UZMA ENGINEERING SDN. BHD.

General Info
Unit ID: 102232 Location : SmB-08
Model: NOV ELMAR SLIM SPLIT C

Running Hours
Date Hours Hours
NO Crew Day Crew Night Total Cumulat. Remarks
1 05-Sep-22 Shokree / Tarmizi 0 Zuriadi/Khairul 4 4 4
2 06-Sep-22 Shokree / Tarmizi 11 Zuriadi/Khairul 12 23 27
3 07-Sep-22 Shokree / Tarmizi 5.75 Zuriadi/Khairul 12 17.75 44.75
4 08-Sep-22 Shokree / Tarmizi 12 Zuriadi/Khairul 12 24 68.75
5 09-Sep-22 Shokree / Tarmizi 12 Zuriadi/Khairul 6 18 86.75
6 10-Sep-22 Shokree / Tarmizi 9.5 Zuriadi/Khairul 12 21.5 108.25
7 11-Sep-22 Shokree / Tarmizi Zuriadi/Khairul 0 108.25
8 12-Sep-22 Shokree / Tarmizi Zuriadi/Khairul 0 108.25
9 13-Sep-22 Shokree / Tarmizi Zuriadi/Khairul 0 108.25
10 0 108.25
11 0 108.25
12 0 108.25
13 0 108.25
14 0 0
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
Total Carry forward to next sheet

