Professional Documents
Culture Documents
Candidate details
Madusanka
Counsellor details
Mandatory competencies
Business planning 1 Every company should have their own business planning 15 September 2018
procedure that would direct to achieve corporate objectives. I
12 12could gather some theoretical knowledge about business
planning by reading articles and participating in group discussion.
12
12
Competency Level Summary of Experience Achieved
12
Data Management 1 I learned the benefits of using proper data management system in 15 September 2018
an organization with both traditional and electronic mechanisms.
Electronic data management is widely practiced in present since it
gives many advantages to data management. Aconex, Primavera
expedition, E-builder, Doors and I connect are some of the
electronic systems available.
12
Furthermore, methods such as keeping regular backups from
computers or setting automatic backups, keeping scan copies,
passwords protecting documents, maintaining a second copy in a
central server can be used to secure and avoid data loss in an
electronic data system.
12
When it comes to construction sites, I always advice my
colleagues to use the site central server to store their day to day
work files as well as to scan and save the copies in the server.
Health and safety 1 Through the undergraduate modules, articles and group 15 September 2018
12 discussions, I realized the importance of having knowledge on
health and safety. I learnt specific items and activities that were
being used to achieve health and safety in construction projects
such as personal protective equipment, manuals, mock drills, tool
box meeting, taking head count etc.
12
12
12
Summary of Experience - Technical Competencies
Core competencies
12
12
Competency Level Summary of Experience Achieved
12
Project financial control 2 When preparation of project cash flow, I provided contractual 11 March 2019
and reporting details such as payment terms, advance payment recovery and
retention to the planning engineer which were required to
establish accurate cash flow forecast.Further, I updated monthly
cost report using relevant sub-contractors and labor supply
payments against allocated budget for each MEP systems. It
12 helped to control labors and sub-contractors cost within the pre-
established budget.
Project financial control 3 When I started my role with current project, there was no proper 13 March 2019
and reporting variation tracking system. However, I could develop a variation
12 tracking system to identify the status of current variation and
expected variations. Moreover, I could insert all expected
variations identified through Engineer Instructions (EI),
commented request for Information (RFI), commented shop
drawings, commented material submissions and confirmation of
verbal instruction (CVI). Using this protocol, it is easy to track
12 variation status and provides required information to management
for decision making.
Quantification and 1 Quantification and costing is the foundation of the quantity 15 September 2018
costing of construction surveying profession. Throughout my undergraduate modules, I
works studied quantification of construction works using standard
methods of measurements namely SMM7 (Standard Method of
12 Measurement 7), CESMM3 (Civil Engineering Standard Method
of Measurement 3) which used respectively for building works
and civil engineering works quantification.
Construction technology 3 I realized that MEP payment application breakdown was not 15 September 2018
and environmental matching with construction process in contract drawings.
12
services Therefore, I advised to the project management about the
advantages to the project cash inflow through payment
application breakdown prepared using the quantities of contract
drawings. Moreover, I advised to my assistance to use the
drawings to prepare future breakdowns.
12 When the main contractor is doing the chipping works at the slab
construction joints, I saw that there were significant damages to
the MEP provisions which already been placed in the slabs. The
rectification of those damages would make considerable
additional cost to the MEP contractor. Therefore, I advised to the
site management to raise this issue to the main contractor to
12 carry out their works with minimum damages to MEP provision.
Commercial 1 This is a vast subject which is practiced in the construction 12 March 2019
management of management. During my undergraduate modules, I started to
construction learn basic commercial management aspects and further I could
gain a decent knowledge through CPDs, group discussions and
12 subject materials. Commercial management can be defined as
the identification and development of business opportunities and
the profitable management of project and contracts from a project
inception to completion.
12
12
Optional competencies
Contract administration 2 Since I’m working as the project MEP quantity surveyor in my 09 March 2019
current project, I have the opportunity to deal with contract
administration duties.At the start of the project, I developed the
12 12
payment application format incorporating all contract drawing and
payment terms and had a meeting with cost consultant to agree a
final format. In the same format, I built up value engineering
recovery system which would demonstrate recovery amount only
for executed activities. It helped the company to avoid early
recovery of value engineering works as conducted in previous
12 project.
