Professional Documents
Culture Documents
PIP-PRC-001 - R1 - PROCEDURE FOR PIPING FABRICATION AND ERECTION WORKS - Signed
PIP-PRC-001 - R1 - PROCEDURE FOR PIPING FABRICATION AND ERECTION WORKS - Signed
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
CODE 1
NO FURTHER COMMENT
MMCEC-MMCOG-SEW JV Revision: 1
TABLE OF CONTENT
1. INTRODUCTION........................................................................................ 4
1.1 Project Overview ......................................................................................... 4
1.2 Purpose and Scope ...................................................................................... 5
2. DEFINITIONS AND ABBREVIATIONS ........................................................ 5
2.1 Definitions .................................................................................................. 5
2.2 Abbreviations ............................................................................................. 6
3. REFERENCES ............................................................................................ 6
3.1 Company References ................................................................................... 6
3.2 Contractor References ................................................................................. 6
3.3 Codes and PTS Standards............................................................................. 7
3.4 Order of Precedence of Reference Document .................................................. 7
4. RESPONSIBILITIES .................................................................................. 8
5. MATERIAL ................................................................................................ 9
6. METHODOLOGY ........................................................................................ 9
6.1 General ...................................................................................................... 9
6.2 Preparation and Material Receiving ................................................................ 9
6.3 Drawing and Document .............................................................................. 10
7. FABRICATION ........................................................................................ 10
7.1 General .................................................................................................... 10
7.2 Cutting .................................................................................................... 10
7.3 End Preparation ........................................................................................ 11
7.4 Alignment and Trimming ............................................................................ 12
7.5 Preheating................................................................................................ 13
7.6 General Requirement for Welding ................................................................ 14
7.7 Welding Rods ............................................................................................ 15
7.8 Welding ................................................................................................... 15
7.9 Identification of Joint and Numbering........................................................... 18
7.10 Identification of Spool Numbering ............................................................... 18
7.11 Storing & Inventory ................................................................................... 18
8. ASSEMBLING AND ERECTION ................................................................. 19
8.1 General .................................................................................................... 19
8.2 Flanged Joint ............................................................................................ 20
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
MMCEC-MMCOG-SEW JV Revision: 1
1. INTRODUCTION
1.1 Project Overview
COMPANY intends to replace Existing NPS 36 PGU-I-Gas Pipeline with New NPS 36 PGU-I
Gas Pipeline (namely GRAPHITE) due to ageing facilities. New PGU-I pipeline will use better
route, eliminating hilly and graphitic soil via Loop 1 Right-of-Way (ROW).
The pipeline adapts like-to-like replacement including the pipe size of NPS 36, with length
of approximately 33 km from Gas Processing Kertih (GPK) until Bukit Anak Dara Kijal,
Kemaman. The works consists of Engineering, Procurement, Construction and
Commissioning (EPCC) of the facilities.
In general, the new pipeline will be installed alongside the existing NPS 36 Loop 1 Gas
Pipeline, NPS 12 Liquid Propane pipeline and two (2) x NPS 8 Liquid Butane pipeline. The
ROW varies from 90m then reduces to 40m width. Generally, the ROW corridor traverse
along light population village areas, railway & road crossings, palm & rubber estates and
hilly & undulating terrains.
MMCEC-MMCOG-SEW JV Revision: 1
This document covers the procedure for fabrication and erection of station piping which
involves welding of branches, fittings and ancillary equipment to or from the mainline pipe
works at Scraper and Launcher Stations, Block Valve Stations and other relevant areas.
Term Explanation
COMPANY shall means PETRONAS Gas Berhad and as the project owner,
includes its representatives
CONTRACTOR shall means MMCEC-MMCOG-SEW Joint Venture which being
appointed to carry out the works in accordance with the Contract
SUB-CONTRACTOR shall means the Party to which CONTRACTOR has sub-contracted a
portion of the works under the Contract
VENDOR shall means Manufacturer/Supplier that manufactures or supplies
equipment and services to perform the duties specified by the
CONTRACTOR
FACILITIES shall mean all the equipment, pipeline, building and station related
details in this PROJECT
PROJECT shall means Engineering, Procurement, Construction and
Commissioning (EPCC) of PGU-I Gas Pipeline Replacement Project
(GRAPHITE)
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
2.2 Abbreviations
The following abbreviations and terminologies are used throughout this document:
Acronym Definition
°C Degree Celsius
AFC Approved for Construction
DFT Dry Film Thickness
ITP Inspection and Test Plan
JHA Job Hazard Analysis
m Meter
mm Milimeter
NPS Nominal Pipe Size
PPE Personal Protective Equipment
PTW Permit to Work
PTS PETRONAS Technical Standard
QA / QC Quality Assurance / Quality Control
ROW Right of Way
SOW Scope of Work
3. REFERENCES
3.1 Company References
MMCEC-MMCOG-SEW JV Revision: 1
MMCEC-MMCOG-SEW JV Revision: 1
4. RESPONSIBILITIES
The following describes the responsibilities of Contractor’s manpower to perform the
activities:
MMCEC-MMCOG-SEW JV Revision: 1
5. MATERIAL
All material shall comply with project requirements, specifications, specified codes and
standards and AFC drawings. CONTRACTOR shall submit full details, test report and
certificates for all materials delivered to site as evidence of soundness, that materials are
the origin and quality specified or approved.
