Project PROPOSED DEVELOPMENT REINFORCED CONCRETE COUNCIL

Client ISAAC C. OKAFOR Made by Date TITLE


Location TYPICAL STAIRCASE FLIGHT SA SEP 2022 STAIR
STAIR FLIGHTS AND LANDINGS to BS 8110:1997 Checked Revision Job No
Originated from Beta/trial version of RCC71.xls' on CD © 1999 BCA for RCC JI -

MATERIALS
fcu 25 N/mm² m 1.5 concrete Min bar Ø = 10
fy 410 N/mm² m 1.05 steel Max bar Ø = 12
h agg 3 mm Density 25 kN/m³
Cover 25 mm (Normal weight concrete) Nominal top steel ? Y

DIMENSIONS Sectional Elevation

a = 1125 mm landing A h = 150


b = 2400 mm flight waist = 150
c = 100 mm landing B h = 150
d = 115 mm
e = 115 mm
Going = 300 mm L = 3625
Rise = 1350 mm total 8 treads
Rise = 150 mm each step Rake = 26.57 º

LOADING
Imposed 2.00 kN/m² 19.51 kN/m ult 21.71 kN/m ult
Flight finishes 1.00 kN/m² (10.06 + 3.40) (11.63 + 3.40)
Landing finishes 1.00 kN/m²

DESIGN
LANDING A, gk = 3.75 + 1.00 = 4.75 kN/m² n = 1.4 x 4.75 + 1.6 x 2.0 = 9.85 kN/m²
FLIGHT, gk = 6.07 + 1.00 = 7.07 kN/m² n = 1.4 x 7.07 + 1.6 x 2.0 = 13.09 kN/m²
LANDING C, gk = 3.75 + 1.00 = 4.75 kN/m² n = 1.4 x 4.75 + 1.6 x 2.0 = 9.85 kN/m²

Zero shear is at 1.125 + (19.51 - 9.95) /13.09 = 1.855 m from left


M = 19.51 x 1.855 - 9.95 x 1.235 - 13.09 x 0.730²/2 = 20.42 kNm/m
d = 150 - 25 - 6 = 119 mm K = 0.0577 As = 472 mm²/m
PROVIDE R12 @ 230 B = 492 mm²/m
. R10 @ 200 T in span
L/d = 3,625 /119 = 30.462 < 23.0 x 1.314 x 1.099 = 33.211 allowed OK