You are on page 1of 23

SECTION 230549

CONCRETE PADS FOR MECHANICAL EQUIPMENT

PART 1 GENERAL

1.01 RELATED WORK SPECIFIED ELSEWHERE

A. Fibrous Concrete Reinforcement: Section 032101.

1.02 REFERENCES

A. Except as shown or specified otherwise, the Work of this Section shall conform to the
requirements of Specifications for Structural Concrete for Buildings ACI 301-99 of the
American Concrete Institute.

1.03 SUBMITTALS

A. Submittals Package: Submit product data for design mix and materials for concrete
specified below at the same time as a package.

B. Shop Drawings: Placing drawings for bar reinforcement.

C. Product Data:
1. Concrete design mix with name and location of batching plant.
2. Portland Cement: Brand and manufacturer's name.
3. Air-Entraining Admixture: Brand and manufacturer's name.
4. Aggregates: Name and location of source, and NYS test numbers.
5. Bonding Agent (Adhesive): Brand and manufacturer's name, and preparation
and application instructions.
6. Fibrous Reinforcement.

D. Samples:
1. Fabric Reinforcement: 8 inches square.
2. Bar Supports: Full size.

E. Quality Control Submittals:

1. Certificates: Bar reinforcement manufacturer's certification that bar material


conforms with ASTM A 615 and specified grade.

1.04 STORAGE

A. Store materials as required to insure the preservation of their quality and fitness for the
Work.

PART 2 PRODUCTS

230549 - 1 Project No. Q1403-C


2.01 MATERIALS

A. Anchor Bolts: Standard bolts, ASTM A 307, with lock washers and nuts.

B. Steel Plates: ASTM A 36.

C. Sleeves: Steel Pipe, Schedule 40, black, ASTM A 53.

D. Steel Shims and Fillers: ASTM A 569.

E. Reinforcement: Furnish the following unless otherwise indicated on the Drawings:

1. Fabric Reinforcement: ASTM A 185 welded wire fabric, 6 x 6 - W2.9 x W2.9


fabricated into flat sheets unless otherwise indicated.

2. Bar Reinforcement: ASTM A 615, Grade 60, deformed.

3. Metal Bar Supports: Galvanized or AISI Type 430 stainless steel, and without
plastic tips.

4. Tie Wire: Black annealed wire, 16 gage minimum.

F. Bonding Agent (Adhesive): Epoxy-resin-base bonding system, Type II, complying with
ASTM C 881. Grade and class as required by conditions of use.

G. Cement Grout: Portland cement and clean natural sand mixed at a ratio of 1.0 part
cement to 3.0 parts sand, with only the minimum amount of water required for placement
and hydration.

H. Dowels: ASTM A 36 steel bars 1/2 inch in diameter by 5 inches long, unless otherwise
indicated on the Drawings.

2.02 PROPORTIONING OF CONCRETE MIXES

A. Compressive Strength: Minimum 4000 psi.

B. Weight: Normal.

C. Durability: Concrete shall be air-entrained. Design air content shall be 6 percent by


volume, with an allowable tolerance of plus or minus 1.5 percent for total air content.
Entrained air shall be provided by use of an approved air-entraining admixture. Air-
entrained cement shall not be used.

D. Slump: Between 2 inches and 4 inches.

E. Admixtures: Do not use admixtures in concrete unless specified or approved in writing


by the Director’s Representative.

230549 - 2 Project No. Q1403-C


F. Selection of Proportions: Concrete proportions shall be established on the basis of
previous field experience or laboratory trial batches, unless otherwise approved in writing
by the Director’s Representative. Proportion mix with a minimum cement content of 611
pounds per cubic yard for 4000 psi concrete.

G. Concrete mix shall include fibrous concrete reinforcement as per Section 032101.

2.03 FABRICATION OF ANCHOR BOLT ASSEMBLIES

A. Bolts: Diameter 1/8 inch less than the bolt holes in the equipment supports and length
equal to the depth of the pad minus 1 inch plus the additional length required to provide
full thread through nuts after shims, equipment, and washers are in place.

B. Sleeves: Diameter 1/2 inch larger than the bolt diameter and length as required to extend
from the head of the bolt to the top of the pad.

C. Plates: 3 x 3 x 1/4 inch steel plate.

D. Weld a plate to the head end of a bolt. Center the bolt in a sleeve and tack-weld the
sleeve to the plate.

PART 3 EXECUTION

3.01 EXAMINATION AND PREPARATION

A. Concrete materials, reinforcement, forms, and earth which will be in contact with fresh
concrete shall be free from frost at the time of concrete placement.

3.02 BONDING TO EXISTING CONCRETE SLABS

A. Where more than one pad is required for a single piece of equipment, install 2 dowels in
existing slab for each pad. Drill existing slab as required to install dowels 3 inches into
the existing concrete. Grout dowels in the drilled holes.

B. Prior to placing concrete, thoroughly roughen and clean existing concrete slab. Saturate
existing concrete surface with clean water. Immediately prior to depositing concrete for
pad, apply a coat of cement grout over the existing damp concrete or allow existing
concrete to dry and apply bonding agent (adhesive) over the existing concrete in
accordance with manufacturer's printed instructions.

3.03 INSTALLING ANCHOR BOLTS AND SLEEVES

A. Install anchor bolts (with sleeves) for all bolt holes in equipment supports.

B. Accurately position and securely support anchor bolts and sleeves prior to placing
concrete. Support head of bolt 1 inch above bottom of pad. Temporarily close open end
of sleeves to prevent entry of concrete.