6. METHODOLOGY
6.1 General
The works of all station piping is as per design code ASME B31.8 & ASME B31.3. (All station
piping works use ASME B31.8 and for utilities use ASME B31.3) i.e., fabrication and
installation of piping at stations, tie-in and tee-off. Welding Procedure & Welder
Qualifications for piping designed to B31.3 shall be ASME IX and designed to ASME B31.8
shall be either ASME Sec IX or API 1104.
Welding Procedure Specification and the Procedure Qualification Record as per GRAPHITE-
EXE-MMSJV-KTHRO-MEC-WPS-001: Welding Procedure Specification (PWPS) Piping shall
be obtained for welding work.
The fabricated spool pieces shall be prepared in such a way as to minimize the number of
field welds require to install the piping. All fabricated spool pieces shall be suitably marked
with identification of weld joints and spool, as per drawing prior to transportation from the
place of fabrication to the job site.
CONTRACTOR shall produce fabrication drawings and weld map prior commencement of
piping fabrication work.
The inspector nominated for the job must be a specialist or an expert in respective
examinations and licensed or qualified by an internationally recognized association and/or
by any statutory requirement applicable.
All piping materials received at storage yard shall be checked physically about the size &
schedule, material grade, material test certificate, and quantity as per purchase order by
Material Controller.
The material test certificate shall be reviewed according to specification/standard and heat
no. / identification no. to confirm the identification and traceability.
Before installing the straight pipe at site, pipes directly shall be released for blasting and
painting. Painting shall be carried out as per respective painting system and approved
procedure.
Site engineer shall raise material request to stores for fabricating the respective spools.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
Site engineer shall issue a set of drawings which are to be fabricated. Piping engineer shall
prepare a weld map / cutting plans for all drawings whose materials has been issued in
Coordination with piping foreman or supervisor.
Piping work shall be carried out with issued AFC drawing and document unless otherwise
specified. All the changes from approved AFC drawing, during shop fabrication and erection
at site will be captured and mark-up inside Redline mark-up drawing. This Redline mark-
up drawing will control by CONTRACTOR and shall be registered and initial by COMPANY.
7. FABRICATION
7.1 General
Fabrication requirement shall be in accordance with PTS 12.30.05, ASME B31.8 and API
STANDARD 1104 unless otherwise specified.
Fabrication shall be executed in accordance with the related Engineering Specification and
the drawings, document stated of this specification.
The bolt holes of flanges shall be located symmetrically from a vertical center line in a
horizontal pipeline, and from plant north in a vertical pipeline unless otherwise indicated
in the drawing.
7.2 Cutting
Cutting line shall be marked on pipe. Where the material marking will become invisible
after cutting, additional material marking shall be provided.
In the case of gas cutting, cutting surface shall be grind off to remove any edge and
roughness and be made flush and smooth so as not to harm welding quality. In the case
of automatic or semi-automatic gas cutter, the cut edge may be beveled without such
grinding off.
In the case of gas cutting, cutting slag stuck inside pipe shall be completely removed,
especially for boring of pipe for weld branch. For small diameter (less than 2inch) opening,
gas cutting is not allowed.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
t<3 I t
37.5 ±
25
t ≤ 22 V
t
1.6 ±
08
10 ±
25
37.5 ±
25
t > 22 Double-V
t
19 ± 2
1.6 ±
08
(2) Shape of beveling other than mentioned in Table 7.1 shall be in accordance with the WPS
approved by COMPANY.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
In the case of butt-welding pipe and/or fitting having unequal wall thickness, of which the
difference is more than 3 mm in outer surface and/or 1.5 mm in inner surface, the end of
the thicker pipe shall be trimmed by grinding as per the Fig. 7.1 (a), (b) and (c) shown
below. The gradient of this trimming shall be less than 30° between worked and unworked
parts shown as below.