12
12
12
Competency Level Summary of Experience Achieved
12
Conflict avoidance, 2 During my stay in tendering department of previous company, I 09 March 2019
management and was able to involve with selecting sub-contractors for different
dispute resolution packages. Throughout this process, we tried to avoid future
procedures conflicts by following initial conflict avoidance techniques such as
forwarding all required tender details and updates, replying to
their tender queries and giving sufficient time for pricing etc.
12
As MEP project quantity surveyor in my current project, I was able
to deal with few conflict situations raised between MEP contractor
and main contractor regarding contra charges, rectification cost
for damages and lightning protection down conductor. In those
situations, we requested negotiation meetings with the main
12 contractor and agreed for a settlement. Moreover, I had to face
with similar kind of disagree situations with sub-contractors,
especially for payment terms and deductions. In that situations
also, I used negotiation method with the advice of project
manager to resolve the conflicts.
12
12
12
12
12
12
12
Log Book
Summary of total number of competency experience days recorded to date: 524.00 days
12
Contract administration 2 12 57.00
12
Project financial control and reporting 2 17.00
12
Continuing Professional Development (CPD) Record
Learning Learned about the new UAE arbitration law (federal law no. 6 of
outcomes: 2018)
08 February 2019 Activity type: Conference/Workshop/Seminar 3.00 hours
Learning Learned the main elements in project financial control and reporting
outcomes: such as change control procedure, value engineering, risk
management, cash flow etc.
08 February 2019 Activity type: Conference/Workshop/Seminar 2.00 hours
Description: Interview for Membership of Institute of Quantity Surveyor Sri Lanka Formal
(IQSSL)
Learning Answered to questions risen by panel members of IQSSL and all
outcomes: the experiences were reminded for creating answers
25 January 2019 Activity type: Private Study 3.00 hours
Learning Studied articles and books related to conflict avoidance and dispute
outcomes: resolution to gain knowledge for APC summer session 2018
16 October 2018 Activity type: Private Study 3.00 hours
Learning Studied articles and books related to project financial controlling and
outcomes: reporting to gain knowledge for APC summer session 2018
13 October 2018 Activity type: Private Study 4.00 hours
Learning Learned accounting principles such as balance sheets, profit & loss
outcomes: account, profitability, ratios etc. Further, learned about business
planning competency
Date CPD Hours
26 May 2018 Activity type: Conference/Workshop/Seminar 3.00 hours
Learning Identification of extension of time, cost and profit in the FIDIC 1999
outcomes: and comparison with FIDIC 1987 4th edition
20 April 2018 Activity type: Training Course 8.00 hours
Learning Learned about the company data management system and project
outcomes: document controlling system. Moreover, I had an opportunity
handled project document controlling as a training
Date CPD Hours
22 December 2017 Activity type: Conference/Workshop/Seminar 3.00 hours
Description: Variation, Payment and EOT clauses in FIDIC 1987 4th edition Informal
Learning Learned the main elements in project financial control and reporting
outcomes: such as change control procedure, value engineering, risk
management, cash flow etc.
10 March 2017 Activity type: Conference/Workshop/Seminar 4.00 hours
Learning Learned the concept of BIM modelling and had practical experience
outcomes: with Autodesk Revit software
Date CPD Hours
22 February 2017 Activity type: Work-based Activity 2.00 hours
Learning Learned about software which can be used for taking off quantities
outcomes: form PDF drawings
20 February 2017 Activity type: On-the-job Training by Internal Expert 5.00 hours
Learning Learned advance excel formulas which were used for proper data
outcomes: management
09 December 2016 Activity type: Exam Setting/Moderation 1.00 hour
Learning Learned aspects which are having a potential causing for conflicts.
outcomes: Further studied how we can resolve them without letting them to
crystallize in to disputes.