230549 - 3 Project No. Q1403-C


C. Grout anchor bolts in sleeves with cement grout or approved shrink-resistant grout after
final positioning.

3.04 REINFORCING

A. Except where other reinforcement is shown on the Drawings, install welded wire fabric at
mid-depth of each pad, extending to 1 inch from perimeter of pad.

3.05 FINISHES

A. Formed Surfaces: Provide a smooth rubbed finish, with rounded or chamfered external
corners, on all concrete surfaces exposed to view.

B. Unformed Surfaces: Provide a troweled finish on top surface of pads.

END OF SECTION

230549 - 4 Project No. Q1403-C


SECTION 231323

ABOVEGROUND JP-8 BULK STORAGE


TANKS AND FUEL TRANSFER SYSTEMS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Work of this Section shall be performed in accordance with the requirements of the
Contract Documents.

B. Provide an integrated fuel system. The detailed system design, equipment, start-up and
training in equipment operation and maintenance shall be the responsibility of a single
specialized fuel system supplier.

C. Provide and install one (1) 20,000 gallon, aboveground, double-wall, welded steel storage
tank with overflow containment compartment and accessories. Tanks shall be suitable
for storing JP-8 Aviation Fuel.

D. Tank shall include an integral welded steel pump house, enclosing all dispensing,
filtering, and metering equipment and accessories required for a complete system.

E. Provide and install a 200 gpm fuel transfer system in the integral pump house. Fuel
transfer system shall include a 200 gpm positive displacement pump, JP-8 fuel filter
separator/coalescer, fuel meter, piping, valves, bonding/grounding system, failsafe
deadman control, floating suction, influent strainer, pump control panel and all other
equipment and accessories necessary for a complete and operational system.

F. Provide and install aboveground piping, pipe supports, valves and accessories as required
to allow the tank’s fuel transfer system to be interconnected to the fuel transfer system of
a second 20,000 gallon storage tank to be installed in the future. The interconnection
piping shall be blanked off inside of the pump house.

Piping and valves shall be designed to allow the fuel transfer system located at each tank
to pump fuel into or out of either tank. The purpose of the piping interconnection is to
allow either fuel transfer system to perform all of the operations of filling either tank
from a delivery tanker, recirculating fuel for filtration from either tank and the filling of
HEMTT tankers using either tank as the fuel source in the event that one of the fuel
transfer systems is out of service.

G. Provide and install a Tank Monitoring and Inventory Control System. This system shall
include at a minimum an interstitial space sensor, product level sensor, high level alarm
and a control panel. The system’s control panel must be upgradeable for future
connection to a Windows based personal computer through a TCP/IP based Ethernet
computer network. The control panel must be designed to provide simultaneous
monitoring and inventory control for a minimum of two (2) tanks.

231323 - 1 Project No. Q1403-C


H. Contractor to coordinate hose sizes, hose lengths and tank adapters as required for bottom
loading of the existing HEMTT tanker trucks with the Rochester AASF Facility
personnel prior to submitting shop drawings for this equipment.
1.02 SUBMITTALS

A. Waiver of Submittals: The “Waiver of Certain Submittal Requirements” in Section


013300 does not apply to this Section.

B. CONTRACTOR shall submit shop drawings and product data in accordance with the
General Conditions.

C. Manufacturer’s literature, product data, installation instructions, and operation and


maintenance data for tanks, remote fill ports, piping, valves, pumps, meters, filters and all
other parts and accessories.

D. Drawings of tanks, supports, ladders or stairs, platforms, tank manholes, emergency relief
vents and all accessories. Include overall dimensions and dimensional locations and sizes
of pipe connections, and access openings.

E. Recommended tank support locations.

F. Application and performance data on coatings from manufacturer of coatings.

G. Certification of compliance with specified standards. Certified copy of UL-142 Inclusive


Label with MH file number.

H. Tank Manufacturer’s Installation Check List.

I. Weight of entire tank assembly, empty and flooded.

J. Design and construction of primary tanks, insulation, secondary containment, supports,


pipe connections, platforms, pumps, valves, etc.

K. Calibration Charts: Contractors shall submit 6 copies of manufacturer’s latest calibration


charts for each tank capacity and diameter specified.

L. Provide an independently certified strapping chart for each tank provided. The certified
strapping chart will, at a minimum, be graduated in feet, inches and 1/8 inch increments
with the associated quantities represented in whole US gallons.

M. ASTM and UL compliance for piping, pipe fittings, unions and flanges.

N. Pressure and temperature ratings for piping, pipe fittings, unions, flanges, ball valves,
gate valves and overfill prevention valves.

O. Tank Fluid Level Monitoring Instrumentation System


1. Drawings showing instruments and in-tank sensing units, with dimensions.
2. Design and construction of all elements of system.
3. Installation instructions.

231323 - 2 Project No. Q1403-C


4. Layout of system.
5. Data on interconnecting wiring systems to be furnished.

P. Performance Data: calibration charts showing the performance characteristics for the
meters, gauges and pumps to be used on this project.

Q. Welding Procedure Specifications: Submit copies of the welding procedure specification


for metals included in work, together with proof of the Contractors qualifications as
outlined in ANSI B 31.1 prior to performing any welding.

