Professional Documents
Culture Documents
PLF-PRC-005 - R0 - Sideboom Capacities For Lower-In Procedure
PLF-PRC-005 - R0 - Sideboom Capacities For Lower-In Procedure
MMCEC-MMCOG-SEW JV Revision: 0
MMCEC-MMCOG-SEW JV Revision: 0
TABLE OF CONTENT
MMCEC-MMCOG-SEW JV Revision: 0
1.1 Introduction
Side booms are being used widely for different activities in pipeline construction
especially for the lowering in purposes. The lifting capacity of the side booms changes
based on the overhang distances. Therefore, optimisation of the number of side booms
for these purposes is very important for the efficient use of available side booms as
per construction schedule.
In this calculation document, Caterpillar side boom specifications are taken as the basis
for the side boom load lift capacity calculations since all manufacturers have equivalent
machinery with different trade names and numbers. Also, excavators with the same
lifting capacity can also be used.
1.2 Purpose
The purpose of this calculation document is to provide the tables for the load lift
capacities of the different types of side booms to use in the calculation of minimum
required side boom numbers for the lower-in construction activity.
Scope of works includes the specifications and load capacity curves of side booms as
well as the calculation method for determination of the number of side booms and load
lift capacities.
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
MODEL
SPEC 561M 572R 583R 589
GENERAL DIMENSIONS
Height to Top of Stack 3.12 m 3.45 m 3.51 m 3.92 m
Height to Top of Counterweight 1.68 m 2.90 m 3.41 m 2.92 m
Width, Weights Retracted 3.19 m 3.65 m 3.63 m 4.53 m
Overall Length 3.73 m 4.74 m 5.48 m 5.94 m
Ground Clearance 438 mm 414 mm 537 mm 625 mm
MMCEC-MMCOG-SEW JV Revision: 0
The below given charts and values are based on the following:
• Maximum lift capacity per ANSI/SAE J743 MAR92
• Rated load per ANSI/ASME B30.14
• Working range per ANSI/ASME B30.14
MMCEC-MMCOG-SEW JV Revision: 0
MMCEC-MMCOG-SEW JV Revision: 0
MMCEC-MMCOG-SEW JV Revision: 0
MMCEC-MMCOG-SEW JV Revision: 0
The chart above provides general information representing typical side boom
applications. When sizing side booms for an application, there are many considerations
other than the machine’s SAE rated lift capacity. These include but are not limited to:
An important consideration is the necessary load overhang. This is the distance from
the centre of the pipe to the side boom’s left track rail. This distance can be estimated
generally by the following formula:
MMCEC-MMCOG-SEW JV Revision: 0
This distance will be shown on the drawings to be prepared separately, based on the
ditch depth and the soil conditions.
The side boom’s rated load capacity at a specific load overhang will be found in the load
capacity graphs given above. Once the load capacity is determined the maximum lift
point spacing will be estimated by the following formula:
The maximum distance between pipe lift points (based on the pipe bending
characteristics) may be shorter distance than the maximum spacing between lift points
as calculated based on side boom load capacity. If this is the case, then in order to avoid
damaging the pipe, the shorter distance will be considered to be the maximum distance
between side booms.
• No of side booms = Total weight of the pipe string / maximum lift point spacing
Or
• No of side booms = (Length of pipe string x pipe weight per meter x safety factor)
/ rated load at overhang
Pipe weights included concrete coating will be taken from the table in item 6.0 and rated
loads will be taken from the table given in item 5.0 below.
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
The following table is prepared based on the above given data and explanations for
different types of side booms for the loads at different overhang dimensions:
In the calculation of number of machineries, side boom type 583 R or equivalent is used.
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
So –
Table 3: Pipe, Concrete and Valve Weights
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
MMCEC-MMCOG-SEW JV Revision: 0
MMCEC-MMCOG-SEW JV Revision: 0
• Distance between the highest point of lifting and supports on the trench bottom;
𝐸𝐸𝐸𝐸
𝑅𝑅 = [1]
𝑆𝑆
With this formula, the elastic theoretical bend radius and minimum elastic bend radius
are calculated.
For the elastic theoretical bend radius, the value of S is %SMYS maximum allowable x
SMYS.
Minimum elastic bend radius, the value of S is “%SMYS” x SMYS.
The “%SMYS” is a value that, used in planimetric and altimetrical combination, does not
allow to exceed %SMYS maximum allowable.
The maximum elastic bend radius is determined with following calculation formula:
𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 2 𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉 2
�� � +� � �
2 2
𝑅𝑅𝑚𝑚𝑚𝑚𝑚𝑚 = [2]
𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉
�2 ∗ �
2
MMCEC-MMCOG-SEW JV Revision: 0
8.2 Stresses
The ideal stress will be equal or less than maximum allowable stress.
𝑥𝑥 = �2𝑦𝑦𝑦𝑦 − 𝑦𝑦 2 [3]
MMCEC-MMCOG-SEW JV Revision: 0
By trigonometry
𝑥𝑥
𝛼𝛼 = 𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 � � [5]
𝑅𝑅
Therefore:
𝑥𝑥
𝐿𝐿 = 𝑅𝑅 ∗ 𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 � � [6]
𝑅𝑅
y R
R y
X X
MMCEC-MMCOG-SEW JV Revision: 0
8.4 Calculation for Total Length and Total Mass of Pipe String
9.1 General
The number of lifting equipment depends on the lifting capacity and elastic bend
required.
The distance between side booms is determined using a simplified model of a beam
above supports. This simplification is generally accepted by specialized literature on
the subject.
