Professional Documents
Culture Documents
From the reference we can say that standard penetration test can be used for
estimating parameters like plasticity characteristics or atterberg limits which will
take less time for getting the result when compared to doing the laboratory work.
Chegg
Answer-(A) standard penetration test. Is the correct answer.
Explanation-Insitu testing can be used to determine the density or shear strength of
soils, particularly sands, gravels, saturated clays and silts. The main advantage of
testing in this way is that it can be undertaken without undue disturbance of the soil.
=Min
= 1 g/cm3
6 Crew
crew =6
volume =720 m3
time =8 hr
= 48 / 720
=0.06667 man.hr/m3
Performance bond is a surety bond which
ensures the completion of project by
contractors if goes broke on project the surety
will pay necessary amount to complete the job.
: The amount of time that a schedule activity can be delayed without delaying the
early start date of any immediately following schedule activ
t
The weight of 1 m3 of brick earth, is about: 1800 kg
# Mechanical Engineer
Civil 5 V. Imporant having Exam Questions
1. Stronger Variety
2. Ability to take very smooth finish
3. Toughness ﺻﻼﺑﺔ
4. Difficult to season
Which of the above characteristics is/are essential for timber to be used as beams?
a. 1 only
b. 2 and 3
c. 3 and 4
d. 1 and 3
a. 1,2 and 3
b. 1 only
c. 1 and 3 only
d. 3 only
a. Uniform settlement
b. Differential settlement
c. Rate of settlement
d. None of the above
Q.10 The factors that govern the workability of fresh concrete are?
a)since all real engineering projects are interdisciplinary all engineers should be
expert in all fields of engineering
b) the interdisciplinary nature of engineering means that all engineers should
study general engineering rather than specialize in a single area .
c) most engineers will wish to specialize , but all engineers must be able to work
effectively alongside others with complimentary skills
A. Responsibility matrix
B. Functional matrix
C. Cost account
D. Sub deliverable
E. Project overlap
A. Always critical
B. Always sub critical
C. Always super critical
D. Depending of specific channel conditions ……….
Q.19: Road project needs a gravel base. Which gravel do you recommend for the
project?
Explanation: Well graded gravels haver partcals of different sizes and thus give
good compaction as the packing volume is good. In a compacted volume the
smaller particles take its position between the voids crareted by large particles and
thus resulting in better packing of particles and resulting higher strength.
a. well graded gravel since gravels are same size and easily compacted
b. poorly graded gravel since gravels are same size and easily compacted
c. poorly graded gravel since gravels are different sizes and easily compacted
d. Well graded gravel since gravels are different sizes and easily compacted.
Civil 6 Civil 6 Civil 6 Civil 6 Civil 6 Civil 6 Civil 6 Civil 6 Civil 6 Civil 6
Civil 6 Civil 6 Civil 6 Civil 6
Q.9) A bid for foundation construction is based on owner supplied soil boring test
results showing sandy clay to a depth of 6m. However during construction the
backhoe encounters Large pieces of concrete buried throughout the construction
site. This situation would normally be referred to a s?
a) A concealed conditions
b) Unexplained features
c) Unexpected characteristics
d) Hidden detriment
Q.14) A bid manager is in charge of a closed bid in which several firms are
involved. The last day of the bidding period arrives and one firm has not yet
submitted an entry. Bbob calls the firm and asks if they are going to submit a bid
and they say they have been too busy to write a proposal but might be able to
get one worked out by the next day. He should
a) Open the bids and reveal the lowest bid to enxourage the firm to enter
b) Open the bids and quote a false low bid so they will enter but he will bot giving
away the contract
c) Tell them he cant do anything for them
d) Allow the firm to enter a late bid
Q.17) The ratio of the maximum normal stress due to maximum vertical shearing
stress in a cantilever beam of length (L), with and loaded at the end is given by
a) L/h
b) 2L/h
c) 4L/h
d) 2L/b
Q22) The process of identifying and evaluating contractors for a bid list is called
a) Prequalification
b) Forecasting
c) Fast tracking
d) None of the above
Q23) Soil samples extracted form the standard penetration test (SPT) can be
used in
a) Liquid limit test Confirm
b) Sieve analysis
c) Hydrometer test
d) All of the above
Q24) The earth pressure that is developed behind a retaining structure depends
on the movement of the structure relative to the soil. The active earth pressure
is developed when
a) The structure moves toward the soil passive
b) The structure does not move
c) The structure moves away from the soil
d) The structure and the soil move away from each other
Civil 8 Civil 8 Civil 8 Civil 8 Civil 8 Civil 8 Civil 8 Civil 8 Civil 8 Civil 8
Civil 8 Civil 8
Q.3) General conditions and home office overhead are examples of what type of
costs
a) Direct
b) Indirect
c) Both () a and b)
d) Contingency
Q.7) The factors that govern the workability of fresh concrete are ?
