.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Lantai WC/KM 1.60 1.10 10.00 17.60 m3

m2

Jumlah total 17.60 m2


SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Jumlah Ruang
Rumus Panjang Tinggi Volume Satuan

Dalam Toilet 4.62 1.50 - 10.00 69.30 m2


Ruangan Ganti 7.41 1.50 2.00 22.23
Ruang Wastafel 7.41 1.50 2.00 22.23
Ruang Orinoir 5.85 1.50 1.00 8.78

Jumlah total 122.54 m2


m2
SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

J1 - 0.46 12.00 - m2
J2 - 0.46 2.00 - m2

Jumlah total - m2

Kaca Mati
Rumus Panjang Lebar Jumlah Volume Satuan

J1 - 0.48 12.00 - m2
J2 - 0.48 2.00 - m2
-
p1 - 0.48 2.00 - m2
p2 - 0.48 1.00 - m2

V1 - 0.40 2.00 -

Jumlah total - m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang Kuda-kuda kayu Klas I
Rumus Panjang Dimensi Jumlah Volume Satuan

Tiang Nok 1.33 0.01 6.00 0.06 m2


Balok tarik 4.55 0.01 6.00 0.20
Sekong gapit 0.96 0.01 12.00 0.08
Sokong tarik 1.06 0.01 24.00 0.18 m2
Kaki Kuda-kuda I 3.23 0.01 6.00 0.14
Kaki Kuda-kuda II 2.70 0.01 6.00 0.12
Kaki Kuda-kuda III
Balok Angin 2.10 0.01 12.00 0.18
Jumlah total 1.915 m2
PEKERJAAN GORDING KAYU KLS II
Rumus Panjang Dimensi Jumlah Volume Satuan

Gording 13.50 0.0050 14.00 0.95 m2

Jumlah total 1.890 m2

2. Pasang atap zincalum/spandek


Rumus Lebar Tinggi Jml sisi Volume Satuan

Bangunan utama 14.00 3.32 2.00 92.96


Teras 14.00 2.32 1.00 32.48
Jumlah total 125.440 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 14.00 M'

Jumlah total x 2 sisi 14.00 M'


SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus Lebar Tinggi Jml sisi Volume Satuan

Sekeen I 8.33 - 2.00 16.66


Sekmen 2 13.50 - 2.00 27.00

Jumlah total x 2 sisi 43.66 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

Dalam Toilet 5.85 5.85 2.00 68.45


Teras 11.85 5.85 1.00 69.32 m3
Tirisan 29.70 0.75 22.28 m3

Jumlah total 160.04 m2


SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

Rumus Panjang Lebar jml ruang Volume Satuan

Dalam Toilet 5.85 5.85 2.00 68.45


Teras 11.85 5.85 1.00 69.32 m3
Tirisan 29.70 0.75 22.28 m3

Jumlah total 160.04 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Dalam 23.40 1.00 23.40 m2


Teras - 1.00 - m2
m2
Jumlah total 23.40 M1
Cat Lis

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 12 Titik
Pas. Lampu down ligth LED 18 watt - bh
Pas. Lampu down ligth LED 11 watt 12.00 bh
Pas. Stop kontak panasonic - bh
Pas. saklar ganda panasonic 2.00 bh
Pas. saklar ganda panasonic 2.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 2.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Ventilasi

Depan 11.40 3.30 3.44 2.24 31.94 m2


Dinding Samping Kiri 22.85 0.36 22.49 m2
Dinding Samping Kanan 22.85 - 0.36 22.49 m2
Dinding Pembagi Ruangan 29.70 2.25 17.20 49.63 m2
Belakang 11.10 3.30 1.44 35.19 m2
- m2

Jumlah total 161.74 m2


323.47
Keramik Dinding 100.28 m2
223.20
SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Jumlah total - m2
SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan
Jumlah total - m2
SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

m2
m2
P1 5.000 0.235 - 12.00 14.100 m2
m2
m2
m2

Jumlah total 14.10 m2


SKETSA

5. Pekerjaan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

J1 m2
J2 m2

P1 m2
P2 m2
P3 2.100 0.700 2.00 12.00 35.280 m2

Jumlah total 35.28 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 43.66 0.30 13.098

Jumlah total 13.10 m2


SKETSA

Meja beton

1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh
tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

Jumlah total - m2
SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : REHABILITASI LABORATORIUM FISIKA BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 9,800,000.00


B. PEKERJAAN PEMBANGUNAN 1 RUANG Rp 302,180,122.81
I PEKERJAAN PASANGAN BATU & BETON Rp 1,956,472.20
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 24,786,771.97
III. PEKERJAAN KERAMIK Rp 13,997,592.00
IV. PEKERJAAN KACA Rp 545,835.11
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 222,124,522.30
VI. PEKERJAAN LISTRIK Rp 7,558,306.00
VII. PEKERJAAN PENGECATAN Rp 22,710,623.23
VIII PEKERJAAN SANITAIR Rp 8,500,000.00

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 10,317,236.60

C. Jumlah Rp 322,297,359.41
D. PPn 11% Rp 35,452,709.54
E. Total (D + E) Rp 357,750,068.95
PEMBULATAN Rp 357,750,000.00

Terbilang :

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT m3

Jumlah total - m3
SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) m3

Jumlah total - m3
SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

m3
m3
m3
m3
m3
m3

m3
m3
m3
m3

Jumlah total 0 m3
SKETSA
5. Pekerjaan urug pasir bawah lantai
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

m3
m3
m3
m3
m3
m3

m3
m3
m3
m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.80 0.05 - m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.80 0.15 - m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t - 0.25 0.70 0.70 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL - 0.46 - - m2

Jumlah total - m2
SKETSA

4. Pekerjaan pasangan dinding batu bata semen


Luas
Rumus Labar Tinggi Volume Satuan
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2

Jumlah total - m2
SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 20/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 16.00 1.73 m3

Jumlah total 1.734 m3


- Pekerjaan Kolom 20/20 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 2.00 0.22 m3

Jumlah total 0.217 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.75 13.00 0.49 m3

Jumlah total 0.488 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan
V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 5.64 0.12 0.15 1.00 0.10 m3

Jumlah total 0.102 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2
Jumlah total x 2 sisi - m2
SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

m2
m2
Jumlah total - m2

3. Pekerjaan Acian dinding


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2
Jumlah total x 2 sisi - m2
SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

m2
m2

Jumlah total - m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

m3
m3
m3
m3
m3
m3

Jumlah total - m3
SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

Pintu I 0.600 2.100 - 4.00 5.040 m2


Pintu II 0.800 2.100 - 3.00 5.040 m2

Jumlah total 10.08 m2


SKETSA
3. Pekerjaan Daun Jendela
Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

0.800 0.800 5.00 3.200 m2

Jumlah total 3.20 m2


SKETSA

4. Pekerjaan Jelusi kayu


Rumus Panjang Lebar Jml jelusi jumlah Volume Satuan

V=PxL

0.500 0.110 9.00 30.00 14.850 m2


0.500 0.110 7.00 2.00 0.770
0.500 0.110 9.00 3.00 1.485

Jumlah total 17.11 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

Pintu I 1.00 3.00 3.00 Buah


Pintu II 3.00 3.00 9.00 Buah

Jumlah total 12.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan
V = jumlah daun jendela x 2

Jendela 20.00 2.00 40.00 Buah

Jumlah total 40.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan
V = jumlah daun jpintu x 2

Pintu I 1.00 2.00 2.00 Buah


Pintu II 3.00 1.00 3.00 Buah

Jumlah total 5.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1
Grendel Jendela 20.00 1.00 20.00 Buah

Jumlah total 20.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

Pintu I 1.00 1.00 1.00 Buah


Pintu II 3.00 1.00 3.00 Buah

Jumlah total 4.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan
V = jumlah jendela x 2

Jendela 20.00 2.00 40.00 Buah

Jumlah total 40.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

m2
m2
m2
m2
m2
Jumlah total - m2
SKETSA

2. Pekerjaan keramik lantai teras 40/40 (anti slip)


Rumus Panjang Lebar Volu kolom Volume Satuan

V=PxL

Lantai teras (anti slip) 18.00 2.00 1.00 36.00 m2

Jumlah total 36.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan
Jumlah total - m2
SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Jumlah total x 4 ruang - m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL 0.66 0.66 5.00 2.18

Jumlah total 2.178 m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen II
v = 1/2 (a) x t 14.00 3.76 2.00 52.64 m2

Sekmen III
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen IV m2
v = sekmen II-sekmen III

Sekmen V
v=axt - - - - m2
Jumlah total 268.192 m2
SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen II
v = 1/2 (a) x t - 14.00 3.76 2.00 52.64 m2

Sekmen III
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen IV m2
v = sekmen II-sekmen III

Sekmen V
v=axt - 2.46 2.00 - m2
Jumlah total 268.192 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 28.56 M'

Jumlah total x 2 sisi 28.56 M'


SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus Volume Satuan

V = panjang Nok 78.88 M'

Jumlah total x 2 sisi 78.88 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2
Jumlah total 106.75 m2
SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2

Jumlah total 106.75 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 11.44 - 1.00 11.44 m2


Ruang penyimpanan 11.44 - 1.00 11.44 m2
Ruang pengelola 11.44 - 1.00 11.44 m2
Ruang administrasi 9.52 - 1.00 9.52 m2
Teras 39.54 - 1.00 39.54 m2
Selasar 56.80 - 1.00 56.80 m2
- - - - m2
- - - - m2

Jumlah total 140.18 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 14 Titik
Pas. Lampu down ligth LED 18 watt 6.00 bh
Pas. Lampu down ligth LED 11 watt 6.00 bh
Pas. Stop kontak panasonic 2.00 bh
Pas. saklar ganda panasonic 2.00 bh
Pas. saklar ganda panasonic 1.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Rumus Panjang Lebar Jml Volume Satuan

Pengecatan dinding dalam


Ruang Praktek 45.36 3.45 1 156
Lubangan jendela 2.54 1.98 8 40
Lubangan Pintu I 3.24 1.29 2 8
Lubangan Pintu II 2.69 0.88 2 5
103
Ruang penyimpanan 11.52 3.45 1 40
Lubangan jendela 2.54 1.98 1 5
Lubangan Pintu II 2.69 0.88 1 2
32

Ruang pengelola 11.52 3.45 1 40


Lubangan jendela 2.54 0.88 1 2
Lubangan Pintu II 2.69 0.88 2 5
33

Ruang administrasi 9.52 3.45 1 33


Lubangan Pintu II 2.69 0.88 1 2
30

Pengecatan dinding luar

53.93 3.50 1 189


Lubangan jendela 2.54 1.98 10 50
Lubangan Pintu I 3.24 1.29 2 8
- - 130.10 m2

Pengecatan dinding latei


22.00 0.55 2.00 24.20

Jumlah total 353.07 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2
- - - - - m2
- - - - - m2

Jumlah total 106.75 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 11.44 0.10 1.00 1.14 m2


Ruang penyimpanan 11.44 0.10 1.00 1.14 m2
Ruang pengelola 11.44 0.10 1.00 1.14 m2
Ruang administrasi 9.52 0.10 1.00 0.95 m2
Teras 39.54 0.10 1.00 3.95 m2
Selasar 56.80 0.10 1.00 5.68 m2
- - - - - m2
- - - - - m2
-
Jumlah total 14.02 m2
SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

Jendela 13.700 0.170 - 10.00 23.290 m2


3.780 0.550 10.00 20.790 m2

Pintu I 6.380 0.170 - 1.00 1.085 m2


3.870 0.170 1.00 0.658 m2
1.000 0.280 1.00 0.280 m2
Pintu II 5.280 0.170 - 1.00 0.898 m2
1.560 0.170 1.00 0.265 m2
Jumlah total 47.27 m2

Jelusi Jenela 0.520 0.240 - 90.00 11.232 m2


Pintu I 0.520 0.240 14.00 1.747 m2
Pintu II 0.520 0.240 27.00 3.370 m2

Jumlah total 16.35 m2


SKETSA

5. Pekerjaan Pengecatan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

Jendela 2.960 0.080 2.00 20.00 9.472 m2


Pintu I 2.100 0.600 2.00 2.00 5.040 m2
Pintu II 2.100 0.800 2.00 3.00 10.080 m2

Jumlah total 15.12 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 78.88 0.30 23.664

Jumlah total 23.66 m2


SKETSA

Meja beton
1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL 1.00 0.30 0.300 0.090

Jumlah total 0.09 m2


SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : REHABILITASI LABORATORIUM FISIKA BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 9,800,000.00
B. PEKERJAAN PEMBANGUNAN 1 RUANG
I PEKERJAAN PASANGAN BATU & BETON
1 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 5 cm (perbaikan yang rusak) M3 0.90 2,173,858.00 1,956,472.20
Jumlah - A.2 1,956,472.20
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Daun Pintu Panel, kayu kls. I 100% M2 10.08 1,186,248.00 11,957,379.84
2 Daun Jendela kaca kayu kla I (gan yang rusak 25%) M2 3.20 866,857.00 2,773,942.40
3 Jalusi Kusen Pintu, Jendela & Ventilasi, kayu kls.II gantu yang rusak 5 % M2 0.86 920,444.00 787,209.73
4 Engsel pintu 4" (ganti 100%) Bh 12.00 83,565.00 1,002,780.00
5 Engsel jendela (ganti 100%) Bh 40.00 60,742.00 2,429,680.00
6 Grendel jendela (ganti 100%) Bh 20.00 49,411.00 988,220.00
7 Kunci tanam (ganti 100%) Bh 4.00 404,180.00 1,616,720.00
8 Kait Angin (ganti 100%) Bh 40.00 80,771.00 3,230,840.00
Jumlah - A.4 24,786,771.97
III. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 36.00 388,822.00 13,997,592.00
Jumlah - A.5 13,997,592.00
IV. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm (ganti yang picah 25%) M2 2.18 250,613.00 545,835.11
Jumlah - A.6 545,835.11
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 267.84 458,397.00 122,777,052.48
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 268.19 142,602.00 38,244,715.58
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 28.56 296,318.00 8,463,138.40
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 78.88 106,002.00 8,361,437.76
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 106.75 233,455.00 24,922,068.31
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 106.75 120,251.00 12,837,179.05
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 140.18 46,504.00 6,518,930.72
Jumlah - A.7 222,124,522.30
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VI. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 10.00 515,312.00 5,153,120.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 157,920.00 947,520.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 6.00 144,211.00 865,266.00
4 Pas. Stop kontak broco BH 2.00 86,464.00 172,928.00
5 Pas. Saklar ganda broco BH 2.00 89,824.00 179,648.00
6 Pas. Saklar tunggal broco BH 1.00 89,824.00 89,824.00
7 Pas. MCB 6 A (lengkap) BH 1.00 150,000.00 150,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 0.00 650,000.00 0.00
Jumlah - A.8 7,558,306.00
VII. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 317.00 41,919.00 13,288,323.00
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 106.75 41,090.00 4,386,488.99
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 14.02 43,257.00 606,376.63
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 47.27 43,257.00 2,044,555.08
5 Pek. Cat Jelusi kayu dengan cat Glotex M2 16.35 43,257.00 707,200.04
6 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 15.12 43,257.00 654,045.84
7 Pek. Cat Papan Lisplank dengan cat Glotex M2 23.66 43,257.00 1,023,633.65
Jumlah - A.9 22,710,623.23
VIII PEKERJAAN SANITAIR
1 Pek. Tanki Limbah & Resapan uk. (120cm x 280cm), H = (140/100) cm Unit 1.00 8,500,000.00 8,500,000.00

B. PEKERJAAN PENGADAAN PERABOT / MEUBELER


1 Papan tulis (P-01) Bh 1.00 1,870,700.00 1,870,700.00
2 Lemari penyimpanan alat (L-01) Bh 1.00 4,243,324.20 4,243,324.20
3 Lemari penyimpanan bahan (L-02) Bh 1.00 3,857,112.40 3,857,112.40
4 Tempat Sampah Bh 1.00 346,100.00 346,100.00
JUMLAH - B 10,317,236.60

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 9,800,000.00


B. PEKERJAAN PEMBANGUNAN 1 RUANG Rp. 302,180,122.81
I PEKERJAAN PASANGAN BATU & BETON Rp. 1,956,472.20
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 24,786,771.97
III. PEKERJAAN KERAMIK Rp. 13,997,592.00
IV. PEKERJAAN KACA Rp. 545,835.11
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 222,124,522.30
VI. PEKERJAAN LISTRIK Rp. 7,558,306.00
VII. PEKERJAAN PENGECATAN Rp. 22,710,623.23
VIII PEKERJAAN SANITAIR Rp. 8,500,000.00

B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 10,317,236.60


JUMLAH Rp. 322,297,359.41
PEMBULATAN Rp 322,297,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : REHABILITASI LABORATORIUM KIMIA BESERTA PERABOTNYA
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 9,800,000.00


B. PEKERJAAN PEMBANGUNAN 1 RUANG Rp 302,180,122.81
I PEKERJAAN PASANGAN BATU & BETON Rp 1,956,472.20
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 24,786,771.97
III. PEKERJAAN KERAMIK Rp 13,997,592.00
IV. PEKERJAAN KACA Rp 545,835.11
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 222,124,522.30
VI. PEKERJAAN LISTRIK Rp 7,558,306.00
VII. PEKERJAAN PENGECATAN Rp 22,710,623.23
VIII PEKERJAAN SANITAIR Rp 8,500,000.00

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 10,317,236.60

C. Jumlah Rp 322,297,359.41
D. PPn 11% Rp 35,452,709.54
E. Total (D + E) Rp 357,750,068.95
PEMBULATAN Rp 357,750,000.00

Terbilang :