Unit: mm
(a)
Max. 30° 3.0 or Over
≥ tm
(b)
≥ tm
1.5 or
Max.
(c)
In case
ultrasonic
≥ tm tm or Over
Max. 30°
1.5 or
Figure 7.1
Note: In the case that “Special End Detail” is specified in the Material Specification for
the pipe and/or fitting of which the nominal wall thickness is 30 mm and over, the
end preparation shall be in accordance with such provision.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
Branch connections which abut the outside surface of the run pipe shall be contoured for groove welds
which meet the WPS requirements [see Fig. 7.2 (a) and (b)].
Branch connection which are inserted through a run opening shall be inserted at least as far as the
inside surface of the run pipe at all points [see Fig. 7.2 (c)].
Figure 7.2
When a pipe having a longitudinal weld seam is used in a horizontal line, the pipe shall be
laid so that the longitudinal weld seam is not on bottom or top of the pipe. Allocation and
relation among circumferential and longitudinal welds are shown in the Fig. 7.3.
Figure 7.3
7.5 Preheating
Preheating shall be performed by propane flame or by another appropriate method prior
to commencement of welding including tack welding. Any flame heating shall be applied
as evenly all round as possible, avoiding hot spots.
MMCEC-MMCOG-SEW JV Revision: 1
When welding dissimilar metals, preheat temperature shall be in accordance with WPS,
notwithstanding the provisions above. The preheat zone shall extend at least 25 mm
beyond each edge of the weld.
b) Welding shall not be carried out in adverse weather conditions where there is
impingement of rain, snow, sleet storm or excessive wind at the working area, unless
appropriate and adequate protection is provided.
c) The bevel shall be fully cleaned so that there is no rust, oil, paint, sand, moisture, etc.
remaining. Where a bevel is not to be welded immediately it shall be protected to
prevent contamination.
d) Spatter, slag, etc. on the weld or in the heat affected zone, shall be thoroughly
removed to the metal surface.
e) Arc strikes on base metal shall be avoided at all times. Arc strike shall be ground flush.
Any defect shall be ground out and weld repaired.
f) Material of wire brush shall be properly selected for working on carbon steel or stainless
steel respectively. They shall always be kept separated and never used on anything
other than the designation.
g) Welding and heat treatment (preheating, post heating, and stress relieving) for a
welded joint valve shall be carried out with the valve opened.
h) Weld internal protrusion at the weld neck joint of an orifice flange, shall be removed
flush and smooth with a grinder. Any concavity in the root, shall be weld repaired and
ground flush and smooth.
i) Socket welding shall be performed at least 2 layers weld and end point of weld at each
layer.
k) Full GTAW shall be employed as an alternative to combined process (GTAW & SMAW)
for pipe either in sizes of 10 inch and smaller, with thickness 10mm and below or any
bigger diameter size with thickness 10mm and below.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
7.8 Welding
Tack welding shall be carried out as follows:
e) Provide sufficient external pipe clamps or internal spiders for setting up.
f) Ensure the contact surface of the clamps or spiders are made of the same base metal,
or an inert compound.
b) Circumferential butt welding shall be performed without the use of a backing ring
unless specified in WPS.
c) Before welding of the root, both ends of the root tack weld bead shall be prepared with
a grinder as shown in the following illustration in order to make complete fusion.
d) Full GTAW process shall be applied for piping NPS less than or equal to 4”.
Figure 7.4
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
Branch connections shall be made by using the fittings as specified in the PTS 12.30.05,
ASME B31.8.
However, where the branch is to be welded directly to the main run in accordance with
Piping Arrangement Drawing, welding shall be performed, unless otherwise specified,
shown in following Fig. 7.5:
MMCEC-MMCOG-SEW JV Revision: 1
Fillet welding of pipe to slip-on and socket weld flanges shall be performed as shown in following Fig.
3.8.4:
Figure 7.6
Socket welding of pipe components other than flanges shall be performed as shown in
following Fig. 7.7.