a) The quantities of cement paste and aggregate relative ot each other
b) The plasticity of the paste itself
c) The grading of the aggregate
d) The shape and surface characteristics of the aggregate
e) All of the above
Q.8) Referring to the figure , wat load combination produces the maximum uplift
on footing A?
a) Decreases BOD
b) Is used to decrease mechanical failure
c) Involves the use of coagulations
d) Can come at any point in the treatment pain
Q.11) The undrained shear strength of clay equals
a) Twice the unconfined compressive strength
b) The unconfined compressive strength
c) Half the unconfined compressive strength
d) Not related to the unconfined compressive strength
Q.16) The --------------- beam theory provides a means of calculating the load –
carrying and defletion characteristics of beams
a) Ferris - witmer
b) Galileo - jacob
c) Leonhard - galilei
d) Eler – Bernoulli
Q.18) Concreting has to be done in cold weather . what type of cement is not
desirable?
a) Type iiii
b) Type iii
c) Type iv
d) Type v
Q.23) A municipal waste is treated with an activated sludge system with recycle
after primary classification. The solids retention time for the
a) Effluent quality
b) Recycle TSS concentration
c) Hydraulic retention time
d) Efficiency of the primary clarifier
Q7) In order to convert from metric system cm, to imperial system inch what
should you do ?
a) Multiply by 2.45
b) Multiply by 2.55
1 in=2.54cm
c) Divided by 2.54
d) Divided by 2.44
Q13) When an activity network is developed by using forward and backward pass
we can find out Exam#2
a) The longest time period that the project will take
Q15) In a two way slab the lifting of the edges of the slab occurs due
a) Resultant shear force at the ends
b) Torsional moments on the slab
c) Unbalanced moments on the slab
d) Heavy shear load at the mid span
Q.16) A two stage anaerobic digester is used to treat a combined primary and
secondary sludge compared to aerobic digestion, anerobic digestion
a) Produces more bacterial cells
b) Uses more energy
c) Is more expensive also this in one Q
d) Is more complex to ooperate
Q18) The slab is designed as one way if the ration of long span to short span is
a) Less tha 1
b) Between 1 and 1.5
c) Between 1.5 and 1.2
d) Greater than 2
Exam#2
Q20) What is a richer scale?
a) A scale for measuring the mass of an object
b) A logarithmic scale for measuring seismic energy of an earthquake
c) A scale for making angle measurement
d) A scale used to measure linear distances of structures and other large objects
Q25) What type of instrument/control system would you specify to insure that a
softening plant precipitation process (i.e, the reaction chemistry) was open
correctly?
a) Flow meter with proportional controller
b) Ph meter with proportional controller
c) Hardness meter with proportional controller
d) None of the above
Q26) The arc definition of the degree of curve (D) is defined as the
Arc definition a) Central angle subtended by 100 ft of arc
Chord definition b) Central angle subtended by 100 ft of chord
c) Central angle subtended by 50 ft of chord
d) Total arc length of the curve in stations divided by the total central angle of degrees
CIVIL 11
Q1) Before the development of any site, construction companies work on site
set-up to ensure:
Select one:
Q7) From among the following activities which is the best example of a project?
Select one:
Select One:
a 50
b 90
c 95
d 100
Q 12) Consider two beams with equal cross-sections, made of the same
material, having the same support conditions, and each loaded with equal
uniform load per length. One beam is twice as long as the other. The
maximum bending stress in the longer beam is larger by a factor of:
a 1.25
b 1.5
c 2
d 4
Select One:
LF Select one:
LS
a. Latest times activities can begin
Critical path
b. Earliest times activities can begin
c. Critical Path
d. A and C are correct
e. A, B and C are all correct
Q26) Clayish substance is:
Select one:
a Excellent material for road construction
b Added material in road layers
c Bad substance for road construction
d Good material for road construction
CIVIL 12
Q1) Consider the following statements:
a. PERT is activity- oriented and adopts deterministic approach.
b. CPM is event-oriented and adopts probabilistic approach. *CPM activity oriented*
c. PERT is event-oriented and adopts probabilistic approach.