R. Performance Qualification Record: Submit copies of the Welder's Performance


Qualification Record according to ANSI B 31.1 showing that the welder was tested under
the approved procedure specification submitted by the Contractor. In addition, the
Contractor shall also submit each welder's assigned number, letter, or symbol which shall
be used to identify the work of the welder and which shall be affixed immediately upon
completion of the weld. Welders making defective welds after passing a qualification
test shall be given a requalification test and upon failing to pass the test shall not be
permitted to work this Contract.

S. Electrical System Design: Provide drawings and specifications that include the proposed
conduit layout and wiring diagrams for equipment covered in this section that requires
electrical connections. Indicate conduit size and material, number and size of wires,
location of wiring in classified areas and location of intrinsically safe circuits and
conduits.

T. Provide a piping and instrumentation diagram for the system, including a complete bill of
material/equipment list.

U. Provide control system designs including electrical schematics, panel physical, and field
wiring diagrams.

V. Provide design calculations for pump selection, pipe sizes, pipe support requirements,
atmospheric vent sizing, and emergency vent sizing.

W. Provide a minimum of five (5) copies of an Operation and Maintenance (O & M) Manual
for the JP-8 Bulk Storage Tank and Fuel Transfer System. The information provided
shall be bound into three-ring binders with appropriately labeled tab dividers separating
the information for each piece of equipment. The O & M manual shall include
manufacturer’s operation and maintenance instructions for all pieces of equipment
provided as part of the JP-8 Bulk Storage Tank and Fuel Transfer System. The O & M
Manual shall also include detailed instructions for the manual valve positions and
equipment operation for the following fueling operations, at a minimum:

1. Offloading of fuel from a delivery tanker into the JP-8 Bulk Storage Tank.

2. Bottom loading of HEMTT Tankers from the JP-8 Bulk Storage Tank.

3. Recirculation of the fuel in the JP-8 Bulk Storage Tank through the
Filter/Separator.

231323 - 3 Project No. Q1403-C


Copies of the manufacturer’s warranties for each piece of equipment provided shall also
be included in the O & M Manual.

Maintenance Data: Include maintenance and inspection data, replacement part numbers
and availability, and service depot location and telephone number.

1.03 QUALITY ASSURANCE

A. Installation: Installation shall be in compliance with Petroleum Equipment Institute


Publications RP100-2000, and RP300, NFPA-30, 30A, and 31 and all manufacturers’
current installation instructions.

B. Qualification of Contractor and Personnel:


1. The Contractor shall have not less than five years continuous experience in the
installation of fuel storage and dispensing systems.
2. Installation of aviation fuel storage and transfer equipment shall be performed
only by workman who have a minimum of two years continuous experience
installing this type of equipment.
3. Tank and piping installation contractor shall be certified as acceptable by local
and state pollution control authorities, if required by such authorities.

C. Apply and install materials, equipment and specialties in accordance with manufacturer’s
written instructions. Conflicts between the manufacturer’s instructions and the contract
drawings and specifications shall be referred to the Director’s Representative for
resolution. Provide copies of installation instruction to the Director’s Representative
prior to commencing installation of any item.

D. Listings: Components of the system(s) for which Underwriters’ Laboratories, Inc. (UL)
provides listing service, shall be listed and bear the listing mark.

E. Tanks, Fuel Piping and Containment Systems, Fuel Transfer Pumps, Fuel Filter
Separator/Coalescer, Tank Level Monitoring Systems and Leak Detection Systems:

Authorized manufacturer’s representatives shall provide on-site training of installers and


supervision of the installation and testing of the equipment and systems to assure
conformance to written instructions of manufacturers.

F. Pipe Welding: Conform to requirements of ASME B31.1. Welders shall show evidence
of qualification. Each welder shall utilize a stamp to identify their work. Unqualified
personnel shall be rejected.

H. Equipment and materials installed shall be compatible in all respects with other items
being furnished and with existing items so that the result will be a complete and fully
operational system that conforms to contract requirements.

I. All equipment shall be the capacity and types required. Substitution will only be allowed
for products proved to be equal or exceeding the design.

231323 - 4 Project No. Q1403-C


J. Do not substitute materials, equipment, or methods unless such substitution has been
approved, in writing, in advance by the Director’s Representative.

K. Storage tank with integral secondary containment must meet the requirements of SPOTS
17 as published by the New York State Department of Environmental Conservation
(NYSDEC) and must be accepted by the NYSDEC for this use.

1.04 STORAGE AND HANDLING OF MATERIALS AND EQUIPMENT

A. Shipping, delivery, storage, rigging and placement shall conform to the written
instructions of the manufacturer.

B. Stored items shall be protected from the weather and contamination. Proper protection
and care of material before, during, and after installation shall be the Contractor’s
responsibility. Any materials found to be damaged shall be replaced at the Contractor’s
expense. During installation, piping and similar openings shall be capped to keep out dirt
and other foreign matter.

C. Equipment and material placed on the job site shall remain in the custody of the
Contractor until phased acceptance, whether or not the Contractor has been reimbursed
for the equipment and material by the Facility. The Contractor is solely responsible for
the protection of such equipment and material against any damage.

D. Protect new equipment and piping systems against entry of foreign matter on the inside.
Clean both inside and outside before painting or placing equipment in operation.

E. Existing equipment and piping being worked on by the Contractor shall be under the
custody and responsibility of the Contractor and shall be protected as required for new
work.

