Professional Documents
Culture Documents
•Contract documents
•General obligations
•Labor
•Materials, plant, and workmanship
•Suspension
•Commencement and delays
•Defects liability
•Alterations, additions and omissions
•Procedure for claims
•Contractor’s equipment, temporary
works and materials
•Measurement
•Provisional sums
•Nominated subcontractors
•Certificates and payment
•Remedies
•Special risks
•Release from performance
•Settlement of disputes
•Notices
•Default of employer
•Changes in cost and legislation
•Currency and rates of exchange
Differing site conditions
One of the most misunderstood of all
contract provisions, and the one
that is frequently the cause of
large contractor claims for
additional work and change orders
is the provision for differing site
conditions.
Subsurface and latent physical
conditions at the site present a
special problem. If they differ
significantly from what is
printed in the contract documents,
the contractor may well be entitled
to additional payment for any
increased work involved.
Bidder’s obligations
a. Bidders are generally advised in the
contract to make a site inspection of
their own.
b. The contract bid price is proportional to
the degree of risk that the construction
contractor must provide for in its
competitive bid.
c. The most cost-effective construction is
obtained by accepting certain risks for
latent or subsurface site conditions.
Types of Drawings comprising the
Construction contract
· Shop drawings – those details and
sketches prepared by the contractor
or the material suppliers or fabricators
that are necessary to assure the
fabricator that the basic concept is
acceptable before beginning costly
fabrication.
They frequently contain information that
is not related to the design concept,
or information that is relative only to
the fabrication process or construction
techniques in the field. In approving
shop drawings, the engineer only
indicates that the items conform to the
design concept of the project and
compliance with the plans and
specifications prepared.
The Functions of Shop Drawings
The shop drawing is the connecting link
between design and construction. Most
specifications require that the contractor
refrain from ordering material until the results
of the review of the shop drawing submittal
from the design organization have been
received. Any delay in processing of shop
drawings affects the contractor’s scheduling
and may result in extra cost of the owner.
Disapproving or stopping the work
Upon receipt of information from the
engineer that the work is defective,
the owner may order the contractor
to stop the work on these grounds.
Thank you for
your listening
and
participation!