28 November 2016 Activity type: Conference/Workshop/Seminar 4.00 hours
Learning Learned aspects which are covered under client care and data
outcomes: management
22 September 2016 Activity type: Private Study 3.00 hours
Learning Identified the health and safety which covered under the
outcomes: competency
17 September 2016 Activity type: Private Study 3.00 hours
Learning Learned aspects in FIDIC 1987 4th edition and FIDIC 1999 red
outcomes: book
04 August 2015 Activity type: Work-based Activity 4.00 hours
Learning The purpose of this training was to give decent knowledge to the
outcomes: site engineers on cost code system which was used to cost
controlling
10 March 2015 Activity type: Private Study 3.00 hours
GRADUATE ROUTE 1
CASE SUDY
TOPIC
By
Table of contents
1.0 INTRODUCTION ...........................................................................................................................................1
3.0 MY ACHIEVEMENTS.................................................................................................................................10
APPENDICES......................................................................................................................................................14
Table of Figures
FIGURE 1: FOUR STAR HOTEL .................................................................................................................................1
List of Tables
List of Abbreviations
MC - Main Contractor
LC - Letter of Credit
1.0 INTRODUCTION
1.1 The Brief
This report was prepared to present a case study based on an issue encountered during the post-contract stage of
a project where I got involved in. The purpose of the report is to demonstrate that I have achieved required
competencies with a satisfactory level, which requires obtaining Royal Institution of Chartered Surveyors
(RICS) membership under graduate route 1.
2.0 MY APPROACH
2.1 The Key Issue
Identify the best solution to deliver the MEP package with no delay to the project completion, when a system
sub-contractor is facing the financial difficulty, which leads to a delay.
SC started the works as agreed and the project activities were moved fast as the project was in fast track form.
However, after four (4) months from the commencement of MEP works, it had been noticed that the progress of
the drainage and water supply works had been reduced compared to the consented program. Having notice
above delay, NEC advised to SC in order to mitigate the ongoing delay and achieve the original time for
completion. Despite our continuous follow-up and reminders, SC has failed to demonstrate required level of
progress at site. Further, SC sent a letter by stating that his intention to terminate the contract by himself as of
his current financial instability to continue works in fast track conditions.
Moreover, the planning engineer has shown that the piping installation works were in a critical situation to make
a delay impact to the MEP work program. Furthermore, if there is a delay to water supply and drainage works, it
will probably impact to make disruption in many other services and architectural installations of the project.
NEC was mainly focusing on timely delivery of the project and quality of the works in order to enhance the
Employer’s relationship and build a good reputation in the industry. In addition, delay damages due to project
delay was to made financial losses on NEC.
As this case was much critical to NEC, I was assigned to investigate more about the situation and to advise the
management to get the best remedial action to keep the project on track by avoiding additional cost to the
company. Therefore, I went through the sub contract conditions, site progress report and payments as my first
approach. Moreover, I had a meeting with SC to understand the current situation of their company. There, I
observed that SC was struggling to arrange finance for material procurement and labour wages to comply with
fast track form. Moreover, I realized that delay in payments in ongoing projects were the main reason for them
to face such financial difficulty. However, at the end of the discussions, I agreed with them to meet again with
our final decision on the issue.
The following could be the consequences of the key issue that can arise upon the above situation;
Delay in drainage and piping works will lead to a sectional or total project delay,
NEC will be penalized by delay damages and disruption claims,
Expected reputation will be faded in the construction market,
NEC’s business relationship between the Employer and Main Contractor (MC) will be damaged,
2.4 The Employer’s Requirement and Project Constraints
The following project constrains were identified as driving factors to the project when consider the key issue;
Time
Time is the most critical factor in this project since it is only 12 months to complete all MEP works under the
Contract. Therefore, the project progress must be continued as per the consented program and if any delay
occurs, that will be adversely affected to the other succeeding activities and that will be directed to whole
project delay. In order to protect the Employer’s business plans, the reputation of MC and NEC in the industry
and to avoid additional cost on NEC, complete the project within original duration will be essential.
Cost
There are specific milestone completion dates and related delay damages agreed in the Contract for sectional
and whole project completion (refer Appendix-B). Therefore, if delay occurs due to MEP works, the relevant
delay damages will be applied against NEC. Subsequently, if other package contractors suffer any delay due to
the delay in MEP works, NEC will be liable to pay disruption costs. Therefore, to keep the project within the
budget and achieve the expected profit, NEC should complete the scope of works within original time for
completion.
Quality
The hotel has been designed to be built as four stars category therein the quality standards must be in
accordance with international quality control procedures. Thus, the required quality standards in the MEP works
should be achieved and maintained throughout the project duration.
Business Prospect
Since NEC is a developing MEP contractor in the market, achieving a close relationship with the Employer, MC
and other sub-contractors will be an advantage in long term business plan.