Figure 7.7
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
The joint number shall be followed by a two letter, SW and for shop weld and FW for field
weld:
Example:
For shop weld
SW1: Shop weld
SW1R1: when joint repair first time
SW1R2: when joint repair second time (if the second repair is not acceptable, the complete
weld shall be removed or repaired subject to COMPANY approval)
SW1RW1: when welded joint cut and re-welded
Valves shall be specially protected by end protective cover. Piping and valves shall be
covered by good quality of tarpaulin to prevent entry of dust, soil and rainwater. Fittings,
gaskets and instruments shall be store inside container storage with lock and key.
Welding consumables especially low hydrogen electrode once open shall be stored in
calibrated oven maintained at suitable temperatures recommend by manufacturer.
Make sure all pipes are securely kept on saddles to avoid moving.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
Before assembling of piping, actual tolerance causing from foundation, steel structure,
equipment installation work shall be considered for the piping assembling work.
If hot work to be performed in the vicinity of instrument control or power cable duct, an
adequate protective cover shall be provided in advance so as not to damage the cables.
When work is carried out in the vicinity of piping made of, or lined with special materials
such as plastics, rubber, glass, etc., care shall be taken so as not to damage them.
Valves shall be assembled in clean condition; they shall not be opened during piping
erection except that welding and heat treatment of a welded valve joint shall be carried
out with valve opened.
If cutting, making of holes to the assembled piping and such kind of work is carried out at
assembled place due to the reason of modification, improvement, etc., cut piece and
foreign materials shall be removed from inside of piping and it shall be confirmed that the
inside of piping is cleaned.
Valves having flow direction shall be installed to conform the flow direction in accordance
with piping drawings. Care shall be taken to the valves in case valve flow direction is
reversed against the flow direction of pipeline.
It is prohibited to use small size piping, pumps, instrument etc. as scaffolding or working
stage.
a) Pipe supports shall be fabricated and installed in accordance with Typical Pipe Support
Details.
c) The pre-setting pieces of the pipe hanger shall be removed after completion of leak
test of the pipeline. However, pipelines which will be insulated, it shall be removed
after completion of the insulation work.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
d) A shoe support shall be attached to the pipe in accordance with the drawings. It is not
permitted to tack-weld a shoe support to the pipe rack, where the shoe support is not
to be permanently fixed to the pipe rack.
Flanged joints shall be bolted up, after checking the alignment of the flange centers and
the parallelness of flange faces, to ensure that the contact faces bear uniformly on the
gasket. Bolting-up shall ensure that bolt tension is spread uniformly around the flange.
Particular care shall be exercised to ensure that all bolt, nut and gasket are correctly
installed in accordance with the requirements of GRAPHITE-PI-SPC-004 Specification for
Mechanical and Piping Installation Works.
When assembling flange connections, paste shall be applied to the gasket and bolts. These
prevent seizure of nuts and adherence of gaskets. Reference of pastes and their
applications shall be in Specific Job Requirement.
b) Then coating shall be applied to surfaces after they have been cleaned. The cleaned
surface shall be primed as soon as possible after inspection. If the surface is to be left
open to atmosphere, then protection from contamination by dust, oil, moisture etc.
shall be applied.
MMCEC-MMCOG-SEW JV Revision: 1
d) A holiday detector shall be used during the coating to ensure the validity of the
application. All defects acquired during transportation or installation shall be repaired,
then retested.
e) All repair work to coating shall comply fully with the original installation requirements.
a) Execution of works shall be started after pegging out and confirmation for the position
of trench to be excavated, referencing the appropriate benchmarks and ensuring the
route is sufficiently clear for safe working.
b) Before commencing the excavation work, it shall be confirmed that there are no other
buried objects around the place of excavation, and that the location proposed for the
excavated soil shall have no bearing load on the excavated trench.
c) Depth of buried pipes shall be in accordance with the piping drawing. Excavation work
shall be performed considering the safety aspects of the work, especially if the depth
of excavation is over 1.5 m in an unbattered trench. The piping work in the excavated
trench shall be carried out only after proper protective measures have been taken to
prevent the collapse of the excavated trench.
a) Before laying pipe is carried out, protective measures to prevent accidents such as
trench collapse or landslide, flooding, danger to workers in the area, etc. shall be taken
into full consideration.
b) During laying of piping, full care shall be taken to prevent soil, water, sand, etc. from
flowing into the pipes. Pipes shall be anchored sufficiently to prevent floating due to
groundwater or rainwater.
To avoid any damage on wrapped surface of the piping, initial backfilling shall be carried
out with small-grain sand, for the part in direct contact with the pipes, as shown in Fig.
9.1.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
Figure 9.1
Where road crossings or the similar are specified in the drawings, particular precautions
shall be taken to ensure installation, testing, backfill and compaction are correctly carried
out.