F. Cleanliness of Equipment and Piping:


1. Exercise care in storage and handling of equipment and piping material to be
incorporated in the work. Remove debris arising from cutting, threading and
welding of piping.
2. Piping systems shall be flushed, blown or pigged as necessary to provide clean
systems.
3. Clean interior of all tanks prior to delivery for beneficial use by the Facility.
4. Contractor shall be fully responsible for all costs, damages and delay arising
from failure to provide clean systems and equipment.

1.05 APPLICABLE CODES, STANDARDS AND PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced and
as required under the applicable local, state and federal laws. The publications listed
below shall be latest issue. They are referenced in the text by the basic designation only.

B. Underwriters Laboratories, Inc. (UL):

142 Steel Aboveground Tanks for Flammable and Combustible Liquids

231323 - 5 Project No. Q1403-C


842 Valves for Flammable Fluids

C. Steel Tank Institute (STI):

F911 Standard for Diked Aboveground Storage Tanks

F921 Installation Instructions For Factory Fabricated Double-Wall Steel Aboveground


Storage Tanks.

F921 Standard for Aboveground Tanks with Integral Secondary Containment

D. Steel Structures Painting Council (SSPC):

SP 6 Commercial Blast Cleaning

SP 10 Near-White Blast Cleaning

E. New York State Regulations (NYCRR)

6 NYCRR Parts 613 & 614 Petroleum Bulk Storage Regulations.

New York State Fire Code

F. Code of Federal Regulations (CFR):

40 CFR Part 280 Technical Standards and Corrective Action Requirements for
Owners and Operators of Underground Storage Tanks.

G. National Fire Protection Association:

NFPA 30 Flammable and Combustible Liquids Code.

NFPA 30A Automotive and Marine Service Station Code.

NFPA 70 National Electrical Code, Articles 513 – 514.

H. Military Specifications:

Mil. Spec. C-4556 Coating Kit, Epoxy, for Interior of Steel Fuel Tanks

I. American Petroleum Institute:

API 1581 Specifications and Qualification Procedures for Aviation Jet Fuel
Filter/Separators

All work specified herein shall conform to or exceed the requirements of the above referenced
codes, regulations and Standards; provided, that whenever the provisions of said publications are
in conflict with the requirements specified herein, the more stringent requirement shall apply.

231323 - 6 Project No. Q1403-C


1.06 OPERATION AND MAINTENANCE

A. Special Tools:
1. One stick gage and two (2) calibration charts for each fuel tank.

B. Operation Data: Include installation instructions and exploded assembly views.

C. Maintenance Data: Include maintenance and inspection data, replacement part numbers
and availability, and service depot location and telephone number.

D. One copy of the Operation and Maintenance Manual shall be attached to the interior wall
of the pump house in a clear PVC weather resistant document tube.

E. One copy of the detailed instructions for the manual valve positions and equipment
operation for each of the following fueling operations shall be laminated in 7 mil plastic
and attached to the interior wall of the pump house.

1. Offloading of fuel from a delivery tanker into the JP-8 Bulk Storage Tank.

2. Bottom loading of HEMTT Tankers from the JP-8 Bulk Storage Tank.

3. Recirculation of the fuel in the JP-8 Bulk Storage Tank through the
Filter/Separator.

231323 - 7 Project No. Q1403-C


PART 2 – PRODUCTS

2.01 ABOVEGROUND STEEL TANKS

A. The fuel storage tanks shall be of a pre-engineered system consisting of an aboveground


primary tank, fully enclosed within a secondary tank and assembled on boxed runner
supports, all bearing an inclusive UL-142 label. The assembly shall meet UFC 79-7
Ballistics criteria, NFPA-30, NFPA-69, NFPA-78,and UL-87, UL-142, NEC-70-514 &
515.

The system shall include an integral pump house, enclosing all dispensing equipment and
accessories required for a complete system. This system shall be completely factory
assembled, tested to the extent possible and to UL standards.

B. Primary Tank Construction


1. The primary tank shall be ASME A-36 ¼” CRPS construction,
2. Submerged arc ‘butt welded’ joints,
3. All tank pipe or fitting penetrations shall be above the liquid level or through the
top center line of the vessel.
4. There shall be no below liquid level penetrations within the shell or heads of the
vessel.
5. All primary tank wetted pipe penetrations shall be welded through the shell or
head, and be flanged connected downstream at diameters greater than 1½”. The
interior tank shall be butt welded. All surfaces shall be ground smooth and shot
blasted to SSPC-SP-10 standard. The prepared surface shall comply with ATA-
103 and meet internal coatings per: Mil Spec 4556 E for compliance with JP-8
jet fuel.

Internal coating shall be a minimum 8 - 10 mil thickness of Plasite 7111 as


manufactured by the Carboline Company, or an approved equal. Internal coating
must comply with the requirements of Mil Spec 4556 E for compliance with JP-8
jet fuel.

C. Primary Tank Components


1. Liquid High Level Sensor shall be intrinsically safe, field testable, fail-safe
engineered in design, and independent of all other devices.
2. 2” Manual gauging access port with weather tight and lockable cap.
3. Ground readable volume gauge read in gallons with magneto-restrictive probe.
4. Positive tank sump per ATA-103 W/ 1” welded Sch#40 sumping pipe penetrating
tank above the liquid level equipped with an anti-siphon valve.
5. Lockable and weather tight 6” Access for QA torpedo.
6. Weather tight and lockable 24” ingress manhole.
7. Structural Lifting lugs, a minimum of two (2).
8. 3” Normal Pressure / Vacuum Vent, weather tight.

