Sub: -APTRANSCO–MRT/SD/Podili – Monthly returns and progress of works for
OCTOBER-2020 – Submitted – Reg.
* * *
The monthly progress of MRT / SD / Podili subdivision for the month of OCTOBER-2020 in respect of the
following is herewith enclosed.
1. Daily progress
2. Targets achieved
3. Test results of Energy meters
4. Operation of frequency relays
5. Test results of CTs Tan D
6. Periodical testing of Relays
7. Feeder tripping report
8. Sick equipment report
9. T&P report
From To
The Deputy Executive Engineer, The Executive Engineer,
MRT / SD / Podili. MRT & Tre / Ongole.
Lr. No. DEE / MRT/ SD / PDL / F. No. 20 / D.No. 255 / 20, Dt. 26 - 10 - 20.
Sir,
Sub: -APTRANSCO–MRT/SD/Podili – Monthly returns and progress of works for
OCTOBER-2020 – Submitted – Reg.
* * *
The monthly progress of MRT / SD / Podili subdivision for the month of OCTOBER-2020 in respect of the
following is herewith enclosed.
1. Daily progress
2. Targets achieved
3. Test results of Energy meters
4. Operation of frequency relays
5. Test results of CTs Tan D
6. Periodical testing of Relays
7. Feeder tripping report
8. Sick equipment report
9. T&P report