Note : * Cumulative Running Hours will be reset to zero upon completed carry-out 200 hours servic
* Total Cumulative Running Hours will be reset to zero upon completed carry-out 3600 hours
No Date Name Location
1 9/3/2022 Amirul Afiq Mohd Zukri SmB Main deck
2 9/3/2022 Mohd Zuriadi Ali SmB Main deck
3 9/3/2022 Khairul Annuar Johari SmB Main deck
4 9/4/2022 Azrul Rezuan Azman SmB Main deck
5 9/4/2022 Shokree Bin Abdul Latif SmB Galley
6 9/4/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad SmB Main deck
7 9/4/2022 Syed Mohd Aminomar SmB Main deck
8 9/4/2022 Amirul Afiq Mohd Zukri SmB Main deck
9 9/4/2022 Mohd Zuriadi Ali SmB Main deck
10 9/4/2022 Khairul Annuar Johari SmB Production Dec
11 9/4/2022 Fransiskus Xaverius Raditya
12 9/5/2022 Azrul Rezuan Azman SmB Main deck
13 9/5/2022 Shokree Bin Abdul Latif SmB Main deck
14 9/5/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad SmB Main deck
15 9/5/2022 Syed Mohd Aminomar
16 9/5/2022 Amirul Afiq Mohd Zukri SmB Main deck
17 9/5/2022 Mohd Zuriadi Ali SK Arctic Galley
18 9/5/2022 Khairul Annuar Johari SmB Main deck
19 9/5/2022 Fransiskus Xaverius Raditya
20 9/6/2022 Azrul Rezuan Azman SmB Main deck
21 9/6/2022 Shokree Bin Abdul Latif SmB Main deck
22 9/6/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad SmB Main deck
23 9/6/2022 Syed Mohd Aminomar SmB Main deck
24 9/6/2022 Amirul Afiq Mohd Zukri SmB Main Deck
25 9/6/2022 Mohd Zuriadi Ali SmB Main Deck
26 9/6/2022 Khairul Annuar Johari SmB Main Deck
27 9/6/2022 Fransiskus Xaverius Raditya
28 9/7/2022 Azrul Rezuan Azman SmB Main deck
29 9/7/2022 Shokree Bin Abdul Latif SmB Main deck
30 9/7/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad SmB Main deck
31 9/7/2022 Syed Mohd Aminomar SmB Main deck
24 9/7/2022 Amirul Afiq Mohd Zukri SmB Main deck
25 9/7/2022 Mohd Zuriadi Ali SmB Main deck
26 9/7/2022 Khairul Annuar Johari SmB Main deck
27 9/7/2022 Fransiskus Xaverius Raditya
28 9/8/2022 Azrul Rezuan Azman SmB Main deck
29 9/8/2022 Shokree Bin Abdul Latif SmB Main deck
30 9/8/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad SmB Main deck
24 9/8/2022 Syed Mohd Aminomar SmB Main deck
25 9/8/2022 Amirul Afiq Mohd Zukri SmB Main deck
26 9/8/2022 Mohd Zuriadi Ali SmB Main deck
26 9/8/2022 Khairul Annuar Johari SmB Main deck
27 9/8/2022 Fransiskus Xaverius Raditya
28 9/9/2022 Azrul Rezuan Azman SmB Main deck
29 9/9/2022 Shokree Bin Abdul Latif SmB Main deck
30 9/9/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad SmB Main deck
24 9/9/2022 Syed Mohd Aminomar SmB Main deck
25 9/9/2022 Amirul Afiq Mohd Zukri SmB Main deck
26 9/9/2022 Mohd Zuriadi Ali SmB Main deck
27 9/9/2022 Khairul Annuar Johari SmB Main deck
28 9/9/2022 Fransiskus Xaverius Raditya
29 9/10/2022 Azrul Rezuan Azman SmB Main deck
30 9/10/2022 Shokree Bin Abdul Latif
31 9/10/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
28 9/10/2022 Syed Mohd Aminomar
29 9/10/2022 Amirul Afiq Mohd Zukri
30 9/10/2022 Mohd Zuriadi Ali
31 9/10/2022 Khairul Annuar Johari
32 9/10/2022 Fransiskus Xaverius Raditya
33 9/11/2022 Azrul Rezuan Azman
34 9/11/2022 Shokree Bin Abdul Latif
35 9/11/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
32 9/11/2022 Syed Mohd Aminomar
33 9/11/2022 Amirul Afiq Mohd Zukri
34 9/11/2022 Mohd Zuriadi Ali
35 9/11/2022 Khairul Annuar Johari
36 9/11/2022 Fransiskus Xaverius Raditya
37 9/12/2022 Azrul Rezuan Azman
38 9/12/2022 Shokree Bin Abdul Latif
39 9/12/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
36 9/12/2022 Syed Mohd Aminomar
37 9/12/2022 Amirul Afiq Mohd Zukri
38 9/12/2022 Mohd Zuriadi Ali
39 9/12/2022 Khairul Annuar Johari
40 9/12/2022 Fransiskus Xaverius Raditya
41 9/13/2022 Azrul Rezuan Azman
42 9/13/2022 Shokree Bin Abdul Latif
43 9/13/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
40 9/13/2022 Syed Mohd Aminomar
41 9/13/2022 Amirul Afiq Mohd Zukri
42 9/13/2022 Mohd Zuriadi Ali
43 9/13/2022 Khairul Annuar Johari
44 9/13/2022 Fransiskus Xaverius Raditya
45 9/14/2022 Azrul Rezuan Azman
46 9/14/2022 Shokree Bin Abdul Latif
47 9/14/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
44 9/14/2022 Syed Mohd Aminomar
45 9/14/2022 Amirul Afiq Mohd Zukri
46 9/14/2022 Mohd Zuriadi Ali
47 9/14/2022 Khairul Annuar Johari
48 9/14/2022 Fransiskus Xaverius Raditya
49 9/15/2022 Azrul Rezuan Azman
50 9/15/2022 Shokree Bin Abdul Latif
51 9/15/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
48 9/15/2022 Syed Mohd Aminomar
49 9/15/2022 Amirul Afiq Mohd Zukri
50 9/15/2022 Mohd Zuriadi Ali
51 9/15/2022 Khairul Annuar Johari
52 9/15/2022 Fransiskus Xaverius Raditya
53 9/16/2022 Azrul Rezuan Azman
54 9/16/2022 Shokree Bin Abdul Latif
55 9/16/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
52 9/16/2022 Syed Mohd Aminomar
53 9/16/2022 Amirul Afiq Mohd Zukri
54 9/16/2022 Mohd Zuriadi Ali
55 9/16/2022 Khairul Annuar Johari
56 9/16/2022 Fransiskus Xaverius Raditya
57 9/17/2022 Azrul Rezuan Azman
58 9/17/2022 Shokree Bin Abdul Latif
59 9/17/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
56 9/17/2022 Syed Mohd Aminomar
57 9/17/2022 Amirul Afiq Mohd Zukri
58 9/17/2022 Mohd Zuriadi Ali
59 9/17/2022 Khairul Annuar Johari
60 9/17/2022 Fransiskus Xaverius Raditya
61 9/18/2022 Azrul Rezuan Azman
62 9/18/2022 Shokree Bin Abdul Latif
63 9/18/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
60 9/18/2022 Syed Mohd Aminomar
61 9/18/2022 Amirul Afiq Mohd Zukri
62 9/18/2022 Mohd Zuriadi Ali
63 9/18/2022 Khairul Annuar Johari
64 9/18/2022 Fransiskus Xaverius Raditya
65 9/19/2022 Azrul Rezuan Azman
66 9/19/2022 Shokree Bin Abdul Latif
67 9/19/2022 Tuan Mohd Tarmizi Bin Tuan Ahmad
64 9/19/2022 Syed Mohd Aminomar
65 9/19/2022 Amirul Afiq Mohd Zukri
66 9/19/2022 Mohd Zuriadi Ali
67 9/19/2022 Khairul Annuar Johari
68 9/19/2022 Fransiskus Xaverius Raditya
69 9/20/2022 Azrul Rezuan Azman
70 9/20/2022 Shokree Bin Abdul Latif
Observation
Observ heavy wind during working on main deck.
Intervent personnel to bend his leg during landing on the deck to absorb impact (using transfer basket)
Good communication between signalman and crane operator during lifting operation.
Rain may cause slippery surface at handrails and stairs
Observed personal wash is hand before entering galley
Found water ponding at work area. Can cause slippery
Observed strong wind outside.
Slippery floor due to rain
Wind speed 35 knot
Found empty bottle lay down on the grating

Observed strong winds.


Observed personal to wearing chin strap on helmet during strong wind
observed crew stop personal going to PTB before PTB fully landed on board.

Observe whipcheck not properly installed on the air hose


Observe paper cups and tissue inside food waste bin
Observe personal perform manual handling with proper body technique

Observed open grating for Eline rigup.