231323 - 8 Project No. Q1403-C


9. Integral overfill diversion system with 20% primary tank capacity overfill
reservoir, including 95% bulkhead partition between compartments.
10. Wear (Striker) Plates: Provide 12-inch square x 0.25 inch thick steel plates,
welded to the tank bottom, directly under the gauging access port, the product
return discharge and the fill discharge.

D. Secondary Containment Tank with Overflow Containment Compartment.

1. The secondary containment tank shall completely enclose the primary tank and
all connected welded fittings, pipe penetrations, and pressure relief vent. It shall
be constructed of ASTM A-36 3/16” CRPS construction. All joggle joints shall
be oriented downstream towards the sumping end of vessel.
2. All tank pipe or fitting penetrations shall be above the liquid level or through the
top center line of the vessel. There shall be no below liquid level penetrations
within the shell or heads of the vessel.
3. All tank penetrations shall be welded through the shell or head, and be flanged
connected downstream if greater than 1½” diameter.
4. The exterior of the secondary containment tank surface shall be SSPC-SP-6
prepared and coated with 8 – 10 mils of Valspar Marine V75-W9 epoxy paint or
an approved equal.
5. All downstream piping from the tank shall be secondarily contained or of double
walled construction.
6. The interstitial space shall be purged of oxygen and filled with nitrogen to
eliminate all forms of oxidation. This interstitial space shall be vented per
NFPA-30 with a gas and weather tight relief vent.
7. The combined volumetric capacity of the secondary containment tank and the
overflow containment compartment shall be a minimum of 120% of the enclosed
primary tank.
8. An OSHA approved access ladder shall be provided to the floor of the interior of
the primary tank.
9. The interstitial shall be monitored for liquids with an intrinsically safe, liquid
discriminating, fail-safe sensor.
10. Platforms, Stairs, Ladders and Handrails: Provide welded structural steel
assemblies conforming to current OSHA requirements. Provided welded steel
tank attachments designed to support platform framing, stairs, ladders and
loadings. Clean and coat all surfaces as specified for dike exterior. Provide
External Stairs, Ladder Platform and Walkway with Handrails as shown on the
Contract Drawings. Steps shall include non-skid tread surfaces, handrails,
platforms, and kick plates as required for OSHA compliance.

E. Full Pump Enclosure.


1. The enclosure shall be constructed of 7 gauge CRS and be designed to stop water
from accumulating within the maintenance spill pan.
2. The enclosure shall be a minimum of 8’- 0” wide and 6’- 0” long.

231323 - 9 Project No. Q1403-C


3. The front roll-up door opening measures 7’- 2” wide and 6’- 0” high.
4. The door opening shall be edged with nylon brushes around the perimeter
keeping out blown dirt, storm, snow and bugs.
5. The all steel, lockable, overhead roll-up door shall be weather proof, hurricane,
and vandal resistant, and meet OSHA rate of closure criteria.
6. The steel floor shall be designed as a secondary containment pan to catch
maintenance spills and be fabricated of ¼” ASTM A-36 CRPS.
7. A locking drain shall be provided to drain off collected liquids from the pump
house spill pan, as required.
8. The floor shall be welded on 4” channel to create both a raised pedestal and
provide a reinforced platform to mount the pumping equipment.
9. The rounded roof is 3/16” CRPS seal welded throughout to eliminate hidden
water pockets where deterioration might occur.
10. The pump house enclosure assembly shall be seal welded to the head of the tank.
11. The entire unit is to be SSPC-SP-6 prepared and painted with 8 to 10 mils of self-
priming Marine Coating Valspar V75-W9 two part epoxy paint.
12. The pump house shall be designed to enclose the complete pumping system,
valves and piping except for piping that will connect the pumping system to a
future second tank.

F. Tank Identification: Permanent stencils, labels or plates mounted on tanks and fill ports;
and which include the following information:
1. Standard of Design by which tank was manufactured.
2. List of products and additives which may be permanently stored in tank.
3. Year in which tank was manufactured.
4. Unique identification number.
5. Dimensions, design, working capacity, and tank model number.
6. Name and address of tank manufacturer.
7. Date of tank installation (Fill port only).
8. Installers name.
9. Any other information that is required by local, state and federal regulations.

2.02 PUMP CONTROLS AND TANK ALARM SYSTEM

A. The panel shall be assembled in a NEMA-4 Hoffman enclosure with a weather tight
gasket edged and hinged door.

B. The panel shall be situated outside of the defined hazardous area but located within easy
view of the system operator. Control panel shall meet NFPA-30, NFPA-407 and NEC-
70: Sections 514 - 515.

C. The functions and displays presented at this location are:

231323 - 10 Project No. Q1403-C


1. Supervisory keyed three position control switch: On / Off / Bypass.
2. Key locked ‘Bypass’ feature removes all automatic safety features.
3. Illuminated ‘Power On’ and ‘Bypass Warning’ position lights.
4. Illuminated ‘Deadman Interrupt’ condition light.
5. Warning Light, tank high-level alarms W/ automatic pump shut down.
6. Warning Light, water detection JP-8 sump and automatic pump shut down.
7. Warning Light, interstitial liquid sensor, and alarm.
8. Alarm Silence button to silence 100 dB horn.
9. Flashing strobe will remain on until condition is corrected.
10. Pump motor enabled On / Off switch.
11. Emergency Stop mushroom button, removes power from all equipment.
12. Maintenance light On / Off switch.
13. Power terminal junction box.
14. Remote Alarm contacts.
15. All sensors are housed in cast aluminum enclosures.
16. All electrical components shall meet criteria per NEC-70 513-514 and shall be
intrinsically safe and or explosion proof.
17. All conduit shall be rigid, galvanized Sch#40 and sized per Code.

