Professional Documents
Culture Documents
Abstract
Loessail soil is a collapsing soil type, sometimes referred to as metastable soil,
which undergoes a structural collapse if saturated. The collapse is due to the loss
of strength in the clay binders between the silt size particles, leading to
construction and design problems for highways and buildings. Use of sand
drains is one of the methods used, to facilitate the pre-wetting of the soil in order
to induce collapse and thus improve its characteristics and strength parameters.
Challenges facing the contractor and the design engineer include predicting the
total settlement associated with the soil collapse, and estimating the water
volume and time needed to complete the soil collapse program. In addition, a
monitoring program employing settlement plates and moisture sensors is
required to monitor change is soil moisture content and subsequent collapse
behaviour, if any. With all the uncertainties of the soil parameters and the
significance of all these parameters on the construction cost, especially the time
for the contractor on site, there is a necessity to come up with an analytical
solution based on the spacing between sand drains to predict the time needed for
complete saturation based on sand drain spacing. Formulas should also be
verified with field work and measurements. This paper presents a case study of
using sand columns to pre-wet loessail soils. This paper also presents an
analytical approach for calculating the time needed for collapsing loessail soils
using sand columns and verifies the approach by analyzing collected field data
during a saturation/collapse process of the soil.
Keywords: loessail soil, soil collapse, sand columns, wetting time.
1 Introduction
This paper presents a case study of use of sand columns to pre-collapse loessail
soil in Asia prior to construction of a four story building. The paper includes
listing of soil laboratory testing done, an analytical approach for estimating the
duration required for saturation, monitoring results during the soil wetting
program and a discussion about the results.
2.50
2.00
Natural Dry Unit Weight (t/m3)
1.50
0.50
0.00
0 5 10 15 20 25 30 35 40 45 50
Liquid Limit (%)
3 Pre-collapse approach
As given in Figure 1, the identified soil parameters indicated that most soil
samples is not collapsible. However, the existence of collapsible soil pockets
embedded in the soil matrix was confirmed with a low potential to collapse, as
most of the soil characteristics are close to the border of collapsible soils. Those
soil pockets tend to give the site susceptibility for differential settlement that
may affect the proposed structure. In order to get rid of those collapsible soil
pockets and minimize the potential of having differential settlement on site, the
following measures were taken:
1. Regardless of the soil collapse potential, soil had to be wetted to induce
collapse, if a considerable potential exists. Wet the soil under the
proposed building foot print (plus a 2 meter buffer all the way around
the building) using a wetting program.
2. The wetting program would consist of a number of sand columns drilled
through the site and distributed in a grid form to ensure adequate
coverage of the area. A set of moisture sensors and settlement plates
would also be installed to monitor change in moisture content along
with any soil movement.
3. Replace the top 2.5 m of soil after collapse with a well compacted sub-
grade soil under the proposed foundation.
4. Use mat foundations with a reinforced concrete slab of 2 foot thickness
to minimize the effect of differential settlement on the proposed
structure.
The measures described above represent a combination of several methods
that are normally used for dealing with soil that is susceptible to collapse due to a
change in their water content. The challenge inherent in the project nature was
to design the wetting program and estimate how long it would take to saturate
the soil.
Ground Surface
Direction of
Water Flow H
L
∆H
∆L
Sand
Column
Q = K*I*A (1)
V = K*I (2)
I = H/L (3)
V = K*H/L (4)
Tn = Tn-1 + ∆L/2V (5)
Tn = Tn-1 + ∆L*L/(2*K*H) (6)
Where (n) designates, the element through which water is flowing and (n-1) is
the previous element through which water was flowing before entering to that
element. Equation (6) given above helps estimate the time needed to wet the soil
particles at a distance (L) from the sand column and at a depth (H) from the
ground surface, assuming a homogenous soil profile with a constant Hydraulic
Conductivity (K) across the site.
Based on equation (6), a finite element grid was established using a
spreadsheet to determine the time it takes to wet each element in the soil matrix.
The shallowest element and furthest from the sand column would take the
longest time and consequently determine the duration of the wetting program.
This element with its characteristics including Hydraulic conductivity of the soil,
depth and distance from the sand column represents the design criterion for the
wetting program. Obviously and based on equation (6) an element at a depth
close to zero from the ground surface would take a very long time to wet, unless
the entire site is soaked with water from the top (i.e. soak the ground surface) in
addition to the water it is receiving from the sand columns. The latter approach
is expensive and not practical to soak the site surface with water, as it leads to
dispensing considerable volumes of water simply to wet the top 2 meters of the
site. To avoid such a scenario it was determined to use an element that is 2
meters below the ground surface to design the wetting program for the adequate
duration to saturate the soil, and that the top 2 meters will have to be replaced
anyway with a compacted granular soil to provide an adequate sub-grade under
the mat foundation.
Sand columns are normally drilled to form a matrix of sand columns with a
spacing of 5 meters, i.e. the maximum length of water to flow away from any
sand column is 2.5 meters. Assuming an incremental distance ∆L of 0.2 meters
for the analysis, one can now use equation (6) to determine the duration required
to wet the site. The only unknown would be K due to its variance from one part
of the site to another for the same silty soil. Therefore, a sensitivity analysis was
done on the soil model provided in equation (6) and the value of K used within
the typical range for silty soils. Results are provided in Figure 3. Results
indicate high sensitivity of the model to K value and an exponential drop in time
needed to wet the soil as K decreases.
Sensitivity of Time Needed to Hydraulic Conductivity
250.0
Time Needed For Soil to Collapse (days)
200.0
150.0
100.0
50.0
0.0
0.00E+00 2.00E-05 4.00E-05 6.00E-05 8.00E-05 1.00E-04 1.20E-04
Hydraulic Conductivity (cm/s)
0.6 825.40
Ground Elevation
825.40
Ground Surface Elevation (m)
0.4
Vol. Water Content
825.40
0.3 825.39
825.39
0.2
825.39
0.1
825.39
0 825.39
11/5 11/10 11/15 11/20 11/25 11/30 12/5 12/10 12/15 12/20 12/25 12/30 1/4 1/9 1/14
DATE
Figure 4: Water content and ground surface elevation change versus time.
6 Conclusion
This paper presents a case study of wetting loessail soil to avoid problems
associated with its susceptibility to collapse due to a change in water content.
Laboratory test results identifying different soil characteristics were reported
along with a method to evaluate the soil susceptibility to collapse.
The geotechnical approach for dealing with the collapsible soil included a
hybrid of common and well known techniques usually used to deal with loessail
soils. The paper presented an analytical approach for estimating the time needed
to wet the soil, with a sensitivity analysis of the time dependence on the
hydraulic conductivity of the soil. The paper also included graphical
presentation and analysis of data measured in the field, and a comparison
between analytical results and field measured data. The two results were
consistent and thus provided some validation of the analytical approach
presented. The paper includes a guide for engineers dealing with loessail soils
and a method of estimating time required to wet the soil backed up with
measured field data.
References
[1] Joseph E. Bowles, 1996, Foundation Analysis and Design, McGraw-Hill
Companies, Inc, New York, NY.
[2] Braja M. Das, 1984, Principles of Foundation Engineering, PWS Publishers,
Boston, MA.