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : REHABILITASI LABORATORIUM KIMIA BESERTA PERABOTNYA
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 9,800,000.00
B. PEKERJAAN PEMBANGUNAN 1 RUANG
I PEKERJAAN PASANGAN BATU & BETON
1 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 5 cm (perbaikan yang rusak) M3 0.90 2,173,858.00 1,956,472.20
Jumlah - A.2 1,956,472.20
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Daun Pintu Panel, kayu kls. I 100% M2 10.08 1,186,248.00 11,957,379.84
2 Daun Jendela kaca kayu kla I (gan yang rusak 25%) M2 3.20 866,857.00 2,773,942.40
3 Jalusi Kusen Pintu, Jendela & Ventilasi, kayu kls.II gantu yang rusak 5 % M2 0.86 920,444.00 787,209.73
4 Engsel pintu 4" (ganti 100%) Bh 12.00 83,565.00 1,002,780.00
5 Engsel jendela (ganti 100%) Bh 40.00 60,742.00 2,429,680.00
6 Grendel jendela (ganti 100%) Bh 20.00 49,411.00 988,220.00
7 Kunci tanam (ganti 100%) Bh 4.00 404,180.00 1,616,720.00
8 Kait Angin (ganti 100%) Bh 40.00 80,771.00 3,230,840.00
Jumlah - A.4 24,786,771.97
III. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 36.00 388,822.00 13,997,592.00
Jumlah - A.5 13,997,592.00
IV. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm (ganti yang picah 25%) M2 2.18 250,613.00 545,835.11
Jumlah - A.6 545,835.11
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 267.84 458,397.00 122,777,052.48
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 268.19 142,602.00 38,244,715.58
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 28.56 296,318.00 8,463,138.40
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 78.88 106,002.00 8,361,437.76
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 106.75 233,455.00 24,922,068.31
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 106.75 120,251.00 12,837,179.05
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 140.18 46,504.00 6,518,930.72
Jumlah - A.7 222,124,522.30
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VI. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 10.00 515,312.00 5,153,120.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 6.00 157,920.00 947,520.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 6.00 144,211.00 865,266.00
4 Pas. Stop kontak broco BH 2.00 86,464.00 172,928.00
5 Pas. Saklar ganda broco BH 2.00 89,824.00 179,648.00
6 Pas. Saklar tunggal broco BH 1.00 89,824.00 89,824.00
7 Pas. MCB 6 A (lengkap) BH 1.00 150,000.00 150,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 0.00 650,000.00 0.00
Jumlah - A.8 7,558,306.00
VII. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 317.00 41,919.00 13,288,323.00
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 106.75 41,090.00 4,386,488.99
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 14.02 43,257.00 606,376.63
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 47.27 43,257.00 2,044,555.08
5 Pek. Cat Jelusi kayu dengan cat Glotex M2 16.35 43,257.00 707,200.04
6 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 15.12 43,257.00 654,045.84
7 Pek. Cat Papan Lisplank dengan cat Glotex M2 23.66 43,257.00 1,023,633.65
Jumlah - A.9 22,710,623.23
VIII PEKERJAAN SANITAIR
1 Pek. Tanki Limbah & Resapan uk. (120cm x 280cm), H = (140/100) cm Unit 1.00 8,500,000.00 8,500,000.00

B. PEKERJAAN PENGADAAN PERABOT / MEUBELER


1 Papan tulis (P-01) Bh 1.00 1,870,700.00 1,870,700.00
2 Lemari penyimpanan alat (L-01) Bh 1.00 4,243,324.20 4,243,324.20
3 Lemari penyimpanan bahan (L-02) Bh 1.00 3,857,112.40 3,857,112.40
4 Tempat Sampah Bh 1.00 346,100.00 346,100.00
JUMLAH - B 10,317,236.60

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 9,800,000.00


B. PEKERJAAN PEMBANGUNAN 1 RUANG Rp. 302,180,122.81
I PEKERJAAN PASANGAN BATU & BETON Rp. 1,956,472.20
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 24,786,771.97
III. PEKERJAAN KERAMIK Rp. 13,997,592.00
IV. PEKERJAAN KACA Rp. 545,835.11
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 222,124,522.30
VI. PEKERJAAN LISTRIK Rp. 7,558,306.00
VII. PEKERJAAN PENGECATAN Rp. 22,710,623.23
VIII PEKERJAAN SANITAIR Rp. 8,500,000.00

B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 10,317,236.60


JUMLAH Rp. 322,297,359.41
PEMBULATAN Rp 322,297,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT m3

Jumlah total - m3
SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) m3

Jumlah total - m3
SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

m3
m3
m3
m3
m3
m3

m3
m3
m3
m3

Jumlah total 0 m3
SKETSA
5. Pekerjaan urug pasir bawah lantai
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

m3
m3
m3
m3
m3
m3

m3
m3
m3
m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.80 0.05 - m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.80 0.15 - m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t - 0.25 0.70 0.70 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL - 0.46 - - m2

Jumlah total - m2
SKETSA

4. Pekerjaan pasangan dinding batu bata semen


Luas
Rumus Labar Tinggi Volume Satuan
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2

Jumlah total - m2
SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 20/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 16.00 1.73 m3

Jumlah total 1.734 m3


- Pekerjaan Kolom 20/20 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 2.00 0.22 m3

Jumlah total 0.217 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.75 13.00 0.49 m3

Jumlah total 0.488 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan
V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 5.64 0.12 0.15 1.00 0.10 m3

Jumlah total 0.102 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2
Jumlah total x 2 sisi - m2
SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

m2
m2
Jumlah total - m2

3. Pekerjaan Acian dinding


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2
Jumlah total x 2 sisi - m2
SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

m2
m2

Jumlah total - m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

m3
m3
m3
m3
m3
m3

Jumlah total - m3
SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

Pintu I 0.600 2.100 - 4.00 5.040 m2


Pintu II 0.800 2.100 - 3.00 5.040 m2

Jumlah total 10.08 m2


SKETSA
3. Pekerjaan Daun Jendela
Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

0.800 0.800 5.00 3.200 m2

Jumlah total 3.20 m2


SKETSA

4. Pekerjaan Jelusi kayu


Rumus Panjang Lebar Jml jelusi jumlah Volume Satuan

V=PxL

0.500 0.110 9.00 30.00 14.850 m2


0.500 0.110 7.00 2.00 0.770
0.500 0.110 9.00 3.00 1.485

Jumlah total 17.11 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

Pintu I 1.00 3.00 3.00 Buah


Pintu II 3.00 3.00 9.00 Buah

Jumlah total 12.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan
V = jumlah daun jendela x 2

Jendela 20.00 2.00 40.00 Buah

Jumlah total 40.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan
V = jumlah daun jpintu x 2

Pintu I 1.00 2.00 2.00 Buah


Pintu II 3.00 1.00 3.00 Buah

Jumlah total 5.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1
Grendel Jendela 20.00 1.00 20.00 Buah

Jumlah total 20.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

Pintu I 1.00 1.00 1.00 Buah


Pintu II 3.00 1.00 3.00 Buah

Jumlah total 4.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan
V = jumlah jendela x 2

Jendela 20.00 2.00 40.00 Buah

Jumlah total 40.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

m2
m2
m2
m2
m2
Jumlah total - m2
SKETSA

2. Pekerjaan keramik lantai teras 40/40 (anti slip)


Rumus Panjang Lebar Volu kolom Volume Satuan

V=PxL

Lantai teras (anti slip) 18.00 2.00 1.00 36.00 m2

Jumlah total 36.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan
Jumlah total - m2
SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Jumlah total x 4 ruang - m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL 0.66 0.66 5.00 2.18

Jumlah total 2.178 m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen II
v = 1/2 (a) x t 14.00 3.76 2.00 52.64 m2

Sekmen III
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen IV m2
v = sekmen II-sekmen III

Sekmen V
v=axt - - - - m2
Jumlah total 268.192 m2
SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen II
v = 1/2 (a) x t - 14.00 3.76 2.00 52.64 m2

Sekmen III
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen IV m2
v = sekmen II-sekmen III

Sekmen V
v=axt - 2.46 2.00 - m2
Jumlah total 268.192 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 28.56 M'

Jumlah total x 2 sisi 28.56 M'


SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus Volume Satuan

V = panjang Nok 78.88 M'

Jumlah total x 2 sisi 78.88 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2
Jumlah total 106.75 m2
SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2

Jumlah total 106.75 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 11.44 - 1.00 11.44 m2


Ruang penyimpanan 11.44 - 1.00 11.44 m2
Ruang pengelola 11.44 - 1.00 11.44 m2
Ruang administrasi 9.52 - 1.00 9.52 m2
Teras 39.54 - 1.00 39.54 m2
Selasar 56.80 - 1.00 56.80 m2
- - - - m2
- - - - m2

Jumlah total 140.18 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 14 Titik
Pas. Lampu down ligth LED 18 watt 6.00 bh
Pas. Lampu down ligth LED 11 watt 6.00 bh
Pas. Stop kontak panasonic 2.00 bh
Pas. saklar ganda panasonic 2.00 bh
Pas. saklar ganda panasonic 1.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Rumus Panjang Lebar Jml Volume Satuan

Pengecatan dinding dalam


Ruang Praktek 45.36 3.45 1 156
Lubangan jendela 2.54 1.98 8 40
Lubangan Pintu I 3.24 1.29 2 8
Lubangan Pintu II 2.69 0.88 2 5
103
Ruang penyimpanan 11.52 3.45 1 40
Lubangan jendela 2.54 1.98 1 5
Lubangan Pintu II 2.69 0.88 1 2
32

Ruang pengelola 11.52 3.45 1 40


Lubangan jendela 2.54 0.88 1 2
Lubangan Pintu II 2.69 0.88 2 5
33

Ruang administrasi 9.52 3.45 1 33


Lubangan Pintu II 2.69 0.88 1 2
30

Pengecatan dinding luar

53.93 3.50 1 189


Lubangan jendela 2.54 1.98 10 50
Lubangan Pintu I 3.24 1.29 2 8
- - 130.10 m2

Pengecatan dinding latei


22.00 0.55 2.00 24.20

Jumlah total 353.07 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2
- - - - - m2
- - - - - m2

Jumlah total 106.75 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 11.44 0.10 1.00 1.14 m2


Ruang penyimpanan 11.44 0.10 1.00 1.14 m2
Ruang pengelola 11.44 0.10 1.00 1.14 m2
Ruang administrasi 9.52 0.10 1.00 0.95 m2
Teras 39.54 0.10 1.00 3.95 m2
Selasar 56.80 0.10 1.00 5.68 m2
- - - - - m2
- - - - - m2
-
Jumlah total 14.02 m2
SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

Jendela 13.700 0.170 - 10.00 23.290 m2


3.780 0.550 10.00 20.790 m2

Pintu I 6.380 0.170 - 1.00 1.085 m2


3.870 0.170 1.00 0.658 m2
1.000 0.280 1.00 0.280 m2
Pintu II 5.280 0.170 - 1.00 0.898 m2
1.560 0.170 1.00 0.265 m2
Jumlah total 47.27 m2

Jelusi Jenela 0.520 0.240 - 90.00 11.232 m2


Pintu I 0.520 0.240 14.00 1.747 m2
Pintu II 0.520 0.240 27.00 3.370 m2

Jumlah total 16.35 m2


SKETSA

5. Pekerjaan Pengecatan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

Jendela 2.960 0.080 2.00 20.00 9.472 m2


Pintu I 2.100 0.600 2.00 2.00 5.040 m2
Pintu II 2.100 0.800 2.00 3.00 10.080 m2

Jumlah total 15.12 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 78.88 0.30 23.664

Jumlah total 23.66 m2


SKETSA

Meja beton
1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL 1.00 0.30 0.300 0.090

Jumlah total 0.09 m2


SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : REHABILITASI RUANG KELAS BESERTA PERABOTNYA
VOLUME : 12 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 20,750,000.00


A. PEKERJAAN REHABILITASI 12 RUANG Rp 2,241,526,258.19
I. PEKERJAAN PASANGAN BATU & BETON Rp 8,695,432.00
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 83,649,244.80
III. PEKERJAAN KERAMIK Rp 130,643,679.69
IV. PEKERJAAN KACA Rp 5,895,019.23
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 1,806,197,373.61
VI. PEKERJAAN LISTRIK Rp 41,007,280.00
VII PEKERJAAN PENGECATAN Rp 165,438,228.86

C. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 58,264,400.00

C. Jumlah Rp 2,320,540,658.19
D. PPn 11% Rp 255,259,472.40
E. Total (D + E) Rp 2,575,800,130.59
PEMBULATAN Rp 2,575,800,000.00
Terbilang : #NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : REHABILITASI RUANG KELAS BESERTA PERABOTNYA
VOLUME : 12 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)

A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI


1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 16,800,000.00 16,800,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 20,750,000.00
B. PEKERJAAN REHABILITASI 12 RUANG
I. PEKERJAAN PASANGAN BATU & BETON
1 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Selasar Keliling Gedung, tbl = 6 cm M3 4.00 2,173,858.00 8,695,432.00
Jumlah - A.2 8,695,432.00
III. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Daun Pintu Panel, kayu kls. I M2 30.24 1,186,248.00 35,872,139.52
2 Daun Jendela / Kom Jendela, kayu kls.I M2 23.04 866,857.00 19,972,385.28
3 Engsel pintu 4" Bh 36.00 83,565.00 3,008,340.00
4 Engsel jendela Bh 120.00 60,742.00 7,289,040.00
5 Grendel jendela Bh 60.00 49,411.00 2,964,660.00
6 Kunci tanam Bh 12.00 404,180.00 4,850,160.00
7 Kait Angin Bh 120.00 80,771.00 9,692,520.00
Jumlah - A.4 83,649,244.80
IV. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Kelas (polos) M2 277.89 376,941.00 104,748,134.49
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 66.60 388,822.00 25,895,545.20
Jumlah - A.5 130,643,679.69
V. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm (ganti yang pecah 15%) M2 23.52 250,613.00 5,895,019.23
Jumlah - A.6 5,895,019.23
VI. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 2,079.97 458,397.00 953,451,091.30
2 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 2,079.97 142,602.00 296,607,596.74
3 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 65.92 296,318.00 19,533,282.56
4 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 382.27 106,002.00 40,521,342.14
5 Pek. Rangka plafond Hollow 2/4 & 4/4 M2 1,318.09 233,455.00 307,715,354.62
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 1,318.09 120,251.00 158,501,977.29
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 407.04 46,504.00 18,928,988.16
8 Pek. Lis plafond kayu profil, lbr = 8 cm (teras) M' 235.20 46,504.00 10,937,740.80
9 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 306.24 46,504.00 14,241,384.96
Jumlah - A.7 1,806,197,373.61
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
VII. PEKERJAAN LISTRIK
1 Pek. Titik listrik (ganti 30%) TTK 17.00 515,312.00 8,760,304.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 48.00 411,264.00 19,740,672.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 20.00 375,648.00 7,512,960.00
4 Pas. Stop kontak broco BH 12.00 86,464.00 1,037,568.00
5 Pas. Saklar ganda broco BH 12.00 89,824.00 1,077,888.00
6 Pas. Saklar tunggal broco BH 12.00 89,824.00 1,077,888.00
7 Pas. MCB 6 A (lengkap) BH 12.00 150,000.00 1,800,000.00
8 Pek. Panel MCB 2 grup lengkap pemasangannya Unit 0.00 650,000.00 0.00
Jumlah - A.8 41,007,280.00
VIII. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 2,141.58 41,919.00 89,772,791.41
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 1,286.09 41,090.00 52,845,553.15
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 94.85 43,257.00 4,102,839.94
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 218.57 43,257.00 9,454,855.52
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 91.20 43,257.00 3,945,038.40
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 122.92 43,257.00 5,317,150.44
Jumlah - A.9 165,438,228.86
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER
Meja Tunggal + Kursi Siswa (M-02/K-02), model ; 1mj + 1kr BH 36.00 1,029,400.00 37,058,400.00
Meja Guru / Meja Kerja (M-01), model ; 1/5 biro BH 2.00 3,636,400.00 7,272,800.00
Kursi Guru & Siswa (K-01), bahan ; kombinasi besi, plastik, spons pakai sandaran BH 2.00 852,600.00 1,705,200.00
Papan Tulis White Board (P-01) BH 2.00 1,870,700.00 3,741,400.00
Lemari Simpan (L-01) BH 2.00 4,243,300.00 8,486,600.00
BH

JUMLAH - B 58,264,400.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 20,750,000.00


B. PEKERJAAN REHABILITASI 12 RUANG Rp. 2,241,526,258.19
I. PEKERJAAN PASANGAN BATU & BETON Rp. 8,695,432.00
II. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 83,649,244.80
III. PEKERJAAN KERAMIK Rp. 130,643,679.69
IV. PEKERJAAN KACA Rp. 5,895,019.23
V. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 1,806,197,373.61
VI. PEKERJAAN LISTRIK Rp. 41,007,280.00
VII PEKERJAAN PENGECATAN Rp. 165,438,228.86

C. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 58,264,400.00


JUMLAH Rp. 2,320,540,658.19
PEMBULATAN Rp 2,320,540,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 40.00 Bh 100,000.00 4,000,000.00
2 Sarung Tangan (Safeti Gloves) 40.00 Psg 15,000.00 600,000.00
3 Sepatu Keselamatan (Safety Shoes) 40.00 Psg 200,000.00 8,000,000.00
4 Rompi Keselamatan (Safety Vest) 40.00 Bh 50,000.00 2,000,000.00
sub total 14,600,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 16,800,000.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 98.53 1.00 0.70 68.97 m3

Jumlah total 68.97 m3


SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 64.00 0.49 0.40 12.54 m3

Jumlah total 12.54 m3


SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) 68.97 26.50 3.94 11.82 26.71 m3

Jumlah total 26.71 m3


SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 1.75 1.75 0.15 0.46 m3


Lantai selasar 56.00 0.75 0.15 6.30 m3
Lantai ruang tamu 2.75 4.75 0.20 2.61 m3
Lantai ruang belajar 11.00 2.75 0.20 6.05 m3
Lantai ruang tidur 11.00 4.75 0.20 10.45 m3
Lantai dapur 2.75 4.75 0.20 2.61 m3
Lantai WC/KM
1 1.50 1.62 0.20 0.49 m3
2 1.50 1.62 0.20 0.49 m3
3 1.50 1.62 0.20 0.49 m3
4 1.50 1.62 0.20 0.49 m3

Jumlah total 30 m3
SKETSA

5. Pekerjaan urug pasir bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

lantai Teras 1.75 1.75 0.05 0.15 m3


Lantai selasar 56.00 0.75 0.05 2.10 m3
Lantai ruang tamu 2.75 4.75 0.05 0.65 m3
Lantai ruang belajar 11.00 2.75 0.05 1.51 m3
Lantai ruang tidur 11.00 4.75 0.05 2.61 m3
Lantai dapur 2.75 4.75 0.05 0.65 m3
Lantai WC/KM
1 1.50 1.62 0.05 0.12 m3
2 1.50 1.62 0.05 0.12 m3
3 1.50 1.62 0.05 0.12 m3
4 1.50 1.62 0.05 0.12 m3