Observed toilet door not properly closed
remind crew to use correct handtool for the right job to prevent pinch point
Observed hot weather today. Remind crew to drink plenty of water to keep hydrated.
High pressure during pressure test the PCE
Observed personnel not bending his knees during transfer basket landing
Remind crew on the correct hand placement during rigup to prevent pinch point

Good communication between crew while rigging down pressure test toolstring .
Observed air hose for control panel lay out walk way area
found air hose was laying on maindeck and block walkway line
Observed insert at lifting plate was not properly fit with tool.
Poor housekeeping inside the logging cabin
Observed bad weather (heavy wind and lightning)
Observed personnel wearing greasy hand glove during descending staircase

Ensure personnel hand placement in correct position while rigup


Remind all crew to make sure impact glove is in good condition
observe handtool was laying on maindeck
Observed no grounding cable was install at Pressure Vacuum pump
Observed grease spills on the main deck floor
Good communication between winch man and operator during connecting tool
Observed personnel clean up the handtools and store it back into toolbox after complete task

Good communication between winchman and crew while rigdown.


Remind crew to always count master & crown valve turn during open and closed valve
Remind crew to use filter funnel during topup diesel into powerpack
Good cooperation from all crew during rig down
Observed sharp edges on the tool due to using the pipe wrench
Remind personnel to watch step while working due to slippery floor after rain
Found used cutton rags laying on the main deck floor

Put signage and inform non related personnel to keep away while performing arming gun
Remind all crew to be Careful while walking at maindeck. Water Pounding everywhere due to heavy rain.

Observed water ponding nearby wireline unit.


Action
Remind crew to secure all loose items
Good job
Good practice and keep it up
Remind team to be extra careful and hold both handrails while walking up or down stairs
Good hygiene and good practice
Push away water ponding to nearest drain
Remind crew to properly hold the door while opening the door to prevent the door from swing
Remind crew to watch their step properly
Remind crew to stay at LQ
Pick it up and throw it into designated bin

Remind team to stay in LQ while waiting for weather to subside


Good practice.
Good practice.

Install the whipcheck properly to prevent any incident


Remind crew to discard the waste on the designated bin
Good practice

Cover gap with wooden planks.


Closed properly
Good practice

Remind crew to stay away from line of fire


Remind him to bend the knees during landing to prevent any injuries
Good reminder

Good job.
move air hose and scure properly
Rearrange the hose and put barrier tape around the hose
Change with the right insert.
Perform housekeeping and remind crew to keep good housekeeping inside the logging cabin
Inform all crew to stop job and stay inside LQ
Stop him and tell him to change the glove

Good job
Good practice.
perform housekeeping
Install grounding cable and connect to grounding point
Wash the floor using rig wash
Good teamwork
Good practice

Good job
Good practice
Good practice
Good job
Filed the tool body to remove the sharp edges
Good reminder
Take the cutton rags and put into the waste bin

Good practice

Wipe water to nearby drain hole


REPORT NO. : 8
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 09-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 10-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 8
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 39
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

RIH Gun #3

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 08:00 1:30 TRV Strong wind and rain.
08:00 08:15 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform.
08:15 08:30 0:15 OPR Receive handover from night shift crew.
08:30 08:45 0:15 OPR Toolbox meeting with WOS and all Well Work contractors. PTW.
08:45 10:30 1:45 WOW Strong wind and rain.
10:30 11:30 1:00 OPR Rigup on toolstring. Perform arming gun electrical before ballistic. Secure lubricator
11:30 11:58 0:28 OPR Open well. RIH.

11:58 14:30 2:32 OPR Reach 200ft below sea bed level. Perform tractor comm check and Power up SGRCCL
14:30 18:20 3:50 OPR Open well and RIH.
18:20 18:30 0:10 OPR Heldup depth at 3710 mMDDF.
Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:15 0:30 OPR Start tractoring from 3710 m MDDF until 3900 m MDDF
19:15 19:45 0:30 OPR Start Correlation Pass for Gun#2 from 3900 m MDDF until 3615 m MDDF
19:45 20:45 1:00 OPR Process the data and send data to town for verification
20:45 21:30 0:45 Got confirmation from town to proceed with perforation gun. Depth shifted agreed with
21:30 22:00 0:30 town
Adjust-3.7m
the depth and start tractoring down to 3900 m MDDF
22:00 22:30 0:30 Start Repeat Pass from 3900 m MDDF to 3800 m MDDF to confirm on depth.
22:30 22:45 0:15 Tractoring down to 3900 m MDDF for Shooting Pass
22:45 23:00 0:15 Start Shooting Pass from 3900 m MDDF and stop at CCL Stop Depth, 3866.15 m MDDF
23:00 23:10 0:10 Send firing sequence to shoot the gun:
23:10 23:30 0:20 Continue Shooting Pass until 3615 m MDDF
23:30 03:00 3:30 POOH to surface. Slow down at accessories area
03:00 03:30 0:30 Stop at 200 m MDDF. Switch off all panels and turn the safety switch to SAFE position.
03:30 03:45 0:15 Continue POOH
Close CV and MV.toBleed
surface
pressure.
03:45 04:45 1:00 Disconnect lubricator at QTS. Laydown and disconnect the toolstring. Observed all
04:45 05:00 charges fired
Check insulation on cable head and backup shock absorber - Good insulation
05:00 05:30 Connect backup tractor and perform surface test as per Altus checklist
05:30 06:00 Connect GRCCL, Shock Absorber and HP sub below the tractor. Perform surface test and
06:00 06:30 hot-check as per
Rigup tractor Surface
vertically Perforation
and Checklist
put into the lubricator

LOOK AHEAD PLANNED FOR NEXT 24HRS

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 8
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 09-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 10-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 8
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 39
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