Which of the above statements is/are correct?
Select one:
Select one:
Q11) What is the primary use for fast Track scheduling? Answer D
Select one:
Q12 )A wastewater effluent is treated with chlorine gas (Cl2) to give a free residual
of 0.5 mg/l. The amount of chlorine required is:
Select one:
Q17) Which of the following can represent an activity on a project network?
Select one:
Tensile and Compression
Q20) What is the difference between normally consolidated soils and over
consolidated soils? Answer D Exam#2
Select one:
i gave wrong ans
Q21) While working on the final stages of a job, you notice that one small clause in
the contract has been violated accidently. What should you do?
Select one:
File
Q22) The Archimedes Principle relates buoyancy to ___________
Select one:
Select one:
Q26) Consider the following statements:
Ultrasonic pulse velocity test to measure the strength of concrete is
Select one:
WBS
Q27) The final step in the definition of a Work Breakdown Structure is to :
Select one:
Explanation:-
Select one:
Q7) Which of the following statements regarding lateral earth pressure is correct?
Select one:
Q9) For a plain cartoon steel, all of the following are true except: Answer D
Select one:
Select one:
Q11) The ratio of maximum water demand to average water demand is called the:
Select one:
Q16) A two stage anaerobic digester is used to treat a combined primary and
secondary sludge. Compared to aerobic, digestion, anaerobic, digestion.
Q18) All of the followings are true about work packages except:
Select one:
Q19) The lowest element in the hierarchical breakdown of the WBS is: Work Packages
3. Curing of Concrete 3
Select one:
chegg.com
Q2) In order to provide the proper geometric standard for each roadway
highway component what is it that needs to be established
a) Functional classification
b) Road networks
traffic capacity
c) Exiting designs
a) the required fire flow is nearly the same as the average day demand
b) the required fire flow is between 2 times and 5 times the average day
demand
c) the required fire flow is between 5 times and 100 times the average day
demand
d) the reqired fire flow is more than 100 times average day demand
a) Vertically
In surveying land areas are treated as horizontal surface
b) Horizontally not as the actual ground surface area.
c) Along the ground surface Always horizontal distances are measured
d) Between the ellipsoid and geoid
a) It is easily available
b) It is the cheapest and good in strength
c) The coefficient of thermal expansion of steel and concrete are almost the
same
d) It forms a good bond
Q21) Your boss has just approved the initiation of a project to celebrate
qatara. Sadia has been assigned the project manager by the boss. Sadia
very first task should be to
Q23) A structure is shown in the figure. For a stress check of colum A1,
which of the following statements is true?
a) Bid bond
b) Performance bond
c) Acceptance bond
d) Payment bond
Q25) If three non parallel forces holds a rigid body in equilibrium they
must
a) Be equal in magnitude
b) Be concurrent
c) Be non concurrent
d) Form an equilateral triangle
e) Be collinear
a) Increases
b) Decreases E) Increases and then decreases
c) Increases and decreases
d) Remains constant
Q27) During a standard penetration test (SPT) unusually low blow counts
are encountered in a foundation expected to be medium sand . this is an
indication that the following condition may be present
a) The sampler drive shoe is badly damaged or worn due to too many
drivings to refusal
b) Cobbles are encountered
c) The sampler drive shoe is plugged
d) The ground water in bore hole is much lower than 111 situ conditions
immediately outside the borehole
A. Petroleum engineer
B. Mechanical engineer
C. Civil engineer
D. Chemical engineer
1. Improve workability
2. Improve durability
3. Reduce segregation during placing
4. Decrease concrete density
A. Cost
B. Availabillity
C. Reliability of deliveries
D. A and b only
E. All the above
10. Well point systems may be used as a dewatering method under certain
conditions. Which of the
following statements best describes the conditions where a single stage
wellpoint system is most
appropriate?