Stress about bending is as follows:
𝑀𝑀 𝑤𝑤𝐿𝐿2
𝜎𝜎 = = [13]
𝑍𝑍 9.3 ∗ 𝑍𝑍
σ = bending stress;
M = bending moment;
Z = resistance modulus;
L = theoretical distance between supports;
w = weight pipeline unit-length.
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
9.3 ∗ 𝑍𝑍 ∗ 𝑆𝑆
𝐿𝐿 = � [14]
𝑤𝑤
The first side boom, in the part q, can’t exceed the distance between lifting equipment
of highest point and support point outside the trench.
When the last equipment (n) moves to replace the second-last side boom, maximum
distance between the second-last equipment and support point on the bottom of trench
can’t be exceed the maximum calculated length.
The maximum value of theoretical free span is minimum value between theoretical
lengths:
𝑀𝑀𝑓𝑓
𝐸𝐸𝑡𝑡 = [15]
0.1 ∗ 𝑤𝑤
0.00651 ∗ 𝑤𝑤 ∗ 𝐿𝐿4
𝑓𝑓 = [17]
𝐸𝐸𝐸𝐸
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
f = deflection [mm];
w = pipeline weight per unit length [N/mm];
L = Length between supports [mm]
E = Elastic Young’s modulus (206000 MPa for steel);
I = Moment of inertia [mm4]
In case of uncertainty about the soil stability, a ground pressure verification may be
made taking into account the most critical conditions during the laying.
The ground pressure is calculated, in the case of the track near the pipe string to be
lowered
(𝑊𝑊𝑠𝑠𝑠𝑠𝑠𝑠 + 2𝑊𝑊𝑠𝑠 )
𝑃𝑃𝑠𝑠 = [19]
2(𝑇𝑇𝑤𝑤 ∗ 𝑇𝑇𝐼𝐼 )
10. CONCLUSION
For the lowering in of 36-inch pipe string, it must fulfill the following:
For wall thickness 11.9 mm, Specific Minimum Yield Stress (SMYS) 448 MPa, stable
soil condition:
• The minimum number of lifting machines is 6 Side booms Cat 583 R or equiv.;
• The minimum distance between the lifting machines is about 14.00 m;
• The maximum distance that can reach the single lifting is about 16.00 m.
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
Based on the above, using 583 R side booms at 15 meters spacing with 4.0- m e t e r
overhang to lower-in pipe sections of 250 meters in overall length, the safety factor is
1.5. Based on the above calculations, six (6) ea. 583 R side booms will be used for
lower-in activities, coupled with a 330 D excavator for catch-off on the pipe end.
Doc No:
PETRONAS GAS GRAPHITE-CON-MMSJV-
BERHAD. KTHRO-PLF-PRC-005
MMCEC-MMCOG-SEW JV Revision: 0
The lifting crew must be appropriately trained and sufficiently numbered to enable a
secure Lowering Operation. Before lowering the pipe into the trench, the JV will assure
that all the curves match the trench profile and, in rocky areas, that the minimum bed
thickness has been respected.
The person in charge will establish a sign system to be used by all the workers. The
person in charge will place himself in a position where he is visible by all the workers.
If needed audible communications such as radios will be used.
The pipe must be secured, lifted and lowered using side-booms. In those situations, in
which the ROW gradient is less than 10° belts will used according with ground
conditions and characteristics of the welded line to be lowered (concrete coating,
thickness, diameter etc.) When the ROW gradient is higher than 10°, side-booms will
be equipped with a system of lowering belts and other apparatus.
The pipe must be lowered carefully to avoid abrasions, scrapes, cracks or any other
damages in the pipe coating.
Lowering activities can’t begin while other activities are taking place in the section, for
example joint coating, holiday reparations, etc. If a coating imperfection is found
during the lowering process, all the equipment must stop the activity until the
imperfection has been repaired.
Tractors equipped with belts / slings will be used in the lowering-in activity.
The number of side-booms required is based not only on the lifting ability but also on
the need to restrict the pipe’s elastic deflection and to make the pipe assume the
tridimensional deformation configuration, avoiding torsions and lateral movements.
MMCEC-MMCOG-SEW JV Revision: 0
The first side-boom must lift the pipe section from the supports and hold it to avoid
lateral movements and falls. The second side-boom keeps the pipe section lifted right
above the trench to avoid it from hitting the trench’s walls and provide the pipe section
with the correct and necessary combined curve. The third and additional side-booms
(from 4th to 6th) which might be needed will be used to place the pipe section in the
bed and to hold it while the head side-boom (from 4th to 6th) moves towards the 3rd
side-boom to occupy its position.
A security side-boom or excavator will be placed in front supporting the pipe section
to make sure that it won’t fall off the skids due to the pipe movement during lowering
activities. Skids that have been released when the Lowering operation gets started will
be thrown to the RoW, away from the next side-boom trajectory, and will be collected
afterwards.
The holiday inspection crew must be right behind the last side-boom to be able to
examine all the previously unreachable points which were situated on top of the
supports.
The holiday reparation crew must be visible to the nearest operator at any time. Due
to the fact that this crew can use bar patches, stairs will be available as well as gloves
to avoid burns.
In case Lowering-in activities should be interrupted for a long period of time, the pipe
would be placed on its original support until the operation is restarted. The lowering
belts/slings system or wedges with rollers must be removed. If necessary, a security
side-boom will be placed behind to guarantee that the pipe won’t fall inside the trench.
The open ends of pipe sections will be closed using appropriate material covers, to
prevent water, wreckage or animals from entering the pipe.
Once the Lowering process has been finished it is necessary to check that the pipe is
perfectly centered inside the trench and placed correctly in its final position. During
the Lowering process no activity will take place inside the trench.