RIH Gun #2

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 07:00 0:30 TRV SK Arctic pickup personnel from SmA.
07:00 07:15 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform.
07:15 07:30 0:15 OPR Receive handover from night shift crew.
07:30 08:00 0:30 OPR Toolbox meeting with WOS and all Well Work contractors. PTW.
Packing and send back 2ea GRCCL down to town.
08:00 10:30 2:30 OPR
Management site visit.
10:30 12:30 2:00 OPR Receive backup tool from icon amira. Tool and tractor checks OK. No stray voltage.
12:30 14:00 1:30 OPR Rigup on toolstring. Hold arming gun for boat to pickup visitors.
14:00 14:30 0:30 OPR Perform electrical before ballistic arming. Secure lubricator and catch tool.
14:30 18:20 3:50 OPR Open well and RIH.
18:20 18:30 0:10 OPR Heldup depth at 3710 mMDDF.
Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:15 0:30 OPR Start tractoring from 3710 m MDDF until 3900 m MDDF
19:15 19:45 0:30 OPR Start Correlation Pass for Gun#2 from 3900 m MDDF until 3615 m MDDF
19:45 20:45 1:00 OPR Process the data and send data to town for verification
20:45 21:30 0:45 Got confirmation from town to proceed with perforation gun. Depth shifted agreed with
21:30 22:00 0:30 town
Adjust-3.7m
the depth and start tractoring down to 3900 m MDDF
22:00 22:30 0:30 Start Repeat Pass from 3900 m MDDF to 3800 m MDDF to confirm on depth.
22:30 22:45 0:15 Tractoring down to 3900 m MDDF for Shooting Pass
22:45 23:00 0:15 Start Shooting Pass from 3900 m MDDF and stop at CCL Stop Depth, 3866.15 m MDDF
23:00 23:10 0:10 Send firing sequence to shoot the gun:
23:10 23:30 0:20 Continue Shooting Pass until 3615 m MDDF
23:30 03:00 3:30 POOH to surface. Slow down at accessories area
03:00 03:30 0:30 Stop at 200 m MDDF. Switch off all panels and turn the safety switch to SAFE position.
03:30 03:45 0:15 Continue POOH
Close CV and MV.toBleed
surface
pressure.
03:45 04:45 1:00 Disconnect lubricator at QTS. Laydown and disconnect the toolstring. Observed all
04:45 05:00 charges fired
Check insulation on cable head and backup shock absorber - Good insulation
05:00 05:30 Connect backup tractor and perform surface test as per Altus checklist
05:30 06:00 Connect GRCCL, Shock Absorber and HP sub below the tractor. Perform surface test and
06:00 06:30 hot-check as per
Rigup tractor Surface
vertically Perforation
and Checklist
put into the lubricator

LOOK AHEAD PLANNED FOR NEXT 24HRS

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 8
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 09-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 10-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 8
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 39
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

RIH Gun #1

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 07:00 0:30 OPR Night shift continue correlation pass. Day shift waiting on passing squal.
07:00 07:15 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform
07:15 07:30 0:15 OPR Receive handover from night shift crew.
07:30 08:47 1:17 OPR Verify data for repeat pass and send to town for green light.
08:47 09:30 0:43 OPR Greenlight received. Pickup to shooting depth.
Perform firing sequence. Repeat several times. Observed current fluctuation and open
circuit.
09:30 10:00 0:30 OPR THP Before: -47 kpa, THP After: -52 kpa
Tension Before: 1250 lbs, Tension After: 1240 lbs.

10:00 11:05 1:05 NPT Observed outer armor loose at cable drum. Inform supervisor and tractor down to rectify.

Outer armor loose found at 3879 mMDDF in front of smarthead. Torque cable, observed
11:05 11:30 0:25 NPT loose cable travel towards drum. Discuss with town on way forward.
Tractor down until 3928 mMDDF while torquing cable. Secure cable with cable clamp.
11:30 13:30 2:00 NPT Observed loose strand moved into cable drum. Tape cable at smart head to prevent cable
untorquing towards in hole. Mark with green spray paint.

13:30 16:30 3:00 OPR POOH safely while monitoring cable condition.
Tool at surface. All shots fired. Rig down on gun and toolstring and cap at BOP.
16:30 18:30 2:00 OPR Prepare for next run.
Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:15 0:30 OPR Toolbox meeting with WOS and all Well Work contractors
19:15 19:45 0:30 OPR Permit to work application
19:45 20:00 0:15 OPR Check insulation on the cable head - Insulation ok
20:00 20:30 0:30 OPR Connect GRCCL tool and perform surface check - observed no GR reading
Inform town and WOS on the issue. Communicate with IE at town on the troubleshooting
20:30 21:00 0:30 NPT steps
Troubleshooting steps as below:

1) Open the tool housing to check on the electronic board. Found no resistors, diodes or
capacitors burnt
2) Remove the hard silicone on top of Gamma Ray section to tighten holder
21:00 00:00 3:00 NPT 3) Found grounding wire got pinched. Cover the pinched wire with high temp tape
4) Re-install the tool housing
5) Power up the tool and found GR reading still zero
6) As per IE, the GR sensor or electronic board got issue and need to be sent to town for
further investigation.