A. Deep cexacavation where the water table must be lowered more than 30 ft but less
than 50
ft
B. Permeable soils where draw down of the water table is greater than 30 ft but less
than 50 ft
C. A small, shallow excavation in dense or cement soils.
D. Permeable soils where draw down of the water table is less than 20 ft
19. What type of instrument control system would you specify to ensure
that a softening plant
precipitation (I.e., the reaction chemistry ) was operating correctly
1. Yield on entry
2. Clockwise circulation
3. Deflection of entering traffic
4. Central island
A. 1,2,3
B. 1,2,4
C. 1,3,4
D. 2,3,4
1. A structural member with the same material properties in all directions at any
particular point is
a) Homogenous
b) Isotropic
c) Isentropic
d) Holomorphic
e) Orthotropic
2. An I Shaped beam is used to carry a uniformly distributed load over a span L = 24ft
as shown. The maximum shear stress (kip/in2) in the beam most nearly.
a) 2.6
b) 3.8
c) 5.1
d) 6.3
3. Find the maximum vertical shear in the beam in fig (2) if W = P/L
a) P/4
b) P/2
c) 3P/4
d) P
a) 20KN
b) 10KN
c) 40KN
d) Zero
5. Calculate the reaction Ra. A uniform load on a beam is hown below. It has a value
of 2.5 KN pee meter.
2.5*4=10 KN
2.5 KN/m
=5 KN = 5 KN
a) 5KN
b) 1.25KN
c) 10KN
d) 0
6. A beam is point load 1000kn and UDL 200N/m. The maximum moment in the
below is :
a) 4200 N.m
b) 5600 N.m (1000*4) + (200*4)2=5600 N.m
c) 6400 N.m
d) 6800 N.m
7. For the shown figure. Find the maximum compressive stress (P= 1000lb, M=
3000lb/ft. B=D=Width of footing = 9 ft)
a) 60 psf
b) 30 psf
c) 49 psf
d) 12 psf *3000/1000=3
* 9+3=12
8. A steel beam supports a uniformly distributed live load W = 60kip/ft. Over a simple
span L = 25ft as shown below. The code permits a maximum live load deflection of
L/480. The required moment of interia of the beam section is most nearly.
5
∆
384
a) 2600 in2
b) 2800 in2
c) 2700 in2
d) 2000 in2
9. There is a weak soil layer 12ft below an existing column footing (5ftx5ft). The
maximum additional stress that can be applied at the midpoint of the weak soil layer
is 700 psf. Any stress more than 700psf would cause excessive settlement. What is
the maximum load that can be applied on the footing. Assume stress distribution to
be 1:1
Weak soil layer
a) 428 tons
b) 341 tons
c) 178 tons
d) 487 tons
10. A 4ft tall 6ft x 20ft wide concrete block will be placed at the bottom of a take assume
100% contact with the late bed and uniform loading. The lake bed and uniform
density of the concrete is 150 lb/ft3. The resulting concrete pressure (lb/ft2) will be
most nearly.
a) 9000 150*4=600
b) 3000
c) 600
d) 350
11. A rigid beam weighting 300lb/ft is lifted using rigging cables as shown. The cables
are wire rope with an effective modulus of elasticity E=30,000ksi and effective cross
sectional area = 0.4 in2. The elongation of the cable is most nearly.
a) 0.06 in
b) 0.08 in
c) 0.10 in
d) 0.13 in
13. Referring to the figure, what load combination produces the maximum uplift on
footing A?
a) Dead+ Live
b) Dead+Wind
c) Dead
d) Dead+Live+Wind
14. Find the total force in the reinforcemnt in the beam shown. fy = 60,000 psi. no 5 bars
has a diameter of 5/8 in total force = fy As
a) 23.8 tons
60 * (5/8)= b) 45.7 tons
c) 76.9 tons
d) 36.8 tons
15. The maximum vertical shearing stress due to VQ/lb in the beam with a rectangular
cross section. The maximum vertical shearing stress occurs
along the neutral axis,
a) Occurs where the normal stress is maximum Shear stress dsitribution is maximum at
b) Occurs at the neutrual axis Neutral axis and minimum at outermost fibre
c) Occurs at the outermost fiber since Q is maximum at Neutral axis
d) Is linearly dependent on the distance from neutral axis
1. Sum of internal and external forces and moments must be equal to zero
2. At ultimate collapse load the number of plastic hinges must be just enough to
form a mechically
a) 1 only
b) 2 only
c) Neither 1 nor 2
d) Both 1and 2
TRANPORTATION ENGINEERING
17. A section of a major street an urban arterial with six traffic signalized intersections
is shown below. The traffic signals at each intersections have a total cycle length of
90 sec and 50 sec of green ( and yellow) time on the major street. It is required that a
progressive signal system having a maximum band width of green for movement
from Ist Avenue intersection toward the 6th Avenue intersection with a progressive
speed of 30 mph be designed. The offset (sec) at 6th avenue
a) 36
b) 43
c) 50
d) 63
18. An unsignalized T- intersection is three logs are each two way. What is most nearly
the total number of conflict points including crossing ,merging and diverging?