2.6.1 Option – 01: Terminate the SC and appoint a new sub-contractor through competitive tender
This option is considered to terminate the employment of SC, and appoint a new sub-contractor through a
competitive tender process. Under this option, my intension was to focus on sub-contractors who had submitted
their proposals in initial tendering stage and ask them to revalidate their proposals to comply with remaining
works.
Advantages
Disadvantages
Additional time is required for appointment and to obtain the Engineer’s approval for the new sub-
contractor,
The scope of the sub-contractor is difficult to ascertain, since the part of the work has been partially
completed,
Take time to mobilize and get familiar with site conditions and works,
Other ongoing works may be interrupted until new sub-contractor get start works,
Settlement of final account for SC may be difficult.
Warranties and guaranties issues due to the partially completed works.
I identified that the drainage and water supply works in the project could be isolated especially for three areas
namely promenade floors and ground floor, typical floors at north side and typical floors at south side (Refer
Appendix C). Moreover, I observed that there was a list of registered sub-contractors in the procurement
department for MEP installation works. Considering these facts, I built up this option which was considered to
terminate SC by appointing three installation sub-contractors to the split areas.
Advantages
Installation sub-contractors can be selected within short time period by agreeing on schedule of rates,
Project activities can be speed up increasing labour force,
Works can be started in a short period of time at site,
Labour cost can be reduced by agreeing competitive installation rates with each sub-contractor.
Disadvantages
Quality of the work should be monitored and maintained continuously by keeping additional site
supervisors,
Require a better arrangement to monitor and reduce the material wastage,
Single point responsibility cannot be maintained for the works,
The responsibility of shop drawings and site management will totally be with MEP contractor.
Warranties and Guaranties issues due to partially completed works,
2.6.3 Option–03: De-scope the works, related to typical floors from SC. Further, raise a Letter of Credit
(LC) on behalf of SC to facilitate his material procurement. Moreover, appoint an
installation sub-contractor to typical floors which has been de-scoped from SC.
In this option, I have considered to de-scope the typical floors from SC, and appoint an installation sub-
contractor for the typical upper floors by negotiation process. Further, a LC is proposed to issue to SC to
facilitate the material procurement.
Advantages
A minimum time period will be required to implement the option thereby delay can be minimized,
Generate positive impact on SC cash flow which will help to avoid termination,
Minimum additional cost implication on NEC as the delay is mitigated,
A win-win situation for both parties,
Labour cost can be reduced by agreeing competitive installation rates with new sub-contractor.
Required quality can be maintained,
Installation can be speed up by increasing number of labours and creating work targets.
Weightage (W)
Possibility (P)
Possibility (P)
Possibility (P)
Project Constraints
WxP
WxP
WxP
Time for completion 40% 3 1.2 5 2.0 5 2.0
As per the result of above quantitative analysis, option-03 was selected as the most appropriate option as it
was with highest points.
As per the background of the key issue, time is the most critical factor to be managed to avoid delays and to
keep the project within the budget to protect NEC’s business plan. If option-1 is considered, it will take less
time to select a sub-contractor since there is no tendering process is involved. However, comparing to the
available options, option 2 and 3 will give proper out put on time constraint than option 1. If option 2 is
implemented, an additional time limit will be required compared to option-3 since all sub-contractors are going
to be new to the project and material procurement to be carried out by NEC. However, by appointing installation
sub-contractors as much as early and arranging proper site management steps, additional time requirement for
option 2 can be minimized.
2.7.2 Cost
Since option 1 and option 2 are considered about termination and appointment of new sub-contractors, both
options impact on increase of time period, which create additional cost and conflict to NEC. However,
comparing to option 2, option 1 will create more delay impact on the original completion date where
considerable additional time period is required to restart the works at site. Therefore, the option 3, which is
considered to work with SC by de-scoping a part of the work, shows lesser risk on cost constraint than option-1
and option-2.
In all the options, specialized sub-contractors have to be selected to carry out the works. Therefore, all the
options will demonstrate lesser risk on the quality of the performance. However, compared to option 3, option 2
has a higher risk of quality in the works since there are three installation sub-contractors to be used. If option-2
or option-3 is to be implemented, it is advised to have additional consideration on site coordination and
supervision to maintain required quality standards. Option 1 will always demonstrate the assured quality of the
works since pre-qualified sub-contractor to be used.