Jumlah total 8.17 m3


SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 98.53 0.80 0.05 3.94 m3

Jumlah total 3.94 m3


SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 98.53 0.80 0.15 11.82 m3

Jumlah total 11.82 m3


SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t 98.53 0.25 0.70 0.70 32.76 m3

Jumlah total 32.76 m3


SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL 64.00 0.46 - 29.44 m2

Jumlah total 29.44 m2


SKETSA

4. Pekerjaan pasangan dinding batu bata semen


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela
V = L x T - (Luas pintu dan
jendela)
Dinding Depan 7.48 3.75 3.47 5.35 19.23 m2
Dinding Belakang 7.24 3.75 3.47 - 23.68 m2
Dinding Samping kiri 16.92 3.75 - 6.76 56.69 m2
Dinding Samping Kanan 16.92 3.75 - 10.37 53.08 m2
Dinding pembagi ruangan 36.24 3.75 20.71 - 115.19 m2
Dinding atas teras 5.64 0.75 4.23 m2

Jumlah total 272.10 m2


SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 20/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 16.00 1.73 m3

Jumlah total 1.734 m3


- Pekerjaan Kolom 20/20 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 2.00 0.22 m3

Jumlah total 0.217 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.75 13.00 0.49 m3

Jumlah total 0.488 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3


Jumlah total 0.180 m3
- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 5.64 0.12 0.15 1.00 0.10 m3

Jumlah total 0.102 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 7.48 3.75 3.47 5.35 19.23 m2
Dinding Belakang 7.24 3.75 3.47 - 23.68 m2
Dinding Samping kiri 16.92 3.75 - 6.76 56.69 m2
Dinding Samping Kanan 16.92 3.75 - 10.37 53.08 m2
Dinding pembagi ruangan 36.24 3.75 20.71 - 115.19 m2
Dinding atas teras 5.64 0.75 - - 4.23 m2
Jumlah total x 2 sisi 544.20 m2
SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.56 3.75 16.00 33.60 m2


Plesteran Kolom teras 0.80 3.75 2.00 6.00 m2

Jumlah total 39.600 m2


3. Pekerjaan Acian dinding
Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

V = L x T - (Luas pintu dan


jendela)
Dinding Depan 7.48 3.75 3.47 5.35 19.23 m2
Dinding Belakang 7.24 3.75 3.47 - 23.68 m2
Dinding Samping kiri 16.92 3.75 - 6.76 56.69 m2
Dinding Samping Kanan 16.92 3.75 - 10.37 53.08 m2
Dinding pembagi ruangan 36.24 3.75 20.71 - 115.19 m2
Dinding atas teras 5.64 0.75 - - 4.23 m2
Jumlah total x 2 sisi 544.20 m2
SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

V = L x t x jumlah

Plesteran Kolom Utama 0.56 3.75 16.00 33.60 m2


Plesteran Kolom teras 0.80 3.75 2.00 6.00 m2

Jumlah total 39.600 m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

Jendela Ventilasi I = 2 bh 11.440 0.110 0.05 2.00 0.126 m3


Jendela Ventilasi II = 8 bh 7.550 0.110 0.05 8.00 0.332 m3
Ventilasi I = 4 bh 1.760 0.110 0.05 4.00 0.039 m3
Pintu ventilasi I = 2 bh 8.260 0.110 0.05 2.00 0.091 m3
Pintu I = 4 bh 5.460 0.110 0.05 4.00 0.120 m3
Pintu II = 4 bh 4.960 0.110 0.05 4.00 0.109 m3

Jumlah total 0.82 m3


SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

Pintu 2.100 1.200 - 15.00 37.800 m2


m2
m2

Jumlah total 37.80 m2


SKETSA

3. Pekerjaan Daun Jendela


Rumus Panjang Lebar Tinggi jumlah Volume Satuan
V=PxL

Jendela 0.800 0.800 - 240.00 153.600 m2


- m2

Jumlah total 153.60 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

12.00 3.00 36.00 Buah

Jumlah total 36.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan
V = jumlah daun jendela x 2

Jendela Ventilasi I = 2 bh 60.00 2.00 120.00 Buah

Jumlah total 120.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan
V = jumlah daun jpintu x 2

12.00 2.00 24.00 Buah

Jumlah total 24.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1

60.00 1.00 60.00 Buah

Jumlah total 60.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

Pintu ventilasi I = 2 bh 2.00 1.00 2.00 Buah


Pintu I = 4 bh 4.00 1.00 4.00 Buah
Pintu II = 4 bh 4.00 1.00 4.00 Buah

Jumlah total 10.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan
V = jumlah jendela x 2

Jendela Ventilasi I = 2 bh 6.00 2.00 12.00 Buah


Jendela Ventilasi II = 8 bh 16.00 2.00 32.00 Buah

Jumlah total 44.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 40/40 (polos)
Rumus Panjang Lebar kolom Volume Satuan

V=PxL

Lantai ruang kelas 8.88 7.88 - 69.97 m2


Lantai depan pintu 1.42 0.12 - 0.17 m2
kolom timbul 0.04 m2

Jumlah total 70.105 m2


Jumlah total x 12 841.258 m2
SKETSA

2. Pekerjaan keramik lantai teras 40/40 (anti slip)


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL

Lantai teras (anti slip) 2.00 27.00 - 54.00 m2


0.36

Jumlah total 53.64 m2


Jumlah total x 4 214.56
SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Lantai KM/WC 20/20 (anti slip)

Sekmen I 1.75 0.78 4.00 5.46 m2


Sekmen II 0.87 0.84 4.00 2.92 m2

Jumlah total 8.38 m2


SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Keramik dinding WC/KM


Sekmen I 1.75 0.50 1.00 0.88 m2
Sekmen II 0.95 1.00 1.00 0.95 m2
Sekmen III 1.63 0.50 1.00 0.82 m2
Sekmen IV 0.81 1.00 1.00 0.81 m2
Sekmen V 0.97 1.50 1.00 1.46 m2
Sekmen VI 1.63 1.50 1.00 2.45 m2

Jumlah total x 4 ruang 7.35 m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL

0.66 0.66 360.00 156.82 m2


m2
m2
m2
m2

Jumlah total 156.816 m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
V= P x L 23.00 - 3.41 2.00 156.86 m2

Sekmen II
v = 1/2 (a+b) x t 23.00 29.00 3.64 2.00 189.28 m2

Sekmen III
v = 1/2 (a+b) x t 4.00 12.22 4.55 2.00 73.80 m2

Sekmen IV m2
v = sekmen II-sekmen III 4.00 12.22 4.55 2.00 73.80

m2

Jumlah total 493.742 m2


Jumlah total x 4 1,974.968
SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
V= P x L 23.00 - 3.41 2.00 156.86 m2

Sekmen II
v = 1/2 (a+b) x t 23.00 29.00 3.64 2.00 189.28 m2

Sekmen III
v = 1/2 (a+b) x t 4.00 12.22 4.55 2.00 73.80 m2

Sekmen IV m2
v = sekmen II-sekmen III 4.00 12.22 4.55 2.00 73.80

m2
Jumlah total 493.742 m2
Jumlah total x 4 1,974.968
SKETSA

3. Pasang Nok atap zincalum/spandek


Rumus Panjang Lebar Volume Satuan

V=PxL 41.20 0.40 16.48 M'


M'

Jumlah total 16.48 M'


Jumlah total x 4 65.92 M'
SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus
Panjang jml sisi Volume Satuan

Sekmen 1 28.77 2.00 57.54


Sekmen 2 12.21 2.00 24.43 M'
Sekmen 3 3.40 4.00 13.60

Jumlah total 95.57 M'


Jumlah total x 4 gedung 382.27 M'
SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang kelas 8.88 7.88 3.00 209.92 m2


Teras 2.00 27.00 - 54.00 m2
Selasar 76.80 0.75 - 57.60 m2

Jumlah total 321.52 m2


Jumlah total x 4 1,286.09
SKETSA
6. Pasang penutup plafond Calsiboard 5mm
Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang kelas 8.88 7.88 3.00 209.92 m2


Teras 2.00 27.00 - 54.00 m2
Selasar 76.80 0.75 - 57.60 m2

Jumlah total 321.52 m2


Jumlah total x 4 1,286.09
SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL
Dalam ruangan kelas 33.92 - 3.00 101.76 m2

Jumlah total 101.76 m2


Jumlah total x 4 407.04

Teras 58.80 - 1.00 58.80 m2

Jumlah total 58.80 m2


Jumlah total x 4 235.20
SKETSA

Luar ruangan 76.56 - 1.00 76.56 m2

Jumlah total 76.56 m2


Jumlah total x 4 306.24
SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 68 Titik
Pas. Lampu down ligth LED 18 watt 48.00 bh
Pas. Lampu down ligth LED 11 watt 20.00 bh
Pas. Stop kontak panasonic 12.00 bh
Pas. saklar ganda panasonic 12.00 bh
Pas. saklar tunggal panasonic 12.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 12.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan Dinding


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Dalam Ruangan 33.92 3.50 12.00 1,424.64 m2


Luar ruangan 72.40 3.35 4.00 970.16 m2
Dinding latei 62.56 0.37 4.00 92.59 m2
2,487.39
Luas Lubang Kusen Pintu 3.24 1.29 12.00 50.16
Luas Lubang kusen jendela 2.54 1.94 60.00 295.66
345.81

Jumlah total 2,141.58 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

v = luas plafond 1,286.09 m2

Jumlah total m2
SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

v = Panjang list x 0,1 948.48 0.10 94.85

Jumlah total - m2
SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Jml sisi Jml jend Volume Satuan

V=PxLxT

Kusen jendela 1.800 0.170 2.00 15.00 9.180


1.800 0.280 2.00 15.00 15.120
2.400 0.170 2.00 15.00 12.240
2.400 0.170 2.00 15.00 12.240
48.780

Kusen pintu 3.190 0.170 2.00 3.00 3.254


0.500 0.280 2.00 3.00 0.840
0.570 0.170 4.00 3.00 1.163
1.190 0.170 1.00 3.00 0.607
5.864

Jumlah total x 4 218.57 m2


SKETSA
5. Pekerjaan pengecatan daun pintu dan daun jendela
Rumus Panjang Lebar Jml sisi jml Volume Satuan

Daun jendela 3.200 0.080 2.00 15.00 7.680 m2

Daun pintu 2.100 1.200 2.00 3.00 15.120


22.800

Jumlah total x 4 91.20 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 382.27 0.30 114.681

Jumlah total 114.68 m2


SKETSA
X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
REKAPITULASI BIAYA

INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : PEMBANGUNAN RUMAH DINAS GURU BESERTA PERABOTNYA
VOLUME : 1 KOPEL / 2 LOKAL
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 9,800,000
B. PEKERJAAN PEMBANGUNAN 2 (DUA) LOKAL Rp 437,982,813.31
I. PEKERJAAN TANAH Rp 9,556,904.00
II. PEKERJAAN PASANGAN BATU & BETON Rp 135,623,035.74
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp 63,544,626.04
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 41,104,199.92
V. PEKERJAAN KERAMIK Rp 32,168,670.06
VI. PEKERJAAN KACA Rp 1,642,801.29
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 98,025,043.40
VIII. PEKERJAAN LISTRIK Rp 14,859,954.00
IX. PEKERJAAN PENGECATAN Rp 28,259,936.86
X. PEKERJAAN SANITAIR Rp 13,197,642.00

C. PENGADAAN PERABOT - RMH DINAS GURU ( 2 LOKAL ) Rp 25,731,600.00

C. Jumlah ( A ) + ( B x 2 Lokal ) Rp 473,514,413.31


D. PPn 11% Rp 52,086,585.46
E. Total (D + E) Rp 525,600,998.77
PEMBULATAN Rp 525,600,000.00

#NAME?

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Wakil Direktur
RENCANA ANGGARAN BIAYA (RAB)
INSTANSI : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : PEMBANGUNAN RUMAH DINAS GURU BESERTA PERABOTNYA
1.00 VOLUME : 1 KOPEL / 2 LOKAL
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI
1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 5,850,000.00 5,850,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 9,800,000.00
B. PEKERJAAN PEMBANGUNAN 2 (DUA) LOKAL
I. PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi M3 18.50 106,400.00 1,968,400.00
2 Pek. Urugan Tanah Kembali M3 12.70 78,400.00 995,680.00
3 Pek. Timbunan Tanah Bawah Lantai (Timbunan Biasa) M3 11.43 576,800.00 6,592,824.00
Jumlah - A.1 9,556,904.00
II. PEKERJAAN PASANGAN BATU & BETON
1 Pas. Pondasi Batu Kali / Karang ad. 1:5 M3 19.43 1,695,036.00 32,934,549.48
2 Pas. Dinding Batu Bata Semen ad. 1:4 M2 223.27 248,192.00 55,412,586.88
3 Pekerjaan Beton Bertulang :
- Beton Sloof 15/20 cm (110 kg/m3) M3 2.49 5,900,806.00 14,693,006.94
- Kolom Praktis 15/15 cm, atas sloof (110 kg/m3) M3 2.16 5,391,724.00 11,646,123.84
- Kolom Praktis 15/15 cm, atas ring balok (110 kg/m3) M3 0.05 5,391,724.00 269,586.20
- Beton Ring Balok 15/20 cm (110 kg/m3) M3 2.49 6,378,760.00 15,883,112.40
- Beton Ring Balok Praktis 15/15 cm, sisi miring (110 kg/m3) M3 0.75 6,378,760.00 4,784,070.00
- Beton Ring Balok Praktis 15/15 cm, Latei (110 kg/m3) M3 0.00 6,378,760.00 0.00
- Plat atap /DAK (110 kg/m3) M3 0.00 6,631,298.00 0.00
Jumlah - A.2 135,623,035.74
III. PEKERJAAN PLESTERAN & ACIAN DINDING
1 Pek. Plesteran Dinding ad. 1 : 4 M2 388.22 104,882.00 40,717,290.04
2 Pek. Acian Dinding dan Kolom M2 388.22 58,800.00 22,827,336.00
Jumlah - A.3 63,544,626.04
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Kosen Pintu, Jendela & Ventilasi, kayu kls. I M3 0.72 15,526,560.00 11,179,123.20
2 Daun Pintu Panel, kayu kls. I M2 17.73 1,119,104.00 19,841,713.92
3 Daun Jendela Panil Kaca, kayu kls.I M2 4.40 813,142.00 3,577,824.80
4 Pas. Engsel Pintu 4" Bh 22.00 80,735.00 1,776,170.00
5 Pas. Engsel Jendela Bh 16.00 58,856.00 941,696.00
6 Pas. Grendel Jendela Bh 8.00 46,508.00 372,064.00
7 Pas. Kunci Tanam (Pintu Panel) Bh 8.00 329,616.00 2,636,928.00
8 Pas. Kait Angin Bh 10.00 77,868.00 778,680.00
Jumlah - A.4 41,104,199.92
V. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Rg. Dalam (polos) M2 66.75 365,750.00 24,413,812.50
2 Pas. Lantai Keramik 40x40 cm Teras Depan (anti slip) M2 4.00 377,631.00 1,510,524.00
3 Pas. Lantai Keramik 20x20 cm Toilet (anti slip) M2 4.32 415,408.00 1,794,562.56
4 Pas. Dinding Keramik 20x25 cm Toilet, H=1,5 m' (polos) M2 15.56 285,975.00 4,449,771.00
Jumlah - A.5 32,168,670.06
VI. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm M2 6.63 247,783.00 1,642,801.29
Jumlah - A.6 1,642,801.29
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pas. Kuda-Kuda Kayu 6/12, Klas I M2 1.20 14,014,784.00 16,817,740.80
2 Pas. Gording Kayu 5/10, Klas II M2 1.04 11,320,680.00 11,773,507.20
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 147.00 139,753.00 20,543,691.00
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 5.60 60,709.00 339,970.40
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 53.00 114,060.00 6,045,180.00
6 Pek. Rangka plafond kayu klas II M2 127.00 185,519.00 23,560,913.00
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 127.00 117,009.00 14,860,143.00
8 Pek. Lis plafond Kayu Profil, lbr = 8 cm (dalam ruang) M' 91.00 44,878.00 4,083,898.00
Jumlah - A.7 98,025,043.40
VIII. PEKERJAAN LISTRIK
1 Pek. Titik Instalasi Lampu TTK 22.00 499,632.00 10,991,904.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 8.00 153,216.00 1,225,728.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 6.00 139,507.00 837,042.00
4 Pas. Stop kontak broco BH 8.00 81,760.00 654,080.00
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
5 Pas. Saklar ganda broco BH 4.00 85,120.00 340,480.00
6 Pas. Saklar tunggal broco BH 6.00 85,120.00 510,720.00
7 Pas. MCB 6 A (lengkap) BH 2.00 150,000.00 300,000.00

Jumlah - A.8 14,859,954.00


IX. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 388.22 40,504.00 15,724,462.88
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 127.00 39,675.00 5,038,725.00
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 127.00 41,966.00 5,329,682.00
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 0.28 41,966.00 11,693.22
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 35.46 41,966.00 1,488,114.36
6 Pek. Cat Lisplank papan Kayu dengan cat Glotex M2 15.90 41,966.00 667,259.40
Jumlah - A.9 28,259,936.86
X. PEKERJAAN SANITAIR
1 Pas. Klosed Jongkok Keramik + Acc Bh 2.00 3,122,884.00 6,245,768.00
2 Pas. Keran Air 1/2" + Asesories Bh 4.00 141,008.00 564,032.00
3 Pas. Floor Drine Stainless steel Bh 2.00 244,834.00 489,668.00
4 Pipa PVC tipe AW 1/2" M' 15.00 63,716.00 955,740.00
5 Pipa PVC tipe AW 2" M' 5.00 154,906.00 774,530.00
6 Pipa PVC tipe AW 3" M' 4.00 166,976.00 667,904.00
7 Pek. Septik Tank & Resapan (Konpensional-Tipe Kecil) Unit 1.00 3,500,000.00 3,500,000.00
Jumlah - A.10 13,197,642.00
C. PENGADAAN PERABOT - RMH DINAS GURU ( 2 LOKAL )
1 Tempat Tidur (ketersediaan) Bh 2.00 4,000,000.00 8,000,000.00
2 Kasur, Bantal, Seprei, Selimut (ketersediaan) Set 2.00 2,500,000.00 5,000,000.00
3 Meja Kerja & Kursi Kerja (M-01 & K-02) Set 2.00 3,588,100.00 7,176,200.00
4 Meja Makan & Kursi Makan (M-10 & K-02) Set 2.00 1,044,000.00 2,088,000.00
5 Meja Tamu & Kursi Tamu (2-1) (K-11 & K-12) Set 2.00 1,733,700.00 3,467,400.00
JUMLAH - B 25,731,600.00