a) 3
b) 6 3*2=6
c) 9
d) 12
19. Road project needs a gravel base. Which gravel do you recommend for this project?
a) Well graded gravel since gravels are of same size and easily compacted
b) Poorly graded gravel since gravels are same size and easily compacted
c) Poorly graded gravel since gravels are different size and easily compacted
d) Well graded gravel since gravels are different size and easily compacted
20. Density of traffic is found to be 230 vehicles per mile speed of vehicles is
measured to be 60mph. what is flow or volume of traffic
21. A 10 ft wide side walk has an effective walkway width of 6.5ft. The peak 15 minutes
pedestrian flow is 1200 pedestrians. The plantation adjusted LOS is most nearly.
a) LOS B
b) LOS C
c) LOS D
SOIL MECHANICS AND FOUNDATION ENGINEERING
22. A consider the framing and structural details shown the load path for this design is
23. The specific gravity of solids, GS for a soil 2.75. The zero air void dry unit weight
of the soil (KN/m3) at a moisture content of 20 percent is about.
a) 16.4
b) 17.4 m.c = 20% = 20/100
c) 18.2 Gs = 2.75 = 1/2.75
d) 16.5
a) 770
b) 2130
120 × 15 + 110 × 7 = 2570
c) 2570
d) 2900
25. Seismic response coefficient (Cs) of a building was found to be 0.10. The effective
seismic weight of a column is 300 tons. What is seismic shear force acting on the
column base?
a) 0.25
b) 0.30
c) 0.45
d) 0.35
27. A pile foundation shown in the figure. The ultimate side resistance Qsu and ultimate
negative skin friction figure. A safety factor of 2.0 is required on the capacity. The
safety factor is not applied to downdrag forces. Assume that the downdrag capacity
of the pile. The allowable load P (kips) that can be applied to the top of the pile is
most nearly.
QR= 160+150=310
a) 115
b) 135 P= (310/2) - 40 = 115
c) 155
d) 310
FOS =2
28. A pile driven in clay soils. Capacity of the pile is not dependent on:
a) Cohesion of soil
b) Pile diameter
c) Pile adhesion coefficient
d) Depth of groundwater
30. During a standard penetration test (SPT) unusually low blow counts are encountered
in a foundation expected to be medium sand. this is an indication that the following
condition may be present
a) The sampler drive shoe is badly damaged or worn due to too many driving to
refusal
b) Cobbles are encountered
c) The sampler drive shoe is plugged
d) The ground water in bore hole is much lower than in-situ conditions immediately outsi
the borehole
31. Site with gray sandy still is shown below. Original groundwater was at 5ft below the
ground surface due to a severe drought groundwater level drops down 9ft below the
ground surface, what would happen to the effective stress at point A when
groundwater level drops down to 9ft below ground surface. Total density of soil is
110 pcf.
a) Vertical effective stress increase by 249.6psf
b) Vertical effective stress increase by 254.6 psf
c) Vertical effective stress increase by 169.6 psf
d) No change
Engineers have decided that loose sand and soft clay are not capable of supporting the
foundation without beight treated. What is the best.
a) Conduct dynamic compaction to treat soft clay and conduct pressure grouting to
treat loose sand.
b) Conduct dynamic compaction to treat loose sand and conduct surcharging to treat
soft clay.
c) Conduct vibro compaction to treat soft clay and conduct pressure grouting to treat
loose sand.
d) Conduct pressure grouting to treat soft clay and conduct surcharging to treat loose
sand.
35. A bridge footing is to be constructed is sand. The water table is at the ground
surface. The ultimate bearing capacity working weight?
a) Always critical
b) Upstream-Super critical, downstream-sub critical
c) Always sub critical
d) Always super critical
37. Which of the following has the most efficient hydraulic section?
a) Semicircle
b) Triangle with 450 included angle
c) Trapezord with 450 angles
d) Trapezord with 300 angles as measured from the horizontal.
