J Visually check the absence of voltage. J Switch off the LV circuit breakers J Open the cable compartment.
J Check than the earthing switch is closed. secondary VT in the LV cabinet.
J Carry out the mandatory audit for J Fix the master jaw of the devices for J Clip the first jaw on the insulating rod.
absence of voltage on each phase. earthing on the circuit main earth. J Tighten the jaw on the phase L1
connection.
J Repeat for the other two phases. J Switch the contacts of VT’s primary
connections.
1
3 Test procedure (tests of cables)
Schneider Electric Energy France As standards, specifications and designs change from time to time, please ask for confirmation
35, rue Joseph Monier of the information given in this publication.
CS 30323
F - 92506 Rueil-Malmaison Cedex
03-2013
AMTNoT217-02 revision: 00