REKAPITULASI BIAYA

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 9,800,000.00


B. PEKERJAAN PEMBANGUNAN 2 (DUA) LOKAL Rp. 437,982,813.31
I. PEKERJAAN TANAH Rp. 9,556,904.00
II. PEKERJAAN PASANGAN BATU & BETON Rp. 135,623,035.74
III. PEKERJAAN PLESTERAN & ACIAN DINDING Rp. 63,544,626.04
IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 41,104,199.92
V. PEKERJAAN KERAMIK Rp. 32,168,670.06
VI. PEKERJAAN KACA Rp. 1,642,801.29
VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 98,025,043.40
VIII. PEKERJAAN LISTRIK Rp. 14,859,954.00
IX. PEKERJAAN PENGECATAN Rp. 28,259,936.86
X. PEKERJAAN SANITAIR Rp. 13,197,642.00
C. PENGADAAN PERABOT - RMH DINAS GURU ( 2 LOKAL ) Rp. 25,731,600.00
JUMLAH Rp. 473,514,413.31
PEMBULATAN Rp 473,514,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PERSIAPAN
1 Pembuatan papan nama proyek Ls 1.00 250,000.00 250,000.00
2 Pembuatan gudang kerja Ls 1.00 5,000,000.00 5,000,000.00
3 Pemasangan bouwplank Ls 1.00 1,750,000.00 1,750,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.00 6,960,000.00 6,960,000.00
5 Air kerja dan listrik Ls 1.00 1,000,000.00 1,000,000.00
Jumlah - A 0.00

XI. PEKERJAAN AKHIR


1 Pek. Pembersihan sisa pekerjaan Ls 1.00 1,200,000.00 1,200,000.00
2 Pelaporan & Dokumentasi Ls 1.00 875,400.00 875,400.00
Jumlah - A.1 0.00

I. PEKERJAAN TANAH
4 Pek. Urugan pasir dibawah pondasi ( 5 cm ) M3 2.92 416,864.00 1,217,242.88
5 Pek. Urugan Pasir dibawah Lantai, tbl = 5 cm M3 3.43 416,864.00 1,429,843.52

II. PEKERJAAN PASANGAN BATU & BETON


1 Pas. Batu kosong M3 #REF! 850,479.00 #REF!
- Kolom Utama 20/20 cm (150 kg/m3) M3 1.25 6,200,588.00 7,738,333.82
4 Pekerjaan Beton ad. 1pc : 2ps : 3kr, Tidak Bertulang :
- Beton Rabat Bawah Lantai, tbl = 5 cm M3 3.43 1,536,668.00 5,270,771.24
- Beton Rabat Keliling Gedung, tbl = 5 cm M3 0.00 1,536,668.00 0.00

III. PEKERJAAN PLESTERAN & ACIAN DINDING


2 Pek. Plesteran kolom ad. 1 : 4 M2 0.00 97,603.00 0.00

IV. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG


4 Jalusi Kusen Pintu & Jendela, kayu kls.II M2 - 797,372.00 0.00
9 Pek. Manumata Unit 2.00 600,000.00 1,200,000.00

V. PEKERJAAN KERAMIK
3 Pas. Plint Keramik 10x40 cm, Ruang Tamu (polos) M' 0.00 51,812.00 0.00

VII. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND


1 Pek. Rangka Atap Baja Ringan (Canai Dingin) Profil C75 M2 147.00 339,817.00 49,953,099.00
3 Pas. Lisplank dobel papan Kayu Klas II, (2 x 30 cm) M' #REF! 99,601.00 #REF!
6 Pek. Rangka Plafond Hollow 2/4 & 4/4 M2 127.00 185,880.00 23,606,760.00
7 Pek. Lis plafond kayu profil, lbr = 8 cm (tirisan luar) M' 14.40 29,966.00 431,510.40

X. PEKERJAAN SANITAIR
2 Pas. Wastafel Keramik + Acc Bh 2.00 911,884.00 1,823,768.00
8 Pek. Saluran Drainase Keliling Gedung uk. 25 x 40 cm M' 48.60 278,112.00 13,516,243.20

XI. PEKERJAAN MEJA BETON


1 Pas. Batu bata Semen ad. 1:4 M2 0.78 182,815.00 142,595.70
2 Pekerjaan Beton Bertulang ad. 1:2:3
- Pelat Lantai Meja Beton, tbl=10 cm (110 kg/m3) M3 0.18 5,503,724.00 990,670.32
3 Pek. Plesteran dinding ad. 1:4 M2 0.78 97,603.00 76,130.34
4 Pas. Keramik 20x20 cm Lantai Meja Beton (polos) M2 1.25 232,901.00 289,961.75
5 Pas. Keramik 20x25 cm Dinding Meja Beton, H=50 cm m (polos) M2 1.35 250,529.00 338,214.15
6 Pas. Wastafel Kitchen Zink Metalco Single Bowls Bh 1.00 871,116.00 871,116.00
7 Pas. Keran air 1/2" + Asesories Bh 1.00 127,512.00 127,512.00
8 Pipa PVC tipe AW 1/2" M' 20.00 31,701.00 634,020.00
9 Pipa PVC tipe AW 2" M' 3.00 63,610.00 190,830.00
0.00
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
GALIAN TANAH PONDASI
Rumus Panjang Lebar Tinggi Volume x2

V=PxLxT 46.85 1.00 0.50 23.43 46.85

Jumlah total 23.43 m3


SKETSA

URGAN KEMBALI
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT 1.00 0.70 5.86 m3

Jumlah total 5.86 m3


SKETSA

TIMBUNAN TANAH BAWAH LANTAI


Rumus Luas Lebar Tinggi Volume x2

Teras 1.66 0.15 0.25 0.50


Ruang Tamu 12.28 0.20 2.46 4.91
Kamar 1 7.59 0.20 1.52 3.04
Kamar 2 6.69 0.20 1.34 2.68
WC 2.43 0.15 0.36 0.73
Ruang Masak 4.86 0.15 0.73 1.46

Jumlah total 6.65 13


SKETSA

PASANG BATU KALI


Rumus Panjang Lebar Tinggi Volume Satuan

46.85 0.48 0.60 13.35 26.70

Jumlah total - 27
SKETSA

BATU KOSONG
Rumus Panjang Lebar Tinggi Volume Satuan

46.85 0.80 0.15 5.62 11.24

Jumlah total - 11
SKETSA
URUG PASIR BAWAH PONDASI
Rumus Panjang Lebar Tinggi Volume Satuan

46.85 0.80 0.05 1.87 3.75

Jumlah total - 4
SKETSA

URUG PASIR BAWAH LANTAI


Rumus Luasan Lebar Tinggi Volume Satuan

Teras 1.66 0.05 0.08 0.17


Ruang Tamu 12.28 0.05 0.61 1.23
Kamar 1 7.59 0.05 0.38 0.76
Kamar 2 6.69 0.05 0.33 0.67
WC 2.43 0.05 0.12 0.24
Ruang Masak 4.86 0.05 0.24 0.49
Jumlah total 1.78 4
SKETSA

DINDING BATA SEMEN


Rumus Panjang Lebar Pintu Jendela Satuan

Depan 1 3.20 2.85 2.33 2.00 4.78


Depan 2 3.73 2.85 - 2.00 8.63
Belakang 1 3.65 2.85 2.33 - 10.40
Belakang 2 4.00 2.85 - - 11.40
Samping kiri 34.70 1.00 - 34.70
Samping kanan 42.00 1.00 - 42.00
Tengah/pembagi ruangan 18.00 3.20 9.32 48.28

Jumlah total 320


Jumlah total X 2

SLOOF15/20
Rumus Panjang Lebar tebal Vol x2

V= Panjang Pondasi 46.85 0.12 0.20 1.12 2.25

Jumlah total 4
SKETSA

KOLOM 15/15
Rumus Tinggi Lebar tebal jml x2

Kolom 1 4.10 0.12 0.12 0.059 0.118


Kolom 2 3.73 0.12 0.12 0.054 0.107
Kolom3 3.20 0.12 0.12 0.046 0.092
Kolom4 3.40 0.12 0.12 0.049 0.098
Kolom5 3.85 0.12 0.12 0.055 0.111

Jumlah total 0.263 0.526


SKETSA
KOLOM GEWEL
Rumus Tinggi Lebar tebal jml x2

Kolom 1 1.78 0.12 0.12 0.026 0.051


Kolom 2 1.32 0.12 0.12 0.019 0.038

Jumlah total 0.045 0.089


SKETSA

BALOK 15/20
Rumus Panjang Lebar tebal jml x2

Balok 1 46.85 0.12 0.20 1.12 2.25


Jumlah total 2.249

Balok Latei 1.50 0.12 0.20 0.04 0.07


Jumlah total 0.072

Kuda-kuda Gewel1 8.45 0.12 0.20 0.20 0.41


Kuda-kuda Gewel 2 8.00 0.12 0.20 0.19 0.38
Jumlah total 0.790

PLAT ATAP
Rumus Tinggi Lebar tebal jml x2

DAK 6.00 0.50 0.12 0.360 0.720


Jumlah total 0.720

ACIAN
Rumus Panjang Lebar Pintu Jendela Satuan

Depan 1 3.20 2.85 2.33 2.00 4.78


Depan 2 3.73 2.85 - 2.00 8.63
Belakang 1 3.65 2.85 2.33 - 10.40
Belakang 2 4.00 2.85 - - 11.40
Samping kiri 17.35 1.00 - 17.35
Samping kanan 42.00 1.00 - 42.00
Tengah/pembagi ruangan 18.00 3.20 9.32 48.28

Jumlah total 286


Jumlah total X 2 571
X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 10.00 Bh 100,000.00 1,000,000.00
2 Sarung Tangan (Safeti Gloves) 10.00 Psg 15,000.00 150,000.00
3 Sepatu Keselamatan (Safety Shoes) 10.00 Psg 200,000.00 2,000,000.00
4 Rompi Keselamatan (Safety Vest) 10.00 Bh 50,000.00 500,000.00
sub total 3,650,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 5,850,000.00
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : REHABILITASI RUANG IBADAH BESERTA PERABOTNYA (SATU RUANG)
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 7,245,000.00


B. PEKERJAAN REHABILITASI 1 RUANG Rp 107,337,663.92
I. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 4,166,300.00
II. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 71,422,147.24
III. PEKERJAAN LISTRIK Rp 2,647,240.00
IV. PEKERJAAN PENGECATAN Rp 29,101,976.68

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 2,400,000.00

C. Jumlah Rp 116,982,663.92
D. PPn 11% Rp 12,868,093.03
E. Total (D + E) Rp 129,850,756.95
PEMBULATAN Rp 129,850,000.00

Terbilang :

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : REHABILITASI RUANG IBADAH BESERTA PERABOTNYA (SATU RUANG)
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI
1 Pembersihan awal dan akhir Ls 1.000 1,500,000.00 1,500,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 3,295,000.00 3,295,000.00
5 Air kerja dan listrik Ls 1.000 1,000,000.00 1,000,000.00
6 Pelaporan dan Dokumentasi Ls 1.000 750,000.00 750,000.00
Jumlah - A.1 7,245,000.00
B. PEKERJAAN REHABILITASI 1 RUANG
I. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Engsel pintu 4" (ganti 100%) Bh 16.00 83,565.00 1,337,040.00
2 Kunci tanam (ganti 100%) Bh 7.00 404,180.00 2,829,260.00
Jumlah - A.7 4,166,300.00
II. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pas. Kuda-Kuda Kayu 6/12, Klas I M2 0.30 15,526,560.00 4,657,968.00
2 Pas. Gording Kayu 5/10, Klas II M2 0.23 11,320,680.00 2,603,756.40
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M2 20.00 296,318.00 5,926,360.00
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M' 1.50 106,002.00 159,003.00
5 Pek. Rangka plafond kayu klas II M2 184.28 185,519.00 34,187,441.32
6 Pek. Penutup Plafond Kalsiboard 5 mm M2 184.28 117,009.00 21,562,418.52
7 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 50.00 46,504.00 2,325,200.00
Jumlah - A.7 71,422,147.24
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
III. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 0.00 515,312.00 0.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 4.00 157,920.00 631,680.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 8.00 144,211.00 1,153,688.00
4 Pas. Stop kontak broco BH 2.00 86,464.00 172,928.00
5 Pas. Saklar ganda broco BH 5.00 89,824.00 449,120.00
6 Pas. Saklar tunggal broco BH 1.00 89,824.00 89,824.00
7 Pas. MCB 6 A (lengkap) BH 1.00 150,000.00 150,000.00
Jumlah - A.8 2,647,240.00
IV. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 450.00 41,919.00 18,863,550.00
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 184.28 41,090.00 7,572,065.20
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 14.00 43,257.00 605,598.00
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 22.98 43,257.00 994,045.86
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 24.66 43,257.00 1,066,717.62
Jumlah - A.9 29,101,976.68
C. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 TOA/ PENGERAS SUARA Bh 2.00 1,200,000.00 2,400,000.00
JUMLAH - B 2,400,000.00

REKAPITULASI BIAYA
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 7,245,000.00
B. PEKERJAAN REHABILITASI 1 RUANG Rp. 107,337,663.92
I. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 4,166,300.00
II. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp. 71,422,147.24
III. PEKERJAAN LISTRIK Rp. 2,647,240.00
IV. PEKERJAAN PENGECATAN Rp. 29,101,976.68

B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 2,400,000.00


JUMLAH Rp. 116,982,663.92
PEMBULATAN Rp 116,982,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
PEK. PINTU CAT PEK. PINTU

Luas jml Luas jml


P1 3.8 3.0 11.3 P1 3.8 3.0 22.5
P2 2 3 5.0 P2 2 3 10.1
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 3.00 Bh 100,000.00 300,000.00
2 Sarung Tangan (Safeti Gloves) 3.00 Psg 15,000.00 45,000.00
3 Sepatu Keselamatan (Safety Shoes) 3.00 Psg 200,000.00 600,000.00
4 Rompi Keselamatan (Safety Vest) 3.00 Bh 50,000.00 150,000.00
sub total 1,095,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 3,295,000.00
REKAPITULASI BIAYA

SKPD : DINAS PENDIDIKAN PROVINSI MALUKU


PEKERJAAN : REHABILITASI RUANG KEPALA SEKOLAH BESERTA PERABOTNYA (SATU RUANG)
VOLUME : 1 RUANG
TAHUN ANGGARAN : 2023
SEKOLAH / LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

JUMLAH HARGA
No JENIS PEKERJAAN
(Rp)

A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp 5,495,000.00


B. PEKERJAAN REHABILITASI 1 RUANG Rp 169,921,239.82
I. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp 18,164,026.40
II. PEKERJAAN KERAMIK Rp 929,284.58
III. PEKERJAAN KACA Rp 300,735.60
IV. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND Rp 126,142,673.44
V. PEKERJAAN LISTRIK Rp 5,045,451.00
VI. PEKERJAAN PENGECATAN Rp 19,339,068.80

B. PEKE PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp 3,636,400.00

C. Jumlah Rp 179,052,639.82
D. PPn 11% Rp 19,695,790.38
E. Total (D + E) Rp 198,748,430.20
PEMBULATAN Rp 198,748,000.00

Terbilang :

Ambon, Mei 2023

Konsultan Perencana
CV. ................................

............................
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
PEKERJAAN : REHABILITASI RUANG KEPALA SEKOLAH BESERTA PERABOTNYA (SATU RUANG)
VOLUME : 1 RUANG
THN. ANGGARAN : 2023
LOKASI : SMA NEGERI 4 SERAM BAGIAN TIMUR

HARGA SATUAN JUMLAH HARGA


No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI
1 Pembersihan awal dan akhir Ls 1.000 1,000,000.00 1,000,000.00
2 Pembuatan papan nama proyek Ls 1.000 200,000.00 200,000.00
3 Pemasangan bouwplank Ls 1.000 500,000.00 500,000.00
4 Pekerjaan SMK3 Konstruksi Ls 1.000 3,295,000.00 3,295,000.00
5 Pelaporan dan Dokumentasi Ls 1.000 500,000.00 500,000.00
Jumlah - A 5,495,000.00
B. PEKERJAAN REHABILITASI 1 RUANG
I. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG
1 Daun Pintu Panel, kayu kls. I 100% M2 11.80 1,186,248.00 13,997,726.40
2 Engsel pintu 4" (ganti 100%) Bh 16.00 83,565.00 1,337,040.00
3 Kunci tanam (ganti 100%) Bh 7.00 404,180.00 2,829,260.00
Jumlah - A.4 18,164,026.40
II. PEKERJAAN KERAMIK
1 Pas. Lantai Keramik 40x40 cm Teras Depan (Ganti yang rusak) M2 2.39 388,822.00 929,284.58
Jumlah - A.5 929,284.58
III. PEKERJAAN KACA
1 Pemasangan Kaca Daun Jendela t= 5 mm (ganti yang picah 25%) M2 1.20 250,613.00 300,735.60
Jumlah - A.6 300,735.60
IV. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND
1 Pas. Kuda-kuda kayu 6/12 kayu kls I (ganti yang rusak) M3 0.21 15,526,560.00 3,260,577.60
2 Pas. Gording Kayu 5/10, Klas II M3 0.60 11,320,680.00 6,792,408.00
3 Pas. Penutup Atap Zincalum Almunium / Spandek, tbl. 0,25 mm M3 210.00 296,318.00 62,226,780.00
4 Pas. Nok Aluminium Spandek (Nok standar 40 cm 18, SWG 22) M2 26.88 296,318.00 7,965,027.84
5 Pas. Lisplank lebar 30 cm, bahan GRC board 9 mm M' 44.00 106,002.00 4,664,088.00
6 Pek. Rangka plafond kayu klas II M2 124.00 185,519.00 23,004,356.00
7 Pek. Penutup Plafond Kalsiboard 5 mm M2 124.00 117,009.00 14,509,116.00
8 Pek. Lis plafond kayu profil, lbr = 8 cm (dalam ruang) M' 80.00 46,504.00 3,720,320.00
Jumlah - A.7 126,142,673.44
HARGA SATUAN JUMLAH HARGA
No ITEM PEKERJAAN SAT VOL.
(Rp) (Rp)
V. PEKERJAAN LISTRIK
1 Pek. Titik listrik TTK 5.00 515,312.00 2,576,560.00
2 Pas. Lampu philips SL 18 watt feting tempel BH 2.00 157,920.00 315,840.00
3 Pas. Lampu philips SL 11 watt feting tempel BH 9.00 144,211.00 1,297,899.00
4 Pas. Stop kontak broco BH 4.00 86,464.00 345,856.00
5 Pas. Saklar ganda broco BH 2.00 89,824.00 179,648.00
6 Pas. Saklar tunggal broco BH 2.00 89,824.00 179,648.00
7 Pas. MCB 6 A (lengkap) BH 1.00 150,000.00 150,000.00
Jumlah - A.8 5,045,451.00
VI. PEKERJAAN PENGECATAN
1 Pek. Cat Dinding luar & Dalam dengan Cat kualitas Metrolite M2 268.80 41,919.00 11,267,827.20
2 Pek. Cat Plafond dengan cat kualitas Metrolite M2 124.00 41,090.00 5,095,160.00
3 Pek. Cat Lis plafond kayu profil, lbr = 8 cm, dengan cat Glotex M2 8.00 43,257.00 346,056.00
4 Pek. Cat Kosen Pintu, Jendela & Ventilasi dengan cat Glotex M2 24.00 43,257.00 1,038,168.00
5 Pek. Cat Daun Pintu, Jendela & Jalusi Ventilasi dengan cat Glotex M2 23.60 43,257.00 1,020,865.20
6 Pek. Cat Papan Lisplank dengan cat Glotex M2 13.20 43,257.00 570,992.40
Jumlah - A.9 19,339,068.80
B. PEKERJAAN PENGADAAN PERABOT / MEUBELER
1 Meja Guru / Meja Kerja (M-01), model ; 1/5 biro Bh 1.00 3,636,400.00 3,636,400.00