IRRGIATION ENGINEERING
38. You are determining the unit hydro graph from an isolated storm event. The
difference between the total runoff and the base flow is the
39. A monitoring station records the following pattern of discharge (cfs) in a stream
following a storm the catchment area for the stream is estimated to be 125acres,
1acre = 43,560ft2
Time (hr) 0 1 2 3 4 5 6 7
The average depth of excess precipitation from the storm is most nearly;
a) 1.2 in
b) 1.5 in
c) 1.8 in
d) 2.1 in
40. A basic assumption of the rational method for determining peak runoff from a
watershed is that peak runoff for a given rainfall intensity
a) The required fire flow is nearly the same as average day demand
b) The required fire flow is between 2 times and 5 times the average day demand
c) The required fire flow is between 5 times and 100 times the average day demand
d) The required fire flow is more than 100 times average demand
SANITARY ENGINEERING
42. Traffic analyst have found that trips genertated per household per day is to be
0.8+1.5P+0.7A
If the area under research includes 800 households and 3.5 persons per household
and 1.8 autos per household what is the number of trips generated per day
a) 4230
b) 5848
c) 6250
d) 10065
43. A circular clarifier is being designed to receive a flow of 4.8 MGD. If the circular
depth is 12ft and rentention times 1.5 hours, the tank diameter
a) 33
b) 65
c) 78
d) 55
44. Flow is delivered from a splitter box to an areation basin through a 12-in. Ductile
iron pipe. For a flow rate of 3MGD, the velocity head 9(ft) in the in the ductile iron
pipe is
a) 0.03
b) 0.54
c) 5.91
d) 59.1
45. A primary sedimentation basin for a municipal waste water treatment plant treats a
flow of 3 MGD and removes 70 percent of the total suspended solids. The basin is
60ft in diameter with a depth of 15ft. The solid flux (lb/ft2.d) in this basin is about
a) 2
b) 5
c) Independent of detention time
d) Independent of depth
46. A 10 MGD water treatment plant is to be designed with eight identical rectangular
clarifiers with length to width ratio 5:1. The clarifiers will the clarifiers are 16ft
deep with a horizontal velocity of 0.4 ft/min, the dimensions (ft) of each clarifier
need to be most nearly
a) L 40 W 8
b) L 90 W 18
c) L 300 W 60
d) L 675 W 135
47. Flow is delivered from splitter box to an aeration basin through a 12-in. Ductile
iron pipe, for a flow rate of 3MGD, the velocity head (ft) in the ductile iron pipe is
a) 0.03
b) 0.54
c) 5.91
d) 59.1
48. In preparation for the design of new water treatment plants, jar tests with slightly
turbid water (4TU) show following design alternative is the most appropriate.
a) 0.0012 g/ml
b) 0.0091 g/ml
c) 0.0076 g/m
d) 0.0252 g/ml
50. A city with expected increase in its future population is to provide complete water
treatment plant for a surface water source, including rapid mix flocculation,
sedimentation, filtration and chlorination. The design flow is 22.5 MGD, assuming
alum is used for coagulation, the approximate area of the sedimentation basin.
The amount of sedimentation will depend on
the contaminant concentration in the water.
a) Is closet to 10,000 ft2 So, higher the concentration, higher the
sedimentation and in turn higher the required
b) Is closet to 20,000 ft3 basin area.
c) Depends on the dosage of alum
d) Depends on the quality of the water source So, area of sedimentation basin will depend
on the quality of water source. Hence option
(d) is correct.
51. A two stage anaerobic digester is used to treat a combined primary and secondary
sludge. The hydraulic detention time is
a) A detention times
b) Percentage removal of BOD5
c) Percent removal of suspended solids
d) Overflow rate
e) Depth
a) Re introduce aerated sludge back to the waste stream to increase the level of
bacteria.
b) Re introduce aerated sludge back to the waste stream to decrease the level of
bacteria.
c) Activate the sludge by adding chemicals
d) None of all.
54. An activated sludge sector with a solis retention time of nine days is to achieve
nitrification. PH Control may be necessary because.
55. A secondary effluent that has “pinpoint” flow escaping over the weir indicates.
a) Over aeration
b) Too low of a return sludge flow
c) Nitrification
d) Rising Sludge
e) Bulkling Sludge
57. A municipal waste is treated with an activated sludge system with recycle after
primary classification. The solids retention time for the
Controlling phosphorous discharged from municipal and industrial wastewater treatment plants is a key
factor in preventing eutrophication of surface waters. Phosphorous is one of the major nutrients contributing
in the increased eutrophication of lakes and natural waters. Its presence causes many water quality
problems including increased purification costs, decreased recreational and conservation value of an
impoundments, loss of livestock and the possible lethal effect of algal toxins on drinking water.