00:00 01:00 1:00 NPT Break


01:00 01:30 0:30 NPT Perform drill
01:30 02:00 0:30 NPT Cover the hatch hole with scaffolding plank and secure with GI wire
02:00 04:30 2:30 NPT Service and redress shock absorber and HP adaptor from previous run
04:30 05:30 1:00 NPT Clean up handtools inside the doghouse
05:30 06:30 1:00 NPT Service and clean up the firing head from the previous run

LOOK AHEAD PLANNED FOR NEXT 24HRS

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 7
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 08-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 09-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 7
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 33
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

RIH Gun #1

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 06:45 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform
06:45 07:00 0:15 OPR Receive handover from night shift
Continue trouble shoot on Gamma Ray telemetry issue. Observed no PMON signal.
Voltage and current normal. CCL reading OK. After communicate with town, trouble
shoot done as below:
07:00 08:00 1:00 NPT - Cycle power
- Cycle tractor VPM-G mode
- Swap STIP.

08:00 11:00 3:00 NPT Unable to rectify issue. Discuss with town and decide to POOH.
Tool at surface. Disconnect dummy gun and gamma gun. Ready backup gamma gun and
11:00 14:00 3:00 OPR perform maintenance checklist.

14:00 17:00 3:00 WOW Passing squal and rain. Sent checklist to town for review. Waiting on greenlight.

Greenlight received. Attach rig to casing monitor. No stray voltage


Perform CCL check and background GR reading check OK.
Perform Hot Check OK.
17:00 19:00 2:00 OPR Function check Altus tractor and stray voltage check.
Make CCL to top shot. 2.85m
Perform electrical before ballistic arming.

Secure lubricator and catch tool.


19:00 19:30 0:30 OPR Open well and RIH.
Night Shift
19:15 19:30 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
19:30 19:45 0:15 OPR Permit to work application
19:45 22:30 2:45 OPR Continue RIH to target depth. Perform pick-up weight for every 500m and record into the
22:30 00:35 2:05 OPR Z-Chart
Held-up at 2167 m MDDF (uncorrected depth). Start tractoring to target depth. Perform
00:35 01:45 1:10 OPR pick-up
Start weight for
Correlation every
Pass from500m.
3900m to 3800m MDDF. Prepare data to be sent to town.
01:45 03:15 1:30 OPR Depth shifted
Send data = -15.93
to town. Gotminstruction from Exxon Geoscientist to log up further into EOT
03:15 04:40 1:25 OPR Start Correlation Pass from 3900m to 3625m MDDF. Prepare data to be sent to town.
04:40 05:30 0:50 OPR Depth shifted
Send data = -15.91
to town. mdepth shift from Exxon Geoscientist is -16.1 m.
Final
05:30 07:00 1:30 OPR Start Repeat Pass from 3900m to 3625m MDDF. Prepare data to be sent to town. Depth
shifted = 0m

LOOK AHEAD PLANNED FOR NEXT 24HRS

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 6
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 07-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 08-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 6
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 27
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

RIH Dummy Gun with Tractor

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 06:45 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform
06:30 07:15 0:45 OPR Toolbox meeting with WOS and all Well Work contractors
07:15 07:30 0:15 OPR Permit to Work application.
07:30 08:30 1:00 OPR Break off lubricator at quick test sub. Rigdown on 6ea weight bar
Laydown UZMA toolstring GRCCL+Shocksub.
08:30 10:00 1:30 OPR Prepare on dummy gun (Tandem 10ft+10ft 2" spent gun).
Pump grease into CH.

10:00 16:30 6:30 STN PTW suspended and safety stand down due to finger injury incident at SmA.

Greenlight for continue operation.


16:30 17:00 0:30 OPR Assist Altus laydown and connect CH+Swivel+Tractor+VPM-G
Altus power up tractor and function check wheels. Check for stray voltage below VPM-G.
17:00 17:30 0:30 STN Max -80V while switching modes.
Add VSS below VPM-G. Swictch modes several times while monitoring voltage with
17:30 18:15 0:45 OPR multimeter. Oberved no voltage pass through, 0V.
18:15 18:30 0:15 OPR Disconnect VSS. Laydown Probe Gamma Gun to connect below VPM-G.
Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:15 0:30 OPR Toolbox meeting with WOS and all Well Work contractors
19:15 19:45 0:30 OPR Permit to work application
19:45 20:00 0:15 Connect Probe GRCCL into the string.
20:00 20:30 0:30 Perform function test and hot check on GRCCL - test ok
20:30 21:30 1:00 Rigup toolstring for Dummy Gun Run
21:30 22:00 0:30 Stab in lubticator and perform pressure test on QTS at 3000 psi and hold for 15 minutes -
22:00 22:15 0:15 pressure
Open CV test
andokMV
RIH from surface to target depth. Tool weight = 360lbs. THP = 0psi. Perform pick up
weight every 500 m and record into the Z-Chart.

Experienced held-up on several depths but managed to pass through:

1) 995 m
22:15 00:50 2:35
2) 1100 m
3) 2080 m
4) 2152 m
5) 2171 m
6) 2305 m

Heldup at 2358m and start tractoring. Perform pickup weight for every 500m and record
into the Z-Chart.

00:50 04:30 3:40 Got heldup with tractor on several depth but managed to pass through as below:

1) 2960 m
2) 3630 m
Arrived at bottom depth. Perform correlation pass. Observed no Gamma Ray reading.
04:30 05:00 0:30 CCL reading was ok.
Troubleshoot and inform town on the issue. Troubleshooting steps done as below:

1) Restart the panel and re-power up the tool


2) Adjust the Sync Gain for Gamma Ray reading
05:00 06:00 1:00 3) Increase the voltage from 60v to 65v
4) Adjust PMON threshold

After all troubleshooting steps done, still no Gamma Ray reading.