JUMLAH - B 3,636,400.00

REKAPITULASI BIAYA
A. PEKERJAAN PERSIAPAN DAN SMK3 KONSTRUKSI Rp. 5,495,000.00
B. PEKERJAAN REHABILITASI 1 RUANG Rp. 169,921,239.82
I. PEKERJAAN KOSEN, KUNCI & PENGGANTUNG Rp. 18,164,026.40
II. PEKERJAAN KERAMIK Rp. 929,284.58
III. PEKERJAAN KACA Rp. 300,735.60
IV. PEKERJAAN RANGKA ATAP, KUDA-KUDA & PLAFOND 126,142,673.44
V. PEKERJAAN LISTRIK Rp. 5,045,451.00
VI. PEKERJAAN PENGECATAN Rp. 19,339,068.80

B. PEKERJAAN PENGADAAN PERABOT / MEUBELER Rp. 3,636,400.00


JUMLAH Rp. 179,052,639.82
PEMBULATAN Rp 179,052,000.00
#NAME?

Keterangan : Harga Tersebut belum termasuk Pajak Pertambahan Nilai (PPn) sebesar 11%
BACK UP DATA

Kegiatan : Pembangunan asrama siswa beserta perabotnya


Lokasi : Desa Gorom
Kec./Kab : Pulau Gorom - Seram Bagian Timur
Item :
II. PEKERJAAN TANAH
1. Pekerjaan galian tanah pondasi bangunan
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT m3

Jumlah total - m3
SKETSA

2. Pekerjaan galian tanah saluran keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT m3

Jumlah total - m3
SKETSA

3. Pekerjaan urug tanah kembali


Galian Pas. Batu pasir urug aanst.
Rumus Volume Satuan
a b c d

V = a-(b+c+d) m3

Jumlah total - m3
SKETSA

4. Pekerjaan urug tanah bawah lantai


Rumus Panjang Lebar Tinggi Volume Satuan

m3
m3
m3
m3
m3
m3

m3
m3
m3
m3

Jumlah total 0 m3
SKETSA
5. Pekerjaan urug pasir bawah lantai
Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT

m3
m3
m3
m3
m3
m3

m3
m3
m3
m3

Jumlah total - m3
SKETSA

6. Pekerjaan urug pasir bawah pondasi


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.80 0.05 - m3

Jumlah total - m3
SKETSA

III. PEKERJAAN PASANGAN BATU & BETON

1. Pekerjaan pasangan batu kosong/aanstaping


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxLxT - 0.80 0.15 - m3

Jumlah total - m3
SKETSA

2. Pekerjaan pasangan pondasi batu kali/karang


lbr atas lbr bwh
Rumus Panjang Tinggi Volume Satuan
a b

V = P x (1/2 x (a+b) x t - 0.25 0.70 0.70 - m3

Jumlah total - m3
SKETSA

3. Pekerjaan pasangan pondasi Rolag rabat keliling


Rumus Panjang Lebar Tinggi Volume Satuan

V=PxL - 0.46 - - m2

Jumlah total - m2
SKETSA

4. Pekerjaan pasangan dinding batu bata semen


Luas
Rumus Labar Tinggi Volume Satuan
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2

Jumlah total - m2
SKETSA

5. Pekerjaan beton bertulang


- Pekerjaan Kolom 20/20 (utama)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 16.00 1.73 m3

Jumlah total 1.734 m3


- Pekerjaan Kolom 20/20 (Kolom teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.17 0.17 3.75 2.00 0.22 m3

Jumlah total 0.217 m3


- Pekerjaan Kolom 12/12 (Kolom praktis)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 0.10 0.10 3.75 13.00 0.49 m3

Jumlah total 0.488 m3

- Pekerjaan Sloof 15/20 (teras)


Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Sloof 15/20 (keliling bangunan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Sloof 12/15 (pembagian ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 15/20 (teras)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan
V = P x L x t x jumlah 6.00 0.15 0.20 1.00 0.18 m3

Jumlah total 0.180 m3


- Pekerjaan Balok 15/20 (Keliling ruangan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 52.00 0.15 0.20 1.00 1.56 m3

Jumlah total 1.560 m3


- Pekerjaan Balok 12/15 (pembagian runagan)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 37.10 0.12 0.15 1.00 0.67 m3

Jumlah total 0.668 m3


- Pekerjaan Balok 12/15 (balok latei)
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 5.64 0.12 0.15 1.00 0.10 m3

Jumlah total 0.102 m3

6. Pekerjaan beton tidak bertulang


- Pekerjaan rabat beton selasar
Rumus Panjang Lebar Tinggi Jumlah Volume Satuan

V = P x L x t x jumlah 56.00 0.76 0.05 1.00 2.11 m3

Jumlah total 2.114 m3

IV. PEKERJAAN PLESTERAN & ACIAN DINDING

1. Pekerjaan Plesteran dinding ad. 1 : 4


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2
Jumlah total x 2 sisi - m2
SKETSA

2. Pekerjaan Plesteran Kolom ad. 1 : 4


Rumus Lebar Tinggi Jumlah Volume Satuan

m2
m2
Jumlah total - m2

3. Pekerjaan Acian dinding


Luas
Rumus Labar Tinggi Volume Satuan
Pintu Jendela

m2
m2
m2
m2
m2
m2
Jumlah total x 2 sisi - m2
SKETSA

4. Pekerjaan Acian Kolom


Rumus Lebar Tinggi Jumlah Volume Satuan

m2
m2

Jumlah total - m2

V. PEKERJAAN KAYU, KUNCI DAN PENGGANTUNG

1. Pekerjaan kusen pintu, jendela dan ventilasi


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

m3
m3
m3
m3
m3
m3

Jumlah total - m3
SKETSA

2. Pekerjaan Daun Pintu


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

Pintu I 0.600 2.100 - 4.00 5.040 m2


Pintu II 0.800 2.100 - 3.00 5.040 m2

Jumlah total 10.08 m2


SKETSA
3. Pekerjaan Daun Jendela
Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxL

0.800 0.800 5.00 3.200 m2

Jumlah total 3.20 m2


SKETSA

4. Pekerjaan Jelusi kayu


Rumus Panjang Lebar Jml jelusi jumlah Volume Satuan

V=PxL

0.500 0.110 9.00 30.00 14.850 m2


0.500 0.110 7.00 2.00 0.770
0.500 0.110 9.00 3.00 1.485

Jumlah total 17.11 m2


SKETSA

4. Pekerjaan Engsel pintu


Rumus Jumlah daun pintu Jumlah engsel Volume Satuan
V = jumlah daun Pintu x 3

Pintu I 1.00 3.00 3.00 Buah


Pintu II 3.00 3.00 9.00 Buah

Jumlah total 12.000 Buah

5. Pekerjaan Engsel jendela


Rumus Jumlah daunjendela Jumlah engsel Volume Satuan
V = jumlah daun jendela x 2

Jendela 20.00 2.00 40.00 Buah

Jumlah total 40.000 Buah

6. Pekerjaan grendel pintu


Rumus Jumlah daun Pintu Jumlah Grendel Volume Satuan
V = jumlah daun jpintu x 2

Pintu I 1.00 2.00 2.00 Buah


Pintu II 3.00 1.00 3.00 Buah

Jumlah total 5.000 Buah

7. Pekerjaan grendel jendela


Rumus Jumlah daun jendela Jumlah Grendel Volume Satuan
V = jumlah daun jendela x 1
Grendel Jendela 20.00 1.00 20.00 Buah

Jumlah total 20.000 Buah

8. Pekerjaan kunci tanam 2"


Rumus Jumlah daun Pintu Jumlah kunci Volume Satuan
V = jumlah pintu x 1

Pintu I 1.00 1.00 1.00 Buah


Pintu II 3.00 1.00 3.00 Buah

Jumlah total 4.000 Buah

9. Pekerjaan kait angin


Rumus Jumlah daun jendela Jumlah kait angin Volume Satuan
V = jumlah jendela x 2

Jendela 20.00 2.00 40.00 Buah

Jumlah total 40.000 Buah

VI. PEKERJAAN KERAMIK


1. Pekerjaan keramik lantai ruang utama 60/60 (polos)
Rumus Panjang Lebar Tinggi Volume Satuan

m2
m2
m2
m2
m2
Jumlah total - m2
SKETSA

2. Pekerjaan keramik lantai teras 40/40 (anti slip)


Rumus Panjang Lebar Volu kolom Volume Satuan

V=PxL

Lantai teras (anti slip) 18.00 2.00 1.00 36.00 m2

Jumlah total 36.00 m2


SKETSA

3. Pekerjaan keramik lantai KM/WC 20/20 (anti slip)


Rumus Panjang Lebar Jml Ruang Volume Satuan
Jumlah total - m2
SKETSA

4. Pekerjaan keramik dinding KM/WC 20/40 (polos)


Rumus Panjang Lebar Jml Ruang Volume Satuan

V=PxL

Jumlah total x 4 ruang - m2


SKETSA

VII. PEKERJAAN KACA


1. Pasang kaca daun jendela dan ventilasi
Rumus Panjang Lebar Jumlah Volume Satuan

V=PxL 0.66 0.66 5.00 2.18

Jumlah total 2.178 m2

VIII. PEKERJAAN ATAP, KUDA-KUDA DAN PLAFOND


1. Pasang rangka atap baja ringan canal C 75 x 35 x 75
Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen II
v = 1/2 (a) x t 14.00 3.76 2.00 52.64 m2

Sekmen III
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen IV m2
v = sekmen II-sekmen III

Sekmen V
v=axt - - - - m2
Jumlah total 268.192 m2
SKETSA

2. Pasang atap zincalum/spandek


Lbr ats Lbr bwh
Rumus Tinggi Jml sisi Volume Satuan
a b

Sekmen I
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen II
v = 1/2 (a) x t - 14.00 3.76 2.00 52.64 m2

Sekmen III
v = 1/2 (a+b) x t 14.00 19.68 3.20 2.00 107.78 m2

Sekmen IV m2
v = sekmen II-sekmen III

Sekmen V
v=axt - 2.46 2.00 - m2
Jumlah total 268.192 m2

3. Pasang Nok atap zincalum/spandek


Rumus Volume Satuan

V = panjang Nok 28.56 M'

Jumlah total x 2 sisi 28.56 M'


SKETSA

4. Pasang Lisplank GRC/ Calsiboard


Rumus Volume Satuan

V = panjang Nok 78.88 M'

Jumlah total x 2 sisi 78.88 M'


SKETSA

5. Pasang rangka plafond Hollow 2/4 dan 4/4


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2
Jumlah total 106.75 m2
SKETSA

6. Pasang penutup plafond Calsiboard 5mm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2

Jumlah total 106.75 m2


SKETSA

7. Pasang list plafond gibsum 10cm


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 11.44 - 1.00 11.44 m2


Ruang penyimpanan 11.44 - 1.00 11.44 m2
Ruang pengelola 11.44 - 1.00 11.44 m2
Ruang administrasi 9.52 - 1.00 9.52 m2
Teras 39.54 - 1.00 39.54 m2
Selasar 56.80 - 1.00 56.80 m2
- - - - m2
- - - - m2

Jumlah total 140.18 m2


SKETSA

VIII. PEKERJAAN LISTRIK


Item pekerjaan Volume Satuan
Pek. Titik instalasi listrik 14 Titik
Pas. Lampu down ligth LED 18 watt 6.00 bh
Pas. Lampu down ligth LED 11 watt 6.00 bh
Pas. Stop kontak panasonic 2.00 bh
Pas. saklar ganda panasonic 2.00 bh
Pas. saklar ganda panasonic 1.00 bh
Pas. Box MCB 4 group tempel tuitup transparan + MCB 6 A = 4bh 1.00 Unit

IX. PEKERJAAN PENGECATAN

1. Pekerjaan Pengecatan dinding


Rumus Panjang Lebar Jml Volume Satuan

Pengecatan dinding dalam


Ruang Praktek 45.36 3.45 1 156
Lubangan jendela 2.54 1.98 8 40
Lubangan Pintu I 3.24 1.29 2 8
Lubangan Pintu II 2.69 0.88 2 5
103
Ruang penyimpanan 11.52 3.45 1 40
Lubangan jendela 2.54 1.98 1 5
Lubangan Pintu II 2.69 0.88 1 2
32

Ruang pengelola 11.52 3.45 1 40


Lubangan jendela 2.54 0.88 1 2
Lubangan Pintu II 2.69 0.88 2 5
33

Ruang administrasi 9.52 3.45 1 33


Lubangan Pintu II 2.69 0.88 1 2
30

Pengecatan dinding luar

53.93 3.50 1 189


Lubangan jendela 2.54 1.98 10 50
Lubangan Pintu I 3.24 1.29 2 8
- - 130.10 m2

Pengecatan dinding latei


22.00 0.55 2.00 24.20

Jumlah total 353.07 m2


SKETSA

2. Pekerjaan Pengecatan Plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 2.84 2.88 1.00 8.18 m2


Ruang penyimpanan 2.84 2.88 1.00 8.18 m2
Ruang pengelola 2.84 2.88 1.00 8.18 m2
Ruang administrasi 2.88 1.88 1.00 5.41 m2
Teras 17.89 1.88 1.00 33.63 m2
Selasar 56.80 0.76 1.00 43.17 m2
- - - - - m2
- - - - - m2

Jumlah total 106.75 m2


SKETSA

3. Pekerjaan Pengecatan list plafond


Rumus Panjang Lebar jml ruang Volume Satuan

V=PxL

Ruang Praktek 11.44 0.10 1.00 1.14 m2


Ruang penyimpanan 11.44 0.10 1.00 1.14 m2
Ruang pengelola 11.44 0.10 1.00 1.14 m2
Ruang administrasi 9.52 0.10 1.00 0.95 m2
Teras 39.54 0.10 1.00 3.95 m2
Selasar 56.80 0.10 1.00 5.68 m2
- - - - - m2
- - - - - m2
-
Jumlah total 14.02 m2
SKETSA

4. Pekerjaan Pengecatan kusen


Rumus Panjang Lebar Tinggi jumlah Volume Satuan

V=PxLxT

Jendela 13.700 0.170 - 10.00 23.290 m2


3.780 0.550 10.00 20.790 m2

Pintu I 6.380 0.170 - 1.00 1.085 m2


3.870 0.170 1.00 0.658 m2
1.000 0.280 1.00 0.280 m2
Pintu II 5.280 0.170 - 1.00 0.898 m2
1.560 0.170 1.00 0.265 m2
Jumlah total 47.27 m2

Jelusi Jenela 0.520 0.240 - 90.00 11.232 m2


Pintu I 0.520 0.240 14.00 1.747 m2
Pintu II 0.520 0.240 27.00 3.370 m2

Jumlah total 16.35 m2


SKETSA

5. Pekerjaan Pengecatan daun pintu dan daun jendela


Rumus Panjang Lebar Jml sisi jml Volume Satuan

V=PxLxT

Jendela 2.960 0.080 2.00 20.00 9.472 m2


Pintu I 2.100 0.600 2.00 2.00 5.040 m2
Pintu II 2.100 0.800 2.00 3.00 10.080 m2

Jumlah total 15.12 m2


SKETSA

6. Pekerjaan pengecatan lisplank


Rumus Jml sisi jml Volume Satuan

V=PxL 78.88 0.30 23.664

Jumlah total 23.66 m2


SKETSA

Meja beton
1. Meja beton
Rumus tinggi lebar tinggi jml Volume Satuan
tipe I
Pas. Bata 0.70 0.60 - 4.00 1.680 m2
Beton tulangan 1.20 0.60 0.07 1.00 0.041 m3
Plesteran 0.70 0.60 2.00 0.840 m2
keramik 40x40 1.20 0.60 1.295
Wastafel 2.000 bh
Kran air 1/2" 2.000 bh

tipe II
Pas. Bata 0.70 0.60 - 3.00 1.260 m2
Beton tulangan 3.25 0.60 0.07 1.00 0.127 m3
Plesteran 0.70 0.60 4.00 1.680 m2
keramik 40x40 3.25 0.60 1.00 1.950 m2
3.25 0.10 1.00 0.325 m2
0.70 0.10 3.000 0.210 m2
0.80 0.60 1.000 0.480 m2
V. Keramik 2.965

V=PxL 1.00 0.30 0.300 0.090

Jumlah total 0.09 m2


SKETSA

X PEKERJAAN SANITAIR
1. Pekerjaan Saluran keliling
2. Pekerjaan pipa pvc 3" untuk air kotor
3. Pekerjaan pipa pvc 1/2" untuk air bersih
4. Pekerjaan pas. kran 1/2" untuk air bersih
5. Pekerjaan pas. Floor drain
6. Pekerjaan pas. Wastafel zink
7. Pekerjaan pas. Bak mandi