Compared to the option 3, option 1 and 2 will show a higher risk of conflicts since both options are dealing with
termination of SC. However, when compared with option 2, option 1 demonstrates a lesser risk of conflicts
while dealing with single point responsibility. Further, the scope of typical floors which are to be executed by
installation sub-contractor are tested and commissioned separately and connected to each other. Therefore,
conflicts deal with option 3 can be minimized further.
To build up and maintain a good business relationship with other stakeholders, it is vital to avoid delays in the
works by completing the project within the original time for completion. When consider options, option 3 will
deal with minimum delay impact and no termination thereby it demonstrates as the best option among others for
maintaining better business relationship with all stakeholders.
3.0 MY ACHIEVEMENTS
3.1 Implementation of the selected option
I presented my findings to the senior management wherein I explained all the identified options. Moreover, I
have further elaborated on the most appropriate option among those identified options in order to keep the
project on track with the minimum impact on the project constraints. Based on my findings, project director
approved the option – 03. Consequently, the following steps were taken to implement the selected option;
Project manager explained our concerns to the financial department and they confirmed that it was
feasible to arrange a LC for material purchasing,
Immediately, we requested to SC to attend for a meeting with us to discuss our proposal,
At the meeting, SC agreed with our proposal and explained that they would be able to continue their
works as per the original program by implementing this option,
Further, our Project Director instructed to certify the pending payment application and release the
payment immediately to encourage SC’s work force at the site,
Based on the details agreed in the meeting, the sub-contract agreement was amended by reducing the
evaluated cost for the de-scoped area. Further, the LC was opened for few suppliers that SC was dealing
with for material procurement.
Subsequently, an installation sub-contractor who had worked with NEC in recent past project was called
for a negotiation meeting and agreed with expected rates.
Moreover, the project manager instructed to concentrate on reducing material wastage for water supply
and drainage works in upper floor areas,
Furthermore, sub-contract works were continuously monitored and advised to achieve the required
progress level,
4.0 CONCLUSION
4.1 Reflective Analysis
As expected, the selected option contributed to eliminate the risk of the delay and assured the successful
delivery of cost, quality and future conflicts constraints. However, I understood that the following preventive
methods would be more appropriate to use in future to avoid a similar circumstance.
Both present technical and financial capabilities should be evaluated when selecting a sub-contractor
without selecting based on past workmanships and experience.
Specific evaluation criteria should be used to evaluate a sub-contractor for fast track project.
My involvement to solve this issue offered me a good opportunity to enhance my knowledge on technical,
commercial and contractual aspects which were encountered throughout the construction process. Further, I
was able to identify the available possible options to resolve the key issue and select the most appropriate
option through analytical evaluation to keep the project on the track without getting delay and avoiding
potential additional cost impact. Moreover, it helped to avoid the upcoming conflicts on the project.
Furthermore, I believe that the knowledge and experience that I obtained, developed my skills to meet the
requirements of chartered Quantity Surveyor in accordance with the RICS guidelines and rules of conduct.
This Case Study consists of 2,964 words, excluding front cover, table of contents, list of figures, list of tables,
confidentiality statement, declaration, abbreviations, figures, tables, headers, footers and appendices.
APPENDICES
Appendix – A - Competencies Demonstrated in This Case Study
Data management
MEP Contractor
S.No Area Area Description LD (Per week)
AED
Promenade Level & Promenade
1 Parking area, incl. MEP plant rooms 35,420
Mid-Level
Promenade Level, Promenade
2 Hotel BOH areas 32,200
Mid-Level & Ground Floor
Retail (F&B & line shops) – shell and core,
Promenade Level, Promenade
3 including retail BOH; MEP plant areas on 24,150
Mid-Level & Ninth Floor
ninth floor
Retail (F&B & line shops) – shell and core,
4 Ground Floor 3,220
including retail BOH
All Day Dining, including adjacent lobby
5 Ground Floor 8,050
restrooms
Public Areas - Reception, lobby, public
6 Ground Floor toilets, including testing and commissioning 40,250
for the entire Works
Guestroom level (complete Level – all
First, Second, Third & Fourth areas on level including meeting rooms,
7 53,130
Floor gym, & including all guest elevators and
one service lift)
Fifth, Sixth, Seventh & Eighth Guestroom level (complete level – all areas
8 53,130
Floor on level)
9 Balance of the Works External areas & balance of the works 43,470
Balance of the works - all areas, including
Whole of the Works 293,020
external areas & testing and commissioning