06:00 06:30 0:30 Inform WOS onboard and day shift crew will continue troubleshooting

LOOK AHEAD PLANNED FOR NEXT 24HRS

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 5
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 06-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 07-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 5
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 21
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

Surface preparation.

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 06:45 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform
06:30 07:15 0:45 OPR Toolbox meeting with WOS and all Well Work contractors
07:15 07:30 0:15 OPR Permit to Work application.
07:30 08:15 0:45 OPR Fire Drill. Scenario leak above BOP.
08:15 08:30 0:15 OPR Review with WOS and Wellworks team on scenario implementation.
Retrieve trigger tool box from Damar. Unload slickline perforation equipment and demob
08:30 09:30 1:00 OPR
back to Sea Link.
09:30 10:00 0:30 OPR Prepare on mast rigup. Connect air and hydraulic hoses.
10:00 10:15 0:15 STN Rigup on skyfold mast 1st section.
10:15 11:00 0:45 OPR Secure on mast 1st section guy wires.
11:00 11:15 0:15 OPR Rigup on skyfold mast 2nd section.
11:15 13:00 1:45 OPR Rigup on mast 3rd section. Secure remaining guy wires.
13:00 14:00 1:00 STN Break
Make up lower PCE section on main deck. XO+Ball valve, 10 ft Lubricator+Tool trap+PIS
14:00 15:00 1:00 OPR

15:00 16:00 1:00 OPR Meeting with town for SmB job review.
Verify zero energy and rigup PCE lower section on well. XO+Ball valve+10 ft
16:00 17:00 1:00 STN Lubricator+Tool Trap+PIS+BOP. Cap on BOP.
Make cable head 9x3 weakpoint. Measured resistance 73.6 ohm.
Secure upper PCE section hoses for rigup.
17:00 18:30 1:30 OPR Assist Altus to test tractor OK.
Topup diesel to power pack.

Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:45 1:00 OPR Toolbox meeting with WOS and all Well Work contractors
19:45 20:15 0:30 OPR Permit to work application
20:15 22:00 1:45 OPR Rigup lower sheave wheel with tie-down chain (primary) and web sling (secondary)
22:00 00:30 2:30 OPR secured report
Prepare to wellhead's pad
for lower eye wheel installation and send to town for approval. Town
sheave
00:30 00:50 0:20 OPR approvedpressure
Perform on the current
test on setup
the lower section of PCE at 3000 psi and hold for 15 minutes -
00:50 01:10 0:20 OPR pressure pressure
Perform test ok test on upper and middle ram BOP at 3000 psi and hold for 15 minutes
01:10 01:30 0:20 OPR -Perform
pressure test ok test on the shear ram BOP at 3000 psi and hold for 15 minutes -
pressure
01:30 03:00 1:30 WOW pressure
Suspend test ok
operation due to heavy rain and thunderstorm
03:00 03:30 0:30 OPR Rigup upper sheave wheel to the top of Skyfold Mast
03:30 05:00 1:30 OPR Lift up upper section PCE and connect another 2 x 10ft lubricators and 1 x 4ft lubricator
05:00 05:30 0:30 OPR Connect 4 x Weight Bars for pressure test and put the tools inside the lubricator. Stab in
05:30 06:00 0:30 OPR the lubricator
Perform andtest
pressure ready
onfor
fullpressure testat 3000 psi and hold for 15 minutes - pressure
string PCE
06:00 06:30 0:30 OPR test
Topup ok diesel and housekeeping at worksite

LOOK AHEAD PLANNED FOR NEXT 24HRS

1) Surface check on toolstring


2) RIH Dummy Gun with Tractor

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 4
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 05-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 06-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 4
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 15
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

1) Backload slickline equipment and offload Eline equipment.


2) Deck arrangement for Eline Operation
3) Surface preparation

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 06:45 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform
06:45 07:15 0:30 OPR Toolbox meeting with WOS and all Well Work contractors
07:15 08:00 0:45 OPR Permit to Work application.
08:00 10:00 2:00 WOW Strong wind and rain. Wait on weather to perform lifting operation.
10:00 11:00 1:00 OPR Discuss with Wellworks team on equipment layout before lifting operation.
11:00 11:30 0:30 OPR Scenario Management Briefing with Exxon team.
Perform lifting and spot 2 Uzma lifts from SK Arctic.
11:30 12:30 1:00 OPR Assist Deleum to backload paritially and position equipment.
12:30 13:30 1:00 STN Lifting to continue after lunch.
Perform lifting 10 Uzma lifts, 2 Altus lifts from SK Arctic to SmB.
13:30 17:00 3:30 OPR Assist Deleum and platform to backload equipment.
17:00 18:20 1:20 OPR Spot equipment.
18:20 18:30 0:10 OPR Housekeeping.
Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:45 1:00 OPR Toolbox meeting with WOS and all Well Work contractors
19:45 20:15 0:30 OPR Permit to work application
20:15 22:00 1:45 OPR Transfer PCE, Tractors & Grease Drum from their basket to the deck
22:00 00:00 2:00 OPR Transfer Grease Drum Basket and Tractor Tool Pallet from SmB platform to SK Arctic.
00:00 01:00 1:00 STN Unable
Break to transfer PCE basket to SK Arctic due to limited space on the vessel deck
01:00 02:30 1:30 OPR Re-arrange equipments on deck for Eline operation
02:30 03:00 0:30 OPR Connect all hoses from power pack to winch and logging cabin
03:00 03:30 0:30 OPR Start the power pack and power up the logging cabin for test run - all good
03:30 04:00 0:30 OPR Hook up Tractor panels inside logging unit
04:00 06:00 2:00 OPR Make up Grease Injection Head with 2 x 10ft lubricators and pass through the Eline cable
06:00 06:30 0:30 OPR Housekeeping at worksite

LOOK AHEAD PLANNED FOR NEXT 24HRS

1) Continue surface preparation


2) Rigup Mast and PCE
3) Surface check on toolstring
4) RIH Dummy Gun with Tractor
NON PRODUCTIVE TIME
DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 3
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 04-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 05-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 3
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 9
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) 0 PSI
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

Slickline operation flapper probe and TCC.