XI PEKERJAAN SEPTINK
1. Pekerjaan Saluran keliling
RENCANA ANGGARAN BIAYA ( RAB )
SKPD : DINAS PENDIDIKAN PROVINSI MALUKU
Kegiatan : PEMBANGUNAN SARANA BELAJAR DAN PENUNJANG SMA NEGERI 4 SERAM BAGIAN TIMUR BESERTA PERABOTN
Tahun Anggaran : 2023
Sekolah / Lokasi : SMA NEGERI 4 SERAM BAGIAN TIMUR

A. PEKERJAAN PERSIAPAN ( UMUM ) DAN SMK3 KONSTRUKSI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. PEKERJAAN SMK3 KONSTRUKSI
I PENYIAPAN RK3K
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan 1.00 Set 250,000.00 250,000.00
sub total 250,000.00
II SOSIALIASI DAN PROMOSI K3
sub total -
III ALAT PELINDUNG KERJA
sub total -
IV AREA PELINDUNG DIRI
1 Topi Pelindung (Safety Net) 2.00 Bh 100,000.00 200,000.00
2 Sarung Tangan (Safeti Gloves) 2.00 Psg 15,000.00 30,000.00
3 Sepatu Keselamatan (Safety Shoes) 2.00 Psg 200,000.00 400,000.00
4 Rompi Keselamatan (Safety Vest) 2.00 Bh 50,000.00 100,000.00
sub total 730,000.00
V ASURANSI DAN PERJANJIAN
sub total -
VI PERSONIL K3
1 Petugas K3 1.00 Ob 1,000,000.00 1,000,000.00
sub total 1,000,000.00
VII FASILITAS SARANA KESEHATAN
1 Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban) 1.00 Ob 300,000.00 300,000.00
sub total 300,000.00
VIII RAMBU-RAMBU
1 Rambu Informasi 1.00 Bh 250,000.00 250,000.00
sub total 250,000.00
IX Lain-Lain Terkait Pengendalian Resiko K3
1 Rambu Petunjuk 1.00 Bh 100,000.00 100,000.00
2 Rambu Larangan 1.00 Bh 100,000.00 100,000.00
3 Rambu Peringatan 1.00 Bh 100,000.00 100,000.00
4 Rambu Kewajiban 1.00 Bh 100,000.00 100,000.00
sub total 400,000.00
TOTAL - A 2,930,000.00
Harga Satuan Pekerjaan Konstruksi Beton
Tahun Anggaran 2023

JML. HRG. per M3 PEMBULATAN


Kode NO.
(Rp.) (Rp.)
M3
BT.13 PN1. Beton Foot Plate 150/150 X 25 Cm (Besi Ø16 -20 Cm = 151,750 Kg/M3) K-250 Site Mix Begisting Papan Rp 5,138,885.40 Rp 5,138,800.00
BT.14 PN2. Beton Foot Plate 130/130 X 25 Cm (Besi Ø16 -20 Cm = 153,431 Kg/M3) K-250 Site Mix Begisting Papan Rp 5,698,707.77 Rp 5,698,700.00
BT.14a PN3. Beton Foot Plate 100/100 X 25 Cm (Besi Ø12 -20 Cm = 87,201 Kg/M3) K-250 Site Mix Begisting Papan Rp 6,272,152.19 Rp 6,272,100.00
BT.14b PN4. Beton Foot Plate 160/160 X 25 Cm (Besi Ø16 -20 Cm = 151,217 Kg/M3) K-250 Site Mix Begisting Papan Rp 4,734,034.47 Rp 4,734,000.00
BT.15 SL1. Beton Sloof 20/30 Cm (Besi 4Ø16 + 6Ø12 Dan Ø8 -15 Cm = 184,953 Kg/M3) K-250 Site Mix Begisting Papan Rp 9,543,155.54 Rp 9,543,100.00
BT.16 SL2. Beton Sloof 20/25 Cm (Besi 8Ø12 Dan Ø8 -15 Cm = 141,087 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.17 SL3. Beton Sloof 15/25 Cm (Besi 4Ø12, Besi 2Ø12 Dan Ø8 -20 Cm = 163,234 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.18 SL4. Beton Sloof 15/20 Cm (Besi 4Ø12, Besi 2Ø10 Dan Ø6 -15 Cm = 155,204 Kg/M3) K-250 Site Mix Begisting Papan Rp 7,567,597.76 Rp 7,567,500.00
BT.19 KL1. Beton Kolom 50/50 Cm (Besi 4Ø19 + 8Ø16 Dan 2Pø10 -10/20 Cm = 114,848 Kg/M3) K-250 Site Mix Begisting Papan Rp 10,098,538.27 Rp 10,098,500.00
BT.20 KL2. Beton Kolom 30/30 Cm (Besi 4Ø16 + 4Ø12 Dan 2Pø10 -10/20 Cm = 153,918 Kg/M3) K-250 Site Mix Begisting Papan Rp 7,989,398.95 Rp 7,989,300.00
BT.21 KL3. Beton Kolom 20/40 Cm (Besi 4Ø16 + 2Ø12 Dan 2Pø10 -20 Cm = 118,984 Kg/M3) K-250 Site Mix Begisting Papan Rp 7,956,963.23 Rp 7,956,900.00
BT.22 KL4. Beton Kolom 25/25 Cm (Besi 4Ø12 + 4Ø10 Dan Ø8 -15 Cm = 104,613 Kg/M3) K-250 Site Mix Begisting Papan Rp 10,113,817.13 Rp 10,113,800.00
BT.23 KL5. Beton Kolom 20/20 Cm (Besi 4Ø12 + 4Ø10 Dan Ø8 -20 Cm = 167,989 Kg/M3) K-250 Site Mix Begisting Papan Rp 16,992,006.47 Rp 16,992,000.00
BT.24 KL6. Beton Kolom 15/15 Cm (Besi 4Ø12 Dan Ø6 -15 Cm = 148,283 Kg/M3) K-175 Site Mix Begisting Papan Rp 11,489,994.69 Rp 11,489,900.00
BT.25 KL7. Beton Kolom Praktis 12/12 Cm (Besi 4Ø10 Dan 2Pø6 -20 Cm = 179,303 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.26 BL1. Beton Balok 30/60 Cm (Besi 8Ø16 + 4Ø12 Dan 2Pø10 -10/20 Cm = 124,813 Kg/M3) K-250 Site Mix Begisting Papan Rp 11,455,820.66 Rp 11,455,800.00
BT.27 BL2. Beton Balok 30/50 Cm (Besi 8Ø16 + 2Ø12 Dan 2Pø10 -10/20 Cm = 132,883 Kg/M3) K-250 Site Mix Begisting Papan Rp 9,252,670.40 Rp 9,252,600.00
BT.28 BL3. Beton Balok 20/40 Cm (Besi 4Ø16 + 2Ø12 Dan 2Pø10 -10/20 Cm = 173,043 Kg/M3) K-250 Site Mix Begisting Papan Rp 8,565,284.38 Rp 8,565,200.00
BT.29 BL4. Beton Balok 20/30 Cm (Besi 3Ø12, Besi 3Ø12 Dan 2Pø8 -20 Cm = 107,982 Kg/M3) K-250 Site Mix Begisting Papan Rp 12,233,477.60 Rp 12,233,400.00
BT.30 BL5. Beton Balok 15/25 Cm (Besi 4Ø12 + 2Ø12 Dan 2Pø8 -20 Cm = 163,234 Kg/M3) K-250 Site Mix Begisting Papan Rp 7,639,722.30 Rp 7,639,700.00
BT.31 BL6. Beton Balok 15/20 Cm (Besi 2Ø12 + 2Ø12 Dan 2Pø8 -20 Cm = 143,650 Kg/M3) K-175 Site Mix Begisting Papan Rp 8,883,949.43 Rp 8,883,900.00
BT.32 BL7. Beton Balok 12/25 Cm (Besi 4Ø10 + 2Ø10 Dan 2Pø6 -20 Cm = 131,446 Kg/M3) K-175 Site Mix Begisting Papan Rp 9,025,251.52 Rp 9,025,200.00
BT.33 PL1. Beton Plat Lantai Tbl. 20 Cm (Besi Ø12 -20 Cm = 101,055 Kg/M3) K-250 Site Mix Begisting Papan Rp 6,121,158.44 Rp 6,121,100.00
BT.34 PL2. Beton Plat Lantai Tbl. 15 Cm (Besi Ø10 -20 Cm + Besi Ø10 -20 Cm = 89,502 Kg/M3) K-250 Site Mix Begisting Papan Rp 7,199,018.39 Rp 7,199,000.00
BT.35 PL3. Beton Plat Lantai Tbl. 12 Cm (Besi Ø10 -20 Cm + Besi Ø10 -20 Cm = 108,263 Kg/M3) K-250 Site Mix Begisting Papan Rp 8,284,800.33 Rp 8,284,800.00
BT.36 PL4. Beton Plat Dinding Tbl. 12 Cm (Besi Ø10 -20 Cm = 107,225 Kg/M3) K-250 Site Mix Begisting Papan Rp 9,904,507.36 Rp 9,904,500.00
BT.37 PL5. Beton Plat Tangga Tbl. 10 Cm (Besi Ø10 -20 Cm = 117,346 Kg/M3) K-250 Site Mix Begisting Papan Rp 8,026,015.68 Rp 8,026,000.00
BT.38 PL6. Beton Plat Kanopi/Lisplank Tbl. 10 Cm, Lbr. 45 Cm (Besi Ø10 -15 Cm = 81,753 Kg/M3) K-250 Site Mix Begisting Papan Rp 6,999,600.01 Rp 6,999,600.00
BT.39 PL7. Beton Plat Meja Pantry Tbl. 10 Cm, Lbr. 60 Cm (Besi Ø10 -20 Cm = 63,297 Kg/M3) K-175 Site Mix Begisting Papan Rp 6,368,178.33 Rp 6,368,100.00
BT.40 PL8. Beton Plat Cetak Ditempat Tbl. 8 Cm, Lbr. 100 Cm (Besi Ø10 -20 Cm = 68,016 Kg/M3) K-175 Site Mix Begisting Papan Rp 7,141,149.16 Rp 7,141,100.00
BT.41 PL9. Beton Plat Lantai Atap Tbl. 10 Cm, Lbr. 100 Cm (Besi Ø10 -20 Cm = 127,135 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.42 KL8. Beton Kolom Bulat Dia. 50 Cm (Besi 8Ø16 Cm Dan 2Pø10 -10/20 Cm = 83,685 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.43 KL9. Beton Kolom Bulat Dia. 25 Cm (Besi Ø12-20 Cm Dan Ø8 -15 Cm = 108,452 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.44 KL10. Beton Kolom 30/40 Cm (Besi 6Ø12 + 4Ø12 Cm Dan Ø8 -15 Cm = 78,898 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.45 SL5. Beton Sloof 20/40 Cm (Besi 8Ø16 + 4Ø12 Dan Ø8 -15 Cm = 195,311 Kg/M3) K-250 Site Mix Begisting Papan Rp 2,352,845.00 Rp 2,352,800.00
BT.46 SL6. Beton Sloof 30/50 Cm (Besi 6Ø16 + 3Ø12 Dan Ø10 -15 Cm = 113,728 Kg/M3) K-250 Site Mix Begisting Papan Rp 8,054,299.84 Rp 8,054,200.00
BT.47 BL8. Beton Balok 20/40 Cm, Portal Pintu Utama (Besi 4Ø12 + 4Ø10 Dan 2Pø8 -20 Cm = 82,669 Kg/M3) K-250 Site Mix Begisting Papan Rp 8,295,972.30 Rp 8,295,900.00
BT.48 KL11. Beton Kolom 30/30 Cm, Portal Pintu Utama (Besi 4Ø12 + 4Ø10 Cm Dan Ø8 -15 Cm = 77,253 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.49 KL12. Beton Kolom 12/25 Cm (Besi 3Ø12 Cm + 3Ø12 Cm Dan Ø6 -15 Cm = 162,375 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.50 KL13. Beton Kolom 12/25 Cm (Besi 6Ø12 Cm Dan Ø6 -15 Cm = 162,375 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.51 KL14. Beton Kolom 12/51 Cm (Besi 10Ø12 Cm Dan Ø6 -15 Cm = 134,895 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.52 KL15. Beton Kolom 12/38 Cm (Besi 8Ø12 Cm Dan Ø6 -15 Cm = 143,888 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.53 KL16. Beton Kolom 12/32 Cm, Pagar Depan (Besi 4Ø12 Cm Dan Ø6 -20 Cm = 89,740 Kg/M3) K-175 Site Mix Begisting Papan #NAME? #NAME?
BT.54 BL9. Beton Balok 12/20 Cm, Pagar Depan (Besi 4Ø10 Dan 2Pø6 -20 Cm = 113,884 Kg/M3) K-175 Site Mix Begisting Papan Rp 9,257,516.17 Rp 9,257,500.00
BT.55 KL17. Beton Kolom 40/60 Cm (Besi 4Ø19 + 8Ø16 Dan 2Pø10 -10/20 Cm = 119,549 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.56 KL18. Beton Kolom 50/60 Cm (Besi 4Ø19 + 10Ø16 Dan 2Pø10 -10/20 Cm = 108,992 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.57 KL19. Beton Kolom 60/60 Cm (Besi 4Ø19 + 12Ø16 Dan 2Pø10 -10/20 Cm = 102,052 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.58 BL10. Beton Balok 30/40 Cm (Besi 5Ø16 + 3Ø16 Dan 2Pø10 -10/20 Cm = 145,070 Kg/M3) K-250 Site Mix Begisting Papan Rp 9,162,919.84 Rp 9,162,900.00
BT.59 BL11. Beton Balok 40/60 Cm (Besi 4Ø19 + 6Ø16 Dan 2Pø10 -10/20 Cm = 106,916 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?
BT.60 PL10. Beton Plat Injakan Tangga Tgi. 50 Cm, Lbr. 100 Cm (Besi Ø10 -20 Cm = 31,589 Kg/M3) K-250 Site Mix Begisting Papan #NAME? #NAME?

Harga Satuan Pekerjaan Beton Halaman : 265


Perhitungan Beton Bertulang
Tahun Anggaran 2017

KODE HARGA +
NO. URAIAN HASIL ANALISA
Anls. KEUNTUNGAN

a b c d

1 Hasil Analisa Pekerjaan Cor Beton Site Mix K-100 D.001 Rp 1,937,927.00
2 Hasil Analisa Pekerjaan Cor Beton Site Mix K-125 D.002 Rp -
3 Hasil Analisa Pekerjaan Cor Beton Site Mix K-150 D.003 Rp 2,095,685.00
4 Hasil Analisa Pekerjaan Cor Beton Site Mix K-100, lantai kerja D.004 Rp 1,819,039.00
5 Hasil Analisa Pekerjaan Cor Beton Site Mix K-175 D.005 Rp 2,177,854.00
6 Hasil Analisa Pekerjaan Cor Beton Site Mix K-200 D.006 Rp 2,255,700.00
7 Hasil Analisa Pekerjaan Cor Beton Site Mix K-225 D.007 Rp -
8 Hasil Analisa Pekerjaan Cor Beton Site Mix K-250 D.008 Rp 2,352,845.00
9 Hasil Analisa Pekerjaan Cor Beton Site Mix K-275 D.009 Rp -
10 Hasil Analisa Pekerjaan Cor Beton Site Mix K-300 D.010 Rp -
11 Hasil Analisa Pekerjaan Cor Beton Site Mix K-325 D.011 Rp -
12 Hasil Analisa Pekerjaan Cor Beton Site Mix K-350 D.012 Rp -
13 Hasil Analisa Pekerjaan Besi Beton Polos/Ulir/U-24 D.013 Rp 22,318.80
14 Hasil Analisa Pekerjaan Sirm & Bongkar D.033 Rp -
15 Hasil Analisa Pekerjaan Begisting Papan D.034 Rp 262,500.00
16 Hasil Analisa Pekerjaan Begisting Plywood 4 mm D.035 Rp 185,190.00
17 Hasil Analisa Pekerjaan Begisting Plywood 9 mm D.036 Rp 187,760.00
18 Hasil Analisa Pekerjaan Stoot Werk D.037 Rp 191,360.00

Analisa_Beton Halaman : 266


Perhitungan Beton Bertulang
Tahun Anggaran 2017

PENGUMPULAN :
PONDASI
PN1. BETON FOOT PLATE 150/150 x 25 CM (Besi ø16 -20 cm = 151,750 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 90.721 Kg Rp 22,318.80 Rp 2,024,790.396
- Begesting Papan (maks. 1 x pakai) 2.900 M2 Rp 262,500.00 Rp 761,250.000
Jumlah PN1. Rp 5,138,885.396

PN2. BETON FOOT PLATE 130/130 x 25 CM (Besi ø16 -20 cm = 153,431 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 121.889 Kg Rp 22,318.80 Rp 2,720,421.980
- Begesting Papan (maks. 1 x pakai) 2.383 M2 Rp 262,500.00 Rp 625,440.789
Jumlah PN2. Rp 5,698,707.770

PN3. BETON FOOT PLATE 100/100 x 25 CM (Besi ø12 -20 cm = 87,201 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 147.756 Kg Rp 22,318.80 Rp 3,297,744.689
- Begesting Papan (maks. 1 x pakai) 2.368 M2 Rp 262,500.00 Rp 621,562.500
Jumlah PN3. Rp 6,272,152.189

PN4. BETON FOOT PLATE 160/160 x 25 CM (Besi ø16 -20 cm = 151,217 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 82.957 Kg Rp 22,318.80 Rp 1,851,501.972
- Begesting Papan (maks. 1 x pakai) 2.018 M2 Rp 262,500.00 Rp 529,687.500
Jumlah PN4. Rp 4,734,034.472

BETON SLOOF
SL1. BETON SLOOF 20/30 CM (Besi 4ø16 + 6ø12 dan ø8 -15 cm = 184,953 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 204.550 Kg Rp 22,318.80 Rp 4,565,310.540
- Begesting Papan (maks. 1 x pakai) 10.000 M2 Rp 262,500.00 Rp 2,625,000.000
Jumlah SL1. Rp 9,543,155.540

SL2. BETON SLOOF 20/25 CM (Besi 8ø12 dan ø8 -15 cm = 141,087 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah SL2. #NAME?