a) Effluent Quality
b) removal
Phosphate Recyle TSS concentration
is currently achieved largely by chemical precipitation, which is expensive and causes
c) Hydraulic
an increase retention
of sludge volume by time
up to 40%. An alternative is the biological phosphate removal (BPR).
d) Efficiency of the primary clarifier
Option (B) is correct. (Chlorine addition)
59. What type of instrument control system would you satisfy to ensure that a
softening plant preciption (i.e the reaction chemistry) was operating correctly
60. A municipal waste is treated with an activated sludge system with recycle after
primary classification. The solids retention time for the
a) Effluent Quality
b) Recyle TSS concentration
c) Hydraulic retention time
d) Efficiency of the primary clarifier
61. A municipal waste is treated with an activated sludge system with recycle after
primary classification. The solids retention time for the
a) Effluent Quality
b) Recyle TSS concentration
c) Hydraulic retention time
d) Efficiency of the primary clarifier
62. Activated sludge process is best described as
a) Re- introduce aerated sludge back to the waste stream to increase the level of
bacteria
b) Re-introduce aerated sludge back to the waste stream to decrease the level of
bacteria
c) Activate the sludge by adding chemicals
d) None of all
63. A schedmatic of a waste water treatment plant is shown, treatment to remove grit
from the waste water.
a) Decreases BOD
b) Is used to decrease mechanical failure
c) Involves the use of coagulations
d) Can come at any point in the treatment pain
64. What type of instrument/control system would you specify to insure that a
softening plant precipitation process (i.e the reaction chemistry) was open correctly
?
a) Flow meter with proportional controller
b) Ph meter with proportional controller
c) Hardness meter with proportional controller
d) None of the above
65. Disinfection with chlorine can be modelled as a first ordered reaction. A reactor
has a flow rate of 12,000 liters per hour and the desired removal of organisms is
from 10x106/100 ml to less than 100 ml, the decay coefficient is 0.35/hr
Option B would me most appropriate.
Short circuiting in this complete mixed reactor will since short circuit reduces treatment efficiency.
For ideal plug flow short circuiting should not
a) Increase treatment efficiency take place.
Short circuit Increase the Volume required.
b) Increase the required volume
c) Make the reactor operate more like a plug flow reactor
d) Reduce the required volume
e) Re- introduce aerated sludge back to the waste stream to increase the level of
bacteria
f) Re-introduce aerated sludge back to the waste stream to decrease the level of
bacteria
g) Activate the sludge by adding chemicals
h) None of all
67. A wastewater effluent is treated with chlorine gas (Cl2) to give a free residual of 0.5
mg/l. The amount of chlorine required is:
a) Much greater than 0.5 mg/l
b) Dependent on the COD of the effluent
c) Dependent on the NH3-N concentration of the effluent
Dosage, mg/L= Pounds of Chemical
(8.34 lbs/gal) *(Flow, mgd)
If the measured effluent residual of the effluent was 3.5 mg/L, then subtracting 3.5 from 17.1 gives us
a chlorine demand of 13.6 mg/L. This means that the effluent demanded 13.6 mg/L of chlorine before
a residual value could be met. Demand = Dosage – Residual
68. An activated sludge reactor with a solids retention time of nine days is to achieve
nitrification ptt control may be necessary because
a) Nitrification produces acid
b) The activated process sludge process consumes alkalinity
c) Nitrification releases ammonia
d) (Nitrification produces acid) and ( the activated sludge process consumes
alkalinity
71. Your boss has just approved the initiation of project to celebrate Qatar national day
sadia has been as assigned the project manager by the boss.sadia very first task should
be
a) Establish the reporting process is the boss
b) Work on the project scope
c) Make a report on required cost for the project
d) Delivering the project chance to the project develop the project chart to do
project
e) Ask the boss as to how many team members would be allowed in to the
project.
75. ABET Strands for Accoditation board fot Engineering and technology
a) True
b) False
76. Carbon brick is made from crushed coke bond bonded with
a) Sulphate
b) Carbon
c) Tar
d) Clay
77. How often shall a visual inspection be done on smoke detectors as per NFPA 72?
a) Monthly
b) Daily
c) Semi Annually
d) Weekly
78. If an absorption chiller load is 500 tons, the required heat input (Btu/hr) to a chiller
a) 4.8x106
b) 6.0x106
c) 7.5x106
d) 9.4x106
C. None
3. An engineer received new scope of work, which is not included at the original scope, what the
action he has to do?
