Doc. No.

: F/09/12
Bharat Petroleum Corporation Limited Page No. : Page 1 of 1
Issue No. : 03
ADVISORY SERVICES DEPARTMENT Issue Date : 27.09.2022
Revision No.: 00
Welding Procedure Date of Rev. : 27.09.2022

JOB DETAILS
Plant : HGU Location : Near emergency hydrogen vessel A
Job description : Flange provision in PSV 4505 A/B bypass line
Line size (in.) : 2” Line spec : A11A
Matl Of Constrn : CS Process fluid : Flare
Des. press (kg/cm2g): 3.5 Bake-out : Not reqd
MOC No. : NA No. of joints :
Filled by (Name) : Date :
WELDING PROCEDURE
Fit-up type : Butt
Welding consumables
For root run : ER70S2 Welding process : GTAW
For subsequent runs : ER70S2 Welding process : GTAW
Pre-Welding / Welding Requirement
Bakeout : NA Post heat : NA
Preheat : NA Interpass : NA
PWHT details (if applicable)
Loading Temp : NA Heating / cooling rate : NA
Soaking temp : NA Soaking time : NA
Inspection requirements
1. Fit up check : 100%
2. Root DP : 100%
3. Final DP : 100%
4. Visual inspection : 100%
5. Radiography : NA
Painting Scheme
Surface Finish : SA 2 ½ Color : HR Aluminium (9006)
Primer : 1 coat of F-9 @
65-75μ µ DFT/coat
Intermediate : 1 coat of F-12 @ 20µ DFT/coat
Top coat : 1 coat of F-12 @ 20µ DFT/coat Total DFT : 105-115µ
Notes
1. Only Inspection qualified welder shall be engaged for the job.
2. Mech Maint. to ensure that MOC and Schedule of pipes issued to fabrication contractor should be as per
piping specification.
3. Piping, fittings and consumables to be offered for inspection prior to the start of the fabrication for MOC
check, visual inspection.
4. Welding grade argon gas having purity minimum 99.995% should be used.
5. Paint batch certificate (specifying RAL color code for F-2) & paint containers to be submitted/ offered for
Inspection approval.