SL3. BETON SLOOF 15/25 CM (Besi 4ø12, Besi 2ø12 dan ø8 -20 cm = 163,234 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah SL3. #NAME?

SL4. BETON SLOOF 15/20 CM (Besi 4ø12, Besi 2ø10 dan ø6 -15 cm = 155,204 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 155.200 Kg Rp 22,318.80 Rp 3,463,877.760
- Begesting Papan (maks. 1 x pakai) 6.670 M2 Rp 262,500.00 Rp 1,750,875.000
Jumlah SL4. Rp 7,567,597.760

SL5. BETON SLOOF 20/40 CM (Besi 8ø16 + 4ø12 dan ø8 -15 cm = 195,311 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 0.000 Kg Rp 22,318.80 Rp -
- Begesting Papan (maks. 1 x pakai) 0.000 M2 Rp 262,500.00 Rp -
Jumlah SL5. Rp 2,352,845.000

SL6. BETON SLOOF 30/50 CM (Besi 6ø16 + 3ø12 dan ø10 -15 cm = 113,728 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 177.046 Kg Rp 22,318.80 Rp 3,951,454.844
- Begesting Papan (maks. 1 x pakai) 6.667 M2 Rp 262,500.00 Rp 1,750,000.000
Jumlah SL6. Rp 8,054,299.844

Analisa_Beton Halaman : 267


Perhitungan Beton Bertulang
Tahun Anggaran 2017

BETON KOLOM
KL1. BETON KOLOM 50/50 CM (Besi 4ø19 + 8ø16 dan 2Pø10 -10/20 cm = 114,848 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 229.434 Kg Rp 22,318.80 Rp 5,120,693.275
- Begesting Papan (maks. 1 x pakai) 10.000 M2 Rp 262,500.00 Rp 2,625,000.000
Jumlah KL1. Rp 10,098,538.275

KL2. BETON KOLOM 30/30 CM (Besi 4ø16 + 4ø12 dan 2Pø10 -10/20 cm = 153,918 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 150.615 Kg Rp 22,318.80 Rp 3,361,553.951
- Begesting Papan (maks. 1 x pakai) 8.667 M2 Rp 262,500.00 Rp 2,275,000.000
Jumlah KL2. Rp 7,989,398.951

KL3. BETON KOLOM 20/40 CM (Besi 4ø16 + 2ø12 dan 2Pø10 -20 cm = 118,984 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 94.276 Kg Rp 22,318.80 Rp 2,104,118.225
- Begesting Papan (maks. 1 x pakai) 13.333 M2 Rp 262,500.00 Rp 3,500,000.000
Jumlah KL3. Rp 7,956,963.225

KL4. BETON KOLOM 25/25 CM (Besi 4ø12 + 4ø10 dan ø8 -15 cm = 104,613 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 141.456 Kg Rp 22,318.80 Rp 3,157,125.972
- Begesting Papan (maks. 1 x pakai) 17.538 M2 Rp 262,500.00 Rp 4,603,846.154
Jumlah KL4. Rp 10,113,817.126

KL5. BETON KOLOM 20/20 CM (Besi 4ø12 + 4ø10 dan ø8 -20 cm = 167,989 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 263.866 Kg Rp 22,318.80 Rp 5,889,161.467
- Begesting Papan (maks. 1 x pakai) 33.333 M2 Rp 262,500.00 Rp 8,750,000.000
Jumlah KL5. Rp 16,992,006.467

KL6. BETON KOLOM 15/15 CM (Besi 4ø12 dan ø6 -15 cm = 148,283 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) 221.210 Kg Rp 22,318.80 Rp 4,937,140.686
- Begesting Papan (maks. 1 x pakai) 16.667 M2 Rp 262,500.00 Rp 4,375,000.000
Jumlah KL6. Rp 11,489,994.686

KL7. BETON KOLOM PRAKTIS 12/12 CM (Besi 4ø10 dan 2Pø6 -20 cm = 179,303 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL7. #NAME?

KL8. BETON KOLOM BULAT DIA. 50 CM (Besi 8ø16 cm dan 2Pø10 -10/20 cm = 83,685 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL8. #NAME?

KL9. BETON KOLOM BULAT DIA. 25 CM (Besi ø12-20 cm dan ø8 -15 cm = 108,452 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL9. #NAME?

KL10. BETON KOLOM 30/40 CM (Besi 6ø12 + 4ø12 cm dan ø8 -15 cm = 78,898 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL10. #NAME?

Analisa_Beton Halaman : 268


Perhitungan Beton Bertulang
Tahun Anggaran 2017

KL11. BETON KOLOM 30/30 CM, Portal Pintu Utama (Besi 4ø12 + 4ø10 cm dan ø8 -15 cm = 77,253 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL11. #NAME?

KL12. BETON KOLOM 12/25 CM (Besi 3ø12 cm + 3ø12 cm dan ø6 -15 cm = 162,375 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL12. #NAME?

KL13. BETON KOLOM 12/25 CM (Besi 6ø12 cm dan ø6 -15 cm = 162,375 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL13. #NAME?

KL14. BETON KOLOM 12/51 CM (Besi 10ø12 cm dan ø6 -15 cm = 134,895 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL14. #NAME?

KL15. BETON KOLOM 12/38 CM (Besi 8ø12 cm dan ø6 -15 cm = 143,888 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL15. #NAME?

KL16. BETON KOLOM 12/32 CM, Pagar Depan (Besi 4ø12 cm dan ø6 -20 cm = 89,740 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL16. #NAME?

KL17. BETON KOLOM 40/60 CM (Besi 4ø19 + 8ø16 dan 2Pø10 -10/20 cm = 119,549 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL17. #NAME?

KL18. BETON KOLOM 50/60 CM (Besi 4ø19 + 10ø16 dan 2Pø10 -10/20 cm = 108,992 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL18. #NAME?

KL19. BETON KOLOM 60/60 CM (Besi 4ø19 + 12ø16 dan 2Pø10 -10/20 cm = 102,052 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL19. #NAME?

KL20. BETON KOLOM 30/50 CM (Besi 5ø16 + 5ø16 dan 2Pø10 -10/20 cm = 102,052 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah KL20. #NAME?

Analisa_Beton Halaman : 269


Perhitungan Beton Bertulang
Tahun Anggaran 2017

BETON BALOK
BL1. BETON BALOK 30/60 CM (Besi 8ø16 + 4ø12 dan 2Pø10 -10/20 cm = 124,813 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 284.367 Kg Rp 22,318.80 Rp 6,346,725.657
- Begesting Papan (maks. 1 x pakai) 10.500 M2 Rp 262,500.00 Rp 2,756,250.000
Jumlah BL1. Rp 11,455,820.657

BL2. BETON BALOK 30/50 CM (Besi 8ø16 + 2ø12 dan 2Pø10 -10/20 cm = 132,883 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 209.355 Kg Rp 22,318.80 Rp 4,672,552.675
- Begesting Papan (maks. 1 x pakai) 8.485 M2 Rp 262,500.00 Rp 2,227,272.727
Jumlah BL2. Rp 9,252,670.402

BL3. BETON BALOK 20/40 CM (Besi 4ø16 + 2ø12 dan 2Pø10 -10/20 cm = 173,043 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 181.846 Kg Rp 22,318.80 Rp 4,058,593.225
- Begesting Papan (maks. 1 x pakai) 8.205 M2 Rp 262,500.00 Rp 2,153,846.154
Jumlah BL3. Rp 8,565,284.379

BL4. BETON BALOK 20/30 CM (Besi 3ø12, Besi 3ø12 dan 2Pø8 -20 cm = 107,982 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 278.045 Kg Rp 22,318.80 Rp 6,205,632.601
- Begesting Papan (maks. 1 x pakai) 14.000 M2 Rp 262,500.00 Rp 3,675,000.000
Jumlah BL4. Rp 12,233,477.601

BL5. BETON BALOK 15/25 CM (Besi 4ø12 + 2ø12 dan 2Pø8 -20 cm = 163,234 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 142.789 Kg Rp 22,318.80 Rp 3,186,877.298
- Begesting Papan (maks. 1 x pakai) 8.000 M2 Rp 262,500.00 Rp 2,100,000.000
Jumlah BL5. Rp 7,639,722.298

BL6. BETON BALOK 15/20 CM (Besi 2ø12 + 2ø12 dan 2Pø8 -20 cm = 143,650 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) 143.650 Kg Rp 22,318.80 Rp 3,206,095.432
- Begesting Papan (maks. 1 x pakai) 13.333 M2 Rp 262,500.00 Rp 3,500,000.000
Jumlah BL6. Rp 8,883,949.432

BL7. BETON BALOK 12/25 CM (Besi 4ø10 + 2ø10 dan 2Pø6 -20 cm = 131,446 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) 189.186 Kg Rp 22,318.80 Rp 4,222,397.523
- Begesting Papan (maks. 1 x pakai) 10.000 M2 Rp 262,500.00 Rp 2,625,000.000
Jumlah BL7. Rp 9,025,251.523

BL8. BETON BALOK 20/40 CM, Portal Pintu Utama (Besi 4ø12 + 4ø10 dan 2Pø8 -20 cm = 82,669 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 142.789 Kg Rp 22,318.80 Rp 3,186,877.298
- Begesting Papan (maks. 1 x pakai) 10.500 M2 Rp 262,500.00 Rp 2,756,250.000
Jumlah BL8. Rp 8,295,972.298

BL9. BETON BALOK 12/20 CM, Pagar Depan (Besi 4ø10 dan 2Pø6 -20 cm = 113,884 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) 223.115 Kg Rp 22,318.80 Rp 4,979,662.170
- Begesting Papan (maks. 1 x pakai) 8.000 M2 Rp 262,500.00 Rp 2,100,000.000
Jumlah BL9. Rp 9,257,516.170

BL10. BETON BALOK 30/40 CM (Besi 5ø16 + 3ø16 dan 2Pø10 -10/20 cm = 145,070 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 148.309 Kg Rp 22,318.80 Rp 3,310,074.842
- Begesting Papan (maks. 1 x pakai) 13.333 M2 Rp 262,500.00 Rp 3,500,000.000
Jumlah BL10. Rp 9,162,919.842

BL11. BETON BALOK 40/60 CM (Besi 4ø19 + 6ø16 dan 2Pø10 -10/20 cm = 106,916 Kg/m3) K-250 SITE MIX BEGISTING PAPAN

Analisa_Beton Halaman : 270


Perhitungan Beton Bertulang
Tahun Anggaran 2017

- Beton Site Mix K-250 #NAME? M3 Rp 2,352,845.00 #NAME?


- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah BL11. #NAME?

BL12. BETON BALOK 40/70 CM (Besi 4ø19 + 8ø16 dan 2Pø10 -10/20 cm = 105,740 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 #NAME? M3 Rp 2,352,845.00 #NAME?
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah BL12. #NAME?

BETON PLAT
PL1. BETON PLAT LANTAI TBL. 20 CM (Besi ø12 -20 cm = 101,055 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 110.033 Kg Rp 22,318.80 Rp 2,455,813.436
- Begesting Papan (maks. 1 x pakai) 5.000 M2 Rp 262,500.00 Rp 1,312,500.000
Jumlah PL1. Rp 6,121,158.436

PL2. BETON PLAT LANTAI TBL. 15 CM (Besi ø10 -20 cm + Besi ø10 -20 cm = 89,502 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 138.725 Kg Rp 22,318.80 Rp 3,096,173.391
- Begesting Papan (maks. 1 x pakai) 6.667 M2 Rp 262,500.00 Rp 1,750,000.000
Jumlah PL2. Rp 7,199,018.391

PL3. BETON PLAT LANTAI TBL. 12 CM (Besi ø10 -20 cm + Besi ø10 -20 cm = 108,263 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 167.771 Kg Rp 22,318.80 Rp 3,744,455.325
- Begesting Papan (maks. 1 x pakai) 8.333 M2 Rp 262,500.00 Rp 2,187,500.000
Jumlah PL3. Rp 8,284,800.325

PL4. BETON PLAT DINDING TBL. 12 CM (Besi ø10 -20 cm = 107,225 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 118.808 Kg Rp 22,318.80 Rp 2,651,662.357
- Begesting Papan (maks. 1 x pakai) 18.667 M2 Rp 262,500.00 Rp 4,900,000.000
Jumlah PL4. Rp 9,904,507.357

PL5. BETON PLAT TANGGA TBL. 10 CM (Besi ø10 -20 cm = 117,346 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 156.176 Kg Rp 22,318.80 Rp 3,485,670.684
- Begesting Papan (maks. 1 x pakai) 8.333 M2 Rp 262,500.00 Rp 2,187,500.000
Jumlah PL5. Rp 8,026,015.684

PL6. BETON PLAT KANOPI/LISPLANK TBL. 10 CM, LBR. 45 CM (Besi ø10 -15 cm = 81,753 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) 90.585 Kg Rp 22,318.80 Rp 2,021,755.013
- Begesting Papan (maks. 1 x pakai) 10.000 M2 Rp 262,500.00 Rp 2,625,000.000
Jumlah PL6. Rp 6,999,600.013

PL7. BETON PLAT MEJA PANTRY TBL. 10 CM, LBR. 60 CM (Besi ø10 -20 cm = 63,297 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) 70.135 Kg Rp 22,318.80 Rp 1,565,324.335
- Begesting Papan (maks. 1 x pakai) 10.000 M2 Rp 262,500.00 Rp 2,625,000.000
Jumlah PL7. Rp 6,368,178.335

PL8. BETON PLAT CETAK DITEMPAT TBL. 8 CM, LBR. 100 CM (Besi ø10 -20 cm = 68,016 Kg/m3) K-175 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-175 1.000 M3 Rp 2,177,854.00 Rp 2,177,854.000
- Besi Beton (polos/ulir) 75.364 Kg Rp 22,318.80 Rp 1,682,045.157
- Begesting Papan (maks. 1 x pakai) 12.500 M2 Rp 262,500.00 Rp 3,281,250.000

Analisa_Beton Halaman : 271


Perhitungan Beton Bertulang
Tahun Anggaran 2017

Jumlah PL8. Rp 7,141,149.157

PL9. BETON PLAT LANTAI ATAP TBL. 10 CM, LBR. 100 CM (Besi ø10 -20 cm = 127,135 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah PL9. #NAME?

PL10. BETON PLAT INJAKAN TANGGA TGI. 50 CM, LBR. 100 CM (Besi ø10 -20 cm = 31,589 Kg/m3) K-250 SITE MIX BEGISTING PAPAN
- Beton Site Mix K-250 1.000 M3 Rp 2,352,845.00 Rp 2,352,845.000
- Besi Beton (polos/ulir) #NAME? Kg Rp 22,318.80 #NAME?
- Begesting Papan (maks. 1 x pakai) #NAME? M2 Rp 262,500.00 #NAME?
Jumlah PL10. #NAME?

Analisa_Beton Halaman : 272


MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

BETON FOOT PLATE

1 Pek. Plat Pondasi Poer P.1 (175x175)


Beton :
Persegi 0.350 x 1.750 x 1.633 = 1.000 m3
BESTAT :
Tulangan atas ø 19 - 20 cm 2.373 x 8.750 bh 2.109 x 2.00 bh = 87.570 kg
Tulangan bawah ø 16 - 20 cm 2.490 x 8.163 bh 1.480 x 2.00 bh = 60.186 kg
Berat besi (kg) -----> = 147.756 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 147.760 = 147.756 kg
Bekisting tiap m3 Beton 2.370 = 2.368 m2

2 Pek. Plat Pondasi Poer P.2 (150x190X25)


Beton :
Persegi 0.350 x 1.900 x 1.504 = 1.000 m3
BESTAT :
Tulangan atas ø 16 - 20 cm 2.244 x 9.500 bh 1.480 x 2.00 bh = 63.115 kg
Tulangan bawah ø 16 - 20 cm 2.640 x 7.519 bh 1.480 x 2.00 bh = 58.774 kg
Berat besi (kg) -----> = 121.889 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 121.890 = 121.889 kg
Bekisting tiap m3 Beton 2.380 = 2.383 m2

3 Pek. Plat Pondasi Poer P.3 (80x80X25)


Beton :
Persegi 0.250 x 0.800 x 5.000 = 1.000 m3
BESTAT :
Tulangan atas ø 12 - 20 cm 5.540 x 4.000 bh 0.815 x 2.00 bh = 36.119 kg
Tulangan bawah ø 12 - 20 cm 1.340 x 25.000 bh 0.815 x 2.00 bh = 54.602 kg
Berat besi (kg) -----> = 90.721 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 90.720 = 90.721 kg
Bekisting tiap m3 Beton 2.900 = 2.900 m2

4 Pek. Plat Pondasi Poer P.4 (175X75+170X70)


Beton :
Persegi 0.250 x 1.750 x 2.286 = 1.000 m3
BESTAT :
Tulangan atas ø 12 - 20 cm 2.826 x 8.750 bh 0.815 x 2.00 bh = 40.300 kg
Tulangan bawah ø 12 - 20 cm 2.290 x 11.429 bh 0.815 x 2.00 bh = 42.657 kg
Berat besi (kg) -----> = 82.957 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 82.960 = 82.957 kg
Bekisting tiap m3 Beton 2.020 = 2.018 m2

5 Pek. Plat Pondasi Poer PT.1 (100x110)


Beton :
Persegi 0.250 x 1.100 x 3.636 = 1.000 m3
BESTAT :
Tulangan atas ø 12 - 20 cm 4.176 x 5.500 bh 0.815 x 2.00 bh = 37.439 kg
Tulangan bawah ø 12 - 20 cm 1.640 x 18.182 bh 0.815 x 2.00 bh = 48.601 kg
Berat besi (kg) -----> = 86.040 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 86.040 = 86.040 kg
Bekisting tiap m3 Beton 2.370 = 2.368 m2

Halaman : 273
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

BETON SLOOF

1 Pek. Sloef Beton Bertulang SL.1 (30x50)


Volume Beton 0.300 x 0.500 x 6.667 = 1.000 m3
BESTAT :
Tulangan ø19 mm 6.767 x 7.000 x 2.109 = 99.898 kg
Tulangan ø16 mm 6.767 x 4.000 x 1.480 = 40.072 kg
Besi Beugel ø10 - 15 cm 1.500 x 44.444 bh 0.556 = 37.076 kg
Berat besi (kg) -----> 177.046 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 177.050 177.046 kg
Bekisting tiap m3 Beton 6.670 = 6.667 m2

