The DATES and NUMBERS behind the Italic TEXT are generated automatically from hidden formulas.
The Result in Cell C-20 Will Change Until the Final Piece of Information is Entered.
Stage 1.
Edit the Text in Cell E-3 to add the Instruction Reference Number.
This is for Audit Purposes which will Serve as a Cross Reference Bundle for any Future CLAIM Report
Then Add the Date of the Instruction in Cell D-4
Stage 2.
Use your Skill and Experience to Add the Estimated Time Required in Rows D – 5 to 11, this MUST be in Calendar Days.
The Date in Cell D-12 is Calculated Automatically.
The Number of Days for Public Holidays and Weekends that Occur Between the Dates in Cell D-4 & D-12 are Produced by
a Formula.
Stage 3.
Open the Spreadsheet labelled “Calculations”.
This Where You will have to Type In ALL the Dates of the Public Holidays & Weekends that are on Your Bar-chart Calendar.
There is NO shortcut for this Task but you Only Have to Do It once, because you Save the File After Each Prediction.
It is a Rolling Process
Stage 4.
When the Final Dates have been Typed into Cells D – 15: 17 & 18 the Process is Complete and your Contract Notice can
be Issued.
Stage 5.
If however there is no Need for Design and Approval and 0 is placed in Cells D – 7 & 8 the Text “No Notice” Appears in
Cell D – 20 and No Further Action is required.
CONCLUSION