B. Emerging markets Because workers are now and again alluded to as labor when
C. Lot of Manpower
they are being considered as a piece of the most common way of
delivering products or offering types of assistance.
D. Favorable exchange rated
A. Make a checklist program requirement for the staff working on the project of use to continuously
monitor their progress as they prepare the drawings.
B. Have the client review a final check set for compliance with the program requirements and request
that any corrections be noted.
C. Have another architect who is unfamiliar with the project review the final set for compliance with the
original program requirement.
D. Hold regular progress meetings with the client and staff involved to compare the current status of
the drawings with the original program requirements. At the conclusion of this phase, require that the
client provide the architect with written approval to proceed to the next phase.
7. Activity on arrow needs to use dummy activities to avoid precedence problem that
A. Parallel Activities
C. Merge Activities
D. Burst Activities
E. Independent Activities
A. Budgeting
9-What type of bond guarantees that if a contractor goes broke on a project, the surety will pay the
necessary amount to complete the job?
A. Bid bond
B. Performance bond
C. Acceptance bond
D. Payment Bond
10-Which of the following choices is not one of the stages of a project life cycle?
A. Concept
B. Initiation
C. Planning
D. Execution
A. Delivery/Closure
A. Arrow
B. Line
C. Node
E. Ask the boss as to how many team members would be allowed in the project
B. General and abstract concept of right and wrong behavior culled from
carry penalties.
17- Which one of the engineering characteristics can best explain the following
A. Quantitative Thinking
B. Interpersonal Skill
C. Honesty
D. Logical Thinking
A. Major Deliverables
B. A cost accounts
C. Work package
D. The project
20- The lowest element in the hierarchical breakdown of the WBS is:
A. Deliverables
B. A Work Package
C. A Cost Account
E. An Object
21- Splitting project into tasks and estimate time and resources required to complete
A. Project scheduling
B. Project optimization : involves using optimization techniques to optimize the cost or duration of the project.
22- Which of the estimates listed would occur last in project time line?
C. Bid Estimate
D. Assemblies Estimate
23 -The delay time for a series of activities that would not affect if occurred the project completion
timing called:
B. Total Slag
C. Critical Float
D. Float Pad
E. Critical Slag
24-.Among the sites being considered for a new main library are those adjacent to the following areas
or services. The most appropriate site is one that is adjacent to:
C. Public schools
A. Before construction
B. During construction
A. Define scope
B. Verify Scope
C. Execute Scope
D. Create WBS
27- Process of decomposing deliverables into smaller, more manageable components is complete
when:
28-Project life cycle is different than product life cycle in that project life cycle:
29-Best time to assign a project manager to a project is during: At the beginning of the project
A. Execution B. Initiation
A. Cyclic executive Scheduling periodic tasks to execute on a processor based on assigning the highest
priority to the task that has the shortest period (greatest frequency) is Rate monotonic.
B. Deadline monotonic
In highest priority to the task that has the shortest period there is no critical region.
C. Earliest deadline first If the longest period, the priority become lower.
Rate Monatic is the highest prioirity based approach.
D. Rate monotonic It is a semi fixed scheduling policy
31-The final step in the definition of a work breakdown structure is to:
A. Accountability
B. Flexibility
C. Innovation
D. Speed
E. Repeatability
34- During which of the following categories are you more likely to find status reports many changes
and the creation of forecasts?
A. Concept B. Initiation
C. Planning
D. Execution
E. Closure
35-The critical path in a project network is the:
36-Of the following engineering discipline, which would be best, suited to manage the construction of
a natural gas pipeline?
A. Petroleum Engineer
B. Mechanical Engineer
C. Civil Engineer
D. Chemical Engineer
37-When an activity network is developed by using forward and backward pass we can find out:
38- An engineer is offered some additional gifts and services in exchange for using superior materials
on a remodeling project. This was not detailed in the contract. He should:
D. Accept the gifts but use the materials specified in the contract in order to retain neutrality.
39-You are a project manager for a company that supplies parts to the government. Part of your
budget plan shows an average can reduce move units. What theory that describes the rationale for
the budget planning?
A. Theory of Constraints
B. Law of Diminishing Return
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical
41- An architect visits the site and found out the gypsum installation ongoing is of very low grade, what
immediate action should he take?
C. Lot of Manpower Because workers are now and again alluded to as labor when
they are being considered as a piece of the most common way
D. Favorable exchange rated of delivering products or offering types of assistance.