2 Pek. Sloef Beton Bertulang SL.2 (20x30)


Volume Beton 0.200 x 0.300 x 16.667 = 1.000 m3
BESTAT :
Tulangan ø16 mm 16.767 x 3.000 x 1.480 = 74.468 kg
Tulangan ø16 mm 16.767 x 3.000 x 1.480 = 74.468 kg
Besi Beugel ø10 - 15 cm 0.900 x 111.111 bh 0.556 = 55.614 kg
Berat besi (kg) -----> 204.551 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 204.550 204.551 kg
Bekisting tiap m3 Beton 10.000 = 10.000 m2

3 Beton Sloof 15/20


Volume Beton 0.150 x 0.200 x 33.333 = 1.000 m3
BESTAT :
Tulangan ø12 mm 33.433 x 2.000 x 0.815 = 54.494 kg
Tulangan ø12 mm 33.433 x 2.000 x 0.815 = 54.494 kg
Besi Beugel ø8 - 20 cm 0.600 x 222.222 bh 0.347 = 46.217 kg
Berat besi (kg) -----> 155.204 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 155.200 155.204 kg
Bekisting tiap m3 Beton 6.670 = 6.667 m2

Halaman : 274
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

BETON KOLOM

1 Pek. Kolom beton Bertulang K.1 (40x40)


Volume Beton 0.400 x 0.400 x 6.250 = 1.000 m3
BESTAT :
Tulangan ø 19 mm ( polos ) 6.350 x 10.000 x 2.109 = 133.924 kg
Tulangan ø 16 mm ( polos ) 6.350 x 6.000 x 1.480 = 56.406 kg
Besi Beugel 2Pø10 - 10/20 cm 1.500 x 46.875 bh 0.556 = 39.104 kg
Berat besi (kg) -----> 229.434 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 229.430 229.434 kg
Bekisting tiap m3 Beton 10.000 = 10.000 m2

2 Pek. Kolom beton Bertulang K.2 (30x100)


Volume Beton 0.300 x 1.000 x 3.333 = 1.000 m3
BESTAT :
Tulangan ø 19 mm ( polos ) 3.433 x 16.000 x 2.109 = 115.856 kg
Tulangan ø 16 mm ( polos ) 3.433 x - x 1.480 = - kg
Besi Beugel 2Pø10 - 10/20 cm 2.500 x 25.000 bh 0.556 = 34.759 kg
Berat besi (kg) -----> 150.615 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 150.620 150.615 kg
Bekisting tiap m3 Beton 8.670 = 8.667 m2

3 Pek. Kolom beton Bertulang K.3 (30x30)


Volume Beton 0.300 x 0.300 x 11.111 = 1.000 m3
BESTAT :
Tulangan ø 16 mm ( polos ) 11.211 x - x 1.480 = - kg
Tulangan ø 12 mm ( polos ) 11.211 x 8.000 x 0.815 = 73.093 kg
Besi Beugel 2Pø10 - 20 cm 1.100 x 55.556 bh 0.347 = 21.183 kg
Berat besi (kg) -----> 94.276 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 94.280 94.276 kg
Bekisting tiap m3 Beton 13.330 = 13.333 m2

4 Pek. Kolom beton Bertulang K.4 (75x15)+(55X10)


Volume Beton 1.300 x 0.125 x 6.154 = 1.000 m3
BESTAT :
Tulangan ø 12 mm ( polos ) 6.254 x 22.000 x 0.815 = 112.126 kg
Tulangan ø 10 mm ( polos ) 6.254 x x 0.556 = - kg
Besi Beugel 2Pø8 - 20 cm 2.750 x 30.769 bh 0.347 = 29.330 kg
Berat besi (kg) -----> 141.456 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 141.460 141.456 kg
Bekisting tiap m3 Beton 17.540 = 17.538 m2

5 Pek. Kolom beton Bertulang K.5 (10X15)


Volume Beton 0.100 x 0.150 x 66.667 = 1.000 m3
BESTAT :
Tulangan ø 12 mm ( polos ) 66.767 x 4.000 x 0.815 = 217.649 kg
Tulangan ø 10 mm ( polos ) 66.767 x - x 0.556 = - kg
Besi Beugel 2Pø8 - 20 cm 0.400 x 333.333 bh 0.347 = 46.217 kg
Berat besi (kg) -----> 263.866 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 263.870 263.866 kg
Bekisting tiap m3 Beton 33.330 = 33.333 m2

6 KOLOM 12/12 (PRAKTIS)


Volume Beton 0.120 x 0.120 x 69.444 = 1.000 m3
BESTAT :
Tulangan ø 12 mm 69.544 x 2.000 x 0.678 = 94.250 kg
Tulangan ø 12 mm 69.544 x 2.000 x 0.678 = 94.250 kg
Besi Beugel ø 6 - 15 cm 0.380 x 462.963 bh 0.186 = 32.709 kg
Berat besi (kg) -----> 221.210 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 221.210 221.210 kg
Bekisting tiap m3 Beton 16.670 = 16.667 m2

7 Pek. Kolom beton Bertulang K.Pg (15X30)


Volume Beton 0.150 x 0.300 x 22.222 = 1.000 m3
BESTAT :
Tulangan ø 12 mm ( polos ) 22.322 x 8.000 x 0.815 = 145.534 kg

Halaman : 275
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

Tulangan ø 10 mm ( polos ) 22.322 x - x 0.556 = - kg


Besi Beugel 2Pø8 - 20 cm 0.800 x 111.111 bh 0.347 = 30.811 kg
Berat besi (kg) -----> 176.345 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 176.340 176.345 kg
Bekisting tiap m3 Beton 20.000 = 20.000 m2

Halaman : 276
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

BETON BALOK

1 Pek. Balok Beton Bertulang B.1 (25x40)


Volume Beton 0.250 x 0.400 x 10.000 = 1.000 m3
BESTAT :
Tulangan ø 19 mm 10.100 x 11.000 x 2.109 = 234.314 kg
Tulangan ø 16 mm 10.100 x x 1.480 = - kg
Besi Beugel 2Pø10 - 10/20 cm 1.200 x 75.000 bh 0.556 = 50.053 kg
Berat besi (kg) -----> 284.367 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 284.370 284.367 kg
Bekisting tiap m3 Beton 10.500 = 10.500 m2

2 Pek. Balok Beton Bertulang B.2 (30x55)


Volume Beton 0.300 x 0.550 x 6.061 = 1.000 m3
BESTAT :
Tulangan ø 19 mm 6.161 x 13.000 x 2.109 = 168.908 kg
Tulangan ø 16 mm 6.161 x x 1.480 = - kg
Besi Beugel 2Pø10 - 10/20 cm 1.600 x 45.455 bh 0.556 = 40.447 kg
Berat besi (kg) -----> 209.355 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 209.360 209.355 kg
Bekisting tiap m3 Beton 8.480 = 8.485 m2

3 Pek. Balok Beton Bertulang B.3 (30x65)


Volume Beton 0.300 x 0.650 x 5.128 = 1.000 m3
BESTAT :
Tulangan ø 19 mm 5.228 x 13.000 x 2.109 = 143.344 kg
Tulangan ø 16 mm 5.228 x x 1.480 = - kg
Besi Beugel 2Pø10 - 10/20 cm 1.800 x 38.462 bh 0.556 = 38.502 kg
Berat besi (kg) -----> 181.846 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 181.850 181.846 kg
Bekisting tiap m3 Beton 8.210 = 8.205 m2

4 Pek. Balok Anak (20x25)


Volume Beton 0.200 x 0.250 x 20.000 = 1.000 m3
BESTAT :
Tulangan ø 16 mm 20.100 x 6.000 x 1.480 = 178.546 kg
Tulangan ø 12 mm 20.100 x 2.000 x 0.815 = 32.761 kg
Besi Beugel 2Pø10 - 10/20 cm 0.800 x 150.000 bh 0.556 = 66.737 kg
Berat besi (kg) -----> 278.045 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 278.050 278.045 kg
Bekisting tiap m3 Beton 14.000 = 14.000 m2

5 Pek. Balok Bordes tangga Beton bertulang (25x40)


Volume Beton 0.250 x 0.400 x 10.000 = 1.000 m3
BESTAT :
Tulangan ø 16 mm 10.100 x 4.000 x 1.480 = 59.812 kg
Tulangan ø 12 mm 10.100 x 4.000 x 0.815 = 32.924 kg
Besi Beugel 2Pø10 - 10/20 cm 1.200 x 75.000 bh 0.556 = 50.053 kg
Berat besi (kg) -----> 142.789 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 142.790 142.789 kg
Bekisting tiap m3 Beton 8.000 = 8.000 m2

6 Pek. Balok kanopi diatas kusen Beton Bertulang (15x20)


Volume Beton 0.150 x 0.200 x 33.333 = 1.000 m3
BESTAT :
Tulangan ø 12 mm 33.433 x 2.000 x 0.815 = 54.494 kg
Tulangan ø 12 mm 33.433 x 2.000 x 0.815 = 54.494 kg
Besi Beugel 2Pø8 - 20 cm 0.600 x 166.667 x 0.347 = 34.663 kg
Berat besi (kg) -----> 143.650 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 143.650 143.650 kg
Bekisting tiap m3 Beton 13.330 = 13.333 m2

7 Pek. Balok Ornamen Teras Beton Bertulang (20x30)


Volume Beton 0.200 x 0.300 x 16.667 = 1.000 m3
BESTAT :
Tulangan ø 16 mm 16.767 x 4.000 x 1.480 = 99.291 kg

Halaman : 277
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

Tulangan ø 12 mm 16.767 x 2.000 x 0.815 = 27.328 kg


Besi Beugel 2Pø10 - 10/20 cm 0.900 x 125.000 bh 0.556 = 62.566 kg
Berat besi (kg) -----> 189.186 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 189.190 189.186 kg
Bekisting tiap m3 Beton 10.000 = 10.000 m2

8 Pek. Balok Dak Profil Tank Beton Bertulang (25x40)


Volume Beton 0.250 x 0.400 x 10.000 = 1.000 m3
BESTAT :
Tulangan ø 16 mm 10.100 x 4.000 x 1.480 = 59.812 kg
Tulangan ø 12 mm 10.100 x 4.000 x 0.815 = 32.924 kg
Besi Beugel 2Pø10 - 10/20 cm 1.200 x 75.000 bh 0.556 = 50.053 kg
Berat besi (kg) -----> 142.789 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 142.790 142.789 kg
Bekisting tiap m3 Beton 10.500 = 10.500 m2

9 Pek. Balok Konsol Talang Beton Bertulang (25x35)


Volume Beton 0.250 x 0.350 x 11.429 = 1.000 m3
BESTAT :
Tulangan ø 16 mm 11.529 x 10.000 x 1.480 = 170.679 kg
Tulangan ø 12 mm 11.529 x - x 0.815 = - kg
Besi Beugel 2Pø10 - 10/20 cm 1.100 x 85.714 bh 0.556 = 52.436 kg
Berat besi (kg) -----> 223.115 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 223.120 223.115 kg
Bekisting tiap m3 Beton 8.000 = 8.000 m2

10 Pek. Ring Balok Atas Beton Bertulang (20/30)


Volume Beton 0.200 x 0.300 x 16.667 = 1.000 m3
BESTAT :
Tulangan ø 12 mm 16.767 x 8.000 x 0.815 = 109.313 kg
Tulangan ø 12 mm 16.767 x - x 0.815 = - kg
Besi Beugel 2Pø8 - 10/20 cm 0.900 x 125.000 bh 0.347 = 38.996 kg
Berat besi (kg) -----> 148.309 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 148.310 148.309 kg
Bekisting tiap m3 Beton 13.330 = 13.333 m2

11 Pek. Ring Balok Atas Beton Bertulang (10/30)


Volume Beton 0.100 x 0.300 x 33.333 = 1.000 m3
BESTAT :
Tulangan ø 12 mm 33.433 x 4.000 x 0.815 = 108.987 kg
Tulangan ø 12 mm 33.433 x 4.000 x 0.815 = 108.987 kg
Besi Beugel 2Pø8 - 10/20 cm 0.700 x 250.000 bh 0.347 = 60.660 kg
Berat besi (kg) -----> 278.634 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 278.630 278.634 kg
Bekisting tiap m3 Beton 23.330 = 23.333 m2

12 Pek. Ring Balok Atas Beton Bertulang (10/15)


Volume Beton 0.100 x 0.150 x 66.667 = 1.000 m3
BESTAT :
Tulangan ø 12 mm 66.767 x 2.000 x 0.815 = 108.824 kg
Tulangan ø 12 mm 66.767 x 2.000 x 0.815 = 108.824 kg
Besi Beugel 2Pø8 - 10/20 cm 0.400 x 500.000 bh 0.347 = 69.325 kg
Berat besi (kg) -----> 286.974 kg
Volume Beton 1.000 m3
Berat besi tiap 1 m3 beton 286.970 286.974 kg
Bekisting tiap m3 Beton 26.670 = 26.667 m2

Halaman : 278
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

BETON PLAT

1 BETON PLAT LANTAI ( tbl. 20 cm, lbr. 100 cm )


Volume Beton 0.200 x 1.000 x 5.000 = 1.000 m3
BESTAT :
Tulangan ø 12 - 20 cm 5.400 x 5.000 x 0.887 x 2.00 lps = 47.918 kg
Tulangan ø 12 - 20 cm 1.400 x 25.000 x 0.887 x 2.00 lps = 62.116 kg
Berat besi (kg) -----> = 110.033 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 110.030 = 110.033 kg
Bekisting tiap m3 Beton 5.000 = 5.000 m2

2 BETON PLAT LANTAI ( tbl. 15 cm, lbr. 100 cm )


Volume Beton 0.150 x 1.000 x 6.667 = 1.000 m3
BESTAT :
Tulangan ø 12 - 20 cm 6.967 x 5.000 x 0.887 x 2.00 lps = 61.820 kg
Tulangan ø 12 - 20 cm 1.300 x 33.333 x 0.887 x 2.00 lps = 76.905 kg
Berat besi (kg) -----> = 138.725 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 138.720 = 138.725 kg
Bekisting tiap m3 Beton 6.670 = 6.667 m2

3 BETON PLAT LANTAI ( tbl. 12 cm, lbr. 100 cm )


Volume Beton 0.120 x 1.000 x 8.333 = 1.000 m3
BESTAT :
Tulangan ø 12 - 20 cm 8.573 x 5.000 x 0.887 x 2.00 lps = 76.077 kg
Tulangan ø 12 - 20 cm 1.240 x 41.667 x 0.887 x 2.00 lps = 91.694 kg
Berat besi (kg) -----> = 167.771 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 167.770 = 167.771 kg
Bekisting tiap m3 Beton 8.330 = 8.333 m2

4 BETON DINDING ( Tebal = 12 cm, Panjang = 100 cm )


Volume Beton 0.120 x 1.000 x 8.333 = 1.000 m3
BESTAT :
Tulangan ø 10 - 20 cm 8.613 x 5.000 x 0.616 x 2.00 lps = 53.078 kg
Tulangan ø 10 - 20 cm 1.280 x 41.667 x 0.616 x 2.00 lps = 65.731 kg
Berat besi (kg) -----> = 118.808 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 118.810 = 118.808 kg
Bekisting tiap m3 Beton 18.670 = 18.667 m2

5 LISPLANK / PLAT KANOPI (tbl. 10 cm, lbr. 50 cm)


Volume Beton 0.100 x 0.500 x 20.000 = 1.000 m3
BESTAT :
Tulangan ø 10 - 15 cm 20.100 x 3.333 x 0.616 x 1.00 lps = 41.287 kg
Tulangan ø 10 - 15 cm 0.600 x 133.333 x 0.616 x 1.00 lps = 49.298 kg
Berat besi (kg) -----> = 90.585 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 90.590 = 90.585 kg
Bekisting tiap m3 Beton 10.000 = 10.000 m2

6 BETON TANGGA ( tbl. 12 cm, lbr. 100 cm )


Volume Beton 0.120 x 1.000 x 8.333 = 1.000 m3
BESTAT :
Tulangan ø 12 - 20 cm 8.433 x 5.000 x 0.887 x 2.00 lps = 74.835 kg
Tulangan ø 12 - 20 cm 1.100 x 41.667 x 0.887 x 2.00 lps = 81.342 kg
Berat besi (kg) -----> = 156.176 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 156.180 = 156.176 kg
Bekisting tiap m3 Beton 8.330 = 8.333 m2

7 MEJA BETON PANTRY (tbl. 10 cm, lbr. 60 cm)


Volume Beton 0.100 x 0.600 x 16.667 = 1.000 m3
BESTAT :
Tulangan ø10 - 20 cm 16.827 x 3.000 x 0.616 x 1.00 lps = 31.107 kg
Tulangan ø10 - 20 cm 0.760 x 83.333 x 0.616 x 1.00 lps = 39.028 kg
Berat besi (kg) -----> = 70.135 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 70.130 = 70.135 kg
Bekisting tiap m3 Beton 10.000 = 10.000 m2

Halaman : 279
MENGHITUNG BERAT BESI DALAM 1 M3 BETON (BESTAT)

8 PLAT BETON CETAK SETEMPAT ( Tbl. 8 cm, lbr. 100 cm ), Besi 1 lapis
Volume Beton 0.080 x 1.000 x 12.500 = 1.000 m3
BESTAT :
Tulangan ø 10 - 20 cm 12.460 x 5.000 x 0.616 x 1.00 lps = 38.391 kg
Tulangan ø 10 - 20 cm 0.960 x 62.500 x 0.616 x 1.00 lps = 36.974 kg
Berat besi (kg) -----> = 75.364 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 75.360 = 75.364 kg
Bekisting tiap m3 Beton 12.500 = 12.500 m2

9 BETON PLAT DAK ATAP ( tbl. 10 cm, lbr. 100 cm )


Volume Beton 0.100 x 1.000 x 10.000 = 1.000 m3
BESTAT :
Tulangan ø 10 - 20 cm 10.200 x 5.000 x 0.616 x 2.00 lps = 62.855 kg
Tulangan ø 10 - 20 cm 1.200 x 50.000 x 0.616 x 2.00 lps = 73.947 kg
Berat besi (kg) -----> = 136.802 kg
Volume Beton = 1.000 m3
Berat besi tiap 1 m3 beton 136.800 = 136.802 kg
Bekisting tiap m3 Beton 10.000 = 10.000 m2

Halaman : 280