Professional Documents
Culture Documents
TT Inflates Brochure
TT Inflates Brochure
E X E C U T I O N
Dual Seal
Dual Seal
Double Anchor
Permanent Bridge Plugs are Retrievable Bridge Plugs can Permanent Cement Retainers
typically conveyed on either coiled be used as primary or secondary allow for the permanent isolation
tubing or electric wireline which barriers to perform the same and cementation of the zone below
Completion
permits a workover while leaving functions as a traditional RBP yet the retainer in a single trip.
the completion in place, without in a Thru-Tubing environment.
killing the well. • Lower zone isolations
• Temporary
• Permanent abandonment
• Lower zone abandonment
water shutoff Oil Production • Remedial squeeze operations
Oil Production • Temporary
• Lower zone zonal isolation
gas shutoff Retrievable
Bridge Plug • Primary/secondary
• Permanent wellhead barrier
Cement Cap abandonment
• Temporary
frac barrier
Permanent
• Tubing Cement
Bridge Plug change outs Retainer
Isolated
Production • Temporary
gauge hanger
Isolated
Water Cement
Water Shut Off Temporary Well Barrier Lower Zonal Cement Squeeze
Dual Selective Chemical Treatment Intermediate Zonal Stimulation Intermediate Zonal Isolation
Case Histories
United Kingdom – Objective Wyoming – Objective
To isolate a lower water producing interval. Carry out a reservoir injectivity test to simulate an
Description oxygen flood into the reservoir.
An increasing trend in produced water from a Solution
normally oil producing well with 4-1/2 in. tubing In order to perform the injectivity test a 1.69 in.
required some investigation work in the expectation OD TTI Retrievable Packer was run and set above
of lowering the water cut. A production logging tool the perforated zone in 2-3/8 in. tubing. This would
(PLT) was utilized and run into the 7.00 in., 29 lb/ft isolate the upper perforations and allow nitrogen to
liner below the tubing. The PLT indicated that the be pumped through the coiled tubing to the zone of
majority of the produced water was being contrib- interest.
uted by the lower zone. The PLT also identified Results
that crossflow was present flowing directly into the The packer was set using fresh water to an inflation
upper zone at a rate of 600 bbls/day. During the PLT, pressure of 3870 psi, at which point the ball seat was
correlating with a conventional casing collar loca- sheared open. Nitrogen was then circulated through
tor (CCL) in the 13% chrome liner proved difficult, the coiled tubing at rates between 185 to 600 SCFM
therefore it was decided that in conjunction with the while maintaining a surface pressure of 4600 psi.
Thru-Tubing Inflatable Bridge Plug a Baker Atlas After a total of 84 hours of constant pumping the
PFC Gamma Ray tool be run for depth correlation. operation was complete. The packer was equalized
Results and pull deflated as per procedure and retrieved from
The 3.375 in. OD Crossflow Retrievable Bridge Plug the well. In the 84 hours of pumping a total of 2.2
was correlated on depth utilizing the Baker Atlas million standard cubic feet of nitrogen was pumped.
PFC Gamma Ray tool. The plug was set successfully
against the 600 bbls/day crossflow. The well was put
back on production and cleaned up. Initial results
indicated a reduction of the water produced and an
increase of 1500 bbls/day in incremental oil.
Netherlands – Objective
A horizontal oil producer completed with a 7.00 in.,
32 lb/ft liner below a 3.688 in. restriction was
producing with an unacceptably high GOR. After
perforating the upper layer the decision was made to
Asia Pacific – Objective isolate the oil producing zone to allow production of
To isolate a watered out lower producing zone the upper gas producing layer.
Description Solution
A customer approached BOT for a solution to a well A 3.00 in. Coiled Tubing set Thru-Tubing Inflatable
in which they believed their lower producing zone Retrievable Bridge Plug was selected to perform the
was watered out. A 3.00 in. OD Thru-Tubing Inflat- isolation. Due to the high coiled tubing overbalance
able Retrievable Bridge Plug was conveyed through a Fluid Separator Reservoir was selected to separate
the completion minimum restriction of 3.13 inches the CT medium (Nitrogen) from the benign pre-
to a setting depth inside the 9-5/8 in. liner of 8470 ft loaded element inflation fluid. The system was run
MD at a deviation of 67º. and set at a depth of 10,335 ft MD and capable of
Results supporting a drawdown of greater then 2900 psi.
The plug was deployed successfully and the coiled Results
tubing and running string were pulled to surface. The operation from make up of the CT toolstring to
After returning the well to production the oil produc- break out was performed in less than 25 hours. After
tion increased from 1400 barrels per day to 4500 installing the inflatable bridge plug and isolating the
barrels per day, and the water reduced by some 4700 zone, all the liquids (oil and water) were eliminated
barrels per day to 7300 barrels per day. and the well was brought back on production at a
maximum plant fill capacity of 7.608 MM SCF/day.
Software developed specifically for inflatable
systems
Baker Quality Assurance INFLATEDESIGN™ software
Baker Oil tools’ Quality 1. Client planning guidelines
Assurance helps you get 2. Pre-job information data sheet
the maximum benefit from
your Thru-Tubing Inflatable 3. Inflatable element performance envelope
operations. Proprietary 4. Hydraulics checking spreadsheet
INFLATEDESIGN™ software
helps ensure optimum job 5. Electric wireline deployment plan calculations
design and setup. Highly 6. Supervisor worksheets
qualified field engineers
7. Element pressure differential calculator
trained and experienced
in Thru-Tubing Inflatable 8. Post-job reporting guide
operations coordinate the
9. Capturing each application on InDEx - Baker Oil Tools
job in the field backed by worldwide database
the global resources of
Baker Oil Tools, the world’s
most experienced company
in oilfield Thru-Tubing
Workover operations.
4M 09/03
Pub. No. BOT-02-3248
© 2003 Baker Hughes Incorporated. All rights reserved.
www.bakerhughes.com/bot/
Headquarters 9100 Emmott Road (77040-3514) • P.O. Box 40129 (77240-0129) • Houston, Texas • Tel (713) 466-1322
e-mail: inflatable.systems@bakeroiltools.com • www.inflatepackers.com