D. The magnetic starters for the pumps and the disconnect shall be housed in separate
NEMA 4 enclosures with weather-tight gasketed edge and hinged door. These
enclosures shall also be located outside of the defined hazardous area.

2.03 OVERFILL PROTECTION

A. A fail-safe engineered high liquid level sensor to sound an alarm at 90% of tank capacity
and stop the pump motor.

B. A third party recognized UL labeled fail-safe designed, internal tank-mounted ductile


iron body hydraulic valve 300 PSI rated by ASME, ASTM. 100% full closure against
incoming product at 95% tank capacity. The device shall not create an upstream
hydraulic shock, be anti-siphon featured and not be electrically operated.

C. A primary tank emergency overflow system capable of directing a fuel overflow into the
overflow containment compartment.

D. A liquid sensor shall be installed within the interstitial space to recognize a non-standard
condition, sound an alarm and stop the pump motor.

2.04 PUMPING SYSTEM CRITERIA

231323 - 11 Project No. Q1403-C


A. The pumping configuration shall be of an engineered design to through-put fuel at a flow
rate not to exceed 12 FPS, thus minimizing possible static generation and turbulence due
to directional ‘switch backs’ and or vibration due to imploding fuel or cavitations of the
pump.

B. The system configuration shall be compliant with FAA, ATA, DOT, NFPA, UFC, NEC,
UL, and good engineering practices and guidelines.

C. The systems standard continuous flow rate is 200 GPM during the following operations:
1. Off-loading delivery transports,
2. Filling HEMTT tanker trucks,
3. Circulating fuel from storage, through filtration, and back to storage.

Through putted fuel is always filtered. All dispensed fuel shall be filtered and metered to
bottom loaded HEMTT tanker trucks. All delivered fuel shall be filtered and metered
from the commercial delivery transports into the tank.

D. The design of the tank and its pumping system must take the following pumping
scenarios into consideration for the future installation of a second 20,000 gallon storage
tank with its own pumping system.
1. The pumping system in Tank #1 can be used to off-load a commercial delivery
transport and transfer the fuel into Tank #2.
2. The pumping system in Tank #1 can be used to withdraw fuel from Tank #2 and
fill a HEMTT tanker truck.
3. The pumping system in Tank #1 can be used to withdraw fuel from Tank #2,
filter the fuel and pump the fuel back into Tank #2.
4. The pumping system in Tank #2 can be used to off-load a commercial delivery
transport and transfer the fuel into Tank #1.
5. The pumping system in Tank #2 can be used to withdraw fuel from Tank #1 and
fill a HEMTT tanker truck.
6. The pumping system in Tank #2 can be used to withdraw fuel from Tank #1,
filter the fuel and pump the fuel back into Tank #1.

E. All piping shall be heli-arc triple pass welded steel ASME Sch#40, Piping downstream of
filtration to dispensing shall be 304L Stainless steel Sch#10 belled fitted fittings and pipe
connections are new ANSI 150# RF Flanged W/ #5 bolts, nuts and stainless washers on
both flange sides.

F. All piping 1½” or less shall be Sch#40 and NPT, piping greater diameter shall be heli-arc
welded and flanged.

G. All equipment and piping shall be properly braced and supported to prevent vibration or
stress.

H. All piping shall be primed and painted with 2 coats of two part epoxy paint.

231323 - 12 Project No. Q1403-C


I. Piping low point shall have a removable NPT drain plug.

J. Sump piping shall be closed circuit configured and be routed back to primary storage
after sampling point and filtration.

2.05 200 GPM JP-8 Pump System Components include:

A. 3” Aluminum Camlock adapter and locking dust cap.

B. Ductile body, viton gasketed, locking and latching butterfly valves with stainless steel
internals. Valves must meet the requirements for API fire safe valves and API 607.

C. Ductile body, steel seated, full ported, spring loaded wafer check valve.

D. Ductile body, 100 SS Mesh Top clean out strainer.

E. Positive Displacement Blackmer GX3-E pump, geared at 200 RPM with 15HP, 208-
230VAC / 3 phase explosion proof motor with remote magnetic starter, heaters, and
fused disconnect.

F. Thermally activated full-ported emergency flow check valve.

G. Flanged 3” x 15” SS flexible convoluted vibration suppression piping on inlet and outlet
sides of pump.

H. JP-8 Filter Separator / Coalescer Model HV-1633-150 as manufactured by Velcon Filters,


Inc. Flow rated at 240 GPM.
1. Equipped with a Gammon Pressure Differential Gauge,
2. 0 - 150 PSI Operating gauge,
3. Inlet / outlet Millipore sampling ports,
4. Flow check valve,
5. SS air eliminator*,
6. Pressure relief valve*,
7. Automatic water detection with alarm and pump motor shut down,
8. Thermostatically activated sump heater that can be calibrated.
9. Fail-Safe manual sump drain.

I. Closed Sump Sampler System separates good fuel from contaminated fuel sump samples.
Good fuel is routed back to storage while contaminated samples are separated for normal
disposal.