Pipeline welds and mechanical joints shall not be placed at road crossing or the similar. If
such condition cannot be avoided, the joint shall be examined prior to back filling by
suitable examination.
If leak test for whole piping system at one time cannot performed, the system may be
divided into any blocks as block testing. However, the joint between block shall be
examined by suitable examination method instead of leak test.
Fabrication of inner pipe shall be made separately within the extent which allows insertion
of outer pipe. Especially in case of three-dimensional bent components, separation of outer
piping components shall be carefully decided by taking the actual procedure of the work
into consideration.
MMCEC-MMCOG-SEW JV Revision: 1
Cutting of outer piping or other work which may influence bad effect to inner piping shall
be prohibited after assembling of outer piping has been completed.
(1)
Flattening ratio and reduction of thickness acceptance criteria, which shall be decided in accordance with
practical conditions, shall not be applied for steam trace piping.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
Figure 10.1
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
MMCEC-MMCOG-SEW JV Revision: 1
(2)
Hardness test for P-No.1 carbon steel will not be required unless otherwise specified.
MMCEC-MMCOG-SEW JV Revision: 1
a) The repair shall be carried out, then the new work shall be re-examined in accordance
with this specification.
b) If the repair is again found to be unacceptable, then it shall be carried out once more.
Permissible number of welding repairs at the same place shall be a maximum of 2
(two). If a further repair is required, then a cut out shall be the sentence. The welder
concerned who made repair more than 3 times shall be retrained and re-qualified.
a) The examination made at random shall consist of examining not less than one
production weld joint selected from each production weld joint lot made by the same
welder or welding operator defined as follows.
b) The examination shall be applied to the entire length of weld of the selected joint,
except as provided in (d) hereof.
c) The weld joints between dissimilar materials shall be examined by the method used
for the material requiring the more stringent examination.
d) Not less than one shot (with a 150 mm weld length) on one in each 50 girth butt weld
joints by each welder or welding operator for Category D Fluid Service as designated
in the Specific Job Requirements, shall be examined by the spot radiography.
When a random or spot examination of weld joints reveals a defect, the progressive
examination for the same lot defined in Section 10.1.2 shall be carried out as per the
following procedure:
a) Two additional weld joints of the same lot, by the same welder shall be given the same
type of examination; and
b) If the weld joints examined as required by (a) above are acceptable, all items
represented by this additional examination shall be accepted; but
c) If any of the items examined as required by (a) above reveals a defect, two further
weld joints of the same lot by the same welder shall be examined for each defective
item found by that examination; and
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
d) If all the items examined as required by (c) above are acceptable, all items represented
by this additional examination shall be accepted; but
e) If any of the items examined as required by (c) above reveals a defect, all items
represented by the random examinations shall be fully examined and repaired or
replaced as necessary to meet the requirement of this specification.
b) For P-No.3, 4 and 5, radiographic examination shall be carried out after completion of
any heat treatment. For P-No. other than the above, the examination for the weld
joints for which PWHT is required, shall be carried out before PWHT unless otherwise
specified.
c) Prior to the radiographic examination, the scattering radioactivity around the area shall
be measured and the controlled area of the radioactivity shall be established, providing
sufficient countermeasures to prevent hazard of radioactivity.
e) Number of films to be taken for one peripheral joint at radiographic examination shall
be as follows:
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
a) Liquid penetrant examination shall be carried out at root pass for girth butt weld except
the weld which require preheating and at cover pass for branch weld, socket weld
attachment weld and girth butt weld require preheating.
b) Numbers for random examination shall be in accordance with Section 10.2 of this
procedure.
MMCEC-MMCOG-SEW JV Revision: 1
Table 10.1: Non-Destructive Examination Table (Refer to PTS 12.30.05 Shop and Field Fabrication of Piping)
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
MMCEC-MMCOG-SEW JV Revision: 1
a) NDE Inspector / Welding Inspector shall trace the repair location from radiographic
film.
b) Welding foreman shall mark the repair location on the pipe through the tracing.
c) Welding foreman shall be responsible to allocate the suitable grinder and welder to
carry out the repair works.
CONTRACTOR shall give sufficient notice to COMPANY prior to joint inspection at least 24
hours’ notice.
Doc No:
GRAPHITE-CON-MMSJV-
KTHRO-PIP-PRC-001
MMCEC-MMCOG-SEW JV Revision: 1
~ End of document ~