INSTRUCTIONS TO CANDIDATES
1. This question paper consists of two (2) questions. Answer ALL questions.
5. Upon completing, please scan and save your work together with the cover page in a singular
PDF file, and then upload to GOOGLE CLASSROOM
QUESTION 1
With reference to the cost data given in Appendix 2 , analyse the unit rates for all items below
(15 marks)
b) Total area of interlocking steel sheet piles to BS 4360, grade 43A, weighing 55.4 kg/m in length not
exceeding 12.00m
(15 marks)
c) 1200mm x 600mm x 4.5mm Thick 'UAC Superflex' or other equal and approved cellulose fibre
cement ceiling sheet and fixing to 50mm x 100mm SPT Grade B timber joist at 1200mm centers and
50mm x 50mm spacer fixed parallel with joist at 1200mm centers and across joint at 600mm
centers.
(15 marks)
d) A school with an estimated tender sum of RM25 million and a contract period of 2 and a
half years is expected to start construction in December 2021. Price these items and
show the calculations and assumptions for the breakdown of the prices clearly.
i. Hoarding
ii. Temporary electric supply
iii. Temporary water supply
(15 marks)
QUESTION 2
With reference to the cost data given in Appendix 1, build the unit rates for all items in the
Bills of Quantities below.
All works were specified according to JKR Standard Specifications for Building Works 2014,
and all quantities were measured according to SMM2. You are allowed to make necessary
Non-loadbearing superstructure
Casement window
Ironmongery
SUPPLIED COST
MATERIAL CONVERSION
delivered to site
7. Single leaf skeleton frame flush door - 900mm x 2100mm RM280.00 /no
8. Timber casement window - 600mm x600mm RM200.00 /no
LABOUR COSTS
LABOUR
LABOUR skilled unskilled
OUTPUT
RM100.00 RM60.00
MACHINERIES MACHINERIES
MACHINERIES COST OUTPUT
A. CONCRETE WORKS
MATERIAL
PLANT
LABOUR CONSTANT
Concrete
Labour for transporting and placing of 8.00 hours per m3 (1 General Labour)
concrete
Labour for mixing concrete 2 hours per m3 (1 General labour)
Transporting and placing of concrete by
concrete mixer 4 General Labour
Transporting and placing concrete by crane 5 General Labour
Ceiling Finishes
Labour for fixing ceiling 1.5 hours
B. PILING WORKS
Assumptions:
a. 430mm x 12m long interlocking steel sheet piles = RM 2800.00/tonne ( 2 times usage)