Scaffolding for Jettison Skid.

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 06:45 0:15 TRV Day Shift crew transfer from SK Arctic to SmB Platform
06:45 07:15 0:30 OPR Safety briefing by DPIC to all crews
07:15 07:45 0:30 OPR Toolbox meeting with WOS and all Well Work contractors
07:45 08:30 0:45 OPR Permit to Work application.
08:30 09:00 0:30 WOW Waiting on weather.
Slickline run flapper probe. SITHP:
09:00 12:00 3:00 OPR Make plan for Eline equipment layout. Request to offload 4 platform container to make
space for Eline setup.
12:00 14:00 2:00 WOW Strong wind and rain.
Slickline run TCC 2.8" toolstring.
14:00 16:00 2:00 OPR Sapura scaffolding crew make platform for jettison skid.

Backload scaffolding basket to SK Arctic and offload explosive box onto maindeck.
16:00 18:00 2:00 OPR Reposition eqiupment at maindeck and production deck.
Position explosive box with jettison skid at jettison platform and secure.

18:00 18:30 0:30 OPR Housekeeping.


Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:45 1:00 OPR Toolbox meeting with WOS and all Well Work contractors
19:45 04:30 8:45 STN Standby for slickline operation
04:30 06:30 2:00 WOW Wait on weather

LOOK AHEAD PLANNED FOR NEXT 24HRS


1) Slickline operation on well SmB-08
2) Deck arrangement for Eline Operation
3) Rigup Eline equipment
NON PRODUCTIVE TIME
DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 2
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 03-09-2022/ 06:30HRS
SMB-08ST#2 REPORT END DATE & TIME: 04-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 2
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 3
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) TBA
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

Mob to Semangkok B from KSB.

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

Day Shift
06:30 18:30 12:00 TRV Continue travel to SmB. 1 pax Uzma personnel transfer from SmA to SK Arctic.
Night Shift
18:30 18:45 0:15 TRV Night Shift crew transfer from SK Arctic to SmB Platform
18:45 19:15 0:30 OPR Safety briefing by DPIC to all crews
19:15 19:45 0:30 OPR Toolbox meeting with WOS and all Well Work contractors
19:45 20:30 0:45 OPR Permit to Work application
20:30 00:00 3:30 OPR Assist slickline and pumping crew to setup their equipment
00:00 01:00 1:00 STN Break
01:00 03:30 2:30 OPR Lifting operation to load and unload equipment from SK Arctic to SmB Platform
03:30 04:30 1:00 OPR Assist slickline
04:30 06:00 1:30 WOW WOW
06:00 06:30 0:30 OPR Housekeeping

LOOK AHEAD PLANNED FOR NEXT 24HRS


1) Slickline operation on well SmB-08
2) Deck arrangement for Eline Operation
3) Rigup Eline equipment
NON PRODUCTIVE TIME
DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
REPORT NO. : 1
DAILY WIRELINE SERVICES REPORT REPORT START DATE & TIME: 02-09-2022/ 10:00HRS
SMB-08ST#2 REPORT END DATE & TIME: 03-09-2022/ 06:30HRS
REPORTING STANDARD
REPORTING TIME

DETAILS
COMPANY NAME UZMA ENGINEERING EVENT CODE TBA DAYS ON PLATFORM 1
WELL NAME SMB-08 WELLBORE TBA PLATFORM Semangkok B
JOB START DATE TBA CASING TYPE 7" 23# l-80 VESSEL SK Arctic
JOB CATEGORY Perforation FIELD Semangkok WWS Aisamuddin/Suhaire
ACTIVITY Eline PLAN DAYS 7 JOB COMPLETION TBA
OBJECTIVE/SCOPE Tractor Perforation ACTUAL DAYS TBA DATE
STATUS @ 0600Hrs
PERSONNEL ONBOARD COMPANIES ONSITE
STRING DATA HSE DATA
COMPANY WORK MEMBERS POSITION COMPANY NO. OF PAX
WELL TYPE Oil Producer UZMA AZRUL REZUAN FE UZMA 6
UA/UC REPORTED 0
WELL HEAD TYPE UZMA AMIRUL AFIQ FE ALTUS 2
SCSSV TYPE UZMA SHOKREE CC
TBG SIZE (") 3-1/2" 9.2# UZMA ZURIADI CC
RIG ELEV (M) UZMA TARMIZI SFO
MAX ANGLE DEV. 88.4 deg UZMA KHAIRUL ANNUAR SFO
STATUS TBA ALTUS SYED AMIN FE
PCP (PSIG) TBA ALTUS RADITYA FE
SCP (PSIG) TBA
FTHP (PSIG) TBA
CITHP (PSIG) TBA
PREVIOUS FLUID LEVEL (FT)
INCIDENT/ ACCIDENT:

OPERATIONS HIGHLIGHTS

Mob to Semangkok B from KSB.