J. Model M-15-A-2 Meter with large register counter as manufactured by Liquid Controls,
Inc. This meter must be designed and installed so that it can be calibrated on an annual
basis.

231323 - 13 Project No. Q1403-C


K. Bonding / Grounding System consists of 55’ of chemical resistant, rubber coated, 16/2
copper wire cord with a two-point spring loaded clamp. In the event the intrinsic loop is
lost the system alerts the operator and stops the pump motor and fuel flow.

L. Spring motored rewind reels with cord guides for Deadman and Bonding/ Grounding
leads.

M. JP-8 bottom loading Goodyear Hose 2½” x 15’

N. Kink resistant hose hangers.

O. Gammon Deadman Control for bottom loading and refueling HEMTT fueling trucks.
The 55’ intrinsic deadman cord is rewound on a Hannay spring motored reel.

P. OPW Aluminum floating suction with swivel at bottom of flanged drop tube and
equipped with a stainless steel test cable attached to tank weather tight and lockable
inspection port.

Q. Totally assembled, pre-tested, epoxy painted pumping system installed in the


compartment that assures user friendly access while protecting the equipment from the
ravages of nature, vandals, and time.

R. Hose connectors required for bottom loading of existing HEMTT tank trucks used at the
Facility.

S. Contractor to coordinate hose sizes, hose lengths and tank adapters as required for bottom
loading of the existing HEMTT tanker trucks with the Rochester AASF Facility
personnel prior to submitting shop drawings for this equipment.

2.06. MANUFACTURER

Aboveground JP-8 Bulk Storage Tanks with Integrated Fuel Transfer Systems shall be as
manufactured by:

A. SmartTank, Inc.
53 Nelson Street
Cazenovia, NY 13035
Tel:(888) 708-5423 Fax: (888) 708-5424

B. An approved equal.

2.07 TANK AND PIPING ACCESSORIES

A. Furnish gaging chart for each tank, gallons versus inches depth.

231323 - 14 Project No. Q1403-C


B. Nameplate Holders: Corrosion resistant steel plates and straps (4-inch) with vandal
resistant fasteners; OPW 107.

C. Nameplate: Minimum 1/8 inch thick two color laminated plastic engravers stock
engraved in contrasting symbol and background colors conforming to the American
Petroleum Institute (API) color coding for the particular product type, and consistent with
facility fuel supplier’s marking.

D. Stick Gage: Hardwood, calibrated in inches.

2.08 TANK GAUGING AND LEAK DETECTION SYSTEM

A. Description: A combined inventory control, interstitial leak sensing system to include:


1. A wall-mounted Nema Type 4 console.
2. A minimum 40 character liquid crystal display for on-site viewing of
inventory/leak detection status.
3. An integral, minimum 32 character printer for hard copy system reports and
alarm notification.
4. LED alarm, warning, and power indicators.
5. Alphanumeric keypad.
6. Dispenser sump / transition sump containment liquid float sensor(s) for
installation in lowest point of the Pump Enclosure sump.
7. Tank interstitial space sensor(s), for dry interstitial space at lowest point in the
tank.
8. Sensors shall be UL listed intrinsically safe.
9. Sensors shall be solid state with no moving parts and constructed of materials
compatible with all hydrocarbons including oxygenated additives.
10. Magneto-restrictive level prove shall measure product level, water level and
temperature to the following resolutions:
a. Product Level +/- .010”
b. Water Level +/- .010”
c. Temperature +/- 2 degrees F.
d. Temperature Range: -30 degrees F to +150 degrees F
11. Automatic continuous on-line monitoring of all tanks simultaneously.

12. Ability to be connected to a Windows-based Personal Computer over an Ethernet


TCP/IP computer network at a future date for remote monitoring of the system.
Provide Ethernet – TCP/IP Communications Module

B. Provide a high level annunciator in a weatherproof exterior panel, NEMA 4x, wall or
pole mounted in close proximity to the remote fill station with an integral horn and
flasher and reset capabilities. The alarm panel shall initiate an audible alarm when the
liquid level within a tank reaches the 90 percent full level.

231323 - 15 Project No. Q1403-C


Provide a warning sign adjacent to the annunciator that reads “Warning – Tank Overfill
Alarm – DO NOT OVERFILL.” Sign shall be constructed on 1/8 inch thick two color
laminated plastic engravers stock, with words engraved in white on red background. Size
sign and lettering for easy reading from ground level at a minimum distance of ten (10)
feet from the sign.

C. Operating Capabilities.

1. The ability to produce both manual and automatic reports which include the
following information:
a. Gallons of Fuel
b. Ullage
c. Inches of Fuel
d. Time and Date
e. Tank Identification
f. Fuel Identification
g. Temperature
h. Programmable automatic report times.
2. Programmable alarm limits to warn of:
a. Liquid in tank’s interstitial space.
b. Low Product Level (Adjustable actuation 0 – 25 % of tank capacity).
c. High Product Level (Adjustable actuation 75 – 100% of tank capacity)
d. High Water
e. High High Level
f. Theft
3. Automatic Inventory Increase (Delivery) report consisting of:
a. Delivery start time and date.
b. Beginning inventory.
c. Fuel Temperature.
d. Delivery End Time and Date
e. Ending Inventory
f. Ending Fuel Temperature
g. Net and Gross Increase
4. Programmable automatic report times.

D. Installation and Start Up.


1. System shall be factory pre-programmed with all site-specific information.

231323 - 16 Project No. Q1403-C


2. System shall be provided with site-specific manufacturer’s wiring schematic.
3. Provide 12 rolls of printer paper.

E. Acceptable Manufacturer:

Model TLS-350 Plus as manufactured by The Veeder-Root Company, 125 Powder Forest
Drive, P.O. Box 2003, Simsbury, CT 06070

Approved Equal.

PART 3 - EXECUTION

3.01 INSTALLATION

A. Storage tanks shall be handled with extreme care to prevent damage during placement
and shall be installed in accordance with the manufacturer’s installation instructions and
as otherwise specified. The exterior surface of each tank shall be inspected for obvious
visual damage prior to the placement of each storage tank. Surface damage to a storage
tank shall be corrected according to the manufacturer’s requirements before proceeding
with the system installation.

3.02 ABOVEGROUND STEEL TANKS

A. Conform to NFPA 30, NFPA 31, STI-F912, and/or 6 NYCRR Parts 595-599 as
applicable.

B. Anchor tanks to concrete foundations at a minimum of six (6) locations.

C. Provide electrical grounding in accordance with NFPA 70.

3.03 TANK ACCESSORIES

A. Product Identification: Attach laminated plastic nameplate to each tank fill pipe to
identify the material stored in the tank.

B. Tank Identification: Attach tank identification stencil, label or plate permanently to tanks
and fill ports.

C. Terminate vent lines with vent caps.

D. Overfill Alarm Sign: Mount sign adjacent to alarm panel in a location that is easily
readable from ground level.

3.03 EQUIPMENT

A. Equipment shall be properly leveled, aligned, and secured in place in accordance with
manufacturer’s instructions. Supports shall be provided for equipment, appurtenances,
and pipe as required. Anchors, bolts, nuts, washers, and screws shall be installed where

231323 - 17 Project No. Q1403-C


required for securing the work in place. Sizes, types, and spacing of anchors and bolts
not indicated or specified shall be as required for proper installation.

3.04 TIGHTNESS TESTING

A. A tightness test shall be performed on each aboveground storage tank. The tests shall be
performed prior to making piping connections. Tests shall be capable of detecting a 0.1
gph leak rate from any portion of the tank while accounting for effects of thermal
expansion or contraction. Gauges used in the tightness tests shall have a scale with a
maximum limit of 10 psig. Each storage tank shall be pressurized with air to 5 psig and
monitored for a drop in pressure over a 2-hour period during which there shall be no drop
in pressure in the tank greater than that allowed for pressure variations due to thermal
effects. Leaks discovered during the test shall be repaired in accordance with the
manufacturer’s instructions. The tightness test shall be performed again in the event a
leak is discovered. Tightness testing shall be performed as per the requirements in UL-
142.

This tightness test shall be performed at the factory before the tank is shipped. It shall
also be performed on the tank after it has been set on its permanent foundation at the
Facility.

B. Following the tank tightness testing, each storage tank shall be leak tested in accordance
with the manufacturer’s written test procedure if the manufacturer’s test procedure is
different from the tightness tests already performed. Any test failure shall require
corrective action and retest.

C. Repair all damaged areas of prime and finish coats on tanks and steel dikes (if furnished).

D. Test interstitial area between tank walls (if specified) with air at pressure recommended
by tank manufacturers at the factory before the tank is shipped. Retest the interstitial
space after the tank has been set on its permanent foundation at the Facility.

E. Test is to be performed in the presence of the Director’s Representative.

3.05 HIGH LIQUID LEVEL ALARM TEST

A. Each storage tank shall be initially overfilled with the appropriate product in order to
verify that the high liquid level alarms in the remote alarm panel function as designed.
The initial overfill shall stop immediately once the overfill device operates. The
Contractor shall not overfill any storage tank more than the 98 percent level even if the
overfill device does not function as intended. Any problems with the high liquid level
alarm system shall be corrected and the system retested. The system shall be drained
below the high liquid levels following all tests.

B. Test is to be performed in the presence of the Director’s Representative.

3.06 FUEL FOR TESTING

231323 - 18 Project No. Q1403-C


A. Coordinate with the Facility through the Director’s Representative for the delivery of a
full tank of appropriate fuel type for testing to verify that fuel transfer equipment and
instrumentation is operating properly.

3.07 INSTALLATION – TANK GAUGING AND LEAK DETECTION SYSTEM

A. Wiring shall conform to NFPA-70.

B. Locate control panel at the location shown on the Contract Documents.

C. Locate remote high level alarm in view of the tank fill point as shown on the plans.

D. Test operation of each probe and monitoring system with fuel and water. If any type of
probe utilized is damaged by exposure to fuel, provide temporary probe for testing of
monitoring system.

3.07 DEMONSTRATION AND TRAINING

A. Train the Rochester AASF Facility’s maintenance personnel on procedures and schedules
related to start-up and shutdown, troubleshooting, servicing, and preventative
maintenance. A minimum of sixteen (16) hours shall be provided for system
demonstration and training.

B. Representatives of equipment suppliers for the leak monitoring system shall provide
necessary training and technical support to the Rochester AASF Facility’s maintenance
personnel so that the Facility may properly operate and maintain the systems. A
minimum of four (4) hours of training shall be provided.

END OF SECTION

231323 - 19 Project No. Q1403-C

You might also like