DURATION PHASE PT/ ACTIVITY


START (HRS) END (HRS) OPERATION DETAILS
(HRS) CODE NPT CODE

10:00 11:00 1:00 TRV Check in to SK Arctic at KSB


11:00 18:30 7:30 TRV SK Arctic undergo maintenance on aircond.
18:30 06:30 12:00 TRV SDFN.

LOOK AHEAD PLANNED FOR NEXT 24HRS

Prepare on PTW.

NON PRODUCTIVE TIME


DURATION
START (HRS) END (HRS) CODE TYPE COMMENT
(HRS)

EQUIPMENT/TOOL/ELASTOMERS/OTHERS LEFT IN HOLE


BOTTOM
ITEM DESCRIPTION PART NO TOP DEPTH (THF) REMARKS
DEPTH (THF)

REMARKS

Short Services Worker (SSW) - For personnel below 6 month at EMEPMI facility will need to use red hard hat as per EMEPMI Rules.

PREPARED BY EMEPMI WWS EMEPMI OPERATIONS REPRESENTATIVE


NAME Azrul Rezuan /Amirul Afiq NAME Aisamuddin/Suhaire NAME

*Mandatory fields
Personnel Load Chart
ExxonMobil Month: June 2022
uzmaWireline Irong Barat A

Well : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total days Standby Man Hr

Engineer
Azrul Rezuan Azman x x x 3 36
Amirul Afiq Mohd Zukfi x x x 3 36
Senior Operator
Shokree Bin Abdul Latif x x 2 24
Mohd Zuriadi Bin Ali @ Mustafa x x x 3 36
Operator
Tuan Mohd Tarmizi Bin Tuan Ahmad x x x 3 36
Khairul Annuar Bin Johari x x x 3 36
Tractor Specialist
Syed Mohd Aminomar Syed Putra x x x 3 36
Fransiskus Xaverius Raditya x x x 3 36

legend S = Standby

1 = Offshore

Total man Hour 276

Uzmawireline Personnel: Client Representatives:

Signature: Signature:

Date: Date:
Equipment Load Chart

Month: June 2022


uzmaWireline
Quantity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total Days
Retainer Equipments
Slim Split Cabin (UZ-LF-LC-003) 1 1 1 2
Slim Split Power Pack (UZ-LF-PP-003) 1 1 1 2
Cradle Winch (UZ-103601) 1 1 1 2
Cradle Winch Skid (UZ-CWS-02) 1 1 1
Dog House (UZ-103500) 1 1 1 2
Storage Container (UZ-103505) 1 1 1 2
Open Top Tray for 4" PCE Package (T3HHOT 14002) 1 1 1 2
70ft Skyfold Mast (L-6901014831-V04-011) 1 1 1 2
Open Drum Skid (UZ-103502) 1 1 1 2
Genset (19185-1) 1 1 1 2
Open Top Tray - ALTUS (PT 3623/1) 1 1 1 2
Mini Offshore Container - ALTUS (TSBU 9014007) 1 1 1 2
Primary Explosive Box (UZ-EXP-P-07) 1 1 1 2
Jettison Skid (UZ-JS-01) 1 1 1
Open Top Tray (UZ-PALLET-NO 05)) 1 1 1 2

Tool
1-11/16" Gamma Gun 2 2 2 2
1-11/16" Perforating CCL 2 2 2 2
Shock Absorber 4 2 2 2
Shear - Seal BOP 1 1 1 2
Junk Basket/Dummy Gun 3 2 2 2
Electronic Control Release Device 2 2 2 2
Swivel Joint 2 2 2 2
Voltage Sensing Switch 2 2 2 2
Voltage Protection Module 2 2 2 2
Tractor Services 2 - 1/8" 2 2 2 2
Swivel 3 3 3 2

Explosive :

UzmaWireline Personnel: Client Representatives:

Signature: Signature:

Date: Date:
SEMANGKOK B-8ST2
WELLBORE SKETCH

TUBING : 3-1/2", 9.2 ppf, N-80, Fox Kawasaki


OP

30° XXO-SVLN (ID 2.813") 5° 145.9m

40° Wellstar SCSSV (ID 2.813") 8° 165.0m

71° X-Nipple (ID 2.813") 71° 1428.4m

71° GLM #1 (w/ 1" GLV PTRO 1315 psi) (ID 2.90") 70° 1446.7m
GLV port size : 8/64; PSO :1400 psi

76° GLM #2 (w/ 1"GLV PTRO 1370 psi) (ID 2.90") 75° 2929.3m
GLV port size : 12/64; PSO :1379 psi

76° GLM #3 (w/ 1" GLV PTRO 1185 psi) (ID 2.90") 77° 3598.8m
GLV port size : 12/64; PSO :1200 psi

76° X-Nipple (ID 2.813") 76° 3618.9m

76° 7" BHR Single Packer (ID 2.94") 76° 3637.9m

76° XD-SSD (ID 2.813") 76° 3657.3m

76° XN-Nipple (ID 2.69") 78° 3669.8m


78° EOT 3699.8m

Last WL depth sinker bar @ 3894m (81 deg)


Last CT depth @ 4145m (88 deg)

E-40: 4170-4275 m MDDF


(105 m)

TD : 4350.0m

Max Angle of 88.4 deg at 4225 m 7",23.0